A Novel Installation Method for Deepwater Conductors 1 Tuesday, April 8 th , 2014 17:0017:20 Marine Construction & Engineering Deepwater Developments Madrid, Spain

Upload: others

Post on 31-Jul-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

A Novel Installation Methodfor Deepwater Conductors

1Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

Page 2: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

TLP, Offshore

• Field layout and target spec• Jetted conductors – review• Driven conductors – review • Installation methodology• Obstacles and solutions• As installed condition• Conclusions

Overview

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

2

Page 3: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

24 m36 m

9% Grade

Field layout & target spec

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

3

15 @ 60 m x 914mm x 38mm WT – 60T5 Templates

±10cm1 deg

Horizontal

Inclination Tolerance

Stick‐up Tolerance

1182m Water Depth

Page 4: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

4

Jetted conductors ‐ review

+ Very mature method+ Very long conductors address capacity uncertainty

– Reduced soil cohesion– Reconsolidation time varies– Susceptible to shallow flow (Ursa)– Long rig‐time hold – costly– Settles if hold period is too short– Imprecise AS‐BUILT well coordinates

ADVANTAGES / CHALLENGESADVANTAGES / CHALLENGES

Page 5: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

5

Driven conductors ‐ review

+ Mature driving technology (pre‐1900)+ Batch‐set cost benefits+ Affordable installation vessels+ Precise control of final position+ Short installation time+ Use shorter conductor for same soils– Experienced installers are few– Specialized equipment (Hammer, STS, shuttle system)

ADVANTAGES / CHALLENGESADVANTAGES / CHALLENGES

Page 6: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

6

Installation methodology

Page 7: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

7

Installation methodology

Page 8: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

8

Project resources

Page 9: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

9

Equipment onboardTP‐1

TP‐2

TP‐3

TP‐4TP‐5

TP‐6

TP‐7Working Zone

Acoustic Positioning SystemAcoustic Positioning System

Deepwater Subsea HammerDeepwater Subsea Hammer

• MENCK 270kJ• Up to 3000m WD

• LBL Array• 7 Compatts

Shuttle SystemShuttle System

STS HeadSTS Head

Page 10: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

10

Installation procedureTripod

 with

 Com

patt x7

Logistics

Installatio

n

1.  Deploy LBL array1.  Deploy LBL array 2.  Deploy 5 templates2.  Deploy 5 templates

Page 11: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

11

Installation procedure3.  Deploy Conductor3.  Deploy Conductor

4.  Self‐weight penetration4.  Self‐weight penetration

Verticality

 Che

ck

Guide

 Con

e

5. ROV Suction Penetration5. ROV Suction Penetration

Suction at STS Head

Pressure gau

ge

Page 12: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

12

Installation procedureDetache

d STS Head

Ope

n guide cone

s

6.  STS & template recovery6.  STS & template recovery

Driv

ing complete

Land

 ham

mer

7.  Batch hammering7.  Batch hammering

Spider Too

l and

 Com

patt

8.  Final as‐laid survey8.  Final as‐laid survey

Self‐weight• Avg: 14.4m (~26%)• Min: 13.0m• Max: 15.4m

Suction• Avg: 16.3m (~29%)• Add: +2.0m (~3.6%)• Min: +1.5m• Max: +2.8m

Page 13: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

As‐installed condition

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

13

Page 14: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

14

• Any subsea installation• Immediate capacities known•Meet strict location spec• Precise stick‐up control

Conclusions• Time savings

• Work begins immediately• Off Rig critical path

• Less soil disturbance

Page 15: A Novel Installation Method Deepwater Conductors Miller...Marine Construction & Engineering Deepwater Developments Madrid, Spain 15 Novel Installation Method for Deepwater Conductors

Tuesday, April 8th, 201417:00‐17:20

Marine Construction & Engineering Deepwater DevelopmentsMadrid, Spain

15

Novel Installation Method for Deepwater ConductorsPresenting Author:

Jonathon Miller([email protected])