a large scale ups for the australian synchrotron don mcgilvery lead accelerator operator

25
A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

Upload: scot-stewart

Post on 17-Dec-2015

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

A Large Scale UPS for the Australian SynchrotronDon McGilvery

Lead Accelerator Operator

Page 2: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

2

OUTLINE OF THIS PRESENTATION

• About the Australian Synchrotron Light Source• Reliability and Causes of Lost Beam Time• Types and causes of Power Interruptions• Possible ways to mitigate power interruptions• Use of Power Quality data to understand how systems fail• Comparison of UPS technological solutions• Ups and Downs of a UPS• Installation Progress

Page 3: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

• 3GeV electron Light Source• 200mA stored beam (fill on fill)• 216m circ Storage ring • Full energy Injector• Currently 9 beamlines• Operation commenced in 2007• Supports ca. 2500 Users from

Australia and New Zealand• Scheduled 5000 hours of User

Beam per year• $35M support facility upgrade

program in progress• Seeking Funding for a further

10 beamlines

AUSTRALIAN SYNCHROTRON LIGHT SOURCE

Page 4: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

MAJOR SUPPORT FACILITY UPGRADE

1. Medical and Imaging far field facilities

2. National Centre for Synchrotron Science

3. User Accomodation Building

4. Office expansion

5. Technical Support Facility (Workshops and Engineering Building)

6. Switch Room Extensions

1

2

3

4

5

6

Page 5: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

USER BEAM AVAILABILITY

Page 6: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

Mean Time Between Failures and Mean Down Time

Page 7: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

LOST USER BEAM TIME BY FAULT CATEGORIES

This equates to a cost of about $560,000.00 in lost productivity due to unreliability of the incoming power feed

Page 8: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

AUSTRALIAN SYNCHROTRON POWER FEED

The Australian Synchrotron receives its power via a dedicated underground 22KV powerfeed from a local substation. This in turn receives its power via 66KV feeders from a major substation on the Eastern Australian Power Grid. This grid serves 80% of Australia’s Population across an area of about 2M square kilometers.

While the grid is very resilient it is possible for large disturbances to reflect across significant areas of the grid.

Often a single event will cause two voltage sag events. When a fault occurs on the PowerGrid an automatic circuit breaker will open removing the fault. The voltage returns to normal. Several seconds later the circuit breaker will close again to see if the fault has gone away.If the fault is still present a second dip is seen before the breaker permanently opens.

Page 9: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

LIST OF CAUSES IDENTIFIED BY POWER SUPPLIER

Fault Frequency Average Lost User Time Total Lost User Time

22kV site feed fault caused by

– another HV customer 1

– a bird strike 5 02:37:10 (4 events) 10:28:39

– conductor clash 3 13:19:29 (1 event) 13:19:29

– fallen trees 2

– lightning strikes 2 08:13:44 (1 event) 8:13:44

– network equipment failures 7 03:05:49 (4 events) 12:23:17

– network equipment switching 1

– a possum 6 02:12:38 (4 events) 8:50:32

– unknown 1

– a vehicle collision 3 00:26:59 (1 event) 0:26:59

– yet to be reported 15 00:27:44 (15 events) 6:56:55

46 total

Page 10: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

DISTRIBUTION OF VOLTAGE SAGS% DROP vs DURATION

Events between the lines are defined as acceptable by the Power Regulator

Page 11: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

3D Magnitude-Duration Histogram

Page 12: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

COMMON FAULTS CAUSED BY VOLTAGE SAGS

Faults cased by disturbances@ 95% Storage Ring RF systems trip (SRRF) [TR4]@ 90% Storage Ring Dipole Power Supply (over current on voltage recovery) [TR6]

Refrigeration Chillers in Cooling Water Plant (overcurrent pulses) [TR2/5]@85% SRRF Low Conductivity Water pump (ramps down /up) trips SRRF @80% most other devices (particularly magnet power supplies) not on local UPS systems

Power requirementsTR2 = 1160kW at 0.95 power factorTR4 = 1000kW at 0.95 power factorTR6 = 1020kW at 0.95 power factor

MSB-T1(Booster and BTS)

MSB-LV-NT (T2)(Building light / power

and LCW / compressed air)

MSB-T3(Linac and LTB)

MSB-T4(Storage ring RF)

MSB-LV-NT (T5)(Building

mechanical plant)

MSB-T6(Storage ring power

supplies and equipment racks)

UPS-T3 (Optional)UPS-T2 (LCW / comp.

air)UPS-T4 (SRRF) UPS-T6 (SR MPS)

Tr1 Tr3 Tr2 Tr5 Tr4 Tr6

22kV switch board

Modifications to MSB-T1 and MSB-T3(Auto bus-tie scheme)

Modifications to MSB-LV-NT(PLC reprogramming)

Bus-tie (New)

Bus-tie (Existing)

Tr5

Page 13: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

WAYS TO REDUCE IMPACT OF VOLTAGE SAGS

1. Make systems more resilient to voltage sags. We have been investigating each system to identify how the disturbances causes the device to fail. Use Power Quality meters and look for machine variables which can mirror voltage transients. We have a project to replace the SRRF analog Low Level Electronics with a digital solution to improve the transient response.(we have found that our Storage Ring Dipole power supply has internal current monitors which are a very sensitive measure of mains voltage variations)

2. Reduce cross talk between devices. We have a major project to retrofit an earth grid and fix many of the earthing anomalies

3. Link into the Power Grid at a stiffer point (66KV)This would be an expensive option and provide limited improvement as many faults propagate at this level.

4. Install UPS systems to reduce or eliminate voltage sags on critical (or all equipment)

Page 14: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

ANALYSIS OF AN EVENT (10% SAG for 700 ms)

•This event caused the SRRF and the SR dipole magnet power supply to trip

•Voltage trace shows a Sag to 90% for 700ms

•Current shows AVR held up RF for 200ms

•2 SRRF cavities tripped at 200ms

•The other 2 cavities tripped when the incoming power feed recovered

•The modulation anode drive currents and •RF drive voltages give us information about •the feedback loops on the RF systems

Page 15: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

ANALYSIS OF SHORT SAG

•Voltage Sag,

•Electrical storm,

•83% min, approx 200msecs

•Chillers faulted,

•no power supplies faulted,

•SRRF702 tripped.

•Standby chiller started without faulting.

Power Supply Feed [T6]

Page 16: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

ANALYSIS of SHORT SAG (cont)

Brown out, Electrical storm, 83% min, approx 200msecsChillers faulted,

Standby chiller started without faulting.

Cooling Plant Power Feed [T2/5]

Page 17: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

ANALYSIS of SHORT SAG (cont)

SRRF power feed [T4]

The current to the SRRFSystem dropped from 1.4KA to about 1.0KA immediately following the first dip indicating the RF systems tripped early in the transient

Even though we are trying to makeThe various systems more resilientIt is unlikely that we will be able to Achieve adequate improvement to eliminate most power related beam trips

Page 18: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

UPS OPTIONS

• Providing at 22KV or at 415V

• Using off-line or double conversion

• Using Phase Compensation

• Using Batteries or Capacitors

• Using Kinetic Energy, with either low or high speed flywheels.

• Most common solutions are designed to provide ride through capabilities for computer systems such as Banks or booking systems while standby generators start up. The voltage stability and harmonic content requirements are much greater for the Australian Synchrotron.

Page 19: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

PROVIDING PROTECTION at 22KV or 415V

• To provide the UPS at 22KV would simplify installation as one system could protect all the susceptible systems.

• Providing protection at 415V requires at least 3 separate UPS systems with no chance to load share. ie Each system needs to be sized large enough to handle its peak load.

• Most solutions rely on extensive semiconductor switching capability which would require down and up conversion to provide at 22KV

• This would add to the cost and result in increased power losses and reduced efficiency.

• Most suppliers recommended strongly against this option

Page 20: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

USING OFFLINE ENERGY STORAGE

• Most computer backup systems can tolerate short (<100ms) sags to 90% or less of the incoming mains voltage.

• The UPS system is set up to store energy offline and be able to switch in to maintain a continuous power feed in the event of a voltage sag.

• In normal operation power passes straight through the UPS system and efficiencies of 98% or greater are possible

• When the incoming mains drops below the threshold (typically 90% but could be as high as 95%) the energy storage system maintains the output voltage. 10% transients and phase discontinuities are common.

• With a large sag the incoming mains may be disconnected for a short time before being restored.

• These systems generally do not offer over voltage suppression

Page 21: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

USING DOUBLE CONVERSION

• With double conversion all power passes through the UPS regulation circuits. This can provide very high voltage stability (>95%) during both voltage and current transient conditions.

• These systems will often disconnect the incoming mains as soon as transient conditions are detected and will resynchronize with the mains voltage and phase before reconnecting. This ensures good voltage and harmonic stability. The reconnection time can be 5 seconds or more.

• These systems will suppress over voltage as well as undervoltage conditions• They rarely achieve efficiencies greater than 95% which can significantly

increase running costs.

Page 22: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

USING BATTERIES OR CAPACITORS

• Due to the very high maintenance and replacement cost we made the decision to not consider battery based solutions

• The lowest cost solution is using capacitor banks to store the charge.

• The systems typically provide up to 1 second ride through capability• While they could provide ride through power for the duration of most

sags they cannot economically proved sufficient power for a continuous conversion system.

• These systems are common for IT solutions.

Page 23: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

USING KINETIC ENERGY

• The incoming mains runs a motor/generator.• Power is stored using either large slow speed flywheels or smaller

high speed flywheels.• Multiple flywheels can be connected in parallel to increase current

or hold up time• All power passes through the regulation circuits• Vibration and bearing degradation can be an issue• Frequency resynchronization time can be many seconds

Page 24: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

UPS and DOWNS of a UPS

• A UPS should provide protection from most incoming voltage transients

• This should reduce the time lost by users and improve the science quality and output

• This comes at a cost of increased power consumption due to the 95% (or less) efficiency of a double conversion UPS system and extra cooling

• There is still a possibility of voltage transients tripping the beam from noise from unprotected systems (the injection system)

• There is another system requiring maintenance• There is potentially more vibration from the flywheels.

We have used the Diesel Generator (located adjacent to the new UPS building) as a vibration test machine and see no detectable increase in noise on the stored beam or close beamlines. Use of heavy compacting machinery during recent construction has been very visible on the beam (50um ,15-25Hz noise on beam)

Page 25: A Large Scale UPS for the Australian Synchrotron Don McGilvery Lead Accelerator Operator

• A Contract for 3 flywheel based double conversion UPS systems has been placed to protect the SRRF, SR magnets and cooling water plant.

• The Switch Room Extension building is almost complete• Cable trays, cabling and interconnect boards will be installed over the next

month• The UPS systems will be installed between May and September• Commissioning should occur during the September maintenance shutdown

PROGRESS WITH THE UPS

The UPS building last Friday