about usssnrprojects.com/files/final broucher.pdf · about us m/s. s. styanarayana raju & co.,...
TRANSCRIPT
ABOUT US
M/s. S. Styanarayana Raju & Co., the flagship firm which was later converted
into SSNR Projects Private Limited is an infrastructure & engineering
construction company promoted by highly experienced young and dynamic
persons to contribute and grow by tapping the emerging opportunities in the
field of Civil Engineering Construction and development of infrastructure.
The registered office of the company is situated at Visakhapatnam, “the City
of Destiny” with plenty of opportunities due to the advent of information
technology S.E.Z and growing infrastructure development.
Mr. S. Satyanarayana Raju, Managing Director of the Company is the guiding
force behind the success of the Company, which is now grown into a
dependable Super Class contracting Company. Mr. Satyanarayana Raju, in
his individual capacity was associated in the execution of various crucial
and prestigious Civil Engineering contract works. The Company has been
executing irrigation projects, Hydro-electric Projects. The Company is a
specialist in executing Civil works of Hydro Electric Projects, Underground
Engineering & other infrastructure projects. The works carried out by the
Company have won great recognition and appreciation from the concerned
authorities.
We chose that way eversince our inception and believe in providing complete
satisfaction to the Clients and that is why today we are one of the leading
and fast growing construction companies with several landmark projects and
achievements delivered across the Nation.
02 SSNR Projects Pvt. Ltd.
Location NC Hills - Assam
Client Northeast Frontier Railways - Patel Engineering Ltd.,
Status Work in Progress
Value of work 1191.90 Millions
Scope of work Construction of Tunnel No 5, 6 and 7 including earthwork in formation to make profileas per BG standard and other miscellaneous works at the approaches in connectionwith Lumding - Silchar Gauge Conversion Project.
Salient Features Length of Tunnel 1680 meters & 240 meters with supports system
Lumding - Silchar Gauge Conversion Project
03SSNR Projects Pvt. Ltd.
Location Lingdok East Sikkim - Sikkim
Client Sneha Kinetic Power Projects Ltd
Status Work in Progress
Value of work 824.60 Millions
Scope of work Construction of Intake, DesiltingChambers, Part of HRT, SFT and Concrete Dam worksin connection with Dikchu Hydroelectric Project
Salient Features Length of Tunnels 3500 meters
Desilting Chambers 140mx12mx15.5m
Dam 38mt Height x 93mt Span
Underground Excavation 113540 Cum
Underground Concrete 23500 Cum
Dam Concrete 63500 Cum
Dam Reinforcement 3300 MT
Dikchu Hydroelectric Project
04 SSNR Projects Pvt. Ltd.
Location Jeypore - Orissa
Client Water Resources Department, Govt. of Orissa
Status Work in Progress
Value of work 1082.10 Millions
Scope of work Construction of Earth dam, Spillway and Main canal - Work includes earthworkexcavation, embankment, filter blanket, riprap for earth dam and concrete for spillwayand minor structures for canal.
Salient Features
Earth Dam Spillway Main Canal
Length of Earth Dam 600 meters Span of Spillway 70 meters Length of Canal 6480m
Height of Dam 40 meters Height of Spillway 50 meters Minor structures 17 Nos
Banking 1600000 Cum Concrete in all 260000 Cum Excavation in all 800000 Cum
Filters - Aggregates 30000 Cum Reinforcement 800 MT FSD at Ch.0.00 9.2x1.9
Filters - Sand 146000 Cum
Rock toe - Boulder 104000 Cum
Telengiri Irrigation Project
05SSNR Projects Pvt. Ltd.
Location Bhavanipatna - Orissa
Client Water Resources Department, Govt. of Orissa
Status Work in Progress
Value of work 652.06 Millions
Scope of work Construction of Spillway - Work includes concrete for spillway with abutment banking
Salient Features Span of Spillway 53 meters
Height of Spillway 30 meters
Spillway concrete 260000 Cum
Spillway reinforcement 800 MT
Embankment/Filling 350000 Cum
RET Spillway Project
06 SSNR Projects Pvt. Ltd.
Location Salur - Andhra Pradesh
Client Sri Parammathalli Mini Hydropower Project Pvt. Ltd.,
Status Work in Progress
Value of work 195.10 Millions
Scope of work Construction of all civil works like Diversion weir, Intake sluice,Power channel, Forebay and Power House.
Salient Features Diversion weir Span 30 meters Height 4 meters
Intake sluice Span 28 meters Height 4 meters
Length of Power Channal 300m
X Section of Channel 6mx3.6m
Power House 24.6mmx33mx12m
Excavation in all Jobs 190000 Cum
Diversion weir, Sluice concrete 9500 Cum
Reinforcement 1000 MT
Sri Parammathalli Mini Hydropower Project
07SSNR Projects Pvt. Ltd.
Location Joshimat - Uttarakhand
Client NTPC - L&T - AM JV
Status Completed in May 2011
Duration 18 Months
Scope of work Construction of HRT through Chormi Adit
Salient Features Length of Tunnel 600 mts
Profile of Tunnel D & Horseshoe
Underground Excavation 20000 Cum
Location Joshimat - Uttarakhand
Client NTPC - SSJV - ZVS JV
Status Completed in May 2009
Duration 24 Months
Scope of work River diversion/training works, Excavation for desilting basin -
Work includes river diversion, open excavation with rock stabilization measures etc.
Salient Features Open excavation - Rock 1400000 Cum
Open excavation - Loose 350000 Cum
Tapovan Vishnugad Hydroelectric Project
08 SSNR Projects Pvt. Ltd.
Location Kamakhyanagar - Orissa
Client Water Resources Department, Govt. of Orissa
Status Completed June - 2009
Duration 42 Months
Scope of work Construction of Left branch canal - work includes excavation in hard rock, medium hardrock, DI and Soil.
Salient Features
Bed width of Canal 19.70 meters
Depth of Canal 25 meters
Excavation in Rock 1159000 Cum
Excavation in Soil 134500 Cum
Rengali Left Branch Canal
09SSNR Projects Pvt. Ltd.
Location Mandi - Himachal Pradesh
Client Himachal Pradesh State Electricity Board
Contractor SSJV Projects Pvt Ltd
Status Completed May - 2006
Duration 48 Months
Scope of work Includes underground excavation in HRT, Intake & Desilting Chambers & Supply ofaggregates including crushing.
Salient Features Length of Tunnels 4400mts
Desilting Chambers 200 x 16 x 27 meters - 4 Nos
Underground excavation 190000 Cum
Supply of Aggregates 200000 Cum
Larji Hydroelectric Project
10 SSNR Projects Pvt. Ltd.
Location North Andaman - Andaman & Nicobar Islands
Client NHPC - SSJV
Status Completed February - 2001
Duration 30 Months
Scope of work Work includes excavation in soils, rock, filling of clay & rock for dam, filters, riprap,rocktoe, pitching and supply of boulder to crusher
Salient Features Project is situated 260km away from the capital city, Portblair and has been completedeight months ahead of scheduled completion date.
Clay & Rock filling 122000 Cum
Excavation in Rock & Soils 293000 Cum
Kalpong Hydroelectric Project
11SSNR Projects Pvt. Ltd.
Location Kalahandi - Orissa
Client Upper Indravati Power House Circle
Contractor SSJV
Status Completed September - 1998
Duration 9 Months
Value 31.20 Millions
Scope of work Work includes construction of silt check dam with rock fill, excavation in rock etc.
Salient Features Major part (Nearly 72%) of alloted job is completed within three months.
Rock filling 53000 Cum
Excavation in Rock 117000 Cum
Upper Indravati Hydroelectric Project
12 SSNR Projects Pvt. Ltd.
Financial Turnovers
13SSNR Projects Pvt. Ltd.
Plant & Equipment
S l N o . Description of Equipment C a p a c i t y N o s
1. Electrical Compressor 600 CFM to 900 CFM 02
2. Diesel Compressor 300 CFM to 900 CFM 08
3. Crawler Rig 72MM to 125MM 05
4. Rock Breakers 7MT to 25MT per Hour 05
5. Excavators 0.4 to 2.00 Cum 24
6. Tippers / Dumpers 8-12 Cum 76
7. Excavator-cum-Loader 0.24 / 1.10 Cum 02
8. Loaders 2.7 Cum 04
9. Vibratory Compactor 4.8 MT 05
10. Crusher including impactor 60 to 100 TPH 05
11. Batching Plant 15Cum to 30 Cum/Hr 05
12. Concrete Pumps 30 Cum/Hour 04
13. Transit Mixers 4 Cum to 6 Cum 19
14. Total Station 1’’ accuracy with 1000m Range 03
15. Leveling Instrument 08
16. Diesel Generator 50 KVA to 380 KVA 08
17. Tunnel Drilling Boomer Two BUT 35 Booms 01
18. Tunnel Drilling Units 10
19. Tunnel PSS Fabrication Units 05
20. Tunnel Ventilation System 3km
21. Tunnel Lining Shutters 5 Mtr. 05
22. Van 05
23. Tractors 05
24. Light Vehicles 17
Mission
14 SSNR Projects Pvt. Ltd.
Vision
Our mission is to provide premier quality engineering services with state of the art technology with utmost
professionalism to the Infrastructure, Irrigation & Construction sectors.
To develop into a dependable company for execution of all types of Infrastructure and construction projects
on turnkey basis.
SSNR PROJECTS PRIVATE LIMITED is committed to ensure total customer satisfaction with value addition at
all stages by implementing the projects within specified time and cost while maintaining high level of quality.
Clients’ feedback is vital for each project to ensure betterment in the forthcoming projects. The response of
the several client organizations and various State Government Departments and corporations with repeated
orders to the Company is testimony to the ability of the Company for timely delivery.
To be a dependable company which can provide end to end solutions on turnkey basis in Infrastructure &
Construction field and a vision to achieve a turnover of Rs. 5000 millions by the year 2020.
Clientele
15SSNR Projects Pvt. Ltd.
SSNR Projects Pvt. Ltd.
Registered Office : D.No. 51-8-40, Behind BOC Ltd.
Seethammadhara, Visakhapatnam-530 013
Telephone : 0891-2503011, 2794881, 2794882,
Telefax: 0891-2558599, E-mail: [email protected]
Web : www.ssnrprojects.com