3rd MTG, Infrastructure Workshop, CHAdeMO Association Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. A project sponsored by MIC in Goto islands, Nagasaki - Studying communication protocol necessary for smart-grid and V2G - 2010.7.8 Takahiro SUZUKI Director General (EV&ITS Promotion) Industry and Labor Department Nagasaki Prefectural Government

Upload: buinhu

Post on 10-May-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

A project sponsored by MICin Goto islands, Nagasaki

- Studying communication protocolnecessary for smart-grid and V2G -

2010.7.8

Takahiro SUZUKIDirector General (EV&ITS Promotion)

Industry and Labor Department

Nagasaki Prefectural Government

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

Nagasaki EV&ITS Project

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

Nagasaki Prefecture

・Composed of mainl3 major island areas of Iki,Goto islands (Goto ci

・ Population: 1,458,404

・ Households: 607,465

・ Gross area: 4,104.48k㎡

・ No.of Cars: 891,544

※ Total coastlines is 4,in Japan (12%).

(excluding Norther

and (incl. Nagasaki city) and Tsushima, and

ty & Shin Kami-Goto town).

196 km is the longest

n Territories)

Goto islands

Population: 67,046Households: 31,375Gross area: 634.78k㎡No.of Cars: 39,334

The longest underwater electric cable

in Japan connects Goto and mainland. (53km)

Tsushima

Iki

MainlandGoto

N

Nagasaki City

20km

Kyushu

Nagasaki

Goto City

Shin Kami-Goto Town

○ ”Nagasaki EV&PHV Town Master Plan”The only one to the west of Kyoto in 8 EV・

PHV towns selected by the Government.

○ ”Revitalization of isolated islands”Job and industry creation is necessary to

solve the problem of decreasing population

in islands, which occupies 40% of Nagasaki.

○ Action for registration to the World Heritage

“Churches and Christian Sites in Nagasaki” are

registered to the candidates list in Jan, 2007.

Environmental protection efforts are important

to the future formal registration.

○ ”Electrically Connected islands”Increasing of electric demand in isolated island

does not always mean “eco”.

Goto islands, Nagasaki

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

<Project Targets>- Implementation of “Practical Introduction and Operation of EVs and ITS Tourism” and

“Model Demonstration of Connecting Energy Grid and EVs” based on the discussions by

Nagasaki EV&ITS Consortium.- Creation of “Nagasaki’s Global Standard” and “Nagasaki’s Regional Business Model” through

promoting collaboration of local industries and universities.

Outline of Nagasaki EV&ITS Project

☆ Introduction and Operation of EVs and ITS Tourism

◎ Electric vehicles (mainly for rent-a-cars) and chargers are introduced in 2009-2010 periods. ◆100 EVs with ITS on-board units are introduced in Goto islands and used mainly for rent-a-car.

◆Quick Chargers: 4 units at 2 sites (March, 2010) + 11 units at 6 sites (June, 2010).

◆Delivering local sight-seeing information by ITS tools→ 10 recommended routes for each islands are installed.

◎ Development to the other uses for EVs (Ex. taxis) and to the other areas after 2010, based on the model clarified from the experiences in Goto.

※Results of rent-a-car use585 cars by 19 agents (until June 4, 2010)(Goto city: 488 cars by 12 agents / Shin Kami-Goto town: 97 cars by 7 agents)

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

Nagasaki EV&ITS Project : Image of “Advanced ITS Tourism”

3.Providing Real-Time Information using ITS Technologies

4.Smooth Toll Collection by ITS on-board unit

1.Smooth Connection of Public Transportation and EV Rent-A-Car

2.Infrastructure Installation: Chargers and ITS Services

NagasakiSuper Express

Jet Foil

Souvenir

..¥画像¥P1010679.JPG

Rent a car

Comfortable trip with eco & silent EV !

Smoothly to Goto !

EV

To a clean travel around world heritage churches…

Plentiful experiences of local specialties

Charging duringsightseeing !

ITS on-board units navigates recommended routes, and guides attracting spots, local souvenirs and events.

Parking ChargingHotel

Choose various optional tours provided as real-time information and guided to the site by car-navigation system !

Smart Payments

Advanced ITS Tourism

Food

Targets: Implementation of EV and ITS Tourism, Demonstration of Smart Community, Creation of “Glocal” Standard Model

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

Aims: <Practical installation and operation of EVs and ITS tourism>, <Conducting project with creating global rules and standards from region>, <Promoting regional industries led by sightseeing and ecology>, <Demonstration of connecting energy grid and EV>, etc.

Nagasaki EV&ITS Consortium (Nagasaki EVITS)

WG1 EVs & Chargers WG3 Local ContentsWG2 ITS Infrastructures

Secretary

Chair:Prof. Hitoshi Morita(Nagasaki Pref. Univ.)

① MembersIT CompaniesTourism CompaniesLocal CompaniesLocal GroupsCities and Townsetc.

Specs ⇒Global Standards

Specs ⇒Global Standards

Board Members

Chair:Prof. Hiroaki Nishi(Keio Univ.)

① MembersPower CompanyGreen Power MakersCities and Townsetc.

② Subjects- Green power technologies- Smart grid and micro grid- V2Getc.

Providing Technical and Functional Specifications by discussions in WGsPresident: Prof. Hironao Kawashima (Keio Univ.)

Nagasaki Pref., Goto city, Shin Kami-Goto town,MLIT Nagasaki Office of National River & Highway Being associated to the consortium,

and implementing and operating EVsand infrastructures

Local Associationsin cities and towns

Local Associationsin cities and towns

WG Supervisor

WG4 Eco-Islands

Nagasaki EV&ITS Consortium (Nagasaki EVITS)

Supervisor: Prof. Jun Ohta (Keio Univ.)

New consortium and WG members are always welcome !!

② Subjects- Sightseeing needs- Service formats- Collection,

arrangements, andoperation oflocal contents

etc.

Chair:Prof. Hiroshi Makino(Univ. of Tokyo)

① MembersE&E MakersCommunication Makersetc.

② Subjects- ITS on-board units- DSRC beacons- ITS servicesetc.

Chair:Dr. Norikazu Ogino (JARI)

① MembersPower CompanyCar MakersCharger Makersetc.

② Subjects- Installation & operation of

EVs and chargers- EV & ITS connectionetc.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

 Isuzu IT space ANA Strategic Research Institute ITS Service Promotion Association ORG. (ISPA)

Toyota IRODORI Kobo NTT Data ITS Japan Nissan OUGISEIKO NTT Data Customer Service Internet ITS Consortium Subaru Kameyama Electric MEC Keio Univ. Mitsubishi Motors Kawakami Kensetu-Kogyo Oriental Consultants Sasebo National College of Technology

Kyowakiden Industry KDDI JEITAKB Software Kyuki ITS Center, IIS, Univ. of TokyoGoto Wind Power Kyushu Electoric Power Kyushu Economic Research Center

 Aisin AW   Goto Shokokai Contents City Organization for Road System Enhancement

 Alpine SAIHI Information Service CBC Highway Industry Development Organization (HIDO)

 Oki Electric Sasebo Heavy Industries Shimizu Corporation Nagasaki Univ. Clarion SEA ALL Shindengen Electric Manufacturing Univ. of Nagasaki Denso Kyushu System5 JTB Nagasaki Institute of Applied Science Toyota Shokki G.S.Eletech. Kyushu Sumitomo Electric Industries JARI Toyoa Tsusho Electronics Superware Inc. SEGWAY Japan Dept. of Advanced Mech. Eng., Waseda Univ.

 NEC Choryo Control System ZENRIN Datacom Pioneer Nagasaki Ecology&Energy Industry Network Chodai Panasonic Solutions Japan Nagasaki Pref. Convention & Visitors Bureau dSPACE Japan Hitachi Foundation of Encourage Nagasaki Industry TEPCO R&D Center Mobility Tech. Group

 Fujitsu Nagasaki Pref. Automotive Industry Promotion Association Nishitetsu Information System Ministry of Economy, Trade and Industry Mitsubishi Electrics Federation of Commerce&Industry in Nagasaki Pref. Nishimu Electronics Ministry of Land, Infrastructure, Transport and Tourism

Federation of Shokokai in Nagasaki Nichicon Japan Tourism AgencyNagasaki IT Solution Industry Association Nippon Koei National Institute for Land and Infrastructure Management

Nagasaki Pref. Taxi Association Nihon UNYSIS MOE, Kyushu Regional Environment Office

 Nagasaki city, Sasebo city, Nagasaki Chuokai Park24 Kanagawa Pref. Shimabara city, Isahaya city, Nagasaki Rent-a-car Association Hakuhodo Aichi Pref. Ohmura city, Hirado city, Nishikyusyu Enbedded Technology Community Pacific Consultants Kyoto Pref. Matsuura city, Goto city, Nishi-Sonogi Shokokai PATLITE Kyoto City Saikai city, Unzen city, PAL Corporation Fukken Co.,Ltd. Minami Shimabara city, HOP Co.,Ltd. Mitsui & Co.,Ltd. Nagayo town, Togitsu town, MHI Nagasaki Shipyard & Machinery Works MHI Sustainability Energy & Environment Strategic Planning Dept.

 Kawatana town, Ojika town, Miyabi Sekkei MHI Power Systems HQ, Solar Cell Power Systems Business Unit

 Shin Kami-Goto town Yamada Denki Kogyo Meidensha

Establishment of Consortium 2009.10.8126 Members (2010.5.20)

Car Makers

E&E, Navi Makers

Local Companies & Groups IT, Infrastructure Companies Academies & Associations

Cities and Towns

Observers (Govs, Prefs, City)

Nagasaki EV&ITS Consortium Members

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

Chichigatake Mt.(467m)

Sannohzan Mt.(439m)

Samples

Quick ChargerRent-a-car AgentEV rent-a-car x 1EV rent-a-car x 10Sightseeing Spot, Port

Udon-no-sato / Arikawa Port

Kashiragashima Church

Kentoshi Furusato-Kan

Dozaki Church

Ohsezaki Observatory

Fukue Port

Narao Port

Tsuwazaki Lighthouse

Now installed …

Goto City65 EVs(2010.3)

+ 2 PHVs(2010.6)

Shin Kami-Goto Town35 EVs(2010.3)

Quick Charger(2) 2010.3【Goto Udon-no-sato】

Quick Charger(2) 2010.6【Narao Port Terminal】

Quick Charger(2) 2010.6【Shin Kami-Goto Town Office】

Quick Charger(2) 2010.6【Fukue Port Terminal】

Quick Charger(1) 2010.6【Miyanomori Park Camping Site】

Egami Church

Old Gorin ChurchQuick Charger(2) 2010.6

【Tomie Onsen Center】

OhsoChurch

Quick Charger(2) 2010.3【Kentoshi Furusato-Kan】

Quick Charger(2) 2010.6【Tamanoura Country Park】

Aosagaura Church

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

WG4:Smart Grid / Micro Grid with EV & PHV

CommercialGrid

time

kW

time

kW

time

kW

Generator

time

kW

Mega Solar Cell

Smoothing by utilizing batteries on EVs and generators

Connection

Li-ion batteries

+ Generators

time

kW

Not Constant Power Supply

(vary by sunshine)Smoothened Current

Generate counter power supply using Li-ion batteries on EVs and distributed generators

Li-ion battery on EV

① EV for private use → Charging EVs during parking at port (when drivers are going to mainland)② Power supply from solar cells is not constant : vary by weather and daylight③ Utilize Li-ion batteries on parked EVs and PHVs as micro-grid cells④ Need negotiation with various relating laws and regulations

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

Solar PanelEV Charger SpotFukue Port Terminal

(Parking)

Fukue Port Map

Solar Cell Image

1. TargetDevelopment of infrastructure as charging spots for EV promotion

2. Plan (unfixed)Supply electric power to parked EVs and port terminal demands produced by solar cells installed on Fukue port.(Area : 1.5ha , System capacity : about 2MW , Year total : 1,818 MWh)

◎Solar Power Supply Levelcorresponding to :★ 237 EVs (per day)★ 3.8 times of total electric

consumption (for lighting)in Fukue Port Terminal

◎Merit★Residents in Goto can

charge EVs while parkingat port terminal.

★Education & disseminationto citizens and visitorsby PR facilities enlarges numbers of visitors.

Cable

WG4“Fuku-ECO~Parking”(Fukue Port) - Green Innovation at Ports & Airports -

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

“Field test for studying communication protocol in Goto Islands, Nagasaki”

Project ManagerKeio University

Associate Professor Hiroaki Nishi

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 11

Table of Contents

1. MIC Public Fund Overview

2. Reference to Nagasaki EV&ITS

3. Project Overview

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 12

1. Ministry of Internal Affairs and Communications (MIC) Public Fund Overview

MIC FY2010 the second supplementary budget (MIC Website) http://www.soumu.go.jp/menu_news/s-news/02tsushin04_000017.html

Project Term From July 2010 To March 2011[Field test at Fukue port: From January 2011 to February 2011]

Title

Summary

To accomplish a reduction of environmental impacts, the standardization of technical standard is promoted, which is linked to “Network control system”. Network control system collects various information from many equipments connected to the network, and the system integrates these equipments with the information for achieving an effective control.

Our Proposal

This project focuses to develop the network communication system by covering and integrating the current various technical standards including communication network, communication QoS, security, information home appliance, EV/ITS, smart grid, etc. Fukue port terminal, Goto city, Nagasaki prefecture is selected as a testing field of this system because the city consists of typical isolated islands and 100 EVs are introduced.

Location Fukue port terminal, Goto islands, Nagasaki Prefecture

Focuses of Project

・Collection, management, exploitation of resource information and environmental information-Actual data of the electric power consumption or power generation-Integration of an amenity index by using environmental sensors and power consumption control

・Practical field test-Implements an actual system and evaluates the communication protocols, data schemers, etc.

・Preliminary standardization

Focuses of Study1. Providing the preliminary standard of the information infrastructure2. ICT environment at an individual location3. Verification of CO2 emission reduction

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 13

2. Reference to Nagasaki EV&ITS_1 – Requirement for Smart Community

Middle/small buildings

Taller buildings

Supply Side Demand Side

1. Demand/Supply control: Demand/Supply forecast, Supply control, Demand allocation2. Supply Forecast/Control: Supply forecast of Photovoltaic/Wind power generator3. Demand Forecast/Control: Smart metering4. Demand Response: Demand control to Smart houses and Smart buildings5. EV Demand Forecast/Control: Demand Forecast/Control of charging infrastructure

and EV parking space

1. Demand/Supply control: Demand/Supply forecast, Supply control, Demand allocation2. Supply Forecast/Control: Supply forecast of Photovoltaic/Wind power generator3. Demand Forecast/Control: Smart metering4. Demand Response: Demand control to Smart houses and Smart buildings5. EV Demand Forecast/Control: Demand Forecast/Control of charging infrastructure

and EV parking space

Transmission G

rid

Smart House

Electric Power

Company

Charging Station Network

Substation

(2)

(3)

(5)

(4)

(1)

5 areas to attain Smart Community5 areas to attain Smart Community

Smart GridControl Center

Requirement for Smart Community from the viewpoint of ICT environment

Power

Information

Battery

PhotovoltaicPowerGenerator

Wind PowerGenerator

Thermal Power Generator

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 14

2. Reference to Nagasaki EV&ITS_2 - Requirement for EV and its Charging station

EV charging station EV charging station management center

・User authentication(with smart card, with EV itself)

・Collect EV charging station info.(User information, Amount of electric power used, error detection)

・User management, authentication・Management of information from EV charging station(User info., Amount of electric power used, error detection, charging status, reservation)

・EV battery demand control/forecast

Requirement for EV and its charging station from the viewpoint of ICT environment1. Operational viewpoint: Individual environment and structure are established to attain user convenience and

safety or to improve an operation efficiency, respectively.2. Smart Grid viewpoint: On the bases of the concept “EV as a energy resource”, EV charging demand is controlled

and integrated with Smart Community (V2G).

平成21年度平成21年度 株式会社NTTデータ株式会社NTTデータ電気自動車普及環境整備実証事業電気自動車普及環境整備実証事業

充電スタンド利用カード充電スタンド利用カード

平成21年度平成21年度 株式会社NTTデータ株式会社NTTデータ電気自動車普及環境整備実証事業電気自動車普及環境整備実証事業

充電スタンド利用カード充電スタンド利用カード

EV (battery) monitoring

・Collect EV probe information(Data of running condition, battery condition etc.)

・Authentication ・Authentication・Location of EV charging station・Electric power consumption

・EV data(probed information, . etc)

・Location of EV charging station

・Charging completion

・EV data((location, battery, etc)

Smart Grid Control Center

・EV data(probe information)

・Electric power consumption

・Demand response

・Demand response

Car navigation

・Visualize probed information from EV・Show the nearest or desirable EV charging station (EV charging status, error, location)

ITS center

・Collect the status of EVs and information from the concerning Smart Community

・Provide the information of the nearest or desirable EV charging station to car navigation systems

Mobile/PC

・Visualize the status of EV(EV status, EV location, charging status etc)

・Visualize the status of EV charging station(EV charging status, error, location)

・Show the nearest or desirable EV charging station・Receive an e-mail from Center

・Location of EV charging station

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 15

User(Stable)User(Stable)

Renewable EnergyRenewable Energy

3. Project Overview - Necessity of Standardization of Information Exchange In a Smart Grid Area

Smart GridControl CenterPhotovoltaic

PowerGenerator

PhotovoltaicPowerGenerator

WindPowerGenerator

WindPowerGenerator

Power GridPower Grid

HousesHouses

BuildingsBuildings

HEMSHEMS

BEMSBEMS

User(mobile)User(mobile)

RMSN

RESN

Wireless communication

(Mobile telephone Network, etc.)

Public Network

(Internet, etc.)

Communication Line for Smart Grid(High-speed wired communication)

RESN

Information Control

Information Control

BatteryBattery

Another Smart Community

Requirements for Smart Grid Network

Flexibility・Scalability, Co-existence

Flexibility・Scalability, Co-existence

Uniformity・Unity of command

Uniformity・Unity of command

Secure・Anti-attack, dependability

Secure・Anti-attack, dependability

High Quality・To guarantee RASIS

High Quality・To guarantee RASIS

Neutrality・Technical neutrality

Neutrality・Technical neutrality

Adaptation of existing standards (NIST, IEEE P2030, etc.)Adaptation of existing standards (NIST, IEEE P2030, etc.)

EVEV

ChargerChargerCenterOfEV・

ITS

CenterOfEV・

ITS

P to G

P to G

B to G

P to G

G to G

V to G

B to G

H to G

Various and enormous amount of information needs to be controlled according to an unified rule for attaining Smart Grid.The project focuses on the preliminary standard of the information infrastructure for fulfilling requirements of X-to-Grid(X2G)

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 16

IEEE P2030IEEE 802.3

IEEE 802.11

IEEE P1090

IEEE 802.15

IEEE SCC21ITU-T SG15

ITU-T SG9

IETF

OCC ISO/IEC 27000

TCG

ISO/TC204

CHAdeMO

Service Application

Common Platform

IEC61968

IEC60870-6

IEC61850

DNP3

IEC1547

IEEC37.118

IEC61968/70

OpenADR

ISO16484-5

ANSI C12.19

OpenHAN

UPnP/DLNA

Jini

ECHONET

ITS・EVSecurityQoSHomeElectronicsNetwork Power GridSmart Grid

ITU-T SG12

ZigBee SEP

NIST SP 800-82

IEEE1686-2007

3. Project Overview - Target of Standardization

This project focuses on the preliminary standard of the information infrastructure, including “Meta-Standard” and X2G (V2G, B2G, H2G, etc.).

“Meta-Standard” enables to provide an easy method for designing a service or an application to evolve

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 17

Mobility[EV/Charging Station](Goto Islands)

Mobility[EV/Charging Station](Goto Islands)

Data collectionby simulation

Data collectionby simulation

Renewable energy(Fukue port terminal)

Renewable energy(Fukue port terminal)

3. Project Overview – Community Resource Management Network

This project aims to develop an ICT environment for controlling various resources of a community intensively. Various data from both supply/demand side are collected and stored into the Resource Management Center and is used for effective system controls. Preliminary standard of this kind of network system is also discussed.

ApplicationApplication

Smart CommunityInfrastructure

Smart CommunityInfrastructure

Resource DatabaseResource Database

Resource information

MobilityInfrastructure

MobilityInfrastructure

User information

NetworkNetwork

Communication ManagementCommunication Management

Node ManagementNode Management

NW MonitoringNW Monitoring

Supply Side Resource Management Center Demand Side

Generation ResultGeneration Result

Charge/DischargeResult

Charge/DischargeResult

Generation ResultGeneration Result

Electric PowerUsed Result

Electric PowerUsed Result

Sensor Info.Sensor Info.

Electric PowerUsed Result

Electric PowerUsed Result

Probe Info.Probe Info.

Charging ResultCharging Result

Authentication Info.Authentication Info.

Requirement for smart community ICT environment

Flexibility・Scalability, Co-existence

Flexibility・Scalability, Co-existence

Uniformity・Unity of command

Uniformity・Unity of command

Secure・Anti-attack, dependability

Secure・Anti-attack, dependability

High Quality・To guarantee RASIS

High Quality・To guarantee RASIS

Neutrality・Technical neutrality

Neutrality・Technical neutrality

Technology standard (NIST, IEEE P2030 etc)Technology standard (NIST, IEEE P2030 etc)

Middle/small buildings(Fukue port terminal)

Middle/small buildings(Fukue port terminal)

SimulatorSimulator

Solar panel

Photovoltaic PowerGenerator

Battery

Resource Environmental Sensor N

etwork

Resource Environmental

Sensor Netw

orkResource M

obilitySensor N

etwork

Community Resource Management Network

Network NetworkCenterPower Meter Meter/Sensor

• Information management by a central resource management server

• Providing the preliminary standard of the information infrastructure

• Verification of CO2 emission reduction

• Collection of resource information and environmental information of demand side

• Evaluation of the method for collecting these information.

• Evaluation of resource information of mobility

• Collection of resource information and environmental information

• Evaluation of the method for collecting these information.

• Evaluation by using a simulator

Common Platform

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 18

3. Project Overview – Reference to Nagasaki EV&ITS_1 SC

Middle/small buildings

Taller buildings

Supply Side Demand Side

1. Demand/Supply control: Demand/Supply forecast, Supply control, Demand allocation2. Supply Forecast/Control: Supply forecast of Photovoltaic/Wind power generator3. Demand Forecast/Control: Smart metering4. Demand Response: Demand control to Smart houses and Smart buildings5. EV Demand Forecast/Control: Demand Forecast/Control of charging infrastructure

and EV parking space

1. Demand/Supply control: Demand/Supply forecast, Supply control, Demand allocation2. Supply Forecast/Control: Supply forecast of Photovoltaic/Wind power generator3. Demand Forecast/Control: Smart metering4. Demand Response: Demand control to Smart houses and Smart buildings5. EV Demand Forecast/Control: Demand Forecast/Control of charging infrastructure

and EV parking space

Transmission G

rid

Smart House

Electric Power

Company

Charging Station Network

Substation

5 areas to attain Smart Community5 areas to attain Smart Community

The project collects the actual data from magenta covered area and study how the data is made use of. (The dotted area is run by simulation)

Smart GridControl Center

Power

Information

Battery

PhotovoltaicPowerGenerator

Wind PowerGenerator

Thermal Power Generator

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved.

3. Project Overview – Reference to Nagasaki EV&ITS_2 EV/Charging Station

The project collects the actual data from magenta-covered area and study how the data is made use of. 1. Operational viewpoint: Individual environment and structure are established to attain user convenience and

safety or to improve an operation efficiency, respectively.2. Smart Grid viewpoint: On the bases of the concept “EV as a energy resource”, EV charging demand is controlled

and integrated with Smart Community (V2G).

EV charging station EV charging station management center

•User authentication(with smart card, with EV itself)

•Collect EV charging station info.(User information, Amount of electric power used, error detection)

•User management, authentication•Management of information from EV charging station(User info., Amount of electric power used, error detection, charging status, reservation)

•EV battery demand control/forecast

平成21年度平成21年度 株式会社NTTデータ株式会社NTTデータ電気自動車普及環境整備実証事業電気自動車普及環境整備実証事業

充電スタンド利用カード充電スタンド利用カード

平成21年度平成21年度 株式会社NTTデータ株式会社NTTデータ電気自動車普及環境整備実証事業電気自動車普及環境整備実証事業

充電スタンド利用カード充電スタンド利用カード

EV (battery) monitoring

•Collect EV probe information(Data of running condition, battery condition etc.)

・Authentication ・Authentication・Location of EV charging station・Electric power consumption

・EV data(probed information, . etc)

・Location of EV charging station

・Charging completion

・EV data((location, battery, etc)

Smart Community Center

・EV data(probe information)

・Electric power consumption

・Demand response

・Demand response

Car navigation

•Visualize probed information from EV•Show the nearest or desirable EV charging station (EV charging status, error, location)

ITS center

•Collect the status of EVs and information from the concerning Smart Community

•Provide the information of the nearest or desirable EV charging station to car navigation systems

Mobile/PC

•Visualize the status of EV(EV status, EV location, charging status etc)

•Visualize the status of EV charging station(EV charging status, error, location)

•Show the nearest or desirable EV charging station

•Receive an e-mail from Center

・Location of EV charging station

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 20

3.Project Overview - Organization

General director:Keio University President Atsushi Seike

Standardizing board

PMO (Project Management Office)・Keio University

-Associate Professor Hiroaki Nishi-Professor Katsuhiko Ogawa-Associate Professor Keisuke Uehara-Research Associate Ryogo Kubo-Emeritus Professor Hironao Kawashima-Professor Jyun Oota-Research Affiliate Toshio Togoshi-Keio University Secretariat

・NTT DATA CORPORATION・Hitachi Information & CommunicationEngineering,Ltd. (Hitachi JTE)

Project board

Project Organization

Fixing of the scope of standardization

Definition of communication data format (XML)

Definition of communication common platform

Fixing of the scope of standardization

Definition of communication data format (XML)

Definition of communication common platform

Project Members

dSPACE JapandSPACE Japan

Hitachi JTE

Hitachi JTE

KDD

IKD

DI

Seiko Instruments Inc.

Seiko Instruments Inc.

Panasonic Electric Works

Panasonic Electric Works

MITSU

BISHI H

EAVEYIN

DU

STRIES, LTDM

ITSUBISH

I HEAVEY

IND

USTRIES, LTD

Project Manager: Keio University Associate Professor Hiroaki Nishi

NTT D

ATA CORPO

RATION

NTT D

ATA CORPO

RATION

Nagasaki EV&ITS consortium

Nagasaki Prefectural Government

Goto Islands council

CooperationCooperation

Copyright©2010 Keio University. All rights reserved.

3rd MTG, Infrastructure Workshop, CHAdeMO Association

Copyright©2010 Nagasaki EV&ITS Consortium. All rights reserved. 21

3. Field Test Overview - Project Schedule

CY2010 CY2011

Apr-Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

System Development/System Test at TokyoSystem Development/System Test at TokyoReal System

Implementation/Test at Fukue

port

Real System Implementation/

Test at Fukue port

Project Kickoff/Planning

Project Kickoff/Planning

Field Test/Measurement

Field Test/Measurement

▲11-Jun Project Kickoff

▲4-Jun Adoption

▲Beginning of development

▲9-AprProposal

▲Report to MIC

RestoreRestore

Report/Road map

Report/Road map

Milestone

▲Field Test Setup

▲Developing the environment at Fukue

Field test is running according to the following schedule.

Field Test