aashto ve awards showcasesp.design.transportation.org/documents/tc value...ve awards showcase aashto...
TRANSCRIPT
AASHTO VE Awards Showcase
AASHTO VE AWARD CONSTRUCTION
National Value Engineering Honorable Mention
During Construction
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
MoDOT & Pace Construction
US 65 North Bound Farmer Creek Bridge Replacement
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
National Value Engineering Award
During Construction
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Pennsylvania Department of Transportation Joseph B. Fay Company
US 219 Somerset to Meyersdale
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
US 219 Corridor – South of Somerset • 1970’s: Portion of the ROW purchased • Early 1990’s: Studies from I-68 (MD) to Turnpike • Late 1990’s: Meyersdale Bypass Constructed • Early 2000’s” Start of Preliminary Engineering for
Section 020 (and Section 019)
Section 020 Meyersdale to Somerset • 2004: Draft Environmental Impact Statement (DEIS)
(4 Alternatives) • 2005: Final Environmental Impact Statement (FEIS) • 2006: Record of Decision (FHWA) • 2012: Right-of-Way Clearance • 2012: MAP-21 (100% Federal Funding) • 2013: Permits Issued & Project Advertised • 2013: Start Construction of Section 20A & 20B • 2014: Start Construction of Section 20C
Local U.S. 6219 History
US 219 New Highway Construction
11 miles of 4-lane (limited access) highway • Mass Excavation = 12 million CY • Drainage Pipe / Inlets = 17.5 miles • Water Retention Basins = 30 ea • Box Culvert Bridges = 4 ea • Dual Span Bridges = 2 ea
Proposed Alignment Shift
• Constructability improvement & project time savings • Large reduction in excavation
Comparison of Design to VE
• Old design required mass toe bench excavation & fill materials; new design builds road on top of slope.
• Eliminated a tensor wall which could introduce settlement. • Reduction in future maintenance costs.
Value Engineering Concept
Savings: $9,072,118 (8.2% of entire project)
Original Plan: Reinforced Soil Slope
Change: Roadway alignment shift, eliminating need for slope
South End of VE – Looking North
North End of VE – Looking South
Other Benefits • 650 lf less streams impacted • 0.08 less acres of wetlands impacted • 6.2 less acres of impervious area due to decreased
rock slope area. • 6.2 acres remains forested for wildlife habitat. • Total – 4.6 less acres of disturbance
Challenges 1) Buy In – Expediting a preliminary design concept to
obtain approval from affiliated Agencies.
Key Agencies included: • USEPA – United States Environmental Protection Agency • USACE – United States Army Corps of Engineers • USF&WS – United States Fish & Wildlife Service • PADEP – Pennsylvania Dept. of Environmental Protection • PF&BC – Pennsylvania Fish & Boat Commission • PGC – Pennsylvania Game Commission • DCNR – PA Dept. of Conservation & Natural Resources • SCCD – Somerset County Conservation District • PHMC - PA Historic & Museum Commission Cultural Clearance • Penelec, Somerset Rural Electric & Wilson Creek Wind, LLC
Challenges
2) Time - Coordination of the engineering design with the NPDES Permit submittal, review and approval process. • NPDES review and approval process took nearly 4 months of
suspense prior to reaching approval.
3) Expedited Engineering - Getting the engineering to a point of completion in order to make necessary property acquisitions. • All efforts were seamlessly orchestrated not to impede with the
overall construction completion date goals.
Challenges 4) Engineering Ownership – With many Engineers and
Surveyors involved with the process, it was a challenge to determine who was responsible for final engineering seals on final drawings for construction. • District 9 and Contractor Executives provided necessary support to
achieve determining factors that established boundaries that were acceptable to all parties.
5) Property Acquisition – Pennsylvania Department of Transportation attained 2.85 acres of property that made the VECP reality and allowed the process to move forward.
Key to Overcome Challenges
Partnering Amongst all Parties!
Tools used to Achieve Complete Success:
1. Accountability Schedule: CPM Format
2. Weekly Partnering & Accountability Reviews: Partnering meetings were mandatory and held on a weekly basis to assure Team effort.
Congrats to our VECP Team! 2015 Award of Excellence
AASHTO VE AWARD IMPROVED PROCESS
National Value Engineering Honorable Mention
Improved Process
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Florida Department of Transportation District Four
Project Development and Environment Process Improvement
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
National Value Engineering Honorable Mention
Improved Process
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
California Department of Transportation
Unbalanced Bid Analysis
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
National Value Engineering Award
Improved Process
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Ontario Ministry of Transportation Snow Removal Equipment Visibility
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
October 29, 2003 Provincial Highways Management Division 22
Ministry of Transportation Ministry of Transportation
Winter Equipment Visibility – the issue • Snow removal equipment often operates under the most adverse
conditions when conspicuity is most important
October 29, 2003 Provincial Highways Management Division 23
Ministry of Transportation Ministry of Transportation
Different Contractors have different markings.
October 29, 2003 Provincial Highways Management Division 24
Ministry of Transportation
New Technology – Tow Plows & LED lights
October 29, 2003 Provincial Highways Management Division 25
Ministry of Transportation
VE Recommendations
• Yellow-green on black checkerboard
October 29, 2003 Provincial Highways Management Division 26
Ministry of Transportation
Airfoils to Keep Snow off Back/Lights
October 29, 2003 Provincial Highways Management Division 27
Ministry of Transportation
Lighting on End of Tow Plow and Wing
October 29, 2003 Provincial Highways Management Division 28
Ministry of Transportation
Field Trials - Rear Panel Colours & Light Patterns
• Initial Test – Rear Panel Colours (9 variations)
• 2nd Test – Lighting Configurations • Closed road – 12 test subjects
October 29, 2003 Provincial Highways Management Division 29
Ministry of Transportation
. 3rd Test - On-Road Testing • Compared existing to new lighting
• Daytime and nighttime (February) • Winter conditions (Huntsville) • 6 test subjects
October 29, 2003 Provincial Highways Management Division 30
Ministry of Transportation
New Equipment Standards Issued in 2014
October 29, 2003 Provincial Highways Management Division 31
Ministry of Transportation
VE Study Process • Learn how we got contractors, technical
specialists, manufacturers and others to help us develop new standards in record breaking time.
• Education Track • Wednesday 3:30-4:30 p.m. • VE product Improvements
AASHTO VE AWARD IMPROVED PERFORMANCE
National Value Engineering Honorable Mention
Improved Performance
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Minnesota Department of Transportation I-90 Pavement Rehab
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
National Value Engineering Award
Improved Performance
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Montana Department of Transportation
North of Kiowa-North and Kiowa Jct. North & South
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
NORTH OF KIOWA – NORTH KIOWA JCT NORTH & SOUTH
2015 AASHTO VE CONFERENCE PRESENTATION
IMPROVED PERFORMANCE
OVERVIEW • LOCATION:
– US 89: Browning to Hudson Bay Divide corridor – Located on the Blackfeet Indian Reservation – Connected to the majestic Glacier National Park
• PURPOSE AND NEED: – “Build a roadway that is a pleasure to drive and give it a
“look and feel” – a theme – that provides a strong identity for the Blackfeet Nation and complements Glacier National Park. Give people a reason to stop, to enjoy the area, and to want to come back.” (Quote from the Final Environmental Impact Statement)
• PROPOSED SCOPE: – 10.3 MILE – RECONSTRUCT
• REALIGNMENT • 2 STRUCTURES
– ORIGINAL PROJECT COST - $31.46 Million
OVERVIEW - continued • CONSTRAINTS:
– Environmental • Wetlands • Historic Blackfeet Trail • Cultural Sites and Tribal Cloth Offering Sites • Threatened and Endangered Species (Grizzly Bear, Canada
Lynx, etc.) • Bridge locations
– Timing restrictions • Short construction season due to extreme weather • Wildlife range activities (Grizzly Bear, Canada Lynx, etc.)
– Constructability/staged construction/variable soils – Tourism – Mountainous Terrain
SHORT CONSTRUCTION SEASON
VE/VA STUDY RECOMMENDATIONS
#1 – Move special borrow out of typical section #2 – Remove/reduce special borrow under surfacing section #3 – Use W740 bridge rail #4 – Optimize bridge location & length #5 – Omit plant mix and waterproof membrane on bridges #6 – Alignment adjustments: 610 to 640 and grade adjustments: 550 to 640 #7 – Typical section – reduce 10 foot 6:1 to 6 foot
Proposed Typical Section No. 1
Original Typical Section No. 1
RECOMMENDATION #1 & 2 Move Special Borrow Out of Typical Section/
Remove/Reduce Special Borrow Under Surfacing Section
Alignment adjustment station 610 to 640
RECOMMENDATION #6 Alignment Adjustments: 610 to 640 and Grade Adjustments: 550 to 640
Yellow – Existing PTW Black – Current Design Red – VA Proposal
The Study Team applied the principals and practices of the Value Engineering Job Plan which resulted in the following improved performance and cost reduction benefits:
• Enhanced Operational Performance • Reduced Environmental Impacts • Reduced Construction Impacts • Expedited Project Delivery • Improved Constructability
Total Potential Cost Savings of $7.26 million or 23.1 % of the original project cost.
IMPROVED PERFORMANCE SUMMARY VA STUDY RESULTED IN:
– More Efficient Typical Section • Reduced project costs • Reduced excavation and borrow quantities
– Smaller Footprint • Greatly reduced wetland and endangered species habitat
impacts • Improved horizontal and vertical alignments
– Finished Roadway • Safe, scenic, and educational with improved drivability • Optimized bridge locations • Sacred Cloth Offerings and other Tribal sites will not be
disturbed • 30% reduction in construction time
AASHTO VE AWARD PRE-CONSTRUCTION ENGINEERING
(<$25 MILLION)
National Value Engineering Honorable Mention
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Washington Department of Transportation
SR 124 Monument Rd/RR Xing – Construct Bridge
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
Pre-Construction Engineering
less than $25 million
National Value Engineering Award
Pre-Construction Engineering
less than $25 million
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Montana Department of Transportation
Flathead River – 3 Miles North West of Big Fork
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
FLATHEAD RIVER BRIDGE 3 MILES NW BIGFORK
2015 AASHTO VE CONFERENCE PRESENTATION
PRE-CONSTRUCTION ENGINEERING (<$25M)
OVERVIEW • LOCATION:
– Northwestern Montana near the towns of Big Fork and Somers
• Located over the Flathead River • Transition between flat terrain and rolling hills
• PURPOSE AND NEED: – Improve safety and mobility by replacing the functionally
obsolete structure and the bridge approaches – The structure ranked high for seismic retrofit because of
its fracture critical two-girder system
OVERVIEW - continued
• PROPOSED SCOPE: – New alignment – Construct new 736 foot, 3 span bridge – Complex 1.4 mile reconstruction project
• ORIGINAL PROJECT COST = $24.3M
OVERVIEW - continued
• CONSTRAINTS: – 4(f) Fish Wildlife and Parks – fishing access site – Environmental issues (wetlands, bull trout, etc.) – High risk Right of Way acquisition
• CONSIDERATIONS: – New offset alignment – Liquefaction may occur during a high seismic event at
the end bents – Deep Water Foundation constructability – Flathead County Master Trail Plan
VE/VA STUDY RECOMMENDATIONS
• 1A - New Alignment or Existing - Evaluate Bridge Foundation Types
• 1B - New Alignment – Evaluate Ground Improvements Beneath Approach Embankments
• 2A - Existing Alignment – With Detour Bridge During Construction
• 2B - Existing Alignment – With Road Closure During Construction
• 3A - Either Alignment – Eliminate Shared Use Path • 3B - Either Alignment – Design For Future Expansion
For Shared Use Path
RECOMMENDATION #1A – New Alignment - Evaluate Bridge Foundation Types
Other Options • 3-72” Diameter Piles • 2 Rows of 5-48”
Diameter Piles for additional stiffness
• 2-96” Diameter Piles for accelerated construction
• Must meet “no rise” requirement
RIVER BOTTOM CROSS-SECTION
Recommendation #1B – New Alignment – Evaluate Ground Improvements Beneath Approach
Embankments
Improve Soil Properties Using Compaction Grouting Original Design: Stone columns used to mitigate potential for liquefaction and lateral spreading at both abutments. Proposed Change: Improve the soil properties at both abutments using compaction grouting. Justification: Compaction grouting improves soil density and increases soil strength. Anticipated reduced mobilization cost and less equipment, can limit treatment to target zone in soil profile, can stage grout pattern/ hole layout as needed. Decreased construction time. POTENTIAL COST SAVINGS = $0.7M
Recommendation #3B – Either Alignment – Design For Future Expansion For Shared Use Path
• Build bridge foundation and superstructure to accommodate future Shared Use Path
• Construct Path when trail connection is constructed
• Potential Cost Savings = $0.91 M • Current design does not include a path along the length of the
project
The Study Team applied the principals and practices of the Value Engineering Job Plan which resulted in cost reduction and performance benefits in the following areas:
• Cost & schedule savings as compared to original design • Project improvements as compared to original design • Improved constructability
Total potential cost savings of $9.73 million, a 40% reduction in the total project cost
SUMMARY • 30-35% reduction in the construction schedule is
anticipated • Innovative techniques to solving complex geotechnical
design • Maintained safety and traffic operations • Reduced Environmental, R/W and Fishing Access site
impacts • Reduced work zone impacts to users • Improved constructability of the bridge • 2 value added ideas:
– Add lighting or conduit to shared use path along the structure
– Extend the separated path along the length of the project to include the fishing access
AASHTO VE AWARD PRE-CONSTRUCTION ENGINEERING
($25 MILLION TO $100 MILLION)
National Value Engineering Honorable Mention
Pre-Construction Engineering
$25 - $100 million
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
City of Oceanside
Melrose Drive Link Project
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
Department of Public Works
National Value Engineering Award
Pre-Construction Engineering
$25 - $100 million
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Cameron County Regional Mobility Authority
SH 32 (East Loop) Project in Brownsville, Texas
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
Value Engineering Overview SH 32 (East Loop) Project
Washington, D.C. August 4, 2015
66
Proposed Project
Project Need and Purpose:
o Provide an alternate east-west major arterial to the southeast area of Brownsville
o Provide a truck overweight corridor to the Port of Brownsville
o Provide infrastructure necessary to support the growing population
67
Proposed Project
East Segment Improvements: o Interim design – 2 lane
roadway o Ultimate design – 4 lane
roadway o ROW acquisitions /
relocations – approximately 44 parcels
o ADT 5,000 (2013) 7,100 (2033)
68
Proposed Project
West Segment Improvements: o U.S. 77/83 to FM 1419 –
6 lane divided roadway o FM 1419 to FM 3068 –
4 lane divided roadway o ADT 21,800 / 8,700 (2013) 30,400 / 12,200 (2033)
o ROW acquisitions / relocations – approximately 31 parcels
69
Proposed Project
Major Items of Work per Cost Estimate: • Pavement • Grading • Subgrade • Utilities • Bridges (Ultimate)
Status of Design Plans: 95% Schematic Environmental Assessment –submitted to TxDOT
70
Estimate and Elements
Item East West Total Concrete Pavement $ 13.92 M $ 9.80 M $ 23.72 M Grading $ 2.40 M $ 8.92 M $ 11.32 M ROW* $ 2.60 M $ 3.84 M $ 6.44 M E/C $ 2.12 M $ 4.13 M $ 6.25 M Surface HMA $ 2.34 M $ 3.00 M $ 5.34 M Utilities* $ 0 M $ 5.10 M $ 5.10 M Subgrade $ 0.75 M $ 2.75 M $ 3.50 M Mobilization $ 1.57 M $ 1.63 M $ 3.20 M Levee $ 0 M $ 3.11 M $ 3.11 M Bridges $ 2.90 M $ 0 M $ 2.90 M Small Structures $ 0.26 M $ 1.48 M $ 1.74 M Miscellaneous $ 0 M $ 0 M $ -
TOTAL $ 28.86 M $ 43.76 M $ 72.62 M
* Non-reimbursable
71
• The VE Team generated 58 Ideas; 30 Ideas were further discussed.
• The VE Team developed 10 Recommendations and 18 Design Suggestions for further review.
• Project elements analyzed: Pavement (P) Grading (G) Subgrade (SG)
Ideas and Recommendations
Bridges (B) Utilities (U) Miscellaneous (M)
72
Design Suggestions
1. Accommodate for future bus bays (P-14) 2. Minimize future pavement removal / Use salvaged road materials for
base use (P-16 / P-17) 3. Use asphalt base in lieu of PG-64-22 (P-18) 4. Reduce design speed (P-20) 5. Evaluate super-elevated section (G-2) 6. Evaluate need for future overpass at FM 3068 (G-5) 7. Install drainage crossings only as needed (extend for ultimate) (G-8) 8. Install conduit or casings for utilities for future development (G-9) 9. Evaluate proposed estimate for new pump station (U-1) 10. Consider SUE services prior to completion of environmental phase
(U-4) 11. Consider no bridges in future or final phases (B-1) 12. Reverse SH 4 and SH 32 overpass (B-9)
73
Design Suggestions
13. Coordination of all parties (government and design entities) throughout project limits (B-10 / M-1) 14. Consider immediate geotechnical effort (SG-2) 15. Re-evaluate need for detention ponds (M-2) 16. Re-evaluate ultimate design based on traffic forecast (M-4 ) 17. Re-evaluate deferring sidewalk construction (M-5) 18. Modify DHS border fence to act as noise wall (M-6)
74
Cost Adjustment Recap
Recommendation Number
Description Individual Savings
Combined Savings
P-7 No Concrete in Median $1.5 M
P-10 Reduce Outside Shoulder $1.8 M
P-12A Eliminate Proposed Raised Median $1.3 M
P-12B Reduce Proposed Raised Median $0.8 M
P-21 Reduce Number of Lanes from 4 to 2 $3.0 M
P-23 Mill Existing Roadway, Add 11” CRCP $5.0 M
P-24 Heavy-Load Pavement Design on Mainlanes Only
$0.8 M
P-25 Reduce Asphalt Bond Breaker by 1” $2.5 M
G-6 Special Intersection Design ($0.2 M)
M-3 Reduce ROW Footprint $3.5 M
TOTAL ------ $11.9 M
AASHTO VE AWARD PRE-CONSTRUCTION ENGINEERING
(>$100 MILLION)
National Value Engineering Honorable Mention
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
New Jersey Department of Transportation
Route 1 & 9T / New Road
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
Pre-Construction Engineering
greater than $100 million
National Value Engineering Honorable Mention
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
North Carolina Department of Transportation
Rehabilitating I-85 from South of US 158 to VA State Line
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
Pre-Construction Engineering
greater than $100 million
National Value Engineering Honorable Mention
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Wisconsin Department of Transportation
IH 39 Stevens Point Corridor VE Study
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
Pre-Construction Engineering
greater than $100 million
National Value Engineering Honorable Mention
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
Sound Transit
Lynnwood Link LRT Extension Project
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
Pre-Construction Engineering
greater than $100 million
National Value Engineering Award
Pre-Construction Engineering
greater than $100 million
Most Value Added
Proposal
Presented by the AASHTO Value Engineering Technical Committee August 4, 2015
San Bernardino Associated Governments
I-10 Express Lane Widening
For Demonstrating Outstanding Value Engineering Achievements in Teamwork, Cost Savings, Enhanced Performance, or Expedited Project Delivery
that Resulted in an Overall Improved Business Practice
Caltrans - District 8
AASHTO VE Conference
August 2015
I-10 EXPRESS LANES PROJECT
Project Costs: $1.6 Billion Construction Duration: 5 years Beneficial Use: 2025
Project Issues
• Increased Traffic Demand • Right of Way Constraints • Limited funding
Express Lane Ingress/Egress
Managed Lanes
• Managed Lanes • HOV (carpool) Lanes
• Managed by occupancy restrictions
• Express Lanes • Managed by occupancy
restrictions and pricing
Benefits of Express Lanes
• Manages traffic demand • Promotes carpooling • Improves air quality • Generates revenue • Provides for reliable trip times • Offers synergy potential with
transit
I-10 Express Lanes Project Purpose and Need
Purpose • The purpose of the project is to facilitate the movement
of people and goods through the I-10 corridor to more optimally service future traffic demands while providing a seamless tie into the regional I-10 corridor in neighboring Riverside and Los Angeles Counties.
Need • The project is needed to reduce congestion, increase
capacity, and generate revenue to improve operations throughout the I-10 corridor with consideration of projected traffic demand and the anticipated impacts to traffic operations.
Key Functions of Project
Higher Order Functions • Improve Travel Time • Increase Throughput • Facilitate Usership • Offset Capital Costs
Basic Functions
• Reduce Congestion • Increase Capacity • Manage Operations • Generate Revenue
Value Analysis
VA Study Objectives • Identify areas for project performance
enhancements • Identify areas of potential cost savings and/or
schedule improvement • Identify solutions to potential uncertainties (risks)
or open issues • Review and validate the design concept • Develop alternative concepts that will improve
project value!
Project Performance
Performance Attributes • Mainline Operations • Environmental Impacts • Construction Impacts • Maintainability • Phaseability • Ride Quality / Driver Expectations
ACCEPTED VA ALTERNATIVES
Alt. 1.0 – Utilize Superpave in Lieu of HMA (Type C)
Alt. 2.0 – Modify Ramps at Haven to avoid ROW
Alt. 3.0 – Replace/rehab the two current outside lanes with 40 year PCC when performing widening
Alt. 5.0 - Use pre-cast/pre-stressed concrete beams for bridge replacements to reduce closures
Alt. 6.0 – Optimize landscaping through corridor
Alt. 7.1 - Construct two HOT lanes in segment 1 through the I-15/I-10 system interchange to Cherry Ave,
and then one HOT lane in segments 2-4
Single Express Lane through Cherry Ave.
Net Effect of Accepted VA Alternatives
Summary of VA Improvements • Right-sizes the facility to accommodate traffic demands
and relieve congestion to improve the movement of people and goods.
• Significant initial and lifecycle cost savings • Schedule savings of 9 months reduces construction
impacts on the travelling public
Accepted Alternatives Initial Cost
Savings LCC
Savings Change in Schedule
Performance Change
Value Change
1.0, 2.0, 3.0, 5.0, 6.0, 7.1 $158,910,000 $107,054,000 -9 months +14 % +25 %
Comparison of Value – Baseline Concept and Accepted VA Alternatives
0%
25%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
Baseline Accepted Alternatives
Chan
ge in
Val
ue
Rela
tive
Scor
es
Performance Cost/Time Rating Change in Value
THANK YOU!
AASHTO
VE Awards Showcase
Thanks to all applicants and winners!