accelerator physics progress and challenges
TRANSCRIPT
Managed by UT-Battellefor the Department of Energy
Accelerator Physics – Progress and
Challenges
J. Galambos
SNS AAC Meeting
Jan. 22-24, 2008
On behalf of the AP Team
2 Managed by UT-Battellefor the Department of Energy Presentation_name
Accelerator Physics Group Activities
Reduce Beam Loss
Reduce Beam Loss
Reduce Beam Loss
Reduce Beam Loss
Perform beam studies
– Same team that commissioned the machine
– Devise measurements to understand and correct causes of beam loss
Request new modified beamline equipment
Develop and maintain the high level software
Perform simulations and beam modeling– ORBIT code for Ring
– Parmila, IMPACT models for linac
Keep an eye on the future– high intensity effects
– laser stripping
3 Managed by UT-Battellefor the Department of Energy Presentation_name
SNS Time Structure Nomenclature
2.4845 ns (1/402.5 MHz)
260 micro-pulses
645 ns 300 ns
945 ns (1/1.059 MHz)
1ms
16.7ms (1/60 Hz)
15.7ms
Macro-pulse
Structure
(made by the
High power
RF)
Mini-pulse
Structure
(made by the
choppers)
Micro-pulse
structure
(made by the
RFQ)
4 Managed by UT-Battellefor the Department of Energy Presentation_name
Accelerator Physics Beam Study Rhythm
Red –
extended
outage
Yellow =
AP
Green =
neutron
Production
•Inter production periods: incremental power ramp up, beam
studies aimed at loss mitigation, understanding beam
behavior.•End of run studies: beam loss mitigation, high intensity studies
(Danilov talk)
Post extended maintenance: linac setup, beam RF, diagnostic studies, equipment shakedown
5 Managed by UT-Battellefor the Department of Energy Presentation_name
SRF, ß=0.61, 33
cavities
1
from
CCL
186 MeV
805 MHz, 0.55 MW klystron
805 MHz, 5 MW klystron
402.5 MHz, 2.5 MW klystron
86.8 MeV2.5 MeV
RFQ
(1)
DTL
(6)
CCL
(4)
Layout of Linac RF with Warm and SCL Modules
SRF, ß=0.81, 48 cavities1000 MeV
(81 total powered)
379 MeV
Warm
Linac
SCL
Linac
•SCL has 81 independently powered cavities
Many values to set w.r.t. the beam
6 cells/ cavity, b changes only a small amount
Many acceptable amplitude / phase setups
•Warm linac has 10 independently powered RF
structures
Typically each structure has 50-100 gaps
b change is substantial
One correct amplitude and phase setting
6 Managed by UT-Battellefor the Department of Energy Presentation_name
Normal Conducting LINAC Tuneup Procedures
Warm Linac RF Amplitude and phase setpoints determined with a phase scan method– Accurate to ~ 1%, 2 degrees
Use design quadrupole strengths and RF settings
First machine to routinely use this method
BP
M P
has
e D
iffe
ren
ce
RF Phase
•Scan RF phase for multiple
amplitude settings
•Solve for input beam energy, RF
amplitude calibration, RF phase
offset
7 Managed by UT-Battellefor the Department of Energy Presentation_name
SCL Cavity Tuneup
Use highest available SCL gradients – far from design
Set the SCL cavity phases using phase scan technique
Scale design quadrupoles with beam energy
RF Cavity Phase
BP
M P
ha
se
Diffe
ren
ce
Example SCL Phase Scan
Black line = measurement fit
Dot = model
Red = cosine fit
RF Cavity Phase
BP
M P
ha
se
Diffe
ren
ce
Example SCL Phase Scan
RF Cavity Phase
BP
M P
ha
se
Diffe
ren
ce
RF Cavity Phase
BP
M P
ha
se
Diffe
ren
ce
Example SCL Phase Scan
Black line = measurement fit
Dot = model
Red = cosine fit
8 Managed by UT-Battellefor the Department of Energy Presentation_name
SCL Cavity Amplitudes
Strategy is to run cavities at their maximum safe amplitude limit (S. Kim’s talk)
Need to be flexible – SRF capabilities change, not near the design
Linac output energy is a moving target
Cavity Design
0
5
10
15
20
25
30
1 5 9
13
17
21
25
29
33
37
41
45
49
53
57
61
65
69
73
77
81
cavity
E0
(M
V/m
)
First Run
0
5
10
15
20
25
30
35
1 5 9
13
17
21
25
29
33
37
41
45
49
53
57
61
65
69
73
77
81
cavity
E0
(M
V/m
)
Second Run
0
5
10
15
20
25
30
35
1 5 9
13
17
21
25
29
33
37
41
45
49
53
57
61
65
69
73
77
81
cavity
E0
(M
V/m
)
Ring Commissioning Run
0
5
10
15
20
25
30
35
1 5 9
13
17
21
25
29
33
37
41
45
49
53
57
61
65
69
73
77
81
cavity
E0
(M
V/m
)
9 Managed by UT-Battellefor the Department of Energy Presentation_name
SCL Setup Times are Decreasing
The procedures used to setup the superconducting linac have matured, and the setup time is now minimal
Still exists a need for fast recovery from changes in the SCL setup
Representative SCL RF Phase Setup
Times
0
20
40
60
80
100
120
Aug-0
5
Nov
-05
Feb-0
6
May
-06
Aug-0
6
Nov
-06
Feb-0
7
May
-07
Ho
urs
Power cavities
on sequentially
Use Beam
Blanking
10 Managed by UT-Battellefor the Department of Energy Presentation_name
SCL Cavity Fault Recovery Scheme
1 GeV is not ultra-relativistic – change in upstream cavity has a large imapct on downstream cavity phase settings
Use a model to predict change in measured downstream arrival times from a change in an upstream cavity
In April 2007 the SCL was lowered from 4.2K to 2 K to facilitate 30 Hz operation, 20 cavity amplitudes changed
The fault recovery scheme restored beam to the previous loss state
-2500
-2000
-1500
-1000
-500
0
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81
cavity
D P
ha
se
(d
eg
)
-30
-20
-10
0
10
20
30
D A
mp
litu
de
(M
V/m
)
Phase
Change
Amplitude
Change
11 Managed by UT-Battellefor the Department of Energy Presentation_name
Linac RMS Beam Size (Nov. 2007)
Lines are model predictions with design Twiss parameters, and dots are wire profile measurements
Warm linac beam size is in good agreement with design values
S (m)
RM
S (
mm
)
CCL1 & 2 Beam Size
DTL Beam Size
12 Managed by UT-Battellefor the Department of Energy Presentation_name
Linac Beam Profiles
Profiles at the start of the HEBT 12/10/2007
Beam profiles are close to Gaussian at the end of the linac than previously observed– Ignore startup portion of the beam
– Quadrupole settings are closer to design values
– Source dependent
13 Managed by UT-Battellefor the Department of Energy Presentation_name
Linac concern: Chopper Quality
(S. Aleksandrov’s Talk)
The MEBT chopper has never been used during neutron production
Sometimes have leading/trailing satellites
Protection measures introduced in the LEBT system have slowed the rise / fall times
Improperly centered beam through the LEBT can cause mini-pulse to mini-pulse position jitter - effectively increasing the beam size.
The chopper system provides clean gaps between mini-pulses to provide a gap to fire the extraction kicker in the Ring
It is a 2 stage system designed to clear the gap to 1 part in 104
– LEBT chopper at 65 keV
– MEBT chopper at 2.5 MeV
March 6,
2007
Satellites
Mini-
pulse
Cu
rren
t
Time
14 Managed by UT-Battellefor the Department of Energy Presentation_name
Beam Loss / Residual Activation
SNS is designed to be a hand’s on maintainable accelerator
100 mRem/hr at 1 foot is considered the limit for relatively easy hands on maintenance– Corresponds to ~ 1 W/m beam loss
BLMs give a measure of beam loss– (~ 400 BLMs throughout the machine)
Residual activation measured after every production run
Use the relationship between BLM readings/ measured activation to predict activation during production setups and prioritize areas for beam study
BLM
DisplayCCL SCL
Radiation survey (mRem/hr at 30 cm after ~ 24 hrs)
15 Managed by UT-Battellefor the Department of Energy Presentation_name
CCL Residual Activation
Hot spots:10-30 mRem/hr
Scaled to 1.4MW: 90-250 mRem/hr
Context: similar residual activation as Dec. 2006 at ~ 30 kW– Better trajectory control (S. Aleksandrov’s talk)
– Additional BLMs
Keys to further improvement:– Longitudinal RF setup refinement
– Transverse matching
– MEBT chopping
1/7/2008 Measurements
16 Managed by UT-Battellefor the Department of Energy Presentation_name
SCL Residual Activation Status
Average warm section residual levels are 10-20 mrem/hr
Context
– These activation levels correspond to 1-2 x 10-4
fractional beam loss
Scaled to 1.4 MW: 90-250 mRem/hr
1/7/2008 Measurements
05
10152025303540
2/2
0/2
00
7
4/2
0/2
00
7
6/2
0/2
00
7
8/2
0/2
00
7
10
/20
/20
07
12
/20
/20
07
MW
-hrs
, m
Rem
/hr
Delivered
Beam
warm section
15 Radiation"
warm section
32 Radiation"
17 Managed by UT-Battellefor the Department of Energy Presentation_name
SCL Beam Loss / Mitigation Efforts
Believe the SCL losses are longitudinal (S.
Aleksandrov’s talk)
– Loss magnitude is not sensitive to matching quadrupole settings
– Loss magnitude and distribution is very sensitive to linac RF phase setpoints
– Developing methods for measuring and increasing the SCL longitudinal acceptance
Measured SCL acceptance
(courtesy Zhang)
-4
-3
-2
-1
0
1
2
3
4
-60 -40 -20 0 20 40 60 80phase (deg)
dE
(M
eV
)
Simulated SCL acceptance
18 Managed by UT-Battellefor the Department of Energy Presentation_name
HEBT Transport Line
Not much beam loss / activation
Upstream transverse + momentum collimation has been tested but is not used
– Causes more beam loss in the arc than halo reduction benefit
Off Energy Beam
19 Managed by UT-Battellefor the Department of Energy Presentation_name
Ring
Primary functions:– Injection
– Fast Extraction
– Collimation
– RF
20 Managed by UT-Battellefor the Department of Energy Presentation_name
Ring Setup Recovery / Repeatability is Good
~ 1 shift to recover a Ring / Transport line setup after an extended maintenance period
Magnet cycling application for hysterisis effects– Determine which magnets require cycling and the minimal cycling
periods
Sophisticated save/compare/restore application
Magnet cycling Save / Compare / Restore
21 Managed by UT-Battellefor the Department of Energy Presentation_name
Ring Injection Area (M. Plum’s talk)
“As delivered” Ring could not transport beam to the injection dump and circulate beam in the Ring (M. Plum’s talk)– Inconsistency in chicane values for Ring and dumpline designs
– Did not fully appreciate the influence of 3-D magnetic effects
Remedial actions– Moved chicane
– Use oversize injection foil (reduce fractional beam to the Injection dump)
– Added additional diagnostics and magnet to the dumpline to understand waste beam transport
– Further upgrades are planned
H- beam from Linac
ThinStripping Foil
To InjectionDump
ThickSecondary Foil
p
H0
H-Dipole magnets
H- beam from Linac
ThinStripping Foil
To InjectionDump
ThickSecondary Foil
p
H0
H-Dipole magnets
22 Managed by UT-Battellefor the Department of Energy Presentation_name
Injection Dump-line Beam Loss
One hot spot from secondary foil scattering
Rest of the Injection dump line ~ 10 mRem/hr residual activation
Future upgrades:
– New, larger aperture septum to be installed in Feb. 08 outage
– Additional quadrupole in the injection line
80
mRem/hr
IDmp Loss
0.00E+00
1.00E+03
2.00E+03
3.00E+03
4.00E+03
5.00E+03
1 2 3 4 5 6 7 8 9 10
BLM
Ra
d/C
8/2006 - 10 kW
8/3 - 150 kW
23 Managed by UT-Battellefor the Department of Energy Presentation_name
Ring Extraction / Collimation beam loss
Extraction area is sensitive to beam in gap
Collimation works close to expectations (J. Holmes talk)
– Presently we are using short pulse beams (small beam size) and to not employ collimation
-5.00E-01
0.00E+00
5.00E-01
1.00E+00
1.50E+00
2.00E+00
2.50E+00
3.00E+00
3.50E+00
40 45 50 55 60 65 70 75 80 85 90
Position (m)
En
erg
y D
ep
ositio
n (Jo
ules)
ORBIT
Experimental
1st collimator
2nd collimator
3rd collimator
Q
V
11 Drift
QV01Dipole
scraper
24 Managed by UT-Battellefor the Department of Energy Presentation_name
Ring RF
Use 2 fundamental cavities, 1 2nd harmonic cavity– Purpose of the dual harmonic is to reduce the bunch factor
to minimize space charge
– 2nd harmonic useful for gap cleaning
– Can further clean the gap with RF manipulations, but time scale is long (100’s of turns) – injection losses increase.
Bunch Shape at
Extraction
25 Managed by UT-Battellefor the Department of Energy Presentation_name
Ring Beam Loss Progress
• In general we are making progress
• Ring injection is the toughest area in the accelerator
• Most of the Ring is loss free
Ring Beam Loss / Activation
0
100
200
300
400
500
600
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
BLM
Rad
/C
6/20 - 60 kW - 9 MW-hrs
7/19 - 120 kW - 22 MW-hrs
12/27 - 160 kW - 36 MW-hrs
Injection
50
90
120 Collimation
15
20
20
Extraction
70
45
20
RF
26 Managed by UT-Battellefor the Department of Energy Presentation_name
Foil
location
Ring Injection Straight Prediction –
Residual activation from foil scattering
5000 hrs operation @ 1.4 MW, 3 hrs after shutdown
> 1000 mRem/hr downstream from the foil –we are on track
Keys to improvement is reducing foil traversals with:
– better injection painting
– Reduced linac beam tails
– Smaller / thinner foil
27 Managed by UT-Battellefor the Department of Energy Presentation_name
Beam Size Control On Target
Use wire profiles and harp to predict the beam size and beam density on the Target (T. McManamy’s talk)
Difficulties understanding transport in the RTBT (M. Plum’s talk)– Swapped plane in harp, coupled H/V beam in the RTBT
Reluctance to vary RTBT quads from values used with view-screen during commissioning
With the power density on Target at the upper limit– Painting a larger beam in the Ring is the only option, but this causes
excessive beam loss at the end of the RTBT
RM
S S
ize m
m)
S (m)
wires
HarpTarget
1/9/2007 Tuneup
28 Managed by UT-Battellefor the Department of Energy Presentation_name
RTBT Radiation
Hot spot from extraction loss – reduced with improved chopping
End of RTBT losses reduced with updated lattice to keep the beam small there.
Beam in gap
induced hot spot
(38 mRem/hr)
Large beam at the end of the
RTBT,
10-40 mRem//hr spots
29 Managed by UT-Battellefor the Department of Energy Presentation_name
Equipment Requirements for 1.4 MW Capability
Ion source current, pulse length and repetition rate requirements to meet the power ramp-up– These requirements assume a 1 GeV beam
Presently at 60 Hz we are limited to:– ~ 850 MeV beam energy
– ~ 880 ms flattop pulse length
– ~ 30 mA current at ~700 ms
0
200
400
600
800
1000
1200
1400
1600
10/1
/2006
12/1
/2006
2/1
/2007
4/1
/2007
6/1
/2007
8/1
/2007
10/1
/2007
12/1
/2007
2/1
/2008
4/1
/2008
6/1
/2008
8/1
/2008
10/1
/2008
12/1
/2008
2/1
/2009
4/1
/2009
6/1
/2009
Po
we
r (k
W)
Pu
lse
Le
ng
th (m
s)
0
10
20
30
40
50
60
70
Re
p R
ate
(H
z)
Cu
rre
nt
(mA
)
Power
Pulse Length
Peak Current
Rep Rate
Today
30 Managed by UT-Battellefor the Department of Energy Presentation_name
Equipment Concerns for Power Ramp Up
Ion source needs to provide 38mA at 1 mS/60 Hz.
– M Stockli’s talk
SCL needs to provide ~20% more accelerating gradient with an additional installed cryomodule + enhanced high beta cavity gradients through cavity reworking and surface processing.
– S. Kim’s + J. Mammosser’s talks
Starting the SCL RF fill during the HVCM ramp-up will provide ~ 70 mS longer flattop .
– S. Kim’s talk
Increase the (medium b / high b) HVCM operating voltages from the present (69/71) kV settings to 73/75 kV to provide an additional 50 ms flattop capability, support the increased cavity gradients, and support beam loading associated with 38 mA.
– D. Anderson’s and T. Hardek’s talks
31 Managed by UT-Battellefor the Department of Energy Presentation_name
AP Concerns
Linac
– Quality of beam chopping (A. Aleksandrov’s talk)
– Understanding and controlling the source of beam loss in the SCL (A. Aleksandrov’s talk)
– Controlling the transverse beam size and halo delivered to the foil
Ring
– Injection area
– Clean transport of waste beams to the Injection Dump (M. Plum’s talk)
– Good understanding and control of the beam distribution delivered to the Target (M. Plum’s talk)
– Foil scattering losses
– Foil survivability (M. Plum’s talk)
– High intensity effects (V. Danilov’s talk)
32 Managed by UT-Battellefor the Department of Energy Presentation_name
Summary
We have increased beam powers from a few kW to > 200 kW.
– Large reductions in normalized beam loss through the ramp-up
Have been equipment issues, but none are show-stoppers.
Now we are dealing with low loss fractions, and are continuing to develop strategies to understand them and further reduce them.