about t5 • the challengeciria.org/buildoffsite/pdf/bos31_07_06/gaconsultants.pdfheathrow tomorrow...

17
1 About T5 The challenge Heathrow Today Heathrow Tomorrow • Scale

Upload: others

Post on 25-Sep-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

1

About T5

• The challenge

• Heathrow Today

• Heathrow Tomorrow

• Scale

Page 2: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

2

T5 Challenge

T5 EXISITING

• To increase Heathrows

operational capacity

• To maintain operations

of the airport

seamlessly

• To the opening of the

new terminal complex

in Spring 08

Page 3: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

3

Heathrow Today

• 90 Airlines

• 1,200 flights a day

• 170 destinations in 85 countries

• 1.2 million tonnes of cargo

• 65 million passengers

• 68,000 people directly employed

• 125k passengers per day

Page 4: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

4

Heathrow Tomorrow – What T5 adds

• Demand for air travel in the South East

is forecast to double in the next 20 years

• Terminal 5 will provide additional

capacity of up to 35 million passengers

per annum

• Terminal 5, at an estimated cost of £4.2

billion, is by far the largest project ever

undertaken at any U.K airport

Page 5: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

5

T5 Scale

• 250 Hectares

• Main Terminal 204,200 sq m

• Satellite : 67,000 sq m

• Hotel: 600 bed

• Retail: 42,000 sq m

• Control tower: 87 m high

• Car parking: 4,000 spaces

• M25 spurr

• 1 new rail stations

• 1 coach station

Page 6: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

6

Services Team Commitment to T5 Agreement

Requirements• Trust

• Commitment

• Integrated team

• Best practice

• Good people

• Openness

• Challenging

Page 7: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

7

Key Statistics:

• Main Airport Terminal Building

• 385 metres long x 165 metres wide x 45 metres high (8 primary floors)

• 270,000 M2 floor space

• 18 jetty served stands

• 6 platform rail station

• M&E Scope:

• Mechanical Services

• Electrical Systems

• Public Health

• Commissioning

• M&E Services Shell & Core Fit-out

• Public opening March 2008

Scope - T5A Main Terminal

Page 8: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

8

Scope - Control Tower

Page 9: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

9

IT ROOMS

Tunnels

Fresh Air

Plant Room

Skid Mounted Plant

Stair Riser

CHIMNEYS

Modularised Products

Oct 05 No

T5A 3500

T5B 1250

Tower 60

Utility Tunnels 350

Energy Center 150

TOTAL 5310

Page 10: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

10

Integrated Design

• Engineering Teams from all parties under taking the task.

• Task Teams investigate issues / solutions sharing the results of their efforts

• Early involvement of Key suppliers & commissioning expertise

Totally Integrated

Modularised

Solutions

Page 11: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

11

TYPICAL MODULARISED CORE

ASSEMBLY ARRANGEMENT

Page 12: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

12

Virtual Product Assembly Process

Product structure assembly line

Page 13: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

13

Page 14: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

14

Central Chimney Module Products.

Virtual Reality View of Manufacturing Assembly Process

George Adams April 2004

Page 15: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

15

Services Team Achieve First Airside Chimney

Pre-Assembled In The Factory Assembly on Site in 1½ days only

g

Page 16: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

16

Manufacturing Train 1 – Energy Centre

Single site lift 90 ton / 34 m

Page 17: About T5 • The challengeciria.org/buildoffsite/pdf/BOS31_07_06/GAconsultants.pdfHeathrow Tomorrow – What T5 adds • Demand for air travel in the South East is forecast to double

17

Benefits

Cost

certainty

and

improvements

650,000

reduced

site labour

hours

Pre Assembly

safety

Improvements

On Site

Programme

Interfaces

Reduced by

up to 60%

Energy

conservation

150 kwhr/m2

/ year

Saving

Spatial fit

and

floor plan

improvements

Earlier

Completion

Programme

6 months

Improvement

Benefits - Results