  • 7/28/2019 Action Plan for WT-2 4.08.12

    1/18

    Action plan for CNCRP Working Team-2

    Md. Rafiqul Islam

    Executive Engineer

    PWD Design Division-III

    &

    Team Leader Working Team-2, CNCRP

  • 7/28/2019 Action Plan for WT-2 4.08.12

    2/18

    Objectives of working Team -2 in the currentJapan tour under CNCRP

    Condition of Existing Buildings

    Various techniques for retrofitting

    Research work on retrofitting

    Selection/Categorization of Building for Retrofitting

    Seismic vulnerability assessment and retrofitting design

    Design of earthquake resistant new building

    Precaution about public safety and security during retrofitting

    design and works

  • 7/28/2019 Action Plan for WT-2 4.08.12

    3/18

    Condition of Existing Buildings

    Present condition in Bangladesh

    Most of the existing buildings were not built by considering

    seismic forces.

    Without seismic detailing.

    Small column size.

    Plain rebar is used.

    Weak Beam Column joint.

    Infill masonry wall is used in frame structure.

    Most of the buildings are not durable due to poor concreting.

    Mixed frame structures.

  • 7/28/2019 Action Plan for WT-2 4.08.12

    4/18

    Condition of Existing Buildings

    Observation in Japan

    Seismic force is considered to design the building.

    Large column size is observed.

    No deterioration of concrete and rebar of the existing building.

    Item of activity to be considered for CNCRP

    Strength of the existing building material to be tested.

    Capacity of the existing building to be estimated by analyticallyand experimentally.

  • 7/28/2019 Action Plan for WT-2 4.08.12

    5/18

    Condition of Existing Buildings

    Way of Implementation

    List of martial strength to be tested by period wise.

    Experimental facility to be established.

    Long term goal/ achievements

    We have to prepare the existing building inventory for the whole

    country by following the test result.

    Depending on the test result we need to retrofit or demolish the

    structure.

    Remarks

    No

  • 7/28/2019 Action Plan for WT-2 4.08.12

    6/18

    Various techniques for retrofitting

    Present condition in Bangladesh

    No retrofitting work

    Observation in Japan

    Retrofitting by

    Steel frame bracing.

    Base Isolation.

    RCC Column Jacketing.

    Insertion of shear wall.

    Seismic Slit.

    Wing Wall.

    Steel Column Jacketing.

  • 7/28/2019 Action Plan for WT-2 4.08.12

    7/18

    Various techniques for retrofitting

    Item of activity to be considered for CNCRP

    Suitability of the different seismic retrofitting techniques should

    be explored for Bangladesh .

    Way of Implementation

    Pilot project should be considered as retrofitting test work.

    Long term goal/ achievements

    We have to retrofit the existing building depending on the seismic

    vulnerability.

    Remarks

    No

  • 7/28/2019 Action Plan for WT-2 4.08.12

    8/18

    Research work on retrofitting

    Present condition in Bangladesh

    There is no research work on retrofitting techniques.

    Observation in Japan

    Research work is enduring in private and public sector.

    Item of activity to be considered for CNCRP

    Some research work need to be implemented.

  • 7/28/2019 Action Plan for WT-2 4.08.12

    9/18

    Research work on retrofitting

    Way of Implementation

    Under the supervision of JICA expert, working team-2 will

    do some research work by analytically and experimentally .

    Long term goal/ achievements

    PWD will establish a research laboratory with the help of

    JICA expert.

    Remarks

    No

  • 7/28/2019 Action Plan for WT-2 4.08.12

    10/18

    Selection/Categorization of Building forRetrofitting

    Present condition in Bangladesh

    There is no guideline for seismic retrofitting.

    Observation in Japan

    No specific categorization procedure in Japan.

    Some top down selection procedure exist.

    Item of activity to be considered for CNCRP

    We have to prepare a categorization guide line for seismic

    retrofitting as per direction of JET.

  • 7/28/2019 Action Plan for WT-2 4.08.12

    11/18

    Selection/Categorization of Building forRetrofitting

    Way of Implementation

    CNCRP together with JET need to find out suitable technique for

    implementation.

    Long term goal/ achievements

    We have to prepare the building inventory for the whole country

    by following this categorization guideline.

    Remarks

  • 7/28/2019 Action Plan for WT-2 4.08.12

    12/18

    Seismic vulnerability assessment and retrofitting

    design

    Present condition in Bangladesh

    Almost no such capacity.

    Observation in Japan

    There are specialized group of structural designer capable for

    seismic assessment and retrofitting design.

    Item of activity to be considered for CNCRP

    Need to prepare seismic vulnerability assessment manual.

    Need to retrofitting design manual.

    Need to learn the way of pushover analysis.

    Need to learn dynamic time history analysis.

  • 7/28/2019 Action Plan for WT-2 4.08.12

    13/18

    Seismic vulnerability assessment andretrofitting design

    Way of Implementation

    Manual should be prepared with the help of JICA Expert Team.

    JET will help to learn these analysis properly.

    Long term goal/ achievements PWD engineer will disseminate these knowledge to the public and

    private sector.

    Licensing system should be developed for retrofitting design.

    Remarks

    No

  • 7/28/2019 Action Plan for WT-2 4.08.12

    14/18

    Design of earthquake resistant new building

    Present condition in Bangladesh

    There is a lack of capable structural design engineer.

    Building construction regulation is not strictly followed.

    Observation in Japan

    Building code is strictly followed by consultant and constructionagency.

    Item of activity to be considered for CNCRP

    Need to prepare seismic design manual for new building.

    Need to learn the way of pushover analysis for the design of new

    building.

    Need to learn dynamic time history analysis for the design of new

    building.

  • 7/28/2019 Action Plan for WT-2 4.08.12

    15/18

    Design of earthquake resistant new building

    Way of Implementation

    PWD engineer will prepare this design manual with the help of JICAExpert Team.

    PWD engineer will learn these analysis procedure with the help of

    JICA Expert Team.

    Long term goal/ achievements

    PWD engineer will disseminate these knowledge to the public and

    private sector.

    Licensing system for the professional engineer for design and

    construction of building should be followed strictly.

    Remarks

    No

  • 7/28/2019 Action Plan for WT-2 4.08.12

    16/18

    Precaution about public safety and securityduring retrofitting design and works

    Present condition in Bangladesh

    Since there is no retrofitting works in Bangladesh so there is no

    guideline for public safety and security.

    Observation in Japan

    Various steps are considered to ensure public safety and security.

    Item of activity to be considered for CNCRP

    Public safety and security guide line need to be prepared.

  • 7/28/2019 Action Plan for WT-2 4.08.12

    17/18

    Precaution about public safety and securityduring retrofitting design and works.

    Way of Implementation

    Need to explore Japanese as well as other international guide

    line to prepare the guide line.

    Long term goal/ achievements Public safety need to ensure.

    Need to increase Public awareness .

    Remarks No

  • 7/28/2019 Action Plan for WT-2 4.08.12

    18/18

    Thank You