a recent example of a difficult project management approach

17
A Recent Example of a Difficult Project Management Approach Scott J. Brandenberg May 16 th , 2011

Upload: pules

Post on 20-Jan-2016

40 views

Category:

Documents


0 download

DESCRIPTION

A Recent Example of a Difficult Project Management Approach. Scott J. Brandenberg May 16 th , 2011. Project Purpose. Funding Source: USGS PI’s: Me and Jon Stewart Duration: 2 yrs, 2 tests. Model Construction Staff. Alek Harounian, UCLA Student. DongSoon Park, UCD Student. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: A Recent Example of a Difficult Project Management Approach

A Recent Example of a Difficult Project Management Approach

Scott J. Brandenberg

May 16th, 2011

Page 2: A Recent Example of a Difficult Project Management Approach

Project Purpose

Funding Source: USGSPI’s: Me and Jon StewartDuration: 2 yrs, 2 tests

Page 3: A Recent Example of a Difficult Project Management Approach

Model Construction Staff

DongSoon Park, UCD StudentLijun Deng, UCD StudentAlek Harounian, UCLA Student

Chad Justice, nees@UCDavis Jason Goff, UCLA Shaun the Sheep

Page 4: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 5: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 6: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 7: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 8: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 9: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 10: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 11: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 12: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 13: A Recent Example of a Difficult Project Management Approach

Model Construction Sequence

Page 14: A Recent Example of a Difficult Project Management Approach

Project Management

• Alek was taking courses at UCLA during model construction and could only be in Davis intermittently.

• The original plan was to have Alek begin consolidation of each lift of clay, and subsequently have Lijun, DongSoon, and/or Chad adjust consolidation pressure.

• Lijun was paid from project for one quarter, and DongSoon was paid by nees@UCDavis to help optimize consolidation system.

Page 15: A Recent Example of a Difficult Project Management Approach

Project Management

• Alek could not be in Davis as often as needed during model construction, and too much of the responsibility was borne by Lijun and DongSoon.

• Who was ultimately in charge of the model became unclear as Lijun and DongSoon increased their involvement (at the expense of their own PhD studies).

• The test was ultimately very successful, but I would never do it this way again.

Page 16: A Recent Example of a Difficult Project Management Approach

Lesson

• The person responsible for the project (student or postdoc) cannot effectively take charge of the project remotely, and if possible should plan to be in Davis during model construction.

Page 17: A Recent Example of a Difficult Project Management Approach

Thank You