a seismic slope stability probabilistic model based on...

14

Upload: vothien

Post on 14-May-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

Scientia Iranica A (2015) 22(3), 728{741

Sharif University of TechnologyScientia Iranica

Transactions A: Civil Engineeringwww.scientiairanica.com

A seismic slope stability probabilistic model based onBishop's method using analytical approach

A. Johari�, S. Mousavi and A. Hooshmand Nejad

Department of Civil and Environmental Engineering, Shiraz University of Technology, Shiraz, Iran.

Received 17 May 2014; received in revised form 20 July 2014; accepted 15 September 2014

KEYWORDSReliability;Jointly distributedrandom variablesmethod;Monte Carlosimulation;Seismic slope stability;Limit equilibriummethod.

Abstract. Probabilistic seismic slope stability analysis provides a tool for consideringuncertainty of the soil parameters and earthquake characteristics. In this paper, the JointlyDistributed Random Variables (JDRV) method is used as an analytical method to developa probabilistic model of seismic slope stability based on Bishop's method. The selectedstochastic parameters are internal friction angle, cohesion and unit weight of soil, whichare modeled using a truncated normal probability density function (pdf) and the horizontalseismic coe�cient which is considered to have a truncated exponential probability densityfunction. Comparison of the probability density functions of slope safety factor with theMonte Carlo simulation (MCs) indicates superior performance of the proposed approach.However, the required time to reach the same probability of failure is greater for the MCsthan the JDRV method. It is shown that internal friction angle is the most in uentialparameter in the slope stability analysis of �nite slopes. To assess the e�ect of seismicloading, the slope stability reliability analysis is made based on total stresses withoutseismic loading and with seismic loading. As a result, two probabilistic models are proposed.c 2015 Sharif University of Technology. All rights reserved.

1. Introduction

Seismic stability analysis of natural and man-madeslopes is an important topic of research for the safedesign in the seismic zone. Natural slopes are usuallystable when they are not disturbed by any externalforce, such as seismic forces. For assessing the seismicresponses of slopes, considering the characteristics ofinput ground motions and the properties of soil mediaare needed. There are four main methods for seismicstability analysis of slopes: pseudo-static [1], Newmarksliding block analysis [2], numerical analysis [3] andtesting method using shaking table and centrifugeapparatus. In these methods, the pseudo-static methodis the simplest at the earliest applications [4].

The pseudo-static method is modi�ed from LimitEquilibrium Method (LEM) in seismic stability analy-

*. Corresponding author.E-mail address: [email protected] (A. Johari)

sis. In fact, the seismic load is equivalent to invariablyhorizontal and vertical forces, and the problem ofseismic stability of slopes is simpli�ed into a staticproblem in the pseudo-static method. In the nextstep, the ratio of resistant forces to driving forces on apotential sliding surface is de�ned as Factor of Safety(FS). The slope is considered safe only if the calculatedsafety factor clearly exceeds unity. However, due tothe model and parameter uncertainties, even a factorof safety greater than one does not con�rm the safetyagainst failure of slope. Therefore, it is importantto calibrate the deterministic method considering thee�ect of di�erent sources of model and parameteruncertainties. Reliability analyses provide a rationalframework for dealing with uncertainties and decisionmaking under uncertainty.

In general, the source of uncertainty in stabilityof a slope is divided into three distinctive categories:soil parameters uncertainty, model uncertainty, andhuman uncertainty [5]. Parameter uncertainty is the

A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741 729

uncertainty in the inputs parameters for analysis [6-9].Model uncertainty is due to the limitation of the the-ories and models used in performance prediction [10],while human uncertainty is due to human errors andmistakes [11]. In this research, parameter uncertaintyis assessed to seismic stability of in�nite slope.

The reliability analysis of slope stability hasattracted considerable research attention in the pastfew decades. Many probabilistic methods have beenused for slopes stability analysis. These methods canbe grouped into four categories: analytical methods,approximate methods, Monte Carlo simulation andrandom �nite element method:

� In analytical methods, the probability density func-tions of input variables are joined together to derivea mathematical expression for density function ofthe factor of safety. These approaches can begrouped into JDRV method [12-14] and First OrderReliability Method (FORM) [15] categories. Manyresearches have been made to apply FORM methodin slope stability (e.g., [16-20]). Limited attemptshave been made to apply JDRV method (e.g., [21-23]).

� Most of the approximate methods are modi�edversion of two methods namely: First Order Sec-ond Moment (FOSM) method [24] and Point Esti-mate Method (PEM) [25]. The approaches requireknowledge of the mean and variance of all inputvariables as well as the performance function thatde�nes safety factor (e.g., Bishop's equation). Manyattempts have been made to apply the PEM (e.g.,[26-29]) and by FOSM method (e.g. [19,27-33]) inslope stability.

� The MCs is based on repeated random sampling toaddress risk and uncertainty in quantitative analysisand decision making [34]. Recent attempts havebeen made to analyze the stability of slopes usingthis method (e.g., [28,31,35-47]).

� Random �nite element method combines elasto-plastic �nite-element analysis with random �eldsgenerated using the local average subdivisionmethod. Several new slope stability researches aredone by this method (e.g., [48-51]).

In this paper, a complete analytical procedureusing JDRV for developing a probabilistic model ofseismic slope stability based on Bishop's method isproposed. For this purpose, the horizontal seismiccoe�cient and soil parameters are considered stochasti-cally, and the probability density function relationshipof safety, factor is derived. For determining thecritical surface with the minimum factor of safety, theParticle Swarm Optimization (PSO) algorithm is used.Furthermore, the steps are repeated for total stresscondition and the results are compared to seismic slope

stability analysis by their reliability index. At theend, two probabilistic models based on total stresseswithout seismic loading and with seismic loading areproposed.

2. Limit equilibrium method

The limit equilibrium method is the most popularapproach in slope stability analysis. This method iswell known to be a statically indeterminate problem,and assumptions on the inter-slice shear forces arerequired to render the problem statically determinate.

In the limit equilibrium method of slices [52-55],the soil mass above the slip surface is subdivided intoa number of vertical slices. The actual number of slicesused depends on the slope geometry and soil pro�le.Some procedures of slices assume a circular slip surfacewhile others assume an arbitrary (noncircular) slipsurface. Procedures that assume a circular slip surfaceconsider equilibrium of moments about the center ofthe circle for the entire free body composed of all slices.In contrast, the procedures that assume an arbitraryshape for the slip surface usually consider equilibriumin terms of the individual slices.

In this study the Bishop's method is used as atypical e�cient method. The Bishop approach is asimpli�ed method rather than Morgenstern-Price andSpencer's methods. Although Figure 1 shows that theSpencer and Morgenstern-Price solutions are in goodagreement with the simpli�ed Bishop results [56]. Inthis �gure Lambda � is a ratio of inter-slice forces forslices.

Figure 1. Variation of factor of safety versus Lambda forvarious methods [56].

730 A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741

2.1. Slope stability analysis by simpli�edBishop's method

In the simpli�ed Bishop's method [53] the forces onthe sides of the slice are assumed to be horizontal(i.e., there are no shear stresses between slices). Thismethod considers equilibrium of moments about thecenter of the circle therefore, the sliding surface isassumed to be circular. The Bishop's equation forfactor of safety in terms of total stresses is as fol-low [53,57]:

FS =

Pni=1

hc:�li: cos�i+wi: tan'

cos�i+(sin�i: tan')=FS

iPni=1 wi: sin�i

; (1)

where:wi Weight of slice = :bi:hi;�li Area of the base of the slice for a slice

of unit thickness;c Cohesion;�i Angle of the base of slice; Unit weight of soil;bi The width of the slice;hi The height of the slice at the centerline;' Internal friction angle;FS Factor of safety.

A slope with circular slip surface has been shownin Figure 2. The soil mass above the slip surface issubdivided into a number of vertical slices. A sampleslice with its forces is shown in Figure 3. Where Niis the normal force applied at center of the base of theslice, Si is soil strength, and Ei and Ei+1 are the normalinter-slice force.

2.2. Seismic slope stability analysis byBishop's method

Bishop developed a pseudo-static method for seismicanalysis of natural slopes. In this approach, thefactor of safety against sliding is obtained by includinghorizontal and vertical forces in the static analysis.These forces are usually expressed as a product ofthe seismic coe�cients and the weight of the potentialsliding mass. Slope model and a typical vertical slice

Figure 2. Slope with circular slip surface and subdividedslices.

Figure 3. Forces on a sample slice.

Figure 4. Slope with weight and seismic forces.

Figure 5. Dimensions for an individual slice.

for seismic stability analysis are shown in Figures 4and 5, respectively. The proposed Bishop's equationfor seismic slope analysis is as follow [57]:

FS =

Pni=1

hc:�li: cos�i+wi: tan'

cos�i+(sin�i: tan')=FS

iPni=1 wi: sin�i + (

Pni=1 kh:wi:di) =r

; (2)

where:kh Horizontal seismic coe�cient;

A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741 731

di The vertical distance between thecenter of the circle and the center ofgravity of the slice;

r Radius of circular slip surface.

It is evident that it would be too conservativeto select for this purpose the peak value of thestrong motion record, amax, because it lasts for avery short time and appears only once in the record.Therefore, instead of amax, a fraction of it, Kh =� � amax=g, is used, where kh is called the seismiccoe�cient [58]. Di�erent magnitudes of �, between0.2-0.65 have been proposed by various authors [59-61].

3. The JDRV method

Jointly distributed random variables method is ananalytical probabilistic method. In this method,probability density functions of independent inputvariables are expressed mathematically and jointedtogether by statistical relations. The adopted slopemodel integrated analytically to derive a mathematicalexpression of the density function of the factor ofsafety. Failure probability is obtained by multipleintegrals of that expression over the entire failuredomain.

4. Stochastic parameters

To account for the uncertainties in slope stability,four input parameters have been de�ned as stochasticvariables. The distribution curve of these stochasticparameters have been studied by numerous researchers(e.g., [62,63]). Generally normal distribution for soilparameters and exponential distribution for seismicparameters are accepted.

Therefore, internal friction angle ('), cohesion(c) and unit weight ( ) are modeled using a normalprobability density function and horizontal seismiccoe�cient (kh) which is considered to have exponentialprobability density function. The parameters relatedto geometry are regarded as constant parameters.The probability density functions for the stochasticparameters are as follows:

fc(c) =1

�cp

2�exp

�0:5

�c� cmean

�c

�2!

cmin � c � cmax; (3)

f'(') =1

�'p

2�exp

�0:5

�'� 'mean

�'

�2!

'min � ' � 'max; (4)

f ( ) =1

� p

2�exp

�0:5

� � mean

�2!

min � � max; (5)

fkh(kh)

=exp(�kh=khmean)

khmean : (exp(�khmin=khmean)�exp(�khmax=khmean))

khmin � kh � khmax ; (6)

where:8>>>>>>>>>><>>>>>>>>>>:

'min = 'mean � 4�''max = 'mean + 4�'cmin = cmean � 4�ccmax = cmean + 4�c min = mean � 4� man = mean + 4� khmin = 0:01

(7)

By considering the stochastic variables within the rangeof their mean plus or minus 4 times standard deviationas in Eq. (7), 99.994% of the area beneath the normaldensity curve is covered. For choosing the initialdata, the following conditions must be observed for soilparameters of slope:8><>:'mean � 4�' > 0

cmean � 4�c > 0 mean � 4� > 0

(8)

5. Slope stability stochastic analysis

For reliability assessment of safety factor of slope usingJDRV method, the suggested safety factor equationsof Bishop's method are rewritten into terms of K1 toK4 and u1 to u4 as given in Eqs. (A.1) to (A.14).These equations are presented in the Appendix. Theprobability density functions of safety factor for eachmethod are derived separately. The terms K1 to K4,are:8>>><>>>:

k1 = ck2 = tan'k3 = k4 = kh

(9)

and u1 to u4 are presented in Eqs. (A.2) and (A.11);derivations of these equations are presented in theAppendix.

Using the new form of input independent param-eters, the probability density functions of k1 to k4 havebeen obtained by Eqs. (3) to (6) directly. Therefore theprobability density functions of k1 to k4 can be writtenas:

732 A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741

fk1(k1) =1

�cp

2�exp

�0:5

�k1 � cmean

�c

�2!

cmin � k1 � cmax; (10)

fk2(k2) =1

(1 + k22)�'

p2�

exp

�0:5

�tan�1(k2)� 'mean

�'

�2!

tan'min � k2 � tan'max; (11)

fk3(k3) =1

� p

2�exp

�0:5

�k3 � mean

�2!

min � k3 � max; (12)

fk4(k4)=exp (�k4=k4mean)

k4mean :(exp(�k4min=k4mean)�exp(�k4max=k4mean))

khmin � kh � khmax : (13)

Using Eqs. (A.1) to (A.14), a computer program wasdeveloped (coded in MATLAB) to determine the prob-ability density functions of the safety factor based ontotal stresses without seismic loading and with seismicloading.

6. Illustrative example

To examine the accuracy of the proposed method indetermining the probability density function of thesafety factor, an illustrative example with arbitrary pa-rameter values is demonstrated. A typical slope shapefor this example is shown in Figure 6. The stochasticparameters with truncated normal and exponentialdistributions are given in Tables 1 and 2, respectively.Furthermore, the selected deterministic parameters aregiven in Table 3.

Figure 6. A typical slope.

Table 3. Deterministic parameters.

Height ofslope (m)

Horizontal lengthof slope (m)

w(kN/m3)

12.0 12.0 10.0

7. Reliability assessment of slope stability

Using the selected deterministic and mean of stochasticparameters, the slip surface with minimum safetyfactor is determined by PSO algorithm [64-66]. UsingEqs. (A.1) to (A.14), the pdf and cumulative densityfunction (cdf) curve of safety factor based on totalstresses without seismic loading and with seismic load-ing are determined. In order to verify the results ofthe presented methods with those of the MCs, the �nalprobability density functions for the safety factor aredetermined, using the same data by this simulationtechnique. For this purpose, 1,000,000 generations areused for the MCs.

The results are shown in Figures 7 to 10 forsimpli�ed Bishop's method. Figures 7 and 8 showthe pdf and cdf of the safety factor based on totalstresses, and Figures 9 and 10 show them for seismicslope stability analysis, respectively. It can be seenthat the obtained results using the proposed methodsare very close to those of the MCs.

To compare the pdf and cdf of safety factor oftwo stability analysis approaches (i.e. total stressand seismic), the prediction by proposed method areplotted in Figures 11 and 12, respectively. It can

Table 1. Stochastic parameters with truncated normal distribution.

Parameters Mean Standarddeviation

Minimum Maximum

c (kPa) 10.0 0:20�cmean 2.0 18.0' (degree) 28.0 0:10�'mean 16.0 40.0 (kN/m3) 18.0 0:05� mean 14.0 24.0

Table 2. Stochastic truncated exponential parameters.

Parameters � Minimum Maximum Mean Standarddeviation

kh 10 0.01 0.35 0.10 0.10

A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741 733

Figure 7. Probability density function of safety factorbased on total stresses.

Figure 8. Cumulative density function of safety factorbased on total stresses.

Figure 9. Probability density function of safety factor forseismic stability analysis.

Figure 10. Cumulative density function of safety factorfor seismic slope stability analysis.

Figure 11. Comparison of probability density functionsof safety factor of the methods.

Figure 12. Comparison of cumulative distributionfunction of safety factor of the methods.

734 A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741

Table 4. Comparison of reliability index of slope safetyfactor by two methods.

Method Total stressanalysis

Seismicanalysis

Reliability index (�) 0.9778 - 0.1759

be seen that the seismic analysis predicted upperprobability of failure with respect to analysis based ontotal stress.

The reliability indices of safety factor of thetwo methods are determined using their pdf and theequation [67].

� =E(FS)� 1�(FS)

; (14)

where � is the reliability index, E(FS) is the mean valueof safety factor and �(FS) is the standard deviation ofthe safety factor.

Reliability index of the two methods are given inTable 4. It can be seen the seismic stability analysisshows the lower reliability index or upper probability offailure with respect to stability analysis based on totalstress.

8. Sensitivity analysis

To evaluate the response of slope stability to changesin parameters, a sensitivity analysis is carried outusing the JDRV method. For this purpose, theseismic method is selected and the sensitivity analysishas been done. In the �rst approach, the meansof the four stochastic input parameters are increasedbased on their standard deviation (new mean = oldmean + 1.0�std). The results of probability densitycurves are shown in Figure 13. Additionally, thecumulative distribution curves are plotted in Figure 14.To evaluate the in uence of changes in each param-eter, the parameter is increased while the rangesof the other stochastic input parameters are keptconstant. Using Figure 14, the amounts of changesin probability of failure (FS=1), corresponding to1�std increase in the pdf of the input parameters,are calculated and given in Table 5. It can beseen that the internal friction angle of sliding surfaceis the most e�ective parameter in the stability ofslopes.

In the second approach, the mean of horizon-tal seismic coe�cient and internal friction angle are

Figure 13. Variation of probability density functions ofthe safety factor in sensitive analysis.

Figure 14. Variation of cumulative density functions ofthe safety factor in sensitive analysis.

changed while the means of the other stochastic inputparameters are kept constant. For this purpose,the mean of kh and ' has been varied between theminimum and maximum. In Figures 15 and 16 the

changes in probability of failure corresponding toincrease in the pdf of the friction angle and hori-zontal seismic coe�cient are shown, respectively. Asexpected, with increasing the friction angle, the prob-ability of failure decrease, however, with increasing thehorizontal seismic coe�cient, the probability of failureincrease.

Table 5. Changes in probability of failure corresponding to 1�std increase (shift rightward) in the pdf of input.

Stochasticparameter

Cohesion(c)

Frictionangle (')

Unitweight ( )

Seismiccoe�cient (kh)

Change (%) -30.36 -32.07 +8.38 +29.27

A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741 735

Figure 15. Sensitivity analysis of tan (') versusprobability of failure.

Figure 16. Sensitivity analysis of horizontal seismiccoe�cient versus probability of failure.

9. Parametric analysis

For further veri�cation of the proposed model, aparametric analysis is performed based on Bishop'sseismic method. The main goal is to determine howeach parameter a�ects the stability of slopes. Figure 17presents the predicted values of the probability offailure (instability) as a function of each parameterwhere others being constant. For this purpose, insix steps, the probability density function of eachstochastic input parameter is increased based on theirstandard deviation (new pdf = old pdf + 1/3�std).The results of the parametric analysis indicate that,as expected, the probability of failure (instability)continuously increases due to increasing in unit weightand horizontal seismic coe�cient. The probability offailure decreases with increase in internal friction angle

Figure 17. Parametric analysis of probability of failurewith respect to change of probability density functions ofinput parameters.

and cohesion. Also it can be seen that the curveof change in internal friction angle with respect toprobability of failure has a steeper slope than othersindicating that it is the most in uential parameter.

10. Probabilistic model

To develop probabilistic slope stability models basedon total stresses without seismic loading and withseismic loading by JDRV, the following procedures werefollowed:

� Several random series of input parameters, c; ' and (including cross correlation -0.5 between c and ')were considered as mean value.

� A �nite slope with arbitrary L = 10 m was selected.� The critical slip surface for each data series has been

obtained by the PSO algorithm for the slope.� The uncertainty in the input parameters used in the

calculation of safety factor of slope for each series ofdatabase was assessed (including cross correlation-0.5 between c and ').

� The cumulative distribution function of each dataseries was determined using the JDRV method asdescribed in Section 7.

� The probability of failure was computed from thecumulative distribution function for each series ofdata.

� The safety factor of each data series was calculatedusing the deterministic approach described in Sec-tion 3.

� The probability of failure (Pf ) and the related factorof safety from two previous steps were plotted with

736 A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741

Table 6. Parameters which used to probabilistic models evaluation.

Parameters Cohesion (c)(kPa)

Friction angle (')(degree)

Unit weight ( )(kN/m3)

Slope angle (�)(degree)

Horizontal length (L)(m)

Values 12.0 35.0 17.0 50.0 10.0

Figure 18. Probability of failure of slopes by di�erentangles based on total stresses stability analysis.

Figure 19. Seismic slope stability analysis probability offailure by di�erent angles.

respect to each other for all data series (as shown inFigures 18 and 19).

� This procedure is repeated for �=40, 50, 60 and 70.The results are shown in Figures 18 and 19.

� The probabilistic slope stability models was devel-oped using MATLAB curve �tting toolbox using alldata. The probabilistic models have the followingform:

Model based on total stresses slope stability anal-ysis:

Table 7. Determined probability of failures by proposedmodels.

Method Factor ofsafety

Probabilityof failure

Total stress analysis 1.31 0.0114Seismic analysis 1.14 0.2041

Table 8. Target reliability indices [68].

Expectedperformance

level

Reliabilityindex(�)

Probability offailure(Pf)

High 5.0 0.30 E -6.0Good 4.0 0.30 E -4.0

Above average 3.0 0.10 E -2.0Below average 2.5 0.60 E -2.0

Poor 2.0 0.23 E -1.0Unsatisfactory 1.5 0.07

Hazardous 1.0 0.16

Pf (FS) =1

1 + exp (14:34(FS� 1:00)): (15)

Seismic slope stability analysis model:

Pf (FS =1

1 + exp (9:72(FS� 1:00)): (16)

In Eqs. (15) and (16), FS is computed using determin-istic methods.

To evaluate the proposed probabilistic models,an illustrative example is presented. The selectedparameters are given in Table 6. The deterministicminimum safety factors are calculated using Eqs. (1)and (2) and PSO algorithm. The probabilities of failureare determined by substituting appropriate calculatedsafety factors in Eqs. (15) and (16). The results aregiven in Table 7. It can be seen that the values of Pffor seismic slope stability is greater than stability ofslope based on total stresses. Table 8 indicates thatincluding seismic force causes the slope condition tochange from below average to hazardous level.

The proposed models are typical which have somelimitations such as:

� The soil is assumed wet and the in uence of watertable and saturation is neglected.

� The models are proposed for �nite slopes.� Due to using Bishop's method, the sliding surface is

assumed to be circular.

A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741 737

� In order to develop the model, a �nite slope witharbitrary horizontal length of 10 m was selected.Therefore, the proposed model is recommended forhorizontal length of 10 m and any arbitrary heights.

11. Conclusion

In this paper, the jointly distributed random variablesmethod was used to develop a probabilistic modelof seismic slope stability based on Bishop's method.The selected stochastic parameters are internal frictionangle, cohesion and unit weight of soil, which aremodeled using a truncated normal probability densityfunction and the horizontal seismic coe�cient which isconsidered to have a truncated exponential probabilitydensity function. The parameters related to geometry,height and angle of slope were regarded as constantparameters.

The safety factor relationships for probabilitydensity functions of the Bishop's method were derivedanalytically for total stress and seismic conditions andfor an arbitrary slope. For this purpose, �rst using themean value of the stochastic parameters, the criticalsurface with the minimum factor of safety was deter-mined by the PSO algorithm. Then, by considering thesoil parameters' uncertainty, the probability densityfunctions of safety factor of the methods were obtainedby JDRV. The results showed that the pdf has a nearlynormal distribution and is compared favorably with theoutput of MCs. However, the required time to reachthe same probability of failure is greater for the MCsthan the JDRV method.

Sensitivity and parametric analyses were con-ducted to verify the results. It is shown that the frictionangle is the most in uential parameter in stability ofslopes. At the end two probabilistic models for theseismic and total stresses methods are proposed.

References

1. Seed, H.B. \Considerations in the earthquake resistantdesign of earth and rock �ll dams", Geotechnique.,29(3), pp. 213-263 (1979).

2. Newmark, N.M. \E�ects of earthquakes on damsand embankments", Geotechnique., 15(2), pp. 139-160(1965).

3. Jingshan, B.O., Guodong, X.U. and Liping J. \Seismicresponse and dynamic stability analysis of soil slopes",Earthquake Engineering and Engineering Vibration.,21(2), pp. 116-120 (2001).

4. Siyahi, B.G. \A pseudo-static stability analysis innormally consolidated soil slopes subjected to earth-quake", Teknik Dergi/Technical Journal of TurkishChamber of Civil Engineers., 9, pp. 457-461 (1998).

5. Morgenstern, N.R. \Managing risk in geotechnicalengineering", Proc., 10th Panamerican Conference on

Soil Mechanics and Foundation Engineering, 4, pp.102-126 (1995).

6. Christian, J.T., Ladd, C. and Baecher, G.B. \Relia-bility applied to slope stability analysis", Journal ofthe Geotechnical Engineering Division ASCE, 12, pp.2180-2207 (1994).

7. Gri�ths, D.V. and Fenton, G.A., Probabilistic Methodsin Geotechnical Engineering, Springer Wien, NewYork(2007).

8. Garevski, M., Zugic, Z. and Sesov, V. \Advancedseismic slope stability analysis", Landslides., pp. 1-8(2012).

9. Ranalli, M., Gottardi, G., Medina-Cetina, Z. andNadim, F. \Uncertainty quanti�cation in the calibra-tion of a dynamic viscoplastic model of slow slopemovements", Landslides., 7(1), pp. 31-41 (2010).

10. Whitman, R.V. \Organizing and evaluating un-certainty in geotechnical engineering", Journal ofGeotechnical and Geoenvironmental Engineering.,126(7), pp. 583-593 (2000).

11. Sowers, G.S. \The human factor in failure", Civil Eng.,ASCE, pp. 72-73 (1991).

12. Hoel, P.G., Port, S.C. and Stone, C.J., Introduction toProbability Theory, Houghton Mi�in Boston (1971).

13. Stirzaker, D., Probability and Random Variables: ABeginner's Guide, Cambridge University Press (1997).

14. Tijms, H., Understanding Probability: Chance Rules inEveryday Life, Cambridge University Press (2007).

15. Hasofer, A.M. and Lind, N.C. \An exact and invariant�rst-order reliability format", Journal of the Engineer-ing Mechanics Division, ASCE, 100(EM1), pp. 111-121 (1974).

16. Low, B.K., Gilbert, R.B. and Wright, S.G. \Slopereliability analysis using generalized method of slices",Journal of Geotechnical and Geoenvironmental Engi-neering, 124(4), pp. 350-362 (1998).

17. Low, B.K. and Tang, W.H. \E�cient spreadsheetalgorithm for �rst-order reliability method", Journalof Engineering Mechanics, 133(12), pp. 1378-1387(2007).

18. Cho, S.E. \First-order reliability analysis of slope con-sidering multiple failure modes", Engineering Geology.,154, pp. 98-105 (2013).

19. Hong, H. and Roh, G. \Reliability evaluation of earthslopes", Journal of Geotechnical and Geoenvironmen-tal Engineering, 134(12), pp. 1700-1705 (2008).

20. Wu, X.Z. \Probabilistic slope stability analysis by acopula-based sampling method", Comput Geosci, 17,pp. 739-755 (2013).

21. Johari, A. and Javadi, A.A. \Reliability assessmentof in�nite slope stability using the jointly distributedrandom variables method", Scientia Iranica, 19(3), pp.423-429 (2012).

22. Johari, A., Fazeli, A. and Javadi, A. \An investigationinto application of jointly distributed random variablesmethod in reliability assessment of rock slope stabil-ity", Computers and Geotechnics, 47, pp. 42-47 (2013).

738 A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741

23. Johari, A. and Khodaparast, A.R. \Analytical reliabil-ity assessment of liquefaction potential based on conepenetration test results", Scientia Iranica, 21(5), pp.1549-1565 (2014).

24. Ang, A.H.S. and Tang, W., Probability Concepts inEngineering Planning and Design, Volume I, BasicPrinciples, John Wiley and Sons, New York, USA(1984).

25. Rosenblueth, E. \Point estimates for probability mo-ments", Proceedings of the National Academy of Sci-ences, 72(10), pp. 3812-3814 (1975).

26. Li, K.S. \A point estimate method for calculating thereliability index of slope", The 6th Australian-NewZealand Conf. on Geomech., Christchurch., pp. 448-451 (1992).

27. Thornton, S. \Probability calculation for slope stabil-ity", Computer Methods in Advanced Geomechanics,pp. 2505-2509 (1994).

28. Abbaszadeh, M., Shahriar, K., Sharifzadeh, M. andHeydari, M. \Uncertainty and reliability analysis ap-plied to slope stability: A case study from sungun cop-per mine", Geotechnical and Geological Engineering,29(4), pp. 581-596 (2011).

29. Wang, J.P. and Huang, D. \RosenPoint: A microsoftexcel-based program for the Rosenblueth point esti-mate method and an application in slope stabilityanalysis", Computers & Geosciences, 48, pp. 239-243(2012).

30. Hassan, A.M. and Wol�, T.F. \Search algorithm forminimum reliability index of earth slopes", Journalof Geotechnical and Geoenvironmental Engineering,125(4), pp. 301-308 (1999).

31. Malkawi H., A.I., Hassan, W.F. and Abdulla, F.A.\Uncertainty and reliability analysis applied to slopestability", Structural Safety, 22, pp. 161-187 (2000).

32. Giasi, C.I., Masi, P. and Cherubini, C. \Probabilisticand fuzzy reliability analysis of a sample slope nearAliano", Engineering Geology, 67(3-4), pp. 391-402(2003).

33. D�uzg�un, H.S.B. and �Ozdemir, A. \Landslide riskassessment and management by decision analyticalprocedure for Derek�oy, Konya, Turkey", Natural Haz-ards, 39(2), pp. 245-263 (2006).

34. Metropolis, N. and Ulam, S. \The Monte Carlomethod", Journal of the American statistical associ-ation, 44, pp. 335-341 (1949).

35. Tobutt, D.C. \Monte Carlo simulation methods forslope stability", Computers & Geosciences, 8(2), pp.199-208 (1982).

36. El-Ramly, H., Morgenstern, N.R. and Cruden, D.M.\Probabilistic slope stability analysis for practice",Canadian Geotechnical Journal, 39, pp. 665-683(2002).

37. Re�ce, A. and Capolongo, D. \Probabilistic modelingof uncertainties in earthquake-induced landslide haz-ard assessment", Computers & Geosciences, 28(6), pp.735-749 (2002).

38. Zhou, G., Esaki, T., Mitani, Y., Xie, M. and Mori, J.\Spatial probabilistic modeling of slope failure usingan integrated GIS Monte Carlo simulation approach",Engineering Geology, 68(3-4), pp. 373-386 (2003).

39. Xie, M., Esaki, T. and Zhou, G. \GIS-based prob-abilistic mapping of landslide hazard using a three-dimensional deterministic model", Natural Hazards,33(2), pp. 265-282 (2004).

40. Park, H.J., West, T.R. and Woo, I. \Probabilisticanalysis of rock slope stability and random propertiesof discontinuity parameters, Interstate Highway 40,Western North Carolina, USA", Engineering Geology,79(3-4), pp. 230-250 (2005).

41. Cho, S.E. \E�ects of spatial variability of soil proper-ties on slope stability", Engineering Geology, 92(3-4),pp. 97-109 (2007).

42. Wang, H., Wang, G., Wang, F., Sassa, K. and Chen,Y. \Probabilistic modeling of seismically triggeredlandslides using Monte Carlo simulations", Landslides,5(4), pp. 387-395 (2008).

43. Cho, S.E. \Probabilistic assessment of slope stabilitythat considers the spatial variability of soil properties",Journal of Geotechnical and Geoenvironmental Engi-neering, 136, pp. 975-984 (2009).

44. Tatone, B.S.A. and Grasselli, G. \ROCKTOPPLE:A spreadsheet-based program for probabilistic block-toppling analysis", Computers & Geosciences, 36(1),pp. 98-114 (2010).

45. Chen, Q. and Chang, L.Y. \Probabilistic slope sta-bility analysis of a 300 m high embankment dam",ASCE Conf. GeoRisk: Geotechnical Risk Assessmentand Management, 224, pp. 452-459 (2011).

46. Wang, Y., Cao, Z. and Au, S.K. \Practical reliabilityanalysis of slope stability by advanced Monte Carlosimulations in a spreadsheet", Canadian GeotechnicalJournal, 48(1), pp. 162-172 (2011).

47. Li, S., Zhao, H.B. and Ru, Z. \Slope reliability anal-ysis by updated support vector machine and MonteCarlo simulation", Natural Hazards, 65(1), pp. 707-722 (2013).

48. Gri�ths, D.V. and Fenton, G.A. \Probabilisticslope stability analysis by �nite elements", Journalof Geotechnical and Geoenvironmental Engineering,130(5), pp. 507-518 (2004).

49. Xu, B. and Low, B.K. \Probabilistic stability analysesof embankments based on �nite-element method",Journal of Geotechnical and Geoenvironmental Engi-neering, 132(11), pp. 1444-1454 (2006).

50. Hammah, R.E., Yacoub, T.E. and Curran, J.H. \Prob-abilistic slope analysis with the �nite element method",The 43rd US Rock Mechanics Symposium and 4thU.S.-Canada Rock Mechanics Symposium, Asheville,North Carolina, USA, ARMA 09-149 (2008).

51. Gri�ths, D.V., Huang, J. and Fenton, G.A. \In uenceof spatial variability on slope reliability using 2-Drandom �elds", Journal of Geotechnical and Geoenvi-ronmental Engineering, 135(10), pp. 1367-1378 (2009).

A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741 739

52. Janbu, N. \Earth pressures and bearing capacitycalculations by generalized procedure of slices", Pro-ceedings of the Fourth International Conference on SoilMechanics and Foundation Engineering, 2, pp. 207-212(1957).

53. Bishop, A.W. \The use of the slip circle in thestability analysis of slopes", Geotechnique, 5(1), pp.7-17 (1955).

54. Spencer, E.A. \A method of analysis of the stabilityof embankments assuming parallel inter slice forces",Geotechnique, 17(1), pp. 11-26 (1967).

55. Morgenstern, N.R. and Price, V.E. \The analysis of thestability of general slip surfaces", Geotechnique, 15(1),pp. 79-93 (1965).

56. Fredlund, D.G. and Krahn, J. \Comparison of slopestability methods of analysis", Canadian GeotechnicalJournal, 14(3), pp. 429-439 (1977).

57. Duncan, J.M. and Wright, S.G., Soil Strength andSlope Stability, John Wiley & Sons, Inc., Hoboken,New Jersey (2005).

58. Matasovic, N. \Selection of method for seismic slopestability analysis", Proc., 2nd Int. Conf. on RecentAdvances in Geotechnical Earthquake Engineering andSoil Dynamics, pp. 1057-1062 (1991).

59. Marcuson, W.F. \Earth dam and stability of slope un-der dynamic loads", Moderators Report, Proc. of Inter-national Conference on Recent Advances in Geotech-nical Earthquake Engineering and Soil Dynamic, pp.1175-1182 (1981).

60. Matsuo, M., Itabashi, K. and Sasaki, Y. \Study ona seismicity of earth structures by inverse analysis ofactual cases", Proc. of JSCE, Japan, 343, pp. 25-33(1984).

61. Taniguchi, E. and Sasaki, Y. \Back analysis oflandslide due to the Naganoken Seibu earthquakeof September 14, 1984", Proc. of 11th InternationalConference on Soil Mechanics and Foundation Engi-neering, Sanfrancisco. pp. 1-55 (1985).

62. Lumb, P. \The variability of natural soils", CanadianGeotech J., 3(2), pp.74-97 (1996).

63. Schultze, E. \Frequency distributions and correlationsof soil properties", Proceedings of the First Inter-national Conference on Application of Statistics andProbability to Soil and Structural Engineering, pp. 371-387 (1971).

64. Kennedy, J. and Eberhart, R. \Particle swarm opti-mization", In: Proceeding of the IEEE InternationalConference on Neural Networks, Perth, Australia 1942-8 (1995).

65. Cheng, Y.M., Li, L., Chi, S.C. and Wei, W.B. \Particleswarm optimization algorithm for the location of thecritical non-circular failure surface in two-dimensionalslope stability analysis", Computers and Geotechnics,34, pp. 92-103 (2007).

66. Erzin, Y. and Cetin, T. \The use of neural networksfor the prediction of the critical factor of safety of

an arti�cial slope subjected to earthquake forces",Scientia Iranica, Trans. A,, 19(2), pp. 188-194 (2012).

67. Abdallah, I., Malkawi, H., Waleed, F.H. and Fayez,A.A. \Uncertainty and reliability analysis applied toslope stability", Structural Safety, 22, pp. 161-187(2000).

68. U.S. Army Corps of Engineers., Risk-Based Analysisin Geotechnical Engineering for Support of PlanningStudies (1999).

Appendix

Derivations of mathematical probability density func-tions of FS based on total stresses without seismicloading and with seismic loading have been presentedin this appendix.

Slope stability analysis based on total stresses

The simpli�ed Bishop's relationship can be rewrittenby changed variables:

FS =

Pni=1

hk1:�li: cos�i+k3:bi:hi:k2

cos�i+(sin�i:k2)=FS

iPni=1 k3:bi:hi: sin�i

: (A.1)

For developing the probability density function ofFS, the variables u1, u2 and u3 are selected as anindependent arbitrary function of k1, k2 and k3 asfollows:8>>>>>><>>>>>>:

u1 = g1 (k1; k2; k3) = FS

=Pni=1

hk1:�li: cos�i+k3:bi:hi:k2

cos�i+(sin�i:k2)=FS

iPni=1 k3:bi:hi: sin�i

u2 = g2 (k1; k2; k3) = k2

u3 = g3 (k1; k2; k3) = k3

(A.2)

Mapping from (k1; k2; k3) to (u1; u2; u3) is one-to-one,Hence, the functions of k1, k2 and k3 can be writtenbased on u1, u2 and u3 as the following form:8>>>>>>><>>>>>>>:

k1 = h1 (u1; u2; u3) = c

=u1:Pni=1(u3:bi:hi: sin�i)�Pn

i=1

hu3:bi:hi:u2

cos�i+(sin�i:u2)=u1

iPni=1

h�li: cos�i

cos�i+(sin�i:u2)=u1

ik2 = h2 (u1; u2; u3) = u2

k3 = h3 (u1; u2; u3) = u3

(A.3)

The probability density function of safety factor can beobtained as follow:

fXi(xi) =ZZRXi

� � �ZfX1;X2;��� ;Xn (x1; x2; :::; xn)

dx1dx2:::dxi�1dxi+1:::dxn; (A.4)

740 A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741

where:

fX1;X2;:::;Xn (x1; x2; :::; xn) = jJ(x1; x2; :::; xn)j

:fX1;X2;:::;Xn

�h1(x1; x2; :::; xn);

:::; hn(x1; x2; :::; xn)�; (A.5)

and:

fX1;X2;:::;Xn (x1; x2; :::; xn) = fX1(x1)

:fX2(x2):::fXn(xn); (A.6)

J (u1; u2; u3) =

��������@k1@u1

@k1@u2

@k1@u3

@k2@u1

@k2@u2

@k2@u3

@k3@u1

@k3@u2

@k3@u3

�������� : (A.7)

Eq. (A.8) is shown in Box I.

B1 = cos�i + (sin�i:u2) =u1: (A.9)

Seismic slope stability analysis

The simpli�ed Bishop's relationship can be rewrittenby changed variables:

FS=

Pni=1

hk1:�li: cos�i+k3:bi:hi:k2

cos�i+(sin�i:k2)=FS

inPi=1

k3:bi:hi: sin�i+�

nPi=1

k4:k3:bi:hi:di�=r; (A.10)

8>>>>>>>>><>>>>>>>>>:

u1 = g1 (k1; k2; k3; k4) = FS

=Pni=1

hk1:�li: cos�i+k3:bi:hi:k2

cos�i+(sin�i:k2)=FS

iPni=1 k3:bi:hi: sin�i+(Pn

i=1 k4:k3:bi:hi:di)=r

u2 = g2 (k1; k2; k3; k4) = k2

u3 = g3 (k1; k2; k3; k4) = k3

u4 = g4 (k1; k2; k3; k4) = k4

(A.11)

Eqs. (A.12) and (A.13) are shown in Box II.

B1 = cos�i + (sin�i:u2)=u1: (A.14)

J =

Pni=1 u3:bi:hi: sin�i �Pn

i=1

hu3:bi:hi: sin�i:u2

2u2

1:(B1)2

iPni=1

h�li: cos�i

B1

i+

�Pni=1

h�li: cos�i: sin�i:u2

u21:(B1)2

i�� �Pni=1

hu3:bi:hi:u2

B1

i� u1:Pni=1(u3:bi:hi: sin�i)

��Pni=1

h�li: cos�i

B1

i�2 (A.8)

Box I

8>>>>>>>><>>>>>>>>:k1 = h1 (u1; u2; u3; u4) = c =

u1:(Pni=1(u3;bi;hi: sin�i)+(

Pni=1 u4:u3:bi:hi:di)=r)�Pn

i=1

hu3:bi:hi:u2

cos�i+(sin�i:u2)=u1

iPni=1

h�li: cos�i

cos�i+(sin�i:u2)=u1

ik2 = h2 (u1; u2; u3; u4) = u2

k3 = h3 (u1; u2; u3; u4) = u3

k4 = h4 (u1; u2; u3; u4) = u4

(A.12)

J =

Pni=1 u3:bi:hi: sin�i + (

Pni=1 u4:u3:bi:hi:di) =r �Pn

i=1

hu3:bi:hi: sin�i:u2

2u2

1:(B1)2

iPni=1

h�li: cos�i

B1

i+

�Pni=1

h�li: cos�i: sin�i:u2

u21:(B1)2

i�� �Pni=1

hu3:bi:hi:u2

B1

i� u1: (Pni=1(u3:bi:hi: sin�i) + (

Pni=1 u4:u3:bi:hi:di) =r)

��Pni=1

h�li: cos�i

B1

i�2(A.13)

Box II

A. Johari et al./Scientia Iranica, Transactions A: Civil Engineering 22 (2015) 728{741 741

Biographies

Ali Johari obtained his BS, MS and PhD degrees in1995, 1999 and 2006, respectively, from Shiraz Univer-sity, Iran, where he is currently Assistant Professor inthe Civil and Environmental Engineering Department.He was a Post-Doctoral Researcher at Exeter Univer-sity in 2008, where he is also a member of the researchsta� of the Computational Geomechanics Group. Hisresearch interests include unsaturated soil mechanics,application of intelligent systems in geotechnical en-gineering, probabilistic models and reliability assess-ment. He has also consulted and supervised numerousgeotechnical projects.

Sobhan Mousavi was born in Behbahan, Iran, in

1989. He received his BS degree in civil Engineeringfrom Yasuj University, Yasuj, Iran, in 2012. He isstudying geotechnical engineering at Shiraz Univer-sity of Technology at MS degree. His current maininterests of research are about soil slope stabilityanalysis and reliability analysis in geotechnical engi-neering.

Ahmad Hooshmand Nejad was born in 1988 inShiraz, Iran. He graduated from Shahid BahonarUniversity of Kerman in 2011 with a BS degree inCivil Engineering and, currently, he is furthering hisgeotechnical engineering education at Shiraz Universityof Technology as an MS student. His main researchinterests include: Arti�cial intelligence and reliabilityanalysis in geotechnical engineering.