acoustic assessment report elginburg quarry … · 3/12/2020 · resources for a license under the...
TRANSCRIPT
HUGH WILLIAMSON ASSOCIATES INC. Ottawa Ontario Canada
Postal Address: PO Box 74056, RPO Beechwood, Ottawa, Ontario, K1M 2H9, Canada
Phone/Fax: 613 747 0983, Email: [email protected], http://www.hwacoustics.ca
ACOUSTIC ASSESSMENT REPORT
ELGINBURG QUARRY EXPANSION
TOWNSHIP OF KINGSTON
Prepared for
Cruickshank Construction Ltd.
Prepared by
Hugh Williamson Associates Inc.
17th September 2014
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | i
HUGH WILLIAMSON ASSOCIATES INC.
ACOUSTIC ASSESSMENT OF THE
ELGINBURG QUARRY EXPANSION
TOWNSHIP OF KINGSTON
Table of Contents Section Page Table of Contents i – ii Executive Summary iii
1.0 Introduction 1 - 4
2.0 Detailed Facility Description 5 - 7
3.0 Noise Source Summary 8 - 9
4.0 Point of Reception Summary 10
5.0 Recommended Noise Mitigation Measures 11 - 13
6.0 Assessment Criteria, Performance Limits 14 - 15
7.0 Impact Assessment 16 - 18
8.0 Conclusions and Recommendations 19
References 20 Tables
Table 1: Points of Reception Table 2: Noise Source Summary Table Table 3: Sound Level Limits - Outdoor Points of Reception Table 4: Sound Level Limits – Plane of Window Points of Reception Table 5: Acoustic Assessment Summary Table, Worst Case – Daytime
Operation Table 6: Acoustic Assessment Summary Table, Worst Case – Evening and
Nighttime Operation
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | ii
HUGH WILLIAMSON ASSOCIATES INC.
Appendix 1 Plans and Figures
Figure A1.1: Area Plan Showing Receptor Locations Figure A1.2: Site Detail & Surface Elevation Contours Figure A1.3: Scenario 1: Worst Case, Phase North of Pipeline; Low Noise Rock Drill
in operation on the surface north of Line A B, Portable Crushing and Screening Plant below grade south of Line A B (Day only)
Figure A1.4: Scenario 1: Worst Case, Phase North of Pipeline - Noise Contours, Day Only: (Noise levels at 4.5 m)
Figure A1.5: Scenario 2: Worst Case, Phase South of Pipeline; Rock Drill in operation on the surface, Portable Crushing and Screening Plant below grade south of Line C D (Day only)
Figure A1.6: Scenario 2: Worst Case, Phase South of Pipeline - Noise Contours, Day Only: (Noise levels at 4.5 m)
Figure A1.7: Scenario 3: Worst Case - Asphalt Plant, Loading and Shipping Only (Night Operation)
Figure A1.8: Scenario 3: Worst Case, Noise Contours, Night Operation: (Noise levels at 4.5 m)
Appendix 2 Zoning Maps
Township of Kingston, Zoning By-Law No.76-26 - Map 1 Appendix 3 Acoustic Modeling Details
Table A3.1 Calculation Configuration
Table A3.2 Point of Reception Location Table
Table A3.3 Point Sources
Table A3.4 Line Sources
Table A3.5 Noise Source Library
Table A3.6.1 Point of Reception Impacts by Source for Scenario 1
Table A3.6.2 Point of Reception Impacts by Source for Scenario 2
Table A3.6.3 Point of Reception Impacts by Source for Scenario 3
Table A3.7 Distance from Point of Reception to Source
Table A3.8 Noise Measurement Data
Table A3.9 Sample Calculation
Appendix 4 Noise Abatement Schedule
Resumes: Hugh Williamson, Michael Wells
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | iii
HUGH WILLIAMSON ASSOCIATES INC.
Executive Summary
Cruickshank Construction Limited are in the process of applying to the Ministry of Natural
Resources for a license under the Aggregate Resources Act, ARA, for the proposed Expansion
Area adjacent to their existing licensed quarry and Asphalt Plant facility, referred as the
Elginburg Quarry, located at 2357 Unity Road in Kingston, Ontario. Cruickshank wish to
expand the Elginburg Quarry and Cruickshank is applying to the City of Kingston for a
rezoning of the Expansion Area to allow quarrying operations. Hugh Williamson Associates
has been retained by Cruickshank to complete an Acoustic Assessment of the proposed
expansion.
The Acoustic Assessment has been carried out according to the applicable Ministry of
Environment (MoE) Noise Assessment Guidelines, including NPC-300, published August
2013. The assessment considers the impacts on nearby noise sensitive land uses (residences)
of noise generated by all on-site equipment operations, including extraction operations,
aggregate processing operations, asphalt production, loading and vehicle movements. The
noise and vibration impacts of blasting are considered in a separate blasting study conducted
by blasting specialists.
Although the ARA license application and Municipal approval process refer only to the
Expansion Area of the Elginburgh Quarry, the following acoustical assessment considers noise
sources from both the existing and expansion areas, as is appropriate under MoE guidelines.
Assessment includes both current and future operations of the expanded Quarry.
Noise impacts have been predicted and compared to the Ministry of Environment (MoE)
sound level limits as set out in NPC-300. Where applicable, noise mitigation measures such as
berms have been designed to ensure all operations are in compliance with the applicable sound
level limits.
Assessment Methodology is provided in Section 1. A detailed description of the facility and its
operations is provided in Section 2. Noise sources associated with operations at the facility are
summarized in Section 3. Critical Receptors are described in Section 1 and Section 4, with
Section 5 and 6 and 7 detailing recommended noise mitigation measure, applicable assessment
criteria and an assessment of noise impacts.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 1
HUGH WILLIAMSON ASSOCIATES INC.
ACOUSTIC ASSESSMENT OF THE
ELGINBURG QUARRY EXPANSION
TOWNSHIP OF KINGSTON 1.0 Introduction
Cruickshank Construction Ltd. is in the process of applying to the Ministry of Natural
Resources for a license under the Aggregate Resources Act, ARA, for the proposed Elginburg
Quarry Expansion Area, located adjacent to Unity Road in the Township of Kingston. Refer to
Figures A1.1 and A1.2, Appendix 1. The existing Elginburgh Quarry has a license under the
ARA and an Amended Environmental Compliance Approval, ECA No. 5860-95CPXG issued
21 June 2013, from the Ontario Ministry of Environment, MoE.
Part of the approval process involves rezoning of the expansion area land, for which a Noise
and Vibration Study is required by municipal authorities.
This report describes an assessment, carried out by Hugh Williamson Associates, of the
potential impact of noise from operations at the Elginburg Quarry on nearby receptors in
accordance with MoE guidelines for stationary noise sources. 1, 2
The ARA license application
and Municipal approval process refer only to the Expansion, however, this acoustical
assessment considers noise sources from both the existing and expanded sites as appropriate
under MoE guidelines.
This report has been prepared in accordance with the MoE Document NPC-233, Information
to be Submitted for Approval of Stationary Sources of Sound, October 19951. Noise from the
facility is assessed according to MoE Documents: NPC-300, Stationary and Transportation
Sources – Approval and Planning, August 20132. The report follows the recommended format
contained in, Sample Application Package, Basic Comprehensive Certificate of Approval (Air
and Noise), July 20093.
The noise assessment methodology is summarised below.
Identification of noise sensitive receptors in the vicinity of the quarry. Potential noise
sensitive receptors include residences, motels, places of worship, schools and hospitals.
Determination of the MoE sound level limits2 which will apply at each of the noise
sensitive receptors.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 2
HUGH WILLIAMSON ASSOCIATES INC.
Identification of the sources of noise that will arise from quarry operations. In the
current study, the strengths of the various noise sources were obtained from (i) a
previous acoustic assessment4 of the existing Elginburgh Quarry performed by Golder
Associates, or, (ii) measurement of similar operations at other aggregate operations in
Ontario by Hugh Williamson Associates.
Based on the strengths of the individual noise sources, noise levels due to quarry
operations are predicted at nearby noise sensitive receptors using a prediction
procedure6 which is favoured by the MoE. The MoE methodology requires that
compliance be assessed under predictable “worst case” conditions for normal
operations.
Assessment of compliance of the noise due to quarry operations with MoE sound level
limits. Where appropriate, mitigation measures are recommended such that compliance
with MoE sound level limits is achieved at all receptors.
Note that this assessment does not consider the noise and vibrations caused by blasting. The
impacts of blasting at the Elginburg Quarry are being assessed by others.
Surrounding Lands, Acoustic Environment and Critical Receptors
The Elginburg Quarry is located on the southern side of Unity Road as shown in Figure A1.1.
The legal description of the land occupied by the Elginburg Quarry is as follows:
PART OF LOTS 12, 13, 14, 15
CONCESSION 5
KINGSTON TOWNSHIP, ONTARIO
A location plan showing the site with respect to the surrounding area is provided in
Figure A1.1. A site layout plan, showing the sites detailed arrangement and source locations,
is provided in Figure A1.2. A land use zoning map is provided in Appendix 2.
The existing Elginburg Quarry is located on land zoned Extractive Industrial Zone (M5-1).
The proposed Expansion Area is on land currently zoned General Agricultural Zone (A2), as
shown on the Zoning Map, Appendix 2.
To the north of the site, the land is zoned Restricted Agricultural Zone (A1) and General
Agricultural Zone (A2). This land is predominantly open pasture land with an existing solar
farm located on a parcel of land located directly north of the site at 2490 Unity Road. A
small number of residences currently exist on the north and south sides of Unity Road on
land zoned A2, with a vacant lot located in a north easterly direction, neighboring the
existing Solar Farm. As per MoE requirements for Vacant Lots (> 1 HA), a Point of
Reception, POR 12, has been included on this vacant lot in location consistent with the
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 3
HUGH WILLIAMSON ASSOCIATES INC.
existing development fabric of the area, to represent a possible future residence. The closest
existing and possible future residences in a northerly direction have been selected as critical
receptors in the following assessment.
To the east of the site, the land is zoned Restricted Agricultural Zone (A1). A small number
of residences currently exist in this direction fronting Unity Road and Sydenham Road. The
closest residences in this direction have been included as critical receptors in the following
assessment.
To the south of the site, the land is zoned General Agricultural Zone (A2). Further south in a
south easterly direction the land is zoned Environmental Protection Area Zone (EPA) with
pockets of land zoned Service Industrial Zone (M3), Open Space Zone (OS), Residential
Type 1 Zone (R1) and Restricted Agricultural Zone (A1) located adjacent to Bur Brook Road.
A number of existing residences currently exist in this direction fronting Bur Brook Road and
Hayview Road. The closest residences in this direction have been included as critical
receptors in the following assessment.
To the west of the site, the land is zoned General Agricultural Zone (A2) with pockets of land
zoned Residential Type 1 Zone (R1), Residential Type 2 Zone (R2) and Restricted
Agricultural Zone (A1) located near the intersection of Cordukes Road and Bur Brook Road.
A number of existing residences currently exist fronting Unity Road and Cordukes Road.
The closest residences in this direction have been selected as critical receptors.
The quarry and surrounding land is relatively hilly with moderate changes in elevation.
The existing licensed quarry site is partially excavated down to an elevation ranging from
121 m and 125 m ASL.
The proposed expansion area is unexcavated with topography ranging from approximately
139 m ASL at Unity Road site boundary, sloping down to the south east to approximately
133 m ASL in the mid region of the site and 124 m ASL at the sites south eastern boundary.
The surrounding land falls generally in a south easterly direction with fairly steep sections
occurring at the sites south boundary adjacent to the environment protection area.
The critical noise sensitive receptors, which have been selected for detailed analysis, are
shown in Figure A1.1. These were selected as being the receptors most likely to be impacted
by noise from the Elginburg Quarry. Other noise sensitive receptors are at greater distances
and will be less affected by noise from the quarry.
Table 1 lists the noise sensitive receptors selected for analysis.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 4
HUGH WILLIAMSON ASSOCIATES INC.
Table 1: Points of Reception
Point of Reception* Description
POR 1 Residence (closest to the north)
2467 Unity Road (1 Storey)
POR 2
Residence (closest to the east) 2309 Unity Road
(2 Storey)
POR 3
Residence(closest to the east) 2295 Unity Road
(1 Storey)
POR 4
Residence(closest to the east) 2043 Sydenham Road
(2 Storey)
POR 5
Residence (closest to the south) 1909 Hayview Road
(1 Storey)
POR 6
Residence (closest to the south) 2440 Bur Brook Road
(1 Storey)
POR 7
Residence (closest to the south) 2630 Bur Brook Road
(2 Storey)
POR 8
Residence (closest to the west) 2034 Cordukes Road
(2 Storey)
POR 9
Residence (closest to the west) 2166 Cordukes Road
(1 Storey)
POR 10 Residence (closest to the west)
2559 Unity Road (1 Storey)
POR 11 Residence (closest to the north)
2528 Unity Road (1.5 Storey)
POR 12 Vacant Lot (closest to the north)
2350 Unity Road (2 Storey)
*For assessment purposes, points of reception have been taken as upper floor windows (4.5 m
above grade), except where site reconnaissance determined a single storey window height was
applicable (2 m above grade). Outdoor Living Areas (OLA), have been assessed up to 30 m
from residence, (1.5 m above grade), in acoustic calculations.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 5
HUGH WILLIAMSON ASSOCIATES INC.
2.0 Detailed Facility Description
The Cruickshank Construction Limited Elginburg Quarry produces a range of products
including various sized aggregates and asphalt products. These products are produced from
on-site operations that can be categorized as follows:
Extraction operations,
Aggregate processing operations, and,
Asphalt production operations.
Asphalt production operations are a major function of the facility with associated extraction
and processing operations occurring on-site to supply raw material in support of this operation.
Imported material i.e. sand, is brought to site as needed.
The main entry to the Elginburg Quarry, as shown in Figure A1.2 is via Unity Road. An
internal haul road runs from the site entry to the various on-site operations.
A Pipeline Corridor, running east /west, divides the site, as shown in Figure A1.2. The two
areas of operation are referred to as Phase North of Pipeline and Phase South of Pipeline.
Extraction Operations:
Extraction will take place in the two extraction areas, referred to as Phase North of Pipeline
and Phase South of Pipeline, as shown in Figure A1.2.
Extraction will proceed in an east to west direction in 3 lifts, benched at 125 m ASL and
115 m ASL. The final depth of the quarry will be to down to an elevation of 103 m ASL with
actual finished depth in each area dependent on quality of extracted material.
The stone is extracted through drilling and blasting. Blasting produces large pieces of rock
which are then taken to one of the on-site aggregate processing operations. Loaders will be
used to facilitate the extraction operation.
For the purposes of assessing worst-case noise impacts for the extraction operation, equipment
is assumed to be located on the surface and or one lift down.
Noise impacts from blasting are assessed in a separate blasting study and do not form part of
the following assessment.
Aggregate Processing Operations:
The aggregate processing operations include a portable crushing and screening plant and a
wash plant.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 6
HUGH WILLIAMSON ASSOCIATES INC.
Portable Crushing and Screening Plant Operations
The operation plan calls for all crushing and screening to be done with a portable plant located
near the pile of blasted rock. After blasting, a loader will be used to feed rock into the portable
crushing and screening plant. The aggregates produced are then placed in stockpiles, using
conveyors. Loaders will then load the stockpiled aggregates onto haul trucks which are used to
haul the product internally on-site for further processing or shipped directly off-site.
A generator is used to provide power to the portable crushing and screening plant and
associated conveyors.
Wash Plant Operations
A wash plant is used to clean aggregate products before being delivered on-site for asphalt
production or shipped off-site. The Wash Plant is located as shown in Figure A1.3.
A loader is used to feed material into the wash plant. Haul trucks are used to deliver products
to and from the wash plant operation as needed. A generator is used to provide power to the
wash plant and associated equipment.
Asphalt Production Operations:
Asphalt Plant
The location of the asphalt plant is shown in Figure A1.3. The production steps for the asphalt
plant include loading aggregate into the Hopper and conveying it into the rotary dryer. In the
dryer, the aggregate is heated by the oil burner to remove surface moisture and raise the
temperature of the aggregate to approximately 120 to 160 ºC. The heated aggregate is
conveyed into the batch plant where it is mixed with liquid asphalt cement, reclaimed dust
from the bag house and recycled asphalt. The asphalt is then dispensed into highway trucks
beneath the asphalt batch plant for transport off-site.
The air, dust, and products of combustion are drawn out of the dryer by a cyclone fan, through
enclosed ductwork, to the bag house before being exhausted to the atmosphere. Dust collected
by the bag house is conveyed back to a dust storage silo for reuse in the mix.
A generator is used to power the plant during production periods as well as maintaining the
plant in stand-by mode during non-production periods. All other processes are generally shut
down.
This assessment considers the noise impact of the asphalt plant in normal operation during
production period. Noise impacts from the plant while in stand-by are insignificant.
Loaders
Up to Four (4) Loaders are used on-site, three (3) for Extraction and Aggregate Processing
Operations, and, one (1) for Asphalt Production Operations.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 7
HUGH WILLIAMSON ASSOCIATES INC.
Haul Trucks
Haul Trucks (Highway Trucks) are used for the transport of material and product between
extraction and processing operations. The on-site haul route of truck movements has been
included in the following assessment.
An office and scale house is located near the entry to the Facility. Small exhausts and vents
associated with the building were considered insignificant noise sources.
The main entry to the Quarry, as shown in Figure A1.2 is onto Unity Road which connects
through to Sydenham Road.
Hours of Operation
Daytime Operations (07:00 – 19:00) - During the daytime period, all significant noise sources
are assumed to be in operation, and include the following:
One Hydraulic Rock Drill or One Low Noise Rock Drill;
One Portable Crushing Plant, may consist of primary, secondary and tertiary crushing
and screening units (up to three total) and an associated diesel generator;
One Wash Plant and associated diesel generator
One Asphalt Plant and associated diesel generator;
Up to four Loaders;
On-Site Truck movements, to haul the product off-site;
Evening and Night Operations (19:00 – 07:00) – During the evening and nighttime period,
the Asphalt Plant, Loaders and Haul Trucks only will be in operation, and include the
following:
One Asphalt Plant and associated diesel generator;
Up to two Loaders;
On-Site Truck movements, to haul the product off-site;
Portable equipment for site preparations and rehabilitation
Portable construction equipment will be used occasionally for site preparation (e.g. land
clearing and construction of berms) and rehabilitation. This equipment would typically include
excavators, hydraulic shovels, dozers and scrapers. To minimize the impact of noise during
site preparation and rehabilitation, the construction equipment used, excavators, bulldozers,
etc., will comply with MoE Publication NPC-1155, Construction Equipment, August 1978.
This publication gives noise standards to be met by construction equipment in Ontario.
Site preparation and rehabilitation activities will take place only during daytime hours (07:00
– 19:00).
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 8
HUGH WILLIAMSON ASSOCIATES INC.
3.0 Noise Source Summary
The following noise sources have been used to model noise generated by operations at the
Elginburg Quarry. In brackets are the shortened names of the noise sources as used in the
acoustic model. The characteristics of these sources, as used in acoustic modelling, are
summarized in Table 2.
One Portable Crushing Plant, may consist of primary, secondary and tertiary
crushing and screening units (up to three total) and an associated diesel
generator and Loader (source: N1, N2, N3);
One Wash Plant and associated diesel generator and Loader (source: N4, N5,
N6);
One Asphalt Plant and associated diesel generator and Loader (source: N7, N8,
N9, N10, N11, N12, N13, N14, N15);
One Hydraulic Rock Drill (source: Rockdrill_TH_70), or, one Low Noise
Rock Drill (source: Rockdrill_SmartRIG);
On-site Truck Movements (source: HWYTruck_Slow58). Refer to Section 2.0 for detailed description of equipment in operation at the facility.
The strengths of the noise sources, i.e. the sound powers shown in Table 2 and used in this
analysis, are taken from a database of noise measurements made by Hugh Williamson
Associates of similar operations made at other aggregate operations in Ontario and from noise
measurements carried out on-site of equipment in operation by Golder Associates in 20104.
The analysis allows for either the use of a standard Hydraulic Rock Drill, or, the use of a Low
Noise Rock Drill such as the Atlas Copco SmartRIG ROC D9C.
Conveyors and Stackers used to transfer crushed stone and sand to stockpiles are considered as
insignificant noise sources.
A number of equipment operations consist of multiple noise sources. Where possible, noise data
was used for each component and modelled as separate point sources.
Noise from the haul routes is estimated using the moving point source method modelled as a
continuous loop indicating the worst case on-site truck movements for the worst case
scenario’s analysed. It is assumed that during the daytime period a maximum of 12 loads per
hour will be shipped during periods of maximum capacity for each of the on-site operations
including the extraction, aggregate processing and asphalt production operations. For night
operations it is assumed a maximum of 5 loads per hour will be shipped during periods of
maximum capacity.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 9
HUGH WILLIAMSON ASSOCIATES INC.
Table 2: Noise Source Summary Table
Source ID Source Description Sound Power (dBA)
Source Height above
ground (m)
Sound Characteristics
Noise Control
Measures
Low Noise Rock Drill (Rockdrill_SmartRIG)
Portable Low Noise Hydraulic Rock Drill
(Atlas Copco ROC D9C or similar) 108.3 2
Steady, non-tonal, non-directional noise source
As per Section 5.0
Rock Drill (Rockdrill_TH_70)
Portable Hydraulic Rock Drill
118.6 2 Steady, non-tonal, non-directional noise source
As per Section 5.0
N1 (Primary Crushing Unit and
Hopper Loader)
Portable Crushing and Screening Plant units and Loader
119 3 Steady, non-tonal, non-directional noise source
As per Section 5.0
N2 (Secondary, Tertiary Crushing
Unit, Primary, Secondary, Tertiary Screening Unit,)
Portable Crushing and Screening Plant units
118 3 Steady, non-tonal, non-directional noise source
As per Section 5.0
N3 (Generator)
Generator to power the Portable Crushing and Screening Plant
units 102 2
Steady, non-tonal, non-directional noise source
As per Section 5.0
N4 (Washplant)
Washplant 115 2 Steady, non-tonal, non-directional noise source
As per Section 5.0
N5 (Washplant Hopper/Loader)
Washplant 113 3 Steady, non-tonal, non-directional noise source
As per Section 5.0
N6 (Washplant Generator)
Washplant 107 2 Steady, non-tonal, non-directional noise source
As per Section 5.0
N7 (Asphalt Plant Truck Loading
and Batch Tower) Asphalt Plant 104 2
Steady, non-tonal, non-directional noise source
As per Section 5.0
N8 (Asphalt Plant Dryer)
Asphalt Plant 107 2 Steady, non-tonal, non-directional noise source
As per Section 5.0
N9 (Asphalt Plant RAP Screen)
Asphalt Plant 111 2 Steady, non-tonal, non-directional noise source
As per Section 5.0
N10 (Asphalt Plant Aggregate Bin
and Screen) Asphalt Plant 104 3
Steady, non-tonal, non-directional noise source
As per Section 5.0
N11 (Asphalt Plant Hopper Loader)
Asphalt Plant 104 2 Steady, non-tonal, non-directional noise source
As per Section 5.0
N12 (Asphalt Plant Cyclone Fan)
Asphalt Plant 111 2 Steady, non-tonal, non-directional noise source
As per Section 5.0
N13 (Asphalt Plant Heater Blower)
Asphalt Plant 108 3 Steady, non-tonal, non-directional noise source
As per Section 5.0
N14 Asphalt Plant (Drum Mixer)
Asphalt Plant 114 2 Steady, non-tonal, non-directional noise source
As per Section 5.0
N15 Asphalt Plant (Compressor)
Asphalt Plant 100 4 Steady, non-tonal, non-directional noise source
As per Section 5.0
N16 (Asphalt Plant Truck Loading
and Batch Tower) Asphalt Plant 110 2
Steady, non-tonal, non-directional noise source
As per Section 5.0
Truck Movements (HWYTruck_Slow58)
Slow moving highway truck, no Jake brakes, maximum speed
20 kph 110 3
Steady, moving, non-tonal,
non-directional noise source
As per Section 5.0
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 10
HUGH WILLIAMSON ASSOCIATES INC.
4.0 Point of Reception Summary
Noise levels have been predicted at the critical receptors using “worst case” assumptions
under normal operations and using the ISO sound propagation methodology6, as implemented
in the sound prediction software Cadna-A, version 4.2.141. The ISO methodology, which is
favored by the MoE, provides a conservative (i.e. high) estimate of the noise level at each
receptor taking into account adverse wind and meteorological conditions.
The estimation method includes the following:
Distance attenuation is based on spherical spreading.
Atmospheric attenuation.
Ground attenuations, as appropriate.
Barrier attenuation, as appropriate.
In order to consider cases of worst noise impacts, a number of operational scenarios have been
modeled. In general, the worst impacts are those which occur when the equipment is operating
on the original surface, i.e. at grade, with the impact becoming less as the equipment is located
on lower lifts, i.e. below grade. The following three worst case scenarios are presented in this
report and form the basis for the mitigation recommendations in Section 5.0.
Scenario 1: Worst Case, Phase North of Pipeline; Low Noise Rock Drill in operation on the
surface north of Line A B, Portable Crushing and Screening Plant below grade
south of Line A B (Day only) - Figures A1.3 & A1.4
Scenario 2: Worst Case, Phase South of Pipeline; Rock Drill in operation on the surface,
Portable Crushing and Screening Plant below grade south of Line C D
(Day only) - Figures A1.5 & A1.6
Scenario 3: Worst Case - Asphalt Plant, Loading and Shipping Only (Night Operation)
Figures A1.7 & A1.8
Detailed prediction results are contained in Appendix 3, with Tables A3.6.1, A3.6.2 and
A3.6.3, presenting a summary of predicted noise impacts at each point of reception (POR) for
the individual noise sources.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 11
HUGH WILLIAMSON ASSOCIATES INC.
5.0 Recommended Noise Mitigation Measures (Site Plan Recommendations)
Noise mitigation measures for the Expansion Area operations are detailed below. It is
recommended that these measures be included on the official Site Plan for the Elginburgh
Quarry Expansion Area.
The predicted noise impacts in Tables A3.6.1, A3.6.2, and A3.6.3, are based on the
implementation of the following mitigation measures.
1. The operation of the Portable Crushing and Screening Plant (Crusher), may take place
only during the daytime period (07:00 – 19:00), and comply with the following:
a. When operating in Phase North of Pipeline:
i. The Portable Crushing and Screening Plant is to be located south of
Line A B at a maximum elevation of 125 m ASL with Lift Faces,
located at a maximum of 25 m to the north and west of the Crusher,
shielding receptors POR 1, 10 and 11.
ii. A 7 m high noise barrier (Barrier 9) located at a maximum of 25 m
from Crusher shielding POR 3 is to be provided. Barrier 9 can be
reduced to 5 m high when operating the Crusher below 115 m ASL.
Refer to Figure A4.3, Appendix 4.
b. When operating in Phase South of Pipeline:
i. The Portable Crushing and Screening Plant is to be located at a
maximum elevation of 125 m ASL when north of Line C D and 115 m
ASL when south of Line C D, with Lift Faces located at a maximum of
25 m to the west of the Crusher, shielding receptors POR 8 and POR 9.
2. The operation of a Standard Hydraulic Rock Drill (Drill), may take place only during
the daytime period (07:00 – 19:00), and shall comply with the following:
a. When operating in Phase North of Pipeline, the Standard Hydraulic Rock Drill
is not to operate above grade north of Line A B.
3. The operation of a Low Noise Rock Drill, such as the Atlas Copco SmartRig ROC
D9C or similar, may take place only during the daytime period (07:00 – 19:00)
anywhere in the extraction area, above or below grade.
4. The operation of the Wash Plant, may take place only during the daytime period
(07:00 – 19:00), and is to be located below grade as shown in Figure A1.3.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 12
HUGH WILLIAMSON ASSOCIATES INC.
5. The operation of the Asphalt Plant and associated equipment, may take place on
24 hour basis (24 hour), and comply with the following:
a. The Asphalt Plant is to be located as shown in Figure A1.3.
b. When operating the Asphalt Plant during the Evening and Nighttime Period
(19:00 to 07:00):
i. a 4 m high noise barrier (Barrier 6), located as shown in Figure A4.1, is
to be provided shielding POR 9.
ii. a 4 m high noise barrier (Barrier 7), located as shown in Figure A4.1,
is to be provided shielding POR 3.
iii. a 4 m high noise barrier (Barrier 8), located as shown in Figure A4.2, is
to be provided shielding POR 3.
6. The loading and shipping of Asphalt and Aggregate product using Highway Trucks,
may take place on a 24 hour basis (24 hour). A maximum of two (2) Loaders may be
in operation concurrently during the evening and nighttime period (19:00 to 07:00).
7. When operating on-site, Highway Trucks shall not exceed 20 kph and shall not use
compression braking (Jake Brakes).
8. Noise Barriers or berms are to be provided as shown in Figures A4.1, A4.2 and A4.3
and as specified in Appendix 4 - Noise Abatement Schedule.
9. Noise barriers shielding portable equipment may be progressively established to
provide shielding from location of operation to the identified noise sensitive point of
reception (POR).
10. Noise barriers or berms are to be solid, having no gaps, and are to have a surface
density of no less than 20 kg/m2. Examples of suitable barriers or berms are as follow:
a. Lift face or existing terrain;
b. Earth, gravel or aggregate berms or stockpiles;
c. Concrete or brick walls;
d. Commercial noise barriers;
e. Shipping containers;
f. A portable barrier such as a truck trailer equipped with movable flaps to block
the space between the ground and the bottom of the trailer.
11. Portable construction equipment used for site preparation (e.g. land clearing and
construction of berms) and rehabilitation shall comply with MoE Publication NPC-
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 13
HUGH WILLIAMSON ASSOCIATES INC.
1155, Construction Equipment, August 1978. (This publication gives noise standards to
be met by construction equipment in Ontario.) Site preparation and rehabilitation
activities shall take place only during daytime hours (07:00 – 19:00).
12. If a new process is introduced to the site, then this process shall be assessed by a
qualified acoustical consultant as soon as possible after commissioning. Noise
mitigation measures shall be reviewed, and altered if necessary, to ensure that MoE
sound level limits are met at all points of reception.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 14
HUGH WILLIAMSON ASSOCIATES INC.
6.0 Assessment Criteria, Performance Limits
Sound level limits as specified in the MoE guideline NPC-3002, depend on the acoustical
classification of the area as Class 1, 2, 3 or 4.
Class 1 area 'an area with an acoustical environment typical of a major population
centre, where the background sound level is dominated by the activities of people,
usually road traffic, often referred to as urban hum.’
Class 2 area 'an area with an acoustical environment that has qualities representative
of both Class 1 and Class 3 areas: sound levels characteristic of Class 1 during daytime
(07:00 to 19:00 or to 23:00 hours); and, low evening and night background sound level
defined by natural environment and infrequent human activity starting as early as
19:00 hours (19:00 or 23:00 to 07:00 hours).’
Class 3 area 'a rural area with an acoustical environment that is dominated by natural
sounds having little or no road traffic, such as: a small community; agricultural area; a
rural resort area such as a cottage or resort area; or, a wilderness area. '
Class 4 area ‘an area or specific site that would otherwise be defined as Class 1 or 2
and which: is an area intended for development with new noise sensitive land use(s)
that are not yet built; is in proximity to existing, lawfully established stationary
source(s); and, has formal confirmation from the land use planning authority with the
Class 4 area classification which is determined during the land use planning process.
Additionally, areas with existing noise sensitive land use(s) cannot be classified as
Class 4 areas.’
Due to the dominant rural nature of the area and the relatively large distance to Unity Road
and minimal road traffic on Cordukes Road, Bur Brook Road and Hayview Road, the
acoustical environment is dominated by natural sounds with little road traffic noise. As such
the area in which the critical receptors, POR 3, POR 5, POR 6, PR 7, POR 8 and POR 9 are
located can be classified as Class 3 Area (Rural).
Due to the relatively high levels of road traffic along Sydenham Road and Unity Road, the
area in which POR 1, POR 2, POR 4, POR 10, POR 11 and POR 12 are located is subject to
road traffic noise, particularly during the period from 07:00 to 19:00 hours. Hence these
receptors are classified as Class 2 Area (Urban).
For the purpose of evaluating the acoustic environment of the area, specifically in relation to
receptors located on Unity Road and Sydenham Road, the Transportation Report, “Elginburg
Quarry (Unity Road) Traffic Review,” prepared by IBI Group was consulted. The estimated
AADT of 2200 vehicles for Unity Road confirm the acoustical classification applied for the
nearby points of reception. This is further confirmed by the Golder Associates, Acoustic
Assessment Report prepared in June 2010 for the existing licensed quarry, which determined
the same acoustical classifications were applicable for the selected receptors.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 15
HUGH WILLIAMSON ASSOCIATES INC.
The applicable outdoor sound level limit at a point of reception, expressed in terms of the
1-hour equivalent sound level, Leq, is the higher of either the applicable exclusion noise limit
value given in Tables 3 and 4, or the background sound level for that point of reception.
Background sound level means the sound level that is present in the environment, produced by
noise sources other than the source under assessment, expressed as the 1-hour equivalent
sound level, Leq.
Under NPC-3002, two types of points of reception exist for noise sensitive receptors. An
Outdoor Living Area (OLA) point of reception can be any location on the noise sensitive
property within 30 m of the dwelling or building at a height of 1.5 m from the ground. Plane
of window (POW) points of reception are to be located on the dwelling or noise sensitive
building, typically 2 m above ground for single storey dwellings and 4.5 m above ground for
two storey dwellings.
Background noise assessment was not carried out, hence the exclusion limit levels, given in
the Tables 3 and 4 below, are taken as the sound level limits for the purpose of this
assessment.
Table 3: Exclusion Limit Values for One-Hour Equivalent Sound Level (Leq, dBA) at Outdoor Points of Reception
Time of Day Class 1 Area
Class 2 Area POR’s 1, 2, 4, 10, 11, & 12
Class 3 Area POR’s 3, 5, 6,
7, 8 & 9
Class 4 Area
07:00 – 19:00 50 50 45 55
19:00 – 23:00 50 45 40 55
Table 4: Exclusion Limit Values for One-Hour Equivalent Sound Level (Leq, dBA) at Plane of Window of Noise Sensitive Spaces
Time of Day Class 1 Area Class 2 Area POR’s 1, 4, 10, 11, & 12
Class 3 Area POR’s 3, 5, 6,
7, 8 & 9
Class 4 Area
07:00 – 19:00 50 50 45 60
19:00 – 23:00 50 50 40 60
23:00 – 07:00 45 45 40 55
Notes: Sound level limits are based on 1-hour equivalent sound levels.
Plane of Window (Building) Points of Reception are at the residential buildings, 2nd
Storey window height – 4.5 m Outdoor Points of Reception (OLA = Outdoor Living Area), up to 30 m from the residence, height 1.5 m
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 16
HUGH WILLIAMSON ASSOCIATES INC.
7.0 Impact Assessment
Noise impacts of the Elginburg Quarry at nearby receptors have been assessed for daytime and
evening and nighttime operations. The analyzed operations are for worst case conditions and
locations of equipment, and include the recommended noise mitigation measures set out in
Section 5.0.
In Table 5 and Table 6, estimated noise levels at the nearest receptors for the worst cases
among all scenarios are compared with the applicable sound level limits. More detailed
estimates, for all sources and scenarios are contained in Appendix 3, Tables A3.6.1, A3.6.2
and A3.6.3. Note that these worst cases will occur for only brief periods during the many year
life of the quarry.
Statement of Compliance
With the recommended noise mitigation measures, the noise impacts of operations at the
Elginburg Quarry Expansion Area are predicted to meet the applicable MoE guideline limits2
for daytime operations, 07:00 to 19:00 and evening and nighttime operations, 19:00 to 07:00.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 17
HUGH WILLIAMSON ASSOCIATES INC.
Table 5: Acoustic Assessment Summary Table, Worst Case – Day
Point of Reception
ID
Daytime Period (07:00 to 19:00)
Estimated Sound Level
at POR (worst case)
Sound Level Limit
07:00 - 19:00 (worst case)
Compliance With Performance
Limit
POR 1 50 dBA 50 dBA Yes
POR 2 46 dBA 50 dBA Yes
POR 3 45 dBA 45 dBA Yes
POR 4 41 dBA 50 dBA Yes
POR 5 44 dBA 45 dBA Yes
POR 6 42 dBA 45 dBA Yes
POR 7 44 dBA 45 dBA Yes
POR 8 44 dBA 45 dBA Yes
POR 9 45 dBA 45 dBA Yes
POR 10 48 dBA 50 dBA Yes
POR 11 49 dBA 50 dBA Yes
POR 12 43 dBA 50 dBA Yes
*Plane of Window height (POW) at 4.5 m or 2 m are given above as these where the most critical at each receptor. Refer to Tables A3.6.1, A3.6.2 and A3.6.3, in Appendix 3, for more detailed sound level estimates by source.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 18
HUGH WILLIAMSON ASSOCIATES INC.
Table 6: Acoustic Assessment Summary Table, Worst Case – Evening and
Night
Point of Reception
ID
Evening and Night Operation (19:00 to 07:00)
Estimated Sound Level
at POR (worst case)
Sound Level Limit
19:00 - 07:00 (worst case)
Compliance With Performance
Limit
POR 1 42 dBA 45 dBA Yes
POR 2 42 dBA 45 dBA Yes
POR 3 40 dBA 40 dBA Yes
POR 4 37 dBA 45 dBA Yes
POR 5 36 dBA 40 dBA Yes
POR 6 34 dBA 40 dBA Yes
POR 7 35 dBA 40 dBA Yes
POR 8 37 dBA 40 dBA Yes
POR 9 38 dBA 40 dBA Yes
POR 10 41 dBA 45 dBA Yes
POR 11 44 dBA 45 dBA Yes
POR 12 39 dBA 45 dBA Yes
*Plane of Window height (POW) at 4.5 m or 2 m are given above as these where the most critical at each receptor. Refer to Tables A3.6.1, A3.6.2 and A3.6.3, in Appendix 3, for more detailed sound level estimates by source.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 19
HUGH WILLIAMSON ASSOCIATES INC.
8.0 Conclusions and Recommendations
An acoustic assessment of operations at the Elginburg Quarry has been conducted according
to MoE noise assessment procedures. Operations include Rock Drilling, Crushing and
Screening, Washing, Asphalt Production, Loading of Highway Trucks and Shipping off-site.
It has been found that noise levels from the operations at nearby receptors are in compliance
with MoE sound level limits as set out in publication NPC-3002, provided that the noise
mitigation measures described in Section 5.0 are followed.
Hugh Williamson, Ph.D., P.Eng.
Member, Canadian Acoustical Society
Michael Wells, B.Architecture (Hons), B.Sc.Arch. Registered Architect of NSW, ARN: 8111
Member, Canadian Acoustical Society
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 20
HUGH WILLIAMSON ASSOCIATES INC.
References
1. Ministry of Environment Publication NPC-233, Information to be Submitted for
Approval of Stationary Sources of Sound, October 1995.
2. Ministry of Environment Publication NPC-300, Stationary and Transportation
Sources - Approval and Planning, August 2013.
3. Ministry of Environment, Sample Application Package, Basic Comprehensive
Certificate of Approval (Air and Noise), July 2009.
4. Golder Associates, Acoustic Assessment Report (of the Elginburgh Quarry), Report
No. 09-1112-0112, June 2010.
5. Ministry of Environment Publication NPC-115, Construction Equipment, August
1978.
6. International Standards Organization, Acoustics - Attenuation of Sound During
Propagation Outdoors, Part 2: General Method of Calculation, ISO 9613-2: 1996(E).
7. IBI GROUP, Transportation Report Elginburg Quarry (Unity Road) Traffic Review,
November 2013.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 21
HUGH WILLIAMSON ASSOCIATES INC.
Appendix 1
Figures
Contents:
Figure A1.1: Area Plan Showing Receptor Locations Figure A1.2: Site Detail & Surface Elevation Contours (elevation contours at
1 meter intervals) Figure A1.3: Scenario 1: Worst Case, Phase North of Pipeline; Low Noise
Rock Drill in operation on the surface north of Line A B, Portable Crushing and Screening Plant below grade south of Line A B (Day only)
Figure A1.4: Scenario 1: Worst Case, Phase North of Pipeline - Noise
Contours, Day Only: (Noise levels at 4.5 m) Figure A1.5: Scenario 2: Worst Case, Phase South of Pipeline; Rock Drill in
operation on the surface, Portable Crushing and Screening Plant below grade south of Line C D (Day only)
Figure A1.6: Scenario 2: Worst Case, Phase South of Pipeline - Noise
Contours, Day Only: (Noise levels at 4.5 m) Figure A1.7: Scenario 3: Worst Case - Asphalt Plant, Loading and Shipping
Only (Night Operation) Figure A1.8: Scenario 3: Worst Case, Noise Contours, Night Operation:
(Noise levels at 4.5 m)
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 22
HUGH WILLIAMSON ASSOCIATES INC.
Figure A1.1: Area Plan Showing Receptor Locations
North
Sydenham Road
Elginburg Quarry (Site Boundary)
Burbrook Road
Unity Road
Cordukes Road
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 23
HUGH WILLIAMSON ASSOCIATES INC.
Figure A1.2: Site Detail & Surface Elevation Contours (elevation contours at 1 meter intervals)
18374400
18374400
18374600
18374600
18374800
18374800
18375000
18375000
18375200
18375200
18375400
18375400
18375600
18375600
18375800
18375800
18376000
18376000
18376200
18376200
18376400
18376400
18376600
18376600
18376800
18376800
18377000
18377000
4906600
4906600
4906800
4906800
4907000
4907000
4907200
4907200
4907400
4907400
4907600
4907600
4907800
4907800
4908000
4908000
4908200
4908200
4908400
4908400
North
POR 5
126
Existing Licensed Quarry
Sydenham Road
Elginburg Quarry (Site Boundary)
Unity Road
Cordukes Road
POR 6
POR 1
POR 2
POR 3
POR 4
POR 12 POR 11
POR 10
POR 9
POR 8
POR 7
Site Entry
Existing Licensed Quarry
Phase North of Pipeline (Expansion Area)
Phase South of Pipeline
(Expansion Area)
140
136 138
130
121 133
133
90
105
125
Pipeline Corridor (Enbridge)
Transmission Line
121
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 24
HUGH WILLIAMSON ASSOCIATES INC.
Figure A1.3: Scenario 1: Worst Case, Phase North of Pipeline; Low Noise Rock Drill in operation on the surface north of Line A B, Portable Crushing and Screening Plant below grade south of Line A B (Day only)
POR 1
POW: 50 dBA
OLA: 50 dBA
POR 2
POW: 45 dBA
OLA: 44 dBA
POR 3
POW: 45 dBA
OLA: 45 dBA
POR 10
POW: 48 dBA
OLA: 48 dBA
POR 11
POW: 49 dBA
OLA: 46 dBA
POR 12
POW: 43 dBA
OLA: 42 dBA
18375000
18375000
18375200
18375200
18375400
18375400
18375600
18375600
18375800
18375800
18376000
18376000
18376200
18376200
4907600
4907600
4907800
4907800
4908000
4908000
4908200
4908200
4908400
4908400
4908600
4908600
POR 1
POR 2 POR 3
POR 12
POR 11
LINE A B
Site Entry
POR 10
North
1 x Wash Plant with associated diesel
generator; 1 x Loader
1 x Portable Crushing and Screening Plant with associated generator located at a maximum
distance of 25 m from lift face to the north and
west; 1 x Loader
1 x Asphalt Plant with associated diesel
generator; 1 x Loader
Barrier 9: Minimum 7 m high noise barrier located at a maximum 25 m from Portable Crushing and
Screening Plant shielding POR 3
138
125
1 x Low Noise Rock Drill Barrier 2: Minimum 7 m high noise barrier shielding POR 11
Barrier 1: Minimum 4 m high noise barrier
shielding POR 1 from Quarry Operation and Internal Haul Route
Internal Haul Route
Pipeline Corridor (Enbridge)
Phase North of Pipeline (Existing Licensed Quarry)
Phase North of Pipeline (Expansion Area)
Pipeline Corridor
Barrier 3: Minimum 4 m high noise barrier
shielding POR 10 when operating the Low Noise Rock Drill north of Line A
B
121
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 25
HUGH WILLIAMSON ASSOCIATES INC.
Figure A1.4: Scenario 1: Worst Case, Phase North of Pipeline - Noise Contours, Day Only: (Noise levels at 4.5 m)
POR 1
POW: 50 dBA
OLA: 50 dBA
POR 2
POW: 45 dBA
OLA: 44 dBA
POR 3
POW: 45 dBA
OLA: 45 dBA
POR 4
POW: 41 dBA
OLA: 40 dBA
POR 5
POW: 41 dBA
OLA: 41 dBA
POR 6
POW: 36 dBA
OLA: 36 dBA
POR 7
POW: 38 dBA
OLA: 36 dBA
POR 8
POW: 41 dBA
OLA: 38 dBA
POR 9
POW: 45 dBA
OLA: 44 dBA
POR 10
POW: 48 dBA
OLA: 48 dBA
POR 11
POW: 49 dBA
OLA: 46 dBA
POR 12
POW: 43 dBA
OLA: 42 dBA
18374000
18374000
18374500
18374500
18375000
18375000
18375500
18375500
18376000
18376000
18376500
18376500
18377000
18377000
18377500
18377500
4906000
4906000
4906500
4906500
4907000
4907000
4907500
4907500
4908000
4908000
4908500
4908500
4909000
4909000
> -99.0 dB
> 35.0 dB
> 40.0 dB
> 45.0 dB
> 50.0 dB
> 55.0 dB
> 60.0 dB
> 65.0 dB
> 70.0 dB
> 75.0 dB
> 80.0 dB
> 85.0 dB
North
Sydenham Road
Elginburg Quarry (Site Boundary)
Burbrook Road
Unity Road
Cordukes Road
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 26
HUGH WILLIAMSON ASSOCIATES INC.
Figure A1.5: Scenario 2: Worst Case, Phase South of Pipeline; Rock Drill in operation on the surface, Portable Crushing and Screening Plant below grade south of Line C D (Day only)
POR 1
POW: 48 dBA
OLA: 48 dBA
POR 2
POW: 45 dBA
OLA: 44 dBA
POR 3
POW: 45 dBA
OLA: 45 dBA
POR 4
POW: 41 dBA
OLA: 40 dBA
POR 5
POW: 43 dBA
OLA: 44 dBA
POR 6
POW: 42 dBA
OLA: 42 dBA
POR 7
POW: 44 dBA
OLA: 43 dBA
POR 8
POW: 44 dBA
OLA: 44 dBA
POR 9
POW: 44 dBA
OLA: 44 dBA
POR 10
POW: 46 dBA
OLA: 45 dBA
POR 11
POW: 49 dBA
OLA: 46 dBA
POR 12
POW: 43 dBA
OLA: 42 dBA
18374400
18374400
18374600
18374600
18374800
18374800
18375000
18375000
18375200
18375200
18375400
18375400
18375600
18375600
18375800
18375800
18376000
18376000
18376200
18376200
18376400
18376400
18376600
18376600
18376800
18376800
18377000
18377000
4906600
4906600
4906800
4906800
4907000
4907000
4907200
4907200
4907400
4907400
4907600
4907600
4907800
4907800
4908000
4908000
4908200
4908200
4908400
4908400
North
POR 5
126
Unity Road
Cordukes Road
POR 6
POR 1
POR 2
POR 3
POR 4
POR 12 POR 11
POR 10
POR 9
POR 8
POR 7
Site Entry
140
136 138
130
125
115
90
105
Pipeline Corridor (Enbridge)
1 x Wash Plant with associated diesel
generator; 1 x Loader
1 x Asphalt Plant with associated diesel
generator; 1 x Loader
Barrier 1: Minimum 4 m high noise barrier
shielding POR 1 from Internal Haul Route
1 x Portable Crushing and Screening Plant with associated generator
located at a maximum distance of 25 m from lift face to the west;
1 x Loader
Barrier 5: Minimum 4 m high noise barrier
shielding POR 8 & POR 9
1 x Rock Drill
Internal Haul Route
Phase South of Pipeline (Existing Licensed Quarry)
Phase South of Pipeline (Expansion Area)
Pipeline Corridor
121
LINE A B
LINE C D
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 27
HUGH WILLIAMSON ASSOCIATES INC.
Figure A1.6: Scenario 2: Worst Case, Phase South of Pipeline - Noise Contours, Day Only: (Noise levels at 4.5 m)
POR 1
POW: 48 dBA
OLA: 48 dBA
POR 2
POW: 45 dBA
OLA: 44 dBA
POR 3
POW: 45 dBA
OLA: 45 dBA
POR 4
POW: 41 dBA
OLA: 40 dBA
POR 5
POW: 43 dBA
OLA: 44 dBA
POR 6
POW: 42 dBA
OLA: 42 dBA
POR 7
POW: 44 dBA
OLA: 43 dBA
POR 8
POW: 44 dBA
OLA: 44 dBA
POR 9
POW: 44 dBA
OLA: 44 dBA
POR 10
POW: 46 dBA
OLA: 45 dBA
POR 11
POW: 49 dBA
OLA: 46 dBA
POR 12
POW: 43 dBA
OLA: 42 dBA
18374000
18374000
18374500
18374500
18375000
18375000
18375500
18375500
18376000
18376000
18376500
18376500
18377000
18377000
18377500
18377500
4906000
4906000
4906500
4906500
4907000
4907000
4907500
4907500
4908000
4908000
4908500
4908500
4909000
4909000
> -99.0 dB
> 35.0 dB
> 40.0 dB
> 45.0 dB
> 50.0 dB
> 55.0 dB
> 60.0 dB
> 65.0 dB
> 70.0 dB
> 75.0 dB
> 80.0 dB
> 85.0 dB
North
Sydenham Road
Elginburg Quarry (Site Boundary)
Burbrook Road
Unity Road
Cordukes Road
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 28
HUGH WILLIAMSON ASSOCIATES INC.
Figure A1.7: Scenario 3: Worst Case - Asphalt Plant, Loading and Shipping Only (Night Operation)
18374400
18374400
18374600
18374600
18374800
18374800
18375000
18375000
18375200
18375200
18375400
18375400
18375600
18375600
18375800
18375800
18376000
18376000
18376200
18376200
18376400
18376400
18376600
18376600
18376800
18376800
18377000
18377000
4906600
4906600
4906800
4906800
4907000
4907000
4907200
4907200
4907400
4907400
4907600
4907600
4907800
4907800
4908000
4908000
4908200
4908200
4908400
4908400
North
POR 5
Sydenham Road
POR 6
POR 1
POR 2
POR 3
POR 4
POR 12 POR 11 POR 10
POR 9
POR 8
POR 7
Site Entry
140
136
90
105
1 x Asphalt Plant with associated diesel
generator; 1 x Loader
Internal Haul Route
Barrier 1: Minimum 4 m high noise barrier
shielding POR 1 from Internal Haul Route
Barrier 7: Minimum 4 m high noise barrier
shielding Asphalt Plant to
POR 3
Barrier 6: Minimum 4 m high noise barrier
shielding Asphalt Plant to POR 9
1 x Loader (Quarry Operation)
Internal Haul Route
Barrier 8: Minimum 4 m high noise barrier
shielding Asphalt Plant to
POR 3
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 29
HUGH WILLIAMSON ASSOCIATES INC.
Figure A1.8: Scenario 3: Worst Case, Noise Contours, Night Operation: (Noise levels at 4.5 m)
POR 1
POW: 42 dBA
OLA: 42 dBA
POR 2
POW: 42 dBA
OLA: 40 dBA
POR 3
POW: 40 dBA
OLA: 40 dBA
POR 4
POW: 36 dBA
OLA: 36 dBA
POR 5
POW: 36 dBA
OLA: 36 dBA
POR 6
POW: 34 dBA
OLA: 33 dBA
POR 7
POW: 35 dBA
OLA: 33 dBA
POR 8
POW: 37 dBA
OLA: 35 dBA
POR 9
POW: 38 dBA
OLA: 38 dBA
POR 10
POW: 41 dBA
OLA: 41 dBA
POR 11
POW: 44 dBA
OLA: 41 dBA
POR 12
POW: 39 dBA
OLA: 38 dBA
18374000
18374000
18374500
18374500
18375000
18375000
18375500
18375500
18376000
18376000
18376500
18376500
18377000
18377000
18377500
18377500
4906000
4906000
4906500
4906500
4907000
4907000
4907500
4907500
4908000
4908000
4908500
4908500
4909000
4909000
> -99.0 dB
> 35.0 dB
> 40.0 dB
> 45.0 dB
> 50.0 dB
> 55.0 dB
> 60.0 dB
> 65.0 dB
> 70.0 dB
> 75.0 dB
> 80.0 dB
> 85.0 dB
North
Sydenham Road
Elginburg Quarry (Site Boundary)
Burbrook Road
Unity Road
Cordukes Road
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 30
HUGH WILLIAMSON ASSOCIATES INC.
Appendix 2
Zoning Plan and Land Use
Designations
Contents:
Zoning Plan, source: Schedule ‘A’ Zone Maps, Township of Kingston, Zoning By-Law No.76-26 - Map 1
Legend for Land Use Designations: ZONES SYMBOLS
Environmental Protection Area Zone EPA
Open Space Zone OS
Restricted Agricultural Zone A1
General Agricultural Zone A2
Residential Type 1 Zone R1
Residential Type 2 Zone R2
Residential Type 3 Zone R3
Residential Type 4 Zone R4
Service Industrial Zone M3
Extractive Industrial Zone M5
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 31
HUGH WILLIAMSON ASSOCIATES INC.
Zoning Plan, source: Schedule ‘A’ Zone Maps, Township of Kingston, Zoning By-Law No.76-26 - Map 1
Elginburg Quarry Site (Existing Licensed
Area)
A2
North
Existing Solar Farm located at
2490 Unity Road
Vacant Lot (Location of possible future noise sensitive
point of reception consistent with existing
development fabric)
Elginburg Quarry Site
(Expansion Area)
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 32
HUGH WILLIAMSON ASSOCIATES INC.
Appendix 3
Acoustic Modelling Details
Modeling Notes:
1. Acoustic model developed uses Cadna-A software, Version 4.4.145.
2. Sound propagation is modeled according to ISO 9613-2: 1996(E).
3. The whole of the extraction area is modeled as reflective, a conservative assumption.
4. MoE favoured conservative modelling assumptions are used, that is, ‘no subtraction of negative ground attenuation’ and ‘no negative path differences’.
Contents: Table A3.1 Calculation Configuration
Table A3.2 Point of Reception Location Table
Table A3.3 Point Sources
Table A3.4 Line Sources
Table A3.5 Noise Source Library
Table A3.6.1 Point of Reception Impacts by Source for Scenario 1
Table A3.6.2 Point of Reception Impacts by Source for Scenario 2
Table A3.6.3 Point of Reception Impacts by Source for Scenario 3
Table A3.7 Distance from Point of Reception to Source
Table A3.8 Noise Measurement Data
Table A3.9 Sample Calculation
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 33
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.1 Calculation Configuration
Configuration
Parameter Value
General
Country (user defined)
Max. Error (dB) 0.00
Max. Search Radius (m) 5000.00
Min. Dist Src to Rcvr 0.00
Partition
Raster Factor 0.50
Max. Length of Section (m) 1000.00
Min. Length of Section (m) 1.00
Min. Length of Section (%) 0.00
Proj. Line Sources On
Proj. Area Sources On
Ref. Time
Reference Time Day (min) 60.00
Reference Time Night (min) 60.00
Daytime Penalty (dB) 0.00
Recr. Time Penalty (dB) 6.00
Night-time Penalty (dB) 10.00
DTM
Standard Height (m) 0.00
Model of Terrain Triangulation
Reflection
max. Order of Reflection 0
Search Radius Src 100.00
Search Radius Rcvr 100.00
Max. Distance Source - Rcvr 1000.00 1000.00
Min. Distance Rvcr - Reflector 1.00 1.00
Min. Distance Source - Reflector 0.10
Industrial (ISO 9613)
Lateral Diffraction some Obj
Obst. within Area Src do not shield On
Screening Excl. Ground Att. over Barrier
Dz with limit (20/25)
Barrier Coefficients C1,2,3 3.0 20.0 0.0
Temperature (°C) 10
rel. Humidity (%) 70
Ground Absorption G 1.00
Wind Speed for Dir. (m/s) 3.0
Roads (RLS-90)
Strictly acc. to RLS-90
Railways (Schall 03)
Strictly acc. to Schall 03 / Schall-Transrapid
Aircraft (???)
Strictly acc. to AzB
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 34
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.2 Point of Reception Location Table
Name ID Height Coordinates, ground
Above Ground
X Y Z
(m) (m) (m) (m)
POR 1 W POR_1_W 2 18375370 4908391 140.5
POR 1 OLA POR_1_OLA 1.5 18375371 4908366 140.2
POR 2 W POR_2_W 4.5 18376140 4908387 136.2
POR 2 OLA POR_2_OLA 1.5 18376097 4908386 133.0
POR 3 W POR_3_W 2 18376311 4908282 132.5
POR 3 OLA POR_3_OLA 1.5 18376281 4908279 131.9
POR 4 W POR_4_W 4.5 18377053 4907347 114.7
POR 4 OLA POR_4_OLA 1.5 18377003 4907346 114.8
POR 5 W POR_5_W 2 18376134 4906465 115.0
POR 5 OLA POR_5_OLA 1.5 18376110 4906517 111.5
POR 6 W POR_6_W 2 18375394 4906494 92.6
POR 6 OLA POR_6_OLA 1.5 18375391 4906530 97.7
POR 7 W POR_7_W 4.5 18374666 4906281 104.1
POR 7 OLA POR_7_OLA 1.5 18374681 4906303 102.7
POR 8 W POR_8_W 4.5 18374453 4906694 135.9
POR 8 OLA POR_8_OLA 1.5 18374483 4906694 132.6
POR 9 W POR_9_W 2 18374468 4907280 137.0
POR 9 OLA POR_9_OLA 1.5 18374498 4907280 136.5
POR 10 W POR_10_W 2 18374904 4908405 140.5
POR 10 OLA POR_10_OLA 1.5 18374936 4908404 139.5
POR 11 W POR_11_W 4.5 18375041 4908465 143.6
POR 11 OLA POR_11_OLA 1.5 18375060 4908456 140.5
POR 12 W POR_12_W 1.5 18375918 4908527 135.4
POR 12 OLA POR_12_OLA 1.5 18375914 4908478 134.6
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 35
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.3 Point Sources
Name Result. PWL Lw / Li Noise Source Operating Time Direct. Source
Day Evening Night Type Library File Day Evening Night Height
(dBA) (dBA) (dBA) (min/Hr) (min/Hr) (min/Hr) (m)
Primary Crushing Unit (Hopper and Loader)
119 119 119 Lw N1 (none) 3
Primary Screen, 2nd and 3rd Crush and Screen Units
118 118 118 Lw N2 (none) 3
Crusher (Generator) 102 102 102 Lw N3 (none) 2
N4_ Washplant 115 115 115 Lw N4 (none) 2
N5 - Washplant Hopper/Loader
113 113 113 Lw N5 (none) 3
N6_Washplant_Generator 107 107 107 Lw N6 (none) 2
Asphalt Plant (Truck Loading and Batch Tower)
104 104 104 Lw N7 (none) 2
Asphalt Plant (Dryer)) 107 107 107 Lw N8 (none) 2
Asphalt Plant (RAP Screen) 111 111 111 Lw N9 (none) 2
Asphalt Plant (Aggregate Bin and Screen)
104 104 104 Lw N10 (none) 3
Loader at Asphalt Plant (Hopper Loader)
104 104 104 Lw N11 (none) 2
Asphalt Plant (Cyclone Fan) 111 111 111 Lw N12 (none) 2
Asphalt Plant (Heater Blower)
108 108 108 Lw N13 (none) 3
Asphalt Plant (Drum Mixer) 114 114 114 Lw N14 (none) 2
Asphalt Plant (Compressor) 100 100 100 Lw N15 (none) 4
South Washplant (Generator and Loader)
110 110 110 Lw N16 (none) 2
South Washplant (Pumps) 110 110 110 Lw N17 (none) 2
Rock Drill 118.6 118.6 118.6 Lw Rockdrill_TH_70 (none) 2
Rock Drill Smart Rig 108.3 108.3 108.3 Lw Rockdrill_SmartRIG (none) 2
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 36
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.4 Line Sources
Name Point Source PWL Numbers of vehicles per hour Modelling Type/ Noise Source Lib. File
Speed
Day Evening Night Day Evening Night
(dBA) (dBA) (dBA) (km/h)
IHR_Trucks (Washplant) 107.8 - - 12 - -
Moving Point Source/ HWYTruck_Slow58
20
IHR_Trucks (Asphalt Plant) 106.9 - - 12 - - Moving Point Source/
HWYTruck_Slow58 20
IHR_Trucks_S1 (Extraction Area)
105.4 - - 12 - - Moving Point Source/
HWYTruck_Slow58 20
IHR_Trucks (Asphalt Plant) 108.7 - - 12 - - Moving Point Source/
HWYTruck_Slow58 20
IHR_Trucks_S2 (Extraction Area)
110.1 - - 12 - - Moving Point Source/
HWYTruck_Slow58 20
IHR_Trucks (Asphalt Plant) - 103.1 103.1 - 5 5 Moving Point Source/
HWYTruck_Slow58 20
IHR_Trucks_S3 (Extraction Area)
- 107.7 107.7 - 5 5 Moving Point Source/
HWYTruck_Slow58 20
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 37
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.5 Noise Source Library
ID Type Spectra (dB) Source*
31.5 63 125 250 500 1000 2000 4000 8000 A lin
N1 Lw 123.5 126.5 129.5 114.5 113.5 112.5 111.5 106.5 96.5 119 132.2 Measured at Elginburg Quarry by Golder, 2010
N2 Lw 121.6 122.6 126.6 120.6 112.6 109.6 109.6 105.6 99.6 118 129.7 Measured at Elginburg Quarry by Golder, 2010
N3 Lw 102.7 105.7 113.7 99.7 98.7 92.7 92.7 87.7 79.7 102 114.9 Measured at Elginburg Quarry by Golder, 2010
N4 Lw 113.3 117.3 118.3 113.3 110.3 110.3 108.3 101.3 95.3 115 122.9 Measured at Elginburg Quarry by Golder, 2010
N5 Lw 121.3 123.3 115.3 111.3 107.3 107.3 106.3 102.3 100.3 113 126.2 Measured at Elginburg Quarry by Golder, 2010
N6 Lw 102.7 111.7 109.7 103.7 103.7 100.7 100.7 95.7 92.7 107 115.3 Measured at Elginburg Quarry by Golder, 2010
N7 Lw 111.1 117.1 116.1 103.1 98.1 95.1 93.1 91.1 89.1 104 120.3 Measured at Elginburg Quarry by Golder, 2010
N8 Lw 113.9 115.9 118.9 108.9 100.9 99.9 93.9 87.9 84.9 107 121.8 Measured at Elginburg Quarry by Golder, 2010
N9 Lw 113.2 115.2 118.2 107.2 103.2 108.2 102.2 92.2 86.2 111 121.3 Measured at Elginburg Quarry by Golder, 2010
N10 Lw 103.2 107.2 112.2 106.2 100.2 96.2 95.2 90.2 85.2 104 114.8 Measured at Elginburg Quarry by Golder, 2010
N11 Lw 102.3 106.3 107.3 102.3 99.3 99.3 97.3 90.3 84.3 104 111.9 Measured at Elginburg Quarry by Golder, 2010
N12 Lw 113.7 117.7 112.7 110.7 103.7 107.7 102.7 97.7 93.7 111 120.9 Measured at Elginburg Quarry by Golder, 2010
N13 Lw 112.9 112.9 116.9 107.9 101.9 102.9 98.9 94.9 91.9 108 120 Measured at Elginburg Quarry by Golder, 2010
N14 Lw 115.1 115.1 113.1 110.1 115.1 106.1 102.1 96.1 99.1 114 121.3 Measured at Elginburg Quarry by Golder, 2010
N15 Lw 107.6 113.6 112.6 97.6 92.6 90.6 88.6 86.6 88.6 100 116.8 Measured at Elginburg Quarry by Golder, 2010
N16 Lw 117.6 117.6 116.6 109.6 107.6 103.6 101.6 95.6 90.6 110 122.5 Measured at Elginburg Quarry by Golder, 2010
N17 Lw 105.8 106.8 110.8 111.8 108.8 100.8 101.8 96.8 88.8 110 116.7 Measured at Elginburg Quarry by Golder, 2010
N18 Lw 113.3 117.3 118.3 113.3 110.3 110.3 108.3 101.3 95.3 115 122.9 Measured at Elginburg Quarry by Golder, 2010
Rockdrill_TH_70 Lw 111.2 110.6 112.4 108.9 108.7 109.3 113.6 112.2 109.9 118.6 120.6 Furukawa Model HCR12-ES Rock Drill Measured 2007*
Rockdrill_SmartRIG Lw 103.4 109.4 112.6 106.8 102.2 101.7 102.5 98.6 91.3 108.3 116 Measured 30/08/11 and 21/05/2009**
HWYTruck_Slow58 Lw 115.9 112.7 110.2 101.6 101.4 105 104.2 97.6 103.5 110.1 119 Brockville McDowell Study, 2003
Loader Lw 103.4 110.4 114.1 113.6 107.1 104.1 97.2 91.2 83.6 109.9 118.5 HW Historical Meas*
* Measured by Hugh Williamson Associates at a similar facility or in similar circumstances in Ontario. Refer to Table A3.8 for noise measurement data. ** J.E.Coulter Associates Ltd.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 38
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.6.1 Point of Reception Impacts by Source for Scenario 1, day only*
Daytime Period (07:00 to 19:00)
POR 1 W
POR 1
OLA
POR 2 W
POR 2
OLA
POR 3 W
POR 3
OLA
POR 4 W
POR 4
OLA
POR 5 W
POR 5
OLA
POR 6 W
POR 6
OLA
POR 7 W
POR 7
OLA
POR 8 W
POR 8
OLA
POR 9 W
POR 9
OLA
POR 10 W
POR 10
OLA
POR 11 W
POR 11
OLA
POR 12 W
POR 12
OLA
Sources dBA dBA dBA dBA dBA dBA dBA dBA dBA dBA dBA dBA
N1_Crusher_S1 41 41 35 34 36 36 34 33 34 34 27 27 30 29 35 31 38 38 44 44 41 41 35 34
N2_Crusher_S1 39 40 34 32 35 34 33 32 33 33 26 25 30 28 35 30 37 37 42 42 39 39 33 33
N3_Crusher_S1 23 24 18 17 19 19 17 17 18 18 11 10 14 13 19 14 21 22 27 27 24 24 17 17
N4_ Washplant 31 30 34 32 35 36 32 32 33 33 27 25 25 23 32 24 33 32 34 32 38 26 29 27
N5_Washplant_Loader 30 30 32 31 33 34 30 30 31 31 27 26 26 25 31 26 32 32 32 30 36 25 27 26
N6_Washplant_Generator 23 23 27 24 28 28 24 23 25 25 19 18 23 20 25 17 25 25 26 24 30 18 20 19
N7_Asphalt_Plant 27 27 29 28 28 28 23 23 22 22 21 21 21 21 23 22 28 28 25 25 26 22 28 26
N8_Asphalt_Plant 30 29 34 32 33 33 26 26 25 25 24 24 24 23 25 25 30 30 28 26 28 24 32 30
N9_Asphalt_Plant 40 39 35 34 35 35 28 28 27 28 28 27 26 25 28 27 34 34 30 29 38 36 33 30
N10_Asphalt_Plant 32 33 31 29 28 28 22 21 20 21 21 21 20 18 21 20 25 24 26 28 31 29 27 25
N11_Asphalt_Plant 33 33 28 23 24 24 21 20 24 20 21 20 19 18 20 19 26 26 28 28 30 28 25 23
N12_Asphalt_Plant 32 32 37 35 36 36 28 27 27 27 24 23 25 24 27 26 33 33 30 29 30 26 33 31
N13_Asphalt_Plant 32 31 35 34 33 33 25 25 24 24 22 22 24 22 25 24 30 29 29 28 29 25 31 28
N14_Asphalt_Plant 35 34 36 33 34 34 32 31 31 31 26 26 30 28 32 30 37 36 31 30 32 27 31 31
N15_Asphalt_Plant 29 29 27 27 26 26 19 19 22 19 18 18 17 17 19 18 23 23 24 24 24 21 25 24
Low_Noise_Rock_Drill_S1 46 46 31 30 28 28 21 20 21 21 20 19 21 20 27 22 30 29 42 42 44 41 31 30
IHR_Trucks_Washplant 30 30 30 30 31 30 24 24 27 26 22 20 21 20 25 22 26 26 27 27 29 24 27 24
IHR_Trucks_S1 39 39 31 32 27 27 18 18 21 19 13 13 17 16 21 19 25 24 29 29 31 29 31 31
IHR_Trucks_S1 32 32 28 28 26 26 17 17 18 18 12 11 17 15 19 18 23 23 32 31 30 26 28 27
Total 50 50 45 44 45 45 41 40 41 41 36 36 38 36 41 38 45 44 48 48 49 46 43 42
* Values at first floor window height (W) at 4.5 m or 2 m and Outdoor Living Area (OLA) at 1.5 m are given above as these where the most critical points at each receptor.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 39
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.6.2 Point of Reception Impacts by Source for Scenario 2, day only*
Daytime Period (07:00 to 19:00)
POR 1 W
POR 1
OLA
POR 2 W
POR 2
OLA
POR 3 W
POR 3
OLA
POR 4 W
POR 4
OLA
POR 5 W
POR 5
OLA
POR 6 W
POR 6
OLA
POR 7 W
POR 7
OLA
POR 8 W
POR 8
OLA
POR 9 W
POR 9
OLA
POR 10 W
POR 10
OLA
POR 11 W
POR 11
OLA
POR 12 W
POR 12
OLA
Source dBA dBA dBA dBA dBA dBA dBA dBA dBA dBA dBA dBA
N4_Washplant 33 36 34 32 35 36 32 32 33 33 31 29 25 23 28 24 31 31 37 36 38 36 29 27
N5_Washplant_Loader 32 30 32 31 33 34 30 30 31 31 30 28 26 25 29 26 32 32 34 34 36 34 27 26
N6_Washplant_Generator 25 23 27 24 28 28 24 23 25 25 23 21 24 22 21 17 24 24 28 28 30 28 20 19
N7_Asphalt_Plant 27 27 29 28 28 28 23 23 22 22 21 21 21 21 23 22 25 25 30 28 31 29 28 26
N8_Asphalt_Plant 30 29 34 32 33 33 26 26 25 25 24 24 24 23 25 25 28 28 31 29 32 30 32 30
N9_Asphalt_Plant 40 39 35 34 35 35 28 28 27 28 28 27 26 25 28 27 30 30 35 36 42 41 33 30
N10_Asphalt_Plant 32 33 31 29 28 28 22 21 20 21 21 21 20 18 21 20 23 22 30 31 35 32 27 25
N11_Asphalt_Plant 33 33 28 23 24 24 21 20 24 20 21 20 19 18 20 19 26 22 28 28 35 29 25 23
N12_Asphalt_Plant 32 32 37 35 36 36 28 27 27 27 24 23 25 24 27 26 29 29 34 33 36 33 33 31
N13_Asphalt_Plant 32 31 35 34 33 33 25 25 24 24 22 22 24 22 25 24 27 27 32 32 34 31 31 28
N14_Asphalt_Plant 35 34 36 33 34 34 32 31 31 31 26 26 30 28 32 30 33 33 36 34 39 34 31 31
N15_Asphalt_Plant 29 29 27 27 26 26 19 19 22 19 18 18 17 17 19 18 23 23 25 25 27 26 25 24
Rock_Drill_S2 28 28 27 25 25 25 28 23 35 34 39 39 39 39 36 36 40 40 28 28 33 27 25 26
N1_Crusher_S2 36 36 35 34 34 34 32 32 38 38 33 33 39 38 39 39 36 37 36 36 36 36 34 33
N2_Crusher_S2 35 35 34 33 33 32 32 31 37 37 31 31 38 37 38 37 35 35 35 35 35 35 33 32
N3_Crusher_S2 20 19 18 17 17 17 16 15 22 22 16 16 22 22 23 23 20 20 20 20 20 19 17 17
IHR_Trucks_Washplant 31 31 30 30 31 30 24 24 27 26 22 20 21 21 25 22 25 25 29 28 31 29 27 24
IHR_Trucks_S2 44 44 34 34 32 32 22 21 23 22 19 18 20 19 25 21 27 26 36 36 38 36 35 36
IHR_Trucks_S2 29 29 27 27 26 26 22 21 28 28 23 22 28 27 32 30 32 30 27 27 28 27 26 25
Total 48 48 46 44 45 45 41 40 44 44 42 42 44 43 44 44 45 45 46 45 49 46 43 42
* Values at first floor window height (W) at 4.5 m or 2 m and Outdoor Living Area (OLA) at 1.5 m are given above as these where the most critical points at each receptor.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 40
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.6.3 Point of Reception Impacts by Source for Scenario 3, evening and night*
Evening and Nighttime Period (19:00 to 07:00)
POR 1 W
POR 1
OLA
POR 2 W
POR 2
OLA
POR 3 W
POR 3
OLA
POR 4 W
POR 4
OLA
POR 5 W
POR 5
OLA
POR 6 W
POR 6
OLA
POR 7 W
POR 7
OLA
POR 8 W
POR 8
OLA
POR 9 W
POR 9
OLA
POR 10 W
POR 10
OLA
POR 11 W
POR 11
OLA
POR 12 W
POR 12
OLA
Source dBA dBA dBA dBA dBA dBA dBA dBA dBA dBA dBA dBA
N7_Asphalt_Plant 27 27 28 28 26 26 23 23 22 22 21 21 21 21 23 22 25 25 30 29 31 29 28 26
N8_Asphalt_Plant 30 29 32 31 32 32 26 26 25 25 24 24 24 23 25 25 28 28 31 29 31 29 30 29
N9_Asphalt_Plant 30 30 32 31 29 29 28 28 27 28 28 27 26 25 28 27 30 30 29 29 34 32 29 29
N10_Asphalt_Plant 29 29 31 29 27 26 22 21 20 21 22 21 20 18 21 20 23 22 28 28 31 29 27 25
N11_Asphalt_Plant 33 33 28 23 20 20 21 20 24 20 21 20 19 18 20 19 26 22 28 28 35 29 25 23
N12_Asphalt_Plant 32 32 37 33 34 34 28 27 27 27 24 24 25 24 27 26 29 29 34 33 36 33 31 29
N13_Asphalt_Plant 32 31 34 32 32 31 25 25 24 24 23 23 24 22 25 24 27 27 32 32 34 31 30 28
N14_Asphalt_Plant 35 34 34 31 30 30 32 31 31 31 26 26 30 28 32 30 33 33 36 35 39 34 30 30
N15_Asphalt_Plant 29 29 27 27 25 25 19 19 22 19 18 18 17 17 19 18 23 23 25 25 27 26 25 24
Loader_S3 20 19 18 17 17 16 15 13 22 22 14 14 18 18 20 16 14 14 19 19 20 19 17 17
IHR_Trucks_S3 35 35 27 28 23 23 14 14 16 15 9 8 13 12 17 15 20 20 29 28 29 29 27 27
IHR_Trucks_S3 28 28 27 27 26 26 22 21 26 26 20 19 24 23 32 27 29 27 26 26 28 27 25 23
Total 42 42 42 40 40 40 37 36 36 36 34 33 35 33 37 35 38 38 41 41 44 41 39 38
* Values at first floor window height (W) at 4.5 m or 2 m and Outdoor Living Area (OLA) at 1.5 m are given above as these where the most critical points at each receptor.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 41
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.7 Distance from Point of Reception to Source
Source
Coordinates Distance from Point of Reception to Source (m)
Source ID X
(m) Y
(m) POR
1 W
POR 1
OLA
POR 2 W
POR 2
OLA
POR 3 W
POR 3
OLA
POR 4 W
POR 4
OLA
POR 5 W
POR 5
OLA
POR 6 W
POR 6
OLA
POR 7 W
POR 7
OLA
POR 8 W
POR 8
OLA
POR 9 W
POR 9
OLA
POR 10 W
POR 10
OLA
POR 11 W
POR 11
OLA
POR 12 W
POR 12
OLA
Low_Noise_Rock_Drill_S1 2E+0
7 5E+0
6 204 192 948 905 1113 1083 2077 2033 2043 1986 1797 1761 2070 2045 1754 1741 1239 1222 319 289 242 223 761 742
N1_Crusher_S1 2E+0
7 5E+0
6 320 305 1033 990 1188 1158 2099 2053 1990 1933 1708 1672 1956 1931 1634 1622 1118 1100 315 293 296 282 863 840
N2_Crusher_S1 2E+0
7 5E+0
6 318 303 1030 988 1185 1155 2097 2051 1990 1933 1709 1673 1958 1932 1635 1623 1120 1102 317 294 296 282 860 838
N3_Crusher_S1 2E+0
7 5E+0
6 318 303 1032 989 1187 1157 2099 2053 1992 1935 1710 1674 1959 1933 1636 1624 1120 1102 314 292 295 280 861 839
N4_Washplant 2E+0
7 5E+0
6 721 697 887 860 936 911 1518 1469 1356 1299 1221 1185 1687 1660 1509 1487 1187 1159 974 951 933 915 893 847
N5_Washplant_Loader 2E+0
7 5E+0
6 713 689 871 843 919 894 1509 1461 1361 1304 1234 1199 1703 1677 1526 1504 1202 1174 974 951 931 913 878 831
N6_Washplant_Generator 2E+0
7 5E+0
6 727 703 882 855 929 904 1506 1457 1348 1291 1219 1184 1691 1664 1516 1494 1197 1169 984 962 943 924 892 845
N7_Asphalt_Plant 2E+0
7 5E+0
6 562 539 734 703 810 783 1542 1495 1512 1455 1404 1368 1857 1830 1656 1635 1288 1262 876 850 813 793 716 671
N8_Asphalt_Plant 2E+0
7 5E+0
6 567 545 728 697 803 775 1533 1486 1507 1450 1404 1369 1860 1834 1662 1641 1296 1270 884 858 820 801 714 667
N9_Asphalt_Plant 2E+0
7 5E+0
6 565 542 720 689 794 767 1529 1482 1511 1454 1411 1376 1869 1842 1670 1649 1304 1278 886 860 820 801 706 659
N10_Asphalt_Plant 2E+0
7 5E+0
6 575 552 716 686 788 761 1517 1470 1501 1444 1407 1372 1869 1842 1674 1653 1311 1285 898 872 832 812 706 660
N11_Asphalt_Plant 2E+0
7 5E+0
6 571 549 688 658 759 732 1501 1455 1510 1453 1427 1392 1896 1869 1702 1681 1339 1313 907 881 837 817 682 635
N12_Asphalt_Plant 2E+0
7 5E+0
6 570 547 731 700 804 777 1532 1485 1504 1447 1401 1366 1858 1831 1659 1638 1295 1268 886 861 823 803 716 670
N13_Asphalt_Plant 2E+0
7 5E+0
6 565 542 731 700 806 779 1537 1490 1509 1452 1403 1368 1859 1832 1659 1638 1293 1266 881 855 817 798 715 669
N14_Asphalt_Plant 2E+0
7 5E+0
6 562 539 731 700 806 779 1540 1493 1512 1455 1406 1370 1860 1833 1659 1638 1292 1266 878 852 814 794 714 668
N15_Asphalt_Plant 2E+0
7 5E+0
6 563 541 729 698 804 777 1537 1490 1511 1454 1406 1371 1861 1834 1661 1640 1294 1268 880 854 816 796 713 667
Rock_Drill_S2 2E+0
7 5E+0
6 1841 1818 2206 2179 2237 2214 2372 2324 1359 1329 624 614 383 357 338 308 711 699 1764 1766 1839 1832 2196 2152
N1_Crusher_S2 2E+0
7 5E+0
6 1667 1643 2037 2009 2073 2050 2264 2215 1323 1288 622 602 558 532 418 389 612 594 1600 1600 1670 1663 2023 1979
N2_Crusher_S2 2E+0
7 5E+0
6 1674 1651 2043 2015 2078 2055 2265 2216 1321 1286 617 598 551 525 416 387 619 601 1608 1608 1678 1671 2029 1985
N3_Crusher_S2 2E+0
7 5E+0
6 1668 1645 2036 2008 2071 2048 2258 2209 1316 1280 614 594 557 531 423 394 620 601 1603 1604 1673 1666 2022 1978
Loader_S3 2E+0
7 5E+0
6 1733 1710 2103 2076 2138 2115 2310 2261 1341 1307 623 607 491 466 374 344 641 625 1660 1662 1733 1726 2090 2046
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 42
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.8 Noise Measurement Data
ID Type Spectra (dB)
Notes
31.5 63 125 250 500 1000 2000 4000 8000 A lin
Loader (CAT Model 950G)
Lp 59.8 66.8 70.5 70 63.4 60.3 53.1 45.7 33 66.1 74.8 Measured at 60 m
(April 2004 at Dimension Stone Quarry near Orillia, Ontario)
Rockdrill_TH_70 (Hydraulic Rock Drill: Furukawa HCR12-ES)
Lp 62.4 61.8 63.6 60.1 59.9 61 64.8 63.4 61.1 69.8 71.8 Measured at 90 m
(3 May 2007 at Braeside, Ontario)
HWYTruck_Slow58 Lp 80.8 77.6 75.1 66.5 66.3 69.9 69.1 62.5 68.4 75 83.9 Measured at 15 m (2003 from
Brockville McDowell measurements)
Meas_N1 Lp 86 89 92 77 76 75 74 69 59 81.5 94.7 Measured at Elginburg Quarry by
Golder June 2010
Meas_N2 Lp 82 83 87 81 73 70 70 66 60 78.4 90.1 Measured at Elginburg Quarry by
Golder June 2010
Meas_N3 Lp 90 93 101 87 86 80 80 75 67 89.3 102.2 Measured at Elginburg Quarry by
Golder June 2010
Meas_N4 Lp 73 77 78 73 70 70 68 61 55 74.7 82.6 Measured at Elginburg Quarry by
Golder June 2010
Meas_N5 Lp 84 86 78 74 70 70 69 65 63 75.7 88.9 Measured at Elginburg Quarry by
Golder June 2010
Meas_N6 Lp 74 83 81 75 75 72 72 67 64 78.3 86.6 Measured at Elginburg Quarry by
Golder June 2010
Meas_N7 Lp 82 88 87 74 69 66 64 62 60 74.9 91.2 Measured at Elginburg Quarry by
Golder June 2010
Meas_N8 Lp 77 79 82 72 64 63 57 51 48 70.1 84.9 Measured at Elginburg Quarry by
Golder June 2010
Meas_N9 Lp 76 78 81 70 66 71 65 55 49 73.8 84.1 Measured at Elginburg Quarry by
Golder June 2010
Meas_N10 Lp 81 85 90 84 78 74 73 68 63 81.8 92.6 Measured at Elginburg Quarry by
Golder June 2010
Meas_N11 Lp 73 77 78 73 70 70 68 61 55 74.7 82.6 Measured at Elginburg Quarry by
Golder June 2010
Meas_N12 Lp 82 86 81 79 72 76 71 66 62 79.3 89.2 Measured at Elginburg Quarry by
Golder June 2010
Meas_N13 Lp 82 82 86 77 71 72 68 64 61 77.1 89.1 Measured at Elginburg Quarry by
Golder June 2010
Meas_N14 Lp 79 79 77 74 79 70 66 60 63 77.9 85.2 Measured at Elginburg Quarry by
Golder June 2010
Meas_N15 Lp 76 82 81 66 61 59 57 55 57 68.4 85.2 Measured at Elginburg Quarry by
Golder June 2010
Meas_N16 Lp 78 78 77 70 68 64 62 56 51 70.4 82.9 Measured at Elginburg Quarry by
Golder June 2010
Meas_N17 Lp 70 71 75 76 73 65 66 61 53 74.2 80.9 Measured at Elginburg Quarry by
Golder June 2010
Meas_N18 Lp 73 77 78 73 70 70 68 61 55 74.7 82.6 Measured at Elginburg Quarry by
Golder June 2010
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 43
HUGH WILLIAMSON ASSOCIATES INC.
Table A3.9 Sample Calculations – Scenario 1
Receiver Name: POR 1 W ID: POR_1_W X: 18375369.84 Y: 4908391.26 Z: 140.54
Point Source, ISO 9613, Name: ''Primary Crushing Unit (Hopper and Loader)'', ID: ''N1_Crusher_S1''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375127.73 4908181.87 127.50 0 32 84.1 84.1 0.0 0.0 61.1 0.0 -4.7 0.0 0.0 9.2 0.0 -0.0 18.5 18.5
2 18375127.73 4908181.87 127.50 0 63 100.3 100.3 0.0 0.0 61.1 0.0 -4.7 0.0 0.0 11.7 0.0 -0.0 32.2 32.2
3 18375127.73 4908181.87 127.50 0 125 113.4 113.4 0.0 0.0 61.1 0.1 -0.6 0.0 0.0 14.4 0.0 -0.0 38.4 38.4
4 18375127.73 4908181.87 127.50 0 250 105.9 105.9 0.0 0.0 61.1 0.3 3.3 0.0 0.0 13.8 0.0 -0.0 27.3 27.3
5 18375127.73 4908181.87 127.50 0 500 110.3 110.3 0.0 0.0 61.1 0.6 -0.4 0.0 0.0 20.1 0.0 -0.0 28.9 28.9
6 18375127.73 4908181.87 127.50 0 1000 112.5 112.5 0.0 0.0 61.1 1.2 -2.5 0.0 0.0 23.0 0.0 -0.0 29.7 29.7
7 18375127.73 4908181.87 127.50 0 2000 112.7 112.7 0.0 0.0 61.1 3.1 -2.6 0.0 0.0 25.0 0.0 -0.0 26.1 26.1
8 18375127.73 4908181.87 127.50 0 4000 107.5 107.5 0.0 0.0 61.1 10.5 -2.6 0.0 0.0 25.0 0.0 -0.0 13.5 13.5
9 18375127.73 4908181.87 127.50 0 8000 95.4 95.4 0.0 0.0 61.1 37.4 -2.6 0.0 0.0 25.0 0.0 -0.0 -25.5 -25.5
Point Source, ISO 9613, Name: ''Primary Screen, 2nd and 3rd Crush and Screen Units '', ID: ''N2_Crusher_S1''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375130.03 4908182.60 127.50 0 32 82.2 82.2 0.0 0.0 61.0 0.0 -4.7 0.0 0.0 9.3 0.0 -0.0 16.5 16.5
2 18375130.03 4908182.60 127.50 0 63 96.4 96.4 0.0 0.0 61.0 0.0 -4.7 0.0 0.0 11.9 0.0 -0.0 28.1 28.1
3 18375130.03 4908182.60 127.50 0 125 110.5 110.5 0.0 0.0 61.0 0.1 -0.6 0.0 0.0 14.6 0.0 -0.0 35.4 35.4
4 18375130.03 4908182.60 127.50 0 250 112.0 112.0 0.0 0.0 61.0 0.3 3.4 0.0 0.0 14.0 0.0 -0.0 33.2 33.2
5 18375130.03 4908182.60 127.50 0 500 109.4 109.4 0.0 0.0 61.0 0.6 -0.4 0.0 0.0 20.3 0.0 -0.0 27.9 27.9
6 18375130.03 4908182.60 127.50 0 1000 109.6 109.6 0.0 0.0 61.0 1.2 -2.5 0.0 0.0 23.2 0.0 -0.0 26.6 26.6
7 18375130.03 4908182.60 127.50 0 2000 110.8 110.8 0.0 0.0 61.0 3.1 -2.6 0.0 0.0 25.0 0.0 -0.0 24.3 24.3
8 18375130.03 4908182.60 127.50 0 4000 106.6 106.6 0.0 0.0 61.0 10.4 -2.6 0.0 0.0 25.0 0.0 -0.0 12.8 12.8
9 18375130.03 4908182.60 127.50 0 8000 98.5 98.5 0.0 0.0 61.0 37.2 -2.6 0.0 0.0 25.0 0.0 -0.0 -22.1 -22.1
Point Source, ISO 9613, Name: ''Crusher (Generator)'', ID: ''N3_Crusher_S1''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375128.40 4908184.07 127.00 0 32 63.3 63.3 0.0 0.0 61.1 0.0 -4.9 0.0 0.0 9.9 0.0 -0.0 -2.8 -2.8
2 18375128.40 4908184.07 127.00 0 63 79.5 79.5 0.0 0.0 61.1 0.0 -4.9 0.0 0.0 12.6 0.0 -0.0 10.7 10.7
3 18375128.40 4908184.07 127.00 0 125 97.6 97.6 0.0 0.0 61.1 0.1 -0.8 0.0 0.0 15.3 0.0 -0.0 21.9 21.9
4 18375128.40 4908184.07 127.00 0 250 91.1 91.1 0.0 0.0 61.1 0.3 3.2 0.0 0.0 15.0 0.0 -0.0 11.5 11.5
5 18375128.40 4908184.07 127.00 0 500 95.5 95.5 0.0 0.0 61.1 0.6 -0.6 0.0 0.0 21.1 0.0 -0.0 13.3 13.3
6 18375128.40 4908184.07 127.00 0 1000 92.7 92.7 0.0 0.0 61.1 1.2 -2.6 0.0 0.0 24.1 0.0 -0.0 9.0 9.0
7 18375128.40 4908184.07 127.00 0 2000 93.9 93.9 0.0 0.0 61.1 3.1 -2.8 0.0 0.0 25.0 0.0 -0.0 7.5 7.5
8 18375128.40 4908184.07 127.00 0 4000 88.7 88.7 0.0 0.0 61.1 10.4 -2.8 0.0 0.0 25.0 0.0 -0.0 -5.0 -5.0
9 18375128.40 4908184.07 127.00 0 8000 78.6 78.6 0.0 0.0 61.1 37.2 -2.8 0.0 0.0 25.0 0.0 -0.0 -41.9 -41.9
Point Source, ISO 9613, Name: ''N4_North Washplant'', ID: ''N4_North Washplant''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375577.26 4907701.11 123.00 0 32 73.9 73.9 0.0 0.0 68.2 0.0 -5.5 0.0 0.0 6.8 0.0 -0.0 4.5 4.5
2 18375577.26 4907701.11 123.00 0 63 91.1 91.1 0.0 0.0 68.2 0.1 -5.5 0.0 0.0 8.2 0.0 -0.0 20.2 20.2
3 18375577.26 4907701.11 123.00 0 125 102.2 102.2 0.0 0.0 68.2 0.3 0.9 0.0 0.0 9.2 0.0 -0.0 23.7 23.7
4 18375577.26 4907701.11 123.00 0 250 104.7 104.7 0.0 0.0 68.2 0.8 2.8 0.0 0.0 9.6 0.0 -0.0 23.4 23.4
5 18375577.26 4907701.11 123.00 0 500 107.1 107.1 0.0 0.0 68.2 1.4 -1.0 0.0 0.0 15.0 0.0 -0.0 23.5 23.5
6 18375577.26 4907701.11 123.00 0 1000 110.3 110.3 0.0 0.0 68.2 2.6 -3.1 0.0 0.0 17.8 0.0 -0.0 24.8 24.8
7 18375577.26 4907701.11 123.00 0 2000 109.5 109.5 0.0 0.0 68.2 7.0 -3.2 0.0 0.0 20.7 0.0 -0.0 16.9 16.9
8 18375577.26 4907701.11 123.00 0 4000 102.3 102.3 0.0 0.0 68.2 23.6 -3.2 0.0 0.0 23.7 0.0 -0.0 -10.0 -10.0
9 18375577.26 4907701.11 123.00 0 8000 94.2 94.2 0.0 0.0 68.2 84.3 -3.2 0.0 0.0 25.0 0.0 -0.0 -80.0 -80.0
Point Source, ISO 9613, Name: ''N5 - North Washplant Hopper/Loader '', ID: ''N5_Washplant_Loader''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375589.32 4907712.54 123.75 0 32 81.9 81.9 0.0 0.0 68.1 0.0 -5.4 0.0 0.0 6.8 0.0 -0.0 12.4 12.4
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 44
HUGH WILLIAMSON ASSOCIATES INC.
Receiver Name: POR 1 W ID: POR_1_W X: 18375369.84 Y: 4908391.26 Z: 140.54
Point Source, ISO 9613, Name: ''Primary Crushing Unit (Hopper and Loader)'', ID: ''N1_Crusher_S1''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375127.73 4908181.87 127.50 0 32 84.1 84.1 0.0 0.0 61.1 0.0 -4.7 0.0 0.0 9.2 0.0 -0.0 18.5 18.5
2 18375127.73 4908181.87 127.50 0 63 100.3 100.3 0.0 0.0 61.1 0.0 -4.7 0.0 0.0 11.7 0.0 -0.0 32.2 32.2
3 18375127.73 4908181.87 127.50 0 125 113.4 113.4 0.0 0.0 61.1 0.1 -0.6 0.0 0.0 14.4 0.0 -0.0 38.4 38.4
4 18375127.73 4908181.87 127.50 0 250 105.9 105.9 0.0 0.0 61.1 0.3 3.3 0.0 0.0 13.8 0.0 -0.0 27.3 27.3
5 18375127.73 4908181.87 127.50 0 500 110.3 110.3 0.0 0.0 61.1 0.6 -0.4 0.0 0.0 20.1 0.0 -0.0 28.9 28.9
6 18375127.73 4908181.87 127.50 0 1000 112.5 112.5 0.0 0.0 61.1 1.2 -2.5 0.0 0.0 23.0 0.0 -0.0 29.7 29.7
7 18375127.73 4908181.87 127.50 0 2000 112.7 112.7 0.0 0.0 61.1 3.1 -2.6 0.0 0.0 25.0 0.0 -0.0 26.1 26.1
8 18375127.73 4908181.87 127.50 0 4000 107.5 107.5 0.0 0.0 61.1 10.5 -2.6 0.0 0.0 25.0 0.0 -0.0 13.5 13.5
9 18375127.73 4908181.87 127.50 0 8000 95.4 95.4 0.0 0.0 61.1 37.4 -2.6 0.0 0.0 25.0 0.0 -0.0 -25.5 -25.5
Point Source, ISO 9613, Name: ''Primary Screen, 2nd and 3rd Crush and Screen Units '', ID: ''N2_Crusher_S1''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375130.03 4908182.60 127.50 0 32 82.2 82.2 0.0 0.0 61.0 0.0 -4.7 0.0 0.0 9.3 0.0 -0.0 16.5 16.5
2 18375130.03 4908182.60 127.50 0 63 96.4 96.4 0.0 0.0 61.0 0.0 -4.7 0.0 0.0 11.9 0.0 -0.0 28.1 28.1
3 18375130.03 4908182.60 127.50 0 125 110.5 110.5 0.0 0.0 61.0 0.1 -0.6 0.0 0.0 14.6 0.0 -0.0 35.4 35.4
4 18375130.03 4908182.60 127.50 0 250 112.0 112.0 0.0 0.0 61.0 0.3 3.4 0.0 0.0 14.0 0.0 -0.0 33.2 33.2
5 18375130.03 4908182.60 127.50 0 500 109.4 109.4 0.0 0.0 61.0 0.6 -0.4 0.0 0.0 20.3 0.0 -0.0 27.9 27.9
6 18375130.03 4908182.60 127.50 0 1000 109.6 109.6 0.0 0.0 61.0 1.2 -2.5 0.0 0.0 23.2 0.0 -0.0 26.6 26.6
7 18375130.03 4908182.60 127.50 0 2000 110.8 110.8 0.0 0.0 61.0 3.1 -2.6 0.0 0.0 25.0 0.0 -0.0 24.3 24.3
8 18375130.03 4908182.60 127.50 0 4000 106.6 106.6 0.0 0.0 61.0 10.4 -2.6 0.0 0.0 25.0 0.0 -0.0 12.8 12.8
9 18375130.03 4908182.60 127.50 0 8000 98.5 98.5 0.0 0.0 61.0 37.2 -2.6 0.0 0.0 25.0 0.0 -0.0 -22.1 -22.1
Point Source, ISO 9613, Name: ''Crusher (Generator)'', ID: ''N3_Crusher_S1''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375128.40 4908184.07 127.00 0 32 63.3 63.3 0.0 0.0 61.1 0.0 -4.9 0.0 0.0 9.9 0.0 -0.0 -2.8 -2.8
2 18375128.40 4908184.07 127.00 0 63 79.5 79.5 0.0 0.0 61.1 0.0 -4.9 0.0 0.0 12.6 0.0 -0.0 10.7 10.7
3 18375128.40 4908184.07 127.00 0 125 97.6 97.6 0.0 0.0 61.1 0.1 -0.8 0.0 0.0 15.3 0.0 -0.0 21.9 21.9
4 18375128.40 4908184.07 127.00 0 250 91.1 91.1 0.0 0.0 61.1 0.3 3.2 0.0 0.0 15.0 0.0 -0.0 11.5 11.5
5 18375128.40 4908184.07 127.00 0 500 95.5 95.5 0.0 0.0 61.1 0.6 -0.6 0.0 0.0 21.1 0.0 -0.0 13.3 13.3
6 18375128.40 4908184.07 127.00 0 1000 92.7 92.7 0.0 0.0 61.1 1.2 -2.6 0.0 0.0 24.1 0.0 -0.0 9.0 9.0
7 18375128.40 4908184.07 127.00 0 2000 93.9 93.9 0.0 0.0 61.1 3.1 -2.8 0.0 0.0 25.0 0.0 -0.0 7.5 7.5
8 18375128.40 4908184.07 127.00 0 4000 88.7 88.7 0.0 0.0 61.1 10.4 -2.8 0.0 0.0 25.0 0.0 -0.0 -5.0 -5.0
9 18375128.40 4908184.07 127.00 0 8000 78.6 78.6 0.0 0.0 61.1 37.2 -2.8 0.0 0.0 25.0 0.0 -0.0 -41.9 -41.9
Point Source, ISO 9613, Name: ''N4_North Washplant'', ID: ''N4_North Washplant''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375577.26 4907701.11 123.00 0 32 73.9 73.9 0.0 0.0 68.2 0.0 -5.5 0.0 0.0 6.8 0.0 -0.0 4.5 4.5
2 18375577.26 4907701.11 123.00 0 63 91.1 91.1 0.0 0.0 68.2 0.1 -5.5 0.0 0.0 8.2 0.0 -0.0 20.2 20.2
3 18375577.26 4907701.11 123.00 0 125 102.2 102.2 0.0 0.0 68.2 0.3 0.9 0.0 0.0 9.2 0.0 -0.0 23.7 23.7
4 18375577.26 4907701.11 123.00 0 250 104.7 104.7 0.0 0.0 68.2 0.8 2.8 0.0 0.0 9.6 0.0 -0.0 23.4 23.4
5 18375577.26 4907701.11 123.00 0 500 107.1 107.1 0.0 0.0 68.2 1.4 -1.0 0.0 0.0 15.0 0.0 -0.0 23.5 23.5
6 18375577.26 4907701.11 123.00 0 1000 110.3 110.3 0.0 0.0 68.2 2.6 -3.1 0.0 0.0 17.8 0.0 -0.0 24.8 24.8
7 18375577.26 4907701.11 123.00 0 2000 109.5 109.5 0.0 0.0 68.2 7.0 -3.2 0.0 0.0 20.7 0.0 -0.0 16.9 16.9
8 18375577.26 4907701.11 123.00 0 4000 102.3 102.3 0.0 0.0 68.2 23.6 -3.2 0.0 0.0 23.7 0.0 -0.0 -10.0 -10.0
9 18375577.26 4907701.11 123.00 0 8000 94.2 94.2 0.0 0.0 68.2 84.3 -3.2 0.0 0.0 25.0 0.0 -0.0 -80.0 -80.0
Point Source, ISO 9613, Name: ''N5 - North Washplant Hopper/Loader '', ID: ''N5_Washplant_Loader''
Nr. X Y Z Refl. Freq. LxT LxN K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL LrT LrN
(m) (m) (m) (Hz) dB(A) dB(A) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) (dB) dB(A) dB(A)
1 18375589.32 4907712.54 123.75 0 32 81.9 81.9 0.0 0.0 68.1 0.0 -5.4 0.0 0.0 6.8 0.0 -0.0 12.4 12.4
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 45
HUGH WILLIAMSON ASSOCIATES INC.
Appendix 4
Noise Abatement Schedule Contents:
Table A4.1 Noise Abatement Schedule Figure A4.1 Noise Barrier Detail – Berms at Site Boundary Figure A4.2 Noise Barrier Detail – Barrier 8 at Asphalt Plant
(required for evening and night operation 19:00 to 07:00) Figure A4.3 Noise Barrier Detail – Barrier 9 at Portable Crushing Plant
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 46
HUGH WILLIAMSON ASSOCIATES INC.
Table A4.1 Noise Abatement Schedule
ID Type Description Minimum
Height (m)
Date of Installation / Construction
Barrier 1 Berm*
To shield noise impacts from Internal Haul Route
and Portable Crushing and Screening Plant to POR 1.
Berm to be located as shown in Figure A4.1.
4 m
Berm established for length of boundary adjacent to internal haul route at site entry then
may be progressively established as extraction and crushing operation progresses
west.
Barrier 2 Berm*
To shield noise impacts from Low Noise Rock Drill when in operation north of Line A B and Portable Crushing and Screening
Plant to POR 11. Berm to be located as shown in Figure A4.1.
7 m Berm progressively
established as operation progresses.
Barrier 3 Berm*
To shield noise impacts from Low Noise Rock Drill when in operation north of Line A B to POR 10 and
POR 11. Berm to be located as shown in Figure A4.1.
4 m Berm progressively
established as operation progresses.
Barrier 4 Berm*
To shield noise impacts from Rock Drill and
Portable Crushing and Screening Plant to POR 8
and POR 9. Berm to be located as shown in Figure A4.1.
4 m Berm progressively
established as operation progresses.
Barrier 5 Berm*
To shield noise impacts from Rock Drill and
Portable Crushing and Screening Plant to POR 8
and POR 9. Berm to be located as shown in Figure A4.1.
4 m Berm progressively
established as operation progresses.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 47
HUGH WILLIAMSON ASSOCIATES INC.
ID Type Description Minimum
Height (m)
Date of Installation / Construction
Barrier 6 Berm*
To shield noise impacts from Asphalt Plant when in operation during the Evening and Nighttime
Period (19:00 to 07:00) to POR 9.
Berm to be located as shown in Figure A4.1.
4 m To be determined.
Barrier 7 Berm*
To shield noise impacts from Asphalt Plant when in operation during the Evening and Nighttime
Period (19:00 to 07:00) to POR 3.
Berm to be located as shown in Figure A4.1.
4 m To be determined.
Barrier 8
Barrier or Berm*
(Possibly Shipping
Containers)
To shield noise impacts from Asphalt Plant when in operation during the Evening and Nighttime
Period (19:00 to 07:00) to POR 3.
Located as shown in
Figure A4.2.
4 m To be determined.
Barrier 9
Local Barrier or Berm or Stockpile
at Portable Crushing
Plant*
To shield noise impacts from Portable Crushing
and Screening Plant when operating in Phase North
of Pipeline to POR 3. Located as shown in
Figure A4.3.
7 m /
5 m**
Berm established as operation progresses relative to location
of current operation of Crushing Plant.
* Alternative types of noise barriers are permissible following review by qualified acoustical consultant. ** Barrier 9 is to be 7 m high minimum when operating the Crusher on lift floor at elevations 115 m to 125 m ASL. Barrier 9 can be reduced to 5 m high minimum when operating Crusher on lift floor below 115 m ASL.
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 48
HUGH WILLIAMSON ASSOCIATES INC.
Figure A4.1 Noise Barrier Detail – Berms at Site Boundary
18374200
18374200
18374400
18374400
18374600
18374600
18374800
18374800
18375000
18375000
18375200
18375200
18375400
18375400
18375600
18375600
18375800
18375800
18376000
18376000
18376200
18376200
18376400
18376400
4906600
4906600
4906800
4906800
4907000
4907000
4907200
4907200
4907400
4907400
4907600
4907600
4907800
4907800
4908000
4908000
4908200
4908200
4908400
4908400
Barrier 1 (Minimum 4 m high berm) Barrier 2
(Minimum 7 m high berm)
Barrier 3 (Minimum 4 m high berm); required when operating the Low Noise Rock Drill
north of Line A B
Barrier 4 and Barrier 6 (Minimum 4 m high berm)
Barrier 5 (Minimum 4 m high berm)
Barrier 7 (Minimum 4 m high
berm); required when operating the Asphalt
Plant during the Evening and Nighttime period
(19:00 to 07:00) North
130 m
100 m
LINE A B POR 3
POR 2
POR 1 POR 11
POR 10
POR 9
POR 8
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 49
HUGH WILLIAMSON ASSOCIATES INC.
Figure A4.2 Noise Barrier Detail – Barrier 8 at Asphalt Plant (required for evening and night operation 19:00 to 07:00)
18375560
18375560
18375570
18375570
18375580
18375580
18375590
18375590
18375600
18375600
18375610
18375610
18375620
18375620
18375630
18375630
18375640
18375640
18375650
18375650
18375660
18375660
18375670
18375670
4907850
4907850
4907860
4907860
4907870
4907870
4907880
4907880
4907890
4907890
4907900
4907900
4907910
4907910
4907920
4907920
POR 3
Barrier 8 (Minimum 4 m high noise
barrier)
North
Asphalt Plant Operation
15 m
Acoustic Assessment of the
Elginburg Quarry Expansion
Unity Road, Kingston, Ontario
ACOUSTIC ASSESSMENT REPORT
17th September 2014
P a g e | 50
HUGH WILLIAMSON ASSOCIATES INC.
Figure A4.3 Noise Barrier Detail – Barrier 9 at Portable Crushing Plant
18375070
18375070
18375080
18375080
18375090
18375090
18375100
18375100
18375110
18375110
18375120
18375120
18375130
18375130
18375140
18375140
18375150
18375150
18375160
18375160
18375170
18375170
18375180
18375180
4908150
4908150
4908160
4908160
4908170
4908170
4908180
4908180
4908190
4908190
4908200
4908200
4908210
4908210
4908220
4908220
Barrier 9 (Minimum 7 m high noise barrier when operating
Crusher at 115 m to 125 m ASL; Minimum 5 m high noise barrier when operating
Crusher below 115 m ASL)
North
Portable Crushing and Screening Plant Operation
Maximum 25 m shielding POR 3
20
m
LINE A B
LIFT FACE
LIF
T F
AC
E
POR 3
HUGH WILLIAMSON ASSOCIATES INC. Ottawa, Ontario, Canada
Postal Address: PO Box 74056, RPO Beechwood, Ottawa, Ontario, K1M 2H9, Canada
Phone/Fax: (613) 747 0983, Email: [email protected], http://www.hwacoustics.ca
RESUMÉ: Dr. HUGH WILLIAMSON, P.Eng.
QUALIFICATIONS: Ph.D. Mechanical Engineering, University of New South Wales, 1972
B.Sc. Mechanical Engineering, (with Distinction), University of Alberta, 1967
Member, Professional Engineers, Ontario
Member, Canadian Acoustical Association
Member, American Society of Heating, Refrigeration and Air-conditioning
Engineers
KEY
COMPETENCIES: Environmental noise and vibration assessments, Environmental Compliance
Approval (ECA). Noise assessment for land use planning
Architectural and building acoustics, acoustics of office spaces, meeting rooms,
auditoriums and studios, noise and vibration control of building mechanical
services.
Industrial noise and vibration assessment and control.
Transportation noise and vibration.
PROFESSIONAL EXPERIENCE:
Hugh Williamson is a professional engineer with many years of experience in the measurement,
analysis and control of noise and vibration. Hugh Williamson Associates was incorporated in 1997 and
provides consulting services in architectural, building, industrial, transportation and environmental
acoustics and vibration. Clients include architects, engineering firms, industrial firms and government
departments. Prior to establishing Hugh Williamson Associates, his career included extensive periods
in industry as well as university level research and teaching. He is a former Director of the Acoustics
and Vibration Unit at the Australian Defence Force Academy. He has published over 50 engineering
and scientific papers and has been an invited speaker on noise and vibration at national and
international conferences. He has more than 20 years of experience as a consultant.
CLIENT LIST:
Hugh Williamson Associates provides consulting services to large and small clients including: National
Research Council, National Capital Commission, J. L. Richards & Associates, Barry Padolsky
Associates, HOK Urbana Architects, Genivar, Nasittuq Corporation, PWGSC, R. W. Tomlinson, Geo.
Tackaberry Construction and Miller Paving.
HUGH WILLIAMSON ASSOCIATES INC. Ottawa, Ontario, Canada
Postal Address: PO Box 74056, RPO Beechwood, Ottawa, Ontario, K1M 2H9, Canada
Phone/Fax: (613) 747 0983, Email: [email protected], http://www.hwacoustics.ca
RESUMÉ: MICHAEL WELLS
QUALIFICATIONS: Registered Architect of NSW, Registration Number: 8111
B. Architecture (Hons), University of Sydney, 2002
B.Sc. Architecture, University of Sydney, 1999
Member, Canadian Acoustical Association
KEY
COMPETENCIES: Environmental noise and vibration assessments, Environmental Compliance
Approval (ECA). Noise assessment for land use planning.
Architectural and building acoustics, acoustics of office spaces, meeting rooms,
auditoriums and studios, noise and vibration control of building mechanical
services.
Industrial noise and vibration assessment and control.
Transportation noise and vibration.
Design services including sketch design, design development (development /
permit applications), contract documents, tendering and contract administration.
PROFESSIONAL EXPERIENCE:
Michael Wells is a professional Architect registered in NSW with many years of experience in the
Architectural and Construction industries. With key competencies in measurement, analysis and
control of noise and vibration, Michael Wells joined Hugh Williamson Associates in 2012 and
provides consulting services in architectural, building, industrial, transportation and environmental
acoustics and vibration. Clients include architects, engineering firms, industrial firms and government
departments. Prior to joining Hugh Williamson Associates, his career includes the founding of
Michael Wells Architect in Sydney Australia which specialized in the design of institutional,
commercial and residential projects. He is a Director of Architectural Workshops Australia and Vision
Blue Pty Ltd. He has more than 10 years of experience as a consultant.
CLIENT LIST:
Hugh Williamson Associates provides consulting services to large and small clients including: National
Research Council, National Capital Commission, J. L. Richards & Associates, Barry Padolsky
Associates, HOK Urbana Architects, Genivar, Nasittuq Corporation, PWGSC, R. W. Tomlinson, Geo.
Tackaberry Construction and Miller Paving.