Design and Construction Review (DCR)
Leading transportation innovation - Investing in Communities.
We drive quality transportation for all Ada County…Anytime, Anywhere!
Ada County Highway District
3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100 - FAX (208) 387-6391 E-mail: [email protected]
DESIGN & CONSTRUCTION REVIEW
Bogus Basin Rd Improvements January 1, 2020
FY 20
Committed to Service
Design and Construction Review (DCR)
January 2020
Project Name Page No.
11th St Maintenance and Bikeway, State St to Heron St 1
13th St Traffic Calming, Fort St to Hill Rd 2
2019 Federal Aid Capital Maintenance - Phase 1 3
2019 Federal Aid Capital Maintenance - Phase 2 4
2019 Federal Aid Capital Maintenance - Phase 3 (Local) 5
2019 Green Stormwater Implementation 6
2020 Arterial and Collector Capital Maintenance - HB312 7
2020 Downtown Boise Implementation - HB312 8
2020 Federal Aid Capital Maintenance - Local 9
2020 Federal Aid Capital Maintenance - Phase 1 10
2020 Federal Aid Capital Maintenance - Phase 2 11
2020 Maintenance Crack Seal - HB312 12
2020 Microseal - HB312 13
2020 Residential Capital Maintenance - HB312 14
2021 Arterial and Collector Capital Maintenance - HB312 15
2021 Federal Aid Capital Maintenance - Local 16
2021 Federal Aid Capital Maintenance - Phase 1 17
2021 Federal Aid Capital Maintenance - Phase 2 18
2021 Residential Capital Maintenance 19
24th St Road and Bridge Project 20
28th Street - Hazel Street to Irene Street 21
32nd St Bridge 1308 22
33rd St Bridge 1318 23
38th St Bridge 1440 24
38th St, Bush Ave to Sunset Ave 25
41st Street Bridge 1437 26
44th St Bridge 1433 27
45th St Bridge 1432 28
Aikens St, Eagle Rd to 2nd St 29
Amity Rd and Maple Grove Rd Roundabout 30
Bogart Ln, State St to Sloan St 31
Broadway Ave and Boise Ave 32
Bryson Ave Bridge 1134 33
Cassia St Bikeway and Pedestrian Improvements 34
Cherry Ln and Meridian Library Pedestrian Crossing 35
Chinden Blvd and Curtis Rd 36
Cloverdale Rd, Columbia Rd to Overland Rd Corridor Preservation 37
Cole Rd and Victory Rd Intersection 38
Columbus St, Overland Rd to Kootenai St 39
Deer Flat Rd and School Ave Pedestrian Crossing 40
Deer Flat Rd, School Ave to Deerhorn Rd 41
Division Ave, Highlands St to Hale St 42
Eagle Rd, Amity Rd to Victory Rd 43
Edgewood Ln, State St to Hill Rd 44
January 2020 DCR TOC TOC 1 of 3
Design and Construction Review (DCR)
January 2020
Project Name Page No.
Enhanced School Crossings - Meridian Middle and Capital HS 45
Fairview Ave and Curtis Rd Accessible Pedestrian Signal 46
Fairview Ave and Locust Grove Rd 47
Fairview Ave and Milwaukee St Accessible Pedestrian Signal 48
Five Mile and Seneca Pedestrian Crossing 49
Five Mile and Smoke Ranch Pedestrian Crossing 50
Franklin St, McKinley St to Pierce St 51
Garden St Franklin Rd to Bethel St 52
Gowen Rd Bridge 2110 53
Gowen Rd Bridge 2173 54
Holcomb Rd, Eastgate Dr to Amity Rd 55
Horseshoe Bend Rd and Shadowview Rd Ped Crossing 56
Lake Hazel Rd and Eagle Rd 57
Lake Hazel Rd and Five Mile Rd 58
Lake Hazel Rd, Cloverdale Rd to Five Mile Rd Pedestrian Improvements 59
Linder Rd and Deer Flat Rd 60
Linder Rd, Franklin Rd to Pine Ave 61
Locust Grove Rd and Chinden Blvd Intersection 62
Locust Grove Rd, Victory Rd to Overland Rd 63
Maple Grove Rd, Victory Rd to Overland Rd 64
McMillan Rd and Leather Way Pedestrian Crossing 65
McMillan Rd, Westview Dr to Maple Grove Rd 66
Meridian Rd, Cherry Ln to Ustick Rd 67
Overland Rd and Phillippi St Ped Crossing 68
Phillippi St, Malad St to Targee St 69
Phillippi Street, Targee Street to Overland Road 70
Pierce St, Washington St to Shenandoah Dr 71
Roosevelt St, Rose Hill St to Emerald St (West Side) 72
Royal Blvd, La Pointe St to Lusk St 73
Shamrock Ave Bridge No 1424 74
Shoshone St Bikeway, Canal St to Capital Blvd 75
State St and Pierce Park Ln 76
State St, 16th to 23rd Street Lighting Improvements 77
Ten Mile Rd and Amity Rd 78
Ten Mile Rd and Crenshaw St Pedestrian Crossing 79
Ten Mile Rd and Victory Rd 80
Ten Mile Rd, McMillan Rd to Chinden Blvd 81
Ten Mile Rd, Victory Rd to Overland Rd 82
Ten Mile Road, Ustick Road to McMillan Road 83
Thurman Mill Bridge Projects 84
Ustick Rd and Milwaukee St School Zone 85
Valley St, Lake Hazel Rd to La Grange St 86
Victory Rd and Locust Grove Rd Roundabout 87
Victory Rd and Standing Timber Ave Pedestrian Crossing 88
January 2020 DCR TOC TOC 2 of 3
Design and Construction Review (DCR)
January 2020
Project Name Page No.
Vista Ave and Nez Perce St Ped Crossing 89
Warm Springs Ave, Glacier Dr to Glacier Dr 90
January 2020 DCR TOC TOC 3 of 3
Design & Construction Review (DCR)
GIS BK218‐01 Contract No
Prj No 819011 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 3 Prj Mgr
Notice to Proceed 12/19/2019 Consultant
Est Completion Date 9/30/2020 Contact
Right of WayEst Start 9/30/2020 ROW Agent
Completion Date 9/15/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 2/8/2022 Proj Inspector
Est Compl Date 5/4/2022
Project Status Notes
Utility Comments
Developing consultant design scope and schedule and negotating contract. (DJR
12/16/19)
11th St Maintenance and Bikeway, State St to Heron St
Implment a bikeway on 11th Street betweeb State Street and Hereon Street as per the
Concept design adopted by ACHD commission on October 23rd, 2019 The project
includes: Roadway Maintenence Between Heron Street and Franklin Street Pavement
Markings, wayfinding signs, and branding signs Between Heron and Franklin. Enhanced
Pedestrian Crossings Fort/11th, Hays/11th and Hays/12th. Crossings on 11th will included
bicyclist push buttons and bulb‐outs. Install a multi‐use path through the Boise High School
Campus and allway stops at the intersections of Franklin/ Washington Install Pavement
markings between Washington Street and the YMCA driveway. Install convetional bike
Dave Rader
Kittelson & Associates
Evan Reed
Dave Serdar
12/31/2019 11:12 AM 2 of 91
Design & Construction Review (DCR)
GIS CM217‐31 Contract No
Prj No 820007 ITD Key No
Project Description
Current Project Phase 10 Ready DSN
DesignStatus 13 Prj Mgr
Notice to Proceed 1/2/2020 Consultant
Est Completion Date 7/17/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 10/8/2020 Proj Inspector
Est Compl Date 12/22/2020
Project Status Notes
Utility Comments
12/13 Finalizing SOW/PSA w HDR SJ 11/25/19
13th St Traffic Calming, Fort St to Hill Rd
Implement components of the 13th St Traffic Calming Concept Study completed in 2018,
including bulbouts at Bella St, Hazel St, Heron St, Alturas St or Sherman St, and an
enhanced pedestrian crossing (RRFB) at Resseguie St. No ROW required for this project.
FY20 Design, FY21 Construction.
Seth Jarsky
HDR Engineering Inc
Cameron Waite
No R/W
12/31/2019 11:12 AM 3 of 91
Design & Construction Review (DCR)
GIS FAO2191 Contract No ITD
Prj No 717030 ITD Key No 13903
Project Description
Current Project Phase 19 Construction
DesignStatus 100 Prj Mgr
Notice to Proceed 8/18/2017 Consultant
Est Completion Date 11/19/2018 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 41 Contractor
Notice to Proceed 8/28/2019 Proj Inspector
Est Compl Date 5/1/2020
Project Status Notes
Utility Comments
Idaho Materials and Construction
Paving complete Fairview Rd, Eagle to Cloverdale Rd, concrete work continues on other
segments. (CH 11/21 /19)
2019 Federal Aid Capital Maintenance ‐ Phase 1
Pavement rehabilita on, select pipe replacement, and upgrade of adjacent pedestrian
ramps on: Annett St, Victory Rd‐Targee St; Division Ave, Boise Ave‐Beacon St; Latah St,
Overland Rd‐Alpine St; Fairview Ave, Dixie Ln‐Cloverdale Rd.
Cody Homan
Parametrix Inc
Cody Janson
No R/W
12/31/2019 11:12 AM 4 of 91
Design & Construction Review (DCR)
GIS FAO2192 Contract No ITD
Prj No 717031 ITD Key No 20003
Project Description
Current Project Phase 19 Construction
DesignStatus 100 Prj Mgr
Notice to Proceed 9/6/2017 Consultant
Est Completion Date 9/5/2018 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 36 Contractor
Notice to Proceed 8/26/2019 Proj Inspector
Est Compl Date 6/11/2020
Project Status Notes
Utility Comments
Central Paving Co Inc
Continuing concrete work, roadwork to be done at night in Spring 2020. (CH 12/09 /19)
2019 Federal Aid Capital Maintenance ‐ Phase 2
Pavement rehabilita on, select pipe replacement, and upgrade of adjacent pedestrian
ramps on Emerald St, Cole Rd‐Orchard St; Orchard St, Overland Rd‐Franklin Rd.
Cody Homan
Six Mile Engineering PA
Jeff Jones
No R/W
12/31/2019 11:12 AM 5 of 91
Design & Construction Review (DCR)
GIS FAO219L Contract No
Prj No 717026 ITD Key No 20091
Project Description
Current Project Phase 17 Bid and Award
DesignStatus 100 Prj Mgr
Notice to Proceed 9/27/2017 Consultant
Est Completion Date Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 5/7/2020 Proj Inspector
Est Compl Date 7/6/2020
Project Status Notes
Utility Comments
R ejected bids, upda ng plans/es mate, plan to re-bid with one of the 2020 Federal Aid
Capital Maintenance projects. (CH 12/09/19)
2019 Federal Aid Capital Maintenance ‐ Phase 3 (Local)
Pavement rehabilitation, select pipe replacement, and upgrade of adjacent pedestrian
ramps on Cherry Ln from Shoshone St to Broxon St, Elder St from Owyhee St to Vista Ave,
and Owyhee St from Elder St to Cherry Ln.
Cody Homan
Kittelson & Associates
Evan Reed
No R/W
12/31/2019 11:12 AM 6 of 91
Design & Construction Review (DCR)
GIS MDR216‐03 Contract No CT220‐05
Prj No 418008 ITD Key No
Project Description
Current Project Phase 19 Construction
DesignStatus 100 Prj Mgr
Notice to Proceed 10/17/2017 Consultant
Est Completion Date 2/21/2019 Contact
Right of WayEst Start 11/26/2018 ROW Agent
Completion Date 8/12/2019 Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 5/29/2020 Proj Inspector
Est Compl Date 9/15/2020
Project Status Notes
Utility Comments
Bid awarded on 12/4/19. Responsvie low bidder is Clearwater Landscape. (DJR 12-17-
2019)
2019 Green Stormwater Implementation
This project consists of retrofitting exsisting alley ways in downtown Boise with permeable
pavers for stormwater management. The alley locations are provided below.
‐Between Idaho and Bannock, 4th and 5th
‐Between Miller and Myrtle, 9th to 10th
Dave Rader
Civil Survey Consultants
Matt Hart
Becca Randall
12/31/2019 11:12 AM 7 of 91
Design & Construction Review (DCR)
GIS OV220 Contract No
Prj No 519018 ITD Key No
Project Description
Current Project Phase 12 Design In House
DesignStatus 100 Prj Mgr
Notice to Proceed 7/24/2019 Consultant
Est Completion Date 10/8/2019 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 3/13/2020 Proj Inspector
Est Compl Date 7/7/2020
Project Status Notes
Utility Comments
The project is in the design phase and is on schedule. [JT III - 12/13/2019]
N/A
2020 Arterial and Collector Capital Maintenance ‐ HB312
Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial
and collector road segments as part of ACHD's Pavement Management Program. Project
funded all or in part through House Bill 312 Funding. In‐House Design. Segments include
the following: Linder Road, Trophy Street to Hubbard Road; Victory Road, McDermott Road
to Black Cat Road; and Victory Road, Eight Mile Lateral to west of Eagle Road.
Joe Tate
ACHD Design
Pierson Dewit / Jeremy Andree
No R/W
12/31/2019 11:12 AM 8 of 91
Design & Construction Review (DCR)
GIS SM220 Contract No
Prj No 519044 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 70 Prj Mgr
Notice to Proceed 7/1/2019 Consultant
Est Completion Date 5/12/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 2/18/2021 Proj Inspector
Est Compl Date 7/9/2021
Project Status Notes
Utility Comments
Design underway, geotechnical work delayed by the downtown Boise traffic control
moratorium. (CH 10/28/19)
2020 Downtown Boise Implementation ‐ HB312
Pavement rehabilita on: State St, 16th St to 15th St; State St 11th St to 1st St; 9th St,
Bannock St to State St; 9th St, University Dr to Front St; 10th St, Front St to Idaho St; Grove
St, 16th St to 9th St. Additional work: widen State St, 15th St to 12th St; add detached
sidewalk to State St, 14th St to 12th St; install RRFB crossing State St on the west side of
14th St; add bulb‐outs to the intersetions of State St at 4th St and 3rd St; replace storm
drain/irrigation pipes as needed
Cody Homan
Precision Engineering LLC
Joel Grounds
No R/W
12/31/2019 11:12 AM 9 of 91
Design & Construction Review (DCR)
GIS FAO220L Contract No
Prj No 718013 ITD Key No 19847
Project Description
Current Project Phase 11 Design
DesignStatus 100 Prj Mgr
Notice to Proceed 5/10/2018 Consultant
Est Completion Date 4/1/2019 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 6/3/2020 Proj Inspector
Est Compl Date 8/18/2020
Project Status Notes
Utility Comments
Construction planned for summer 2020. (BM 12-18-19)
2020 Federal Aid Capital Maintenance ‐ Local
Pavement rehabili a on and upgrade of adjacent pedestrian ramps on iden fed arterial
and collector road segments. Segments include: Owyhee St, Cherry Ln to Overland Rd
Brian McCarthy
HW Lochner Inc
No R/W
12/31/2019 11:12 AM 10 of 91
Design & Construction Review (DCR)
GIS FAO2201 Contract No
Prj No 718042 ITD Key No 18728
Project Description
Current Project Phase 17 Bid and Award
DesignStatus 100 Prj Mgr
Notice to Proceed 8/13/2018 Consultant
Est Completion Date 7/9/2019 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 2/28/2020 Proj Inspector
Est Compl Date 9/23/2020
Project Status Notes
Utility Comments
Final design complete, project moving towards PS&E 11.26.19 RC
2020 Federal Aid Capital Maintenance ‐ Phase 1
Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial
and collector road segments. Segments inlcude: 13th St, Alturas St to Brumback St,
Beacon Light Rd, SH‐16 to Ballantyne Ln, Cole Rd, Lake Hazel Rd to Latigo Dr, Edna St, Five
Mile Rd to Patton Ave, Floating Feather Rd, Lanewood Rd to Linder Rd, Hill Rd Pkwy,
Horseshoe Bend Rd to Seasman Gulch Rd, Horseshoe Bend Rd, State St to Cemetery
Entrance, Locust Grove Rd, Ustick Rd to McMillan Rd, Pine St, Linder Rd to Meridian Rd,
Technology Way, Columbia Rd to SH‐21.
Ryan Cutler
Precision Engineering LLC
Joel Grounds
No R/W
12/31/2019 11:12 AM 11 of 91
Design & Construction Review (DCR)
GIS FAO2202 Contract No
Prj No 718025 ITD Key No 19887
Project Description
Current Project Phase 11 Design
DesignStatus 100 Prj Mgr
Notice to Proceed 6/27/2018 Consultant
Est Completion Date 12/31/2019 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 6/3/2020 Proj Inspector
Est Compl Date 9/25/2020
Project Status Notes
Utility Comments
The Gowen Rd segment will be seperated out to construct it in FY20. The Collister Rd
segment is reprogrammed to FY22. (BM 12-18-19)
2020 Federal Aid Capital Maintenance ‐ Phase 2
Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial
and collector road segments. Segments include: Collister Dr, Quail Ridge Dr to North End
and Gowen Rd, Orchard St to Broadway Ave.
Brian McCarthy
Six Mile Engineering PA
No R/W
12/31/2019 11:12 AM 12 of 91
Design & Construction Review (DCR)
GIS MCS220 Contract No CT220‐10
Prj No 520006 ITD Key No
Project Description
Current Project Phase 17 Bid and Award
DesignStatus 100 Prj Mgr
Notice to Proceed 10/1/2019 Consultant
Est Completion Date 11/4/2019 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 2/3/2020 Proj Inspector
Est Compl Date 3/10/2020
Project Status Notes
Utility Comments
11/22 Submi ed bid docs to Procurement, scheduled Commission approval on 1/22,
construction NTP 2/6 12/13/19 SMJ
2020 Maintenance Crack Seal ‐ HB312
Seal cracks in arterial and collector roadways in Preventative Maintenance Zone 2 South
(south of I‐84, north of Lake Hazel Rd, between McDermott Rd and Five Mile Rd) as part of
ACHD's Pavement Management Program. Project funded all or in part through House Bill
312 funding.
Seth Jarsky
ACHD Design
Scott Forrey
No R/W
12/31/2019 11:12 AM 13 of 91
Design & Construction Review (DCR)
GIS MIC220 Contract No
Prj No 520004 ITD Key No
Project Description
Current Project Phase 10 Ready DSN
DesignStatus 21 Prj Mgr
Notice to Proceed 2/12/2020 Consultant
Est Completion Date 5/18/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 8/20/2020 Proj Inspector
Est Compl Date 9/11/2020
Project Status Notes
Utility Comments
12/13 Working w Six Mile on SOW/PSA, Seth to present w City staff at 1/29 Commission
mtg 12/13/19 SMJ
2020 Microseal ‐ HB312
Microseal roadways as part of ACHD's Pavement Management Program. Project funded all
or in part through House Bill 312 funding. SegmentsJefferson St ‐ 1st St to 16th St13th St ‐
Front St to Main St3rd St ‐ Jefferson St to Front St4th St ‐ State St to S End8th St ‐ Myrtle St
to Broad StAve A ‐ Myrtle St to Front StBroad St ‐ 9th St to 8th StFront St ‐ 16th St to 13th
StRiver St ‐ 9th St to Capital Blvd
Seth Jarsky
Six Mile Engineering PA
No R/W
12/31/2019 11:12 AM 14 of 91
Design & Construction Review (DCR)
GIS MTL220 Contract No
Prj No 518026 ITD Key No
Project Description
Current Project Phase 12 Design In House
DesignStatus 99 Prj Mgr
Notice to Proceed 7/11/2018 Consultant
Est Completion Date Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 5/7/2020 Proj Inspector
Est Compl Date 9/14/2020
Project Status Notes
Utility Comments
95% review meeting scheduled for early 12/10/19 . (CH 12/09/19)
2020 Residential Capital Maintenance ‐ HB312
Gather exis ng roadway condi on informa on and rehabilitee the pavement along with
upgrading pedestrian ramps on residential streets. Segments inlcude: 10th St, Fort St to
Heron St; Cunningham Pl, 8th St to 6th St; Heron St, Harrison Blvd to 13th St; Maple Ave,
Warm Springs Ave to Franklin St; O'Farrell St, 13th St to 4th St; Pierce Ct, Shenandoah Dr to
North End.
Part of the ACHD Pavement Management Program, funded all or in part through House
Bill 312 funding. In‐house design project.
Cody Homan
ACHD Design
Jeremy Andree
No R/W
12/31/2019 11:12 AM 15 of 91
Design & Construction Review (DCR)
GIS OV221 Contract No
Prj No 520002 ITD Key No
Project Description
Current Project Phase 12 Design In House
DesignStatus 29 Prj Mgr
Notice to Proceed 9/25/2019 Consultant
Est Completion Date 8/21/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 7/2/2021 Proj Inspector
Est Compl Date 8/31/2021
Project Status Notes
Utility Comments
Geotechnical report has been reviewed, met with geotech consultant. Will provide
another design option. Design to start beginning of February (CD 12/16/19)
2021 Arterial and Collector Capital Maintenance ‐ HB312
Pavement rehabilita on on Pleasant Vally Rd between Hollolynn Dr and Amyx Rd. project
funding all or in part through House Bill 312. In‐house design.
Chris Dayley
ACHD Design
Pierson Dewit
Dave Serdar
12/31/2019 11:12 AM 16 of 91
Design & Construction Review (DCR)
GIS FAO221L Contract No
Prj No 719019 ITD Key No 20159
Project Description
Current Project Phase 11 Design
DesignStatus 100 Prj Mgr
Notice to Proceed 11/26/2018 Consultant
Est Completion Date 9/13/2019 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 6/14/2021 Proj Inspector
Est Compl Date 7/27/2021
Project Status Notes
Utility Comments
Staff is proposiing 10' travel lanes on NW8th to accomodate a standard width bike lane.
Will take proposal to the ACHD commission for a work session on January 15th. DJR
(12/17/19)
2021 Federal Aid Capital Maintenance ‐ Local
This project provides pavement rehabilitation and upgrade of adjacent pedestrian ramps
on 8th Street, from Pine Avenue to Cherry Lane.The project includes a total centerline
roadway length of approximately 0.53 miles. All work associated with this project shall be
done in accordance with Idaho Transportation Department design and drafting standards
and follow the Federal‐Aid process
Dave Rader
Parametrix Inc
Jim Koopman
No R/W
12/31/2019 11:12 AM 17 of 91
Design & Construction Review (DCR)
GIS FAO2211 Contract No
Prj No 719035 ITD Key No 18701
Project Description
Current Project Phase 11 Design
DesignStatus 58 Prj Mgr
Notice to Proceed 7/23/2019 Consultant
Est Completion Date 6/29/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 2/11/2021 Proj Inspector
Est Compl Date 8/24/2021
Project Status Notes
Utility Comments
Concept review is complete. Proceeding with environmental submittals. (BM 11-20-19)
2021 Federal Aid Capital Maintenance ‐ Phase 1
Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial
and collector road segments. Fairview Ave, Maple Grove to Milwuakee St; Curtis Rd, Ustick
Rd to Fairview Ave; Curtis Rd, Overland Rd to Targee St; Surprise Way, Amity Rd to Hwy 21;
Linden St, Broadway Ave to Gekeler Ln; Boise Ave, Broadway Ave to Gekeler Ln; Pleasant
Valley Rd, Hollilynn Dr to Gowen Rd.
Brian McCarthy
Parametrix Inc
No R/W
12/31/2019 11:12 AM 18 of 91
Design & Construction Review (DCR)
GIS FAO2212 Contract No
Prj No 719036 ITD Key No 20129
Project Description
Current Project Phase 11 Design
DesignStatus 39 Prj Mgr
Notice to Proceed 7/8/2019 Consultant
Est Completion Date 8/4/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 4/7/2021 Proj Inspector
Est Compl Date 8/12/2021
Project Status Notes
Utility Comments
The project is in the design phase and is on schedule. [JT III - 12/13/2019 ]
N/A
2021 Federal Aid Capital Maintenance ‐ Phase 2
Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial
and collector road segments as part of ACHD's Pavement Management Program.
Segments include the following: Warm Springs Avenue, Starcrest Drive to Starview Drive;
Warm Springs Avenue, Glacier Drive to Highway 21; and Edna Street, Five Mile Road to
Patton Avenue.
Joe Tate
Six Mile Engineering PA
Pierson Dewit
No R/W
12/31/2019 11:12 AM 19 of 91
Design & Construction Review (DCR)
GIS MTL221 Contract No
Prj No 519017 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 25 Prj Mgr
Notice to Proceed 10/14/2019 Consultant
Est Completion Date 8/25/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 5/6/2021 Proj Inspector
Est Compl Date 9/14/2021
Project Status Notes
Utility Comments
Field survey underway. DJR (12/17/19)
2021 Residential Capital Maintenance
Pavement rehabilita on and upgrade of adjacent pedestrian ramps residenital street
segments. Segments identified as part of ACHD's Pavement Management Program. Project
funded all or in part of House Bill 312 funding. In House design. Identified Segments are in
Meridan, Idaho and include: 5th St E ‐ Franklin Rd to Bower St 3rd St. E. ‐ Franklin St to
Bower St 2nd St E. ‐ Broadway Ave to Carlton Ave Bower St ‐ Maint St to East End 2.5 St E ‐
Carlton Ave to Fairview Ave Washington St ‐ 2.5 St to Cathy Ave 4th St E ‐ Washington Ave
to North End 5th St E ‐ State St to East End Carlton Ave ‐ Main St to 2.5 St Carlton Ave ‐
Main St to E 2nd St State Ave ‐ Main St to Ease End 4th St E ‐ Broadway Ave to State Ave
Dave Rader
ACHD Design
Ramon Wells
No R/W
12/31/2019 11:12 AM 20 of 91
Design & Construction Review (DCR)
GIS RD219‐01 Contract No
Prj No 819033 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 84 Prj Mgr
Notice to Proceed 1/23/2019 Consultant
Est Completion Date 9/26/2019 Contact
Right of WayEst Start 9/26/2019 ROW Agent
Completion Date 5/20/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 2/4/2021 Proj Inspector
Est Compl Date 5/11/2021
Project Status Notes
Utility Comments
Project is in ROW phase. DJR (12-17-19)
24th St Road and Bridge Project
Replace bridge #1466, bridge #1467, and bridge #1468 over Boise City Canal as a part of
ACHD’s Bridge Maintenance Program with a pre‐cast box culverts. Rebuild 24th St between
Bella and Irene to improve overall pavement condition.
Dave Rader
Keller Associates Inc
Rob Gronowski
Michele White
12/31/2019 11:12 AM 21 of 91
Design & Construction Review (DCR)
GIS CM215‐06 Contract No CT220‐06
Prj No 818017 ITD Key No
Project Description
Current Project Phase 19 Construction
DesignStatus 100 Prj Mgr
Notice to Proceed 12/1/2017 Consultant
Est Completion Date 6/22/2018 Contact
Right of WayEst Start 10/3/2018 ROW Agent
Completion Date 6/24/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 6/4/2020 Proj Inspector
Est Compl Date 7/31/2020
Project Status Notes
Utility Comments
Bid awarded on 12/4/2019. Sunroc Corporation is the responsive low bidder. DJR
(12/17/19)
28th Street ‐ Hazel Street to Irene Street
Construct bulb‐outs at the intersections of 28th Street & Irene, 28th and Bella Street, and
28th and Hazel Street to provide traffic calming.
Dave Rader
Six Mile Engineering PA
Larry White
Becca Randall
12/31/2019 11:12 AM 22 of 91
Design & Construction Review (DCR)
GIS MI215‐18 Contract No
Prj No 219025 ITD Key No
Project Description
Current Project Phase 16 Shelved/Bid Ready
DesignStatus 100 Prj Mgr
Notice to Proceed 11/30/2018 Consultant
Est Completion Date 5/20/2019 Contact
Right of WayEst Start 5/20/2019 ROW Agent
Completion Date 7/24/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 1/4/2021 Proj Inspector
Est Compl Date 4/13/2021
Project Status Notes
Utility Comments
100% design complete, ROW certs complete. Shelved until FY21 construction. SJ
9/30/19
32nd St Bridge 1308
Replace bridge #1308 over the Boise City Canal on 32nd St as part of ACHD's Bridge
Maintenance Program with a reinforced concrete pipe (RCP).
Seth Jarsky
Elite Edge Engineers
Lisa Vernon
Michele White
12/31/2019 11:12 AM 23 of 91
Design & Construction Review (DCR)
GIS MI215‐17 Contract No
Prj No 219020 ITD Key No
Project Description
Current Project Phase 16 Shelved/Bid Ready
DesignStatus 100 Prj Mgr
Notice to Proceed 11/30/2018 Consultant
Est Completion Date 5/20/2019 Contact
Right of WayEst Start 5/20/2019 ROW Agent
Completion Date 8/26/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 1/25/2021 Proj Inspector
Est Compl Date 5/4/2021
Project Status Notes
Utility Comments
100% design docs recieved, ROW certification recieved. Shelve project until FY21. SJ
9/16/19
33rd St Bridge 1318
Replace bridge #1318 over the Boise City Canal as a part of ACHD’s Bridge Maintenance
Program with a reinforced concrete pipe (RCP). Design to accommodate future 5’
sidewalks.
Seth Jarsky
Elite Edge Engineers
Bill Nelson
12/31/2019 11:12 AM 24 of 91
Design & Construction Review (DCR)
GIS MI216‐12 Contract No
Prj No 219004 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 75 Prj Mgr
Notice to Proceed 10/9/2018 Consultant
Est Completion Date 6/7/2019 Contact
Right of WayEst Start 6/7/2019 ROW Agent
Completion Date 12/31/2019 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 11/2/2020 Proj Inspector
Est Compl Date 2/8/2021
Project Status Notes
Utility Comments
In ROW phase. One property signed, one le to sign. License Agreement recorded.
Floodplain Application to be resubmitted with final plans. (CD 12/16 /19)
38th St Bridge 1440
Replace existing bridge #1440 over Thurman Mill Canal as part of ACHD’s Bridge
Maintenance Program with a reinforced concrete pipe. Widen existing roadway limits to 50
feet to accommodate future sidewalks.
Chris Dayley
Elite Edge Engineers
Lisa Vernon
Michele White
12/31/2019 11:12 AM 25 of 91
Design & Construction Review (DCR)
GIS CM216‐03 Contract No
Prj No 819021 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 11/26/2018 Consultant
Est Completion Date 7/25/2019 Contact
Right of WayEst Start 7/25/2019 ROW Agent
Completion Date 3/25/2020 Possession % 33
ConstructionStatus 0 Contractor
Notice to Proceed 4/20/2022 Proj Inspector
Est Compl Date 6/30/2022
Project Status Notes
Utility Comments
99% plans recieved and ROW staking was completed 10/28 (12/2/19 JT)
38th St, Bush Ave to Sunset Ave
Extend roadway and complete sidewalk on 38th St from Bush Ave to Sunset Ave. Par al
roadway reconstruction may be necessary.
Jason Tugby
T-O Engineers Inc
Pat Colwell
Renee Jayo
12/31/2019 11:12 AM 26 of 91
Design & Construction Review (DCR)
GIS MI216‐02 Contract No
Prj No 218039 ITD Key No
Project Description
Current Project Phase 12 Design In House
DesignStatus 100 Prj Mgr
Notice to Proceed 1/2/2018 Consultant
Est Completion Date 9/13/2018 Contact
Right of WayEst Start 9/13/2018 ROW Agent
Completion Date 4/22/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 11/30/2020 Proj Inspector
Est Compl Date 4/9/2021
Project Status Notes
Utility Comments
ROW complete. Construction moved to FY21. (12.04.19 JT)
41st Street Bridge 1437
Replace bridge #1437 over the Thurman Mill Canal on 41st St as part of ACHD's Bridge
Maintenance Program.
Jason Tugby
ACHD Design
Jeremy Andree
Becca Randall
12/31/2019 11:12 AM 27 of 91
Design & Construction Review (DCR)
GIS MI215‐05 Contract No
Prj No 219005 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 97 Prj Mgr
Notice to Proceed 10/26/2018 Consultant
Est Completion Date 4/23/2019 Contact
Right of WayEst Start 10/1/2018 ROW Agent
Completion Date 11/14/2019 Possession % 82
ConstructionStatus 0 Contractor
Notice to Proceed 3/4/2021 Proj Inspector
Est Compl Date 7/9/2021
Project Status Notes
Utility Comments
Project is currently in the ROW phase. Cultural scan completed, License agreement
recieved at Sawtooth law for Thurman Mill Signitures . Const programed for FY21 [
12.04.19 JT)
44th St Bridge 1433
Replace bridge #1433 over the Thurman Mill Canal on 44th St as part of ACHD's Bridge
Maintenance Program .
Jason Tugby
ACHD Design
Kraig Wartman
Bill Nelson
12/31/2019 11:12 AM 28 of 91
Design & Construction Review (DCR)
GIS MI215‐06 Contract No
Prj No 219003 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 10/26/2018 Consultant
Est Completion Date 4/23/2019 Contact
Right of WayEst Start 4/23/2019 ROW Agent
Completion Date 7/30/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 12/14/2020 Proj Inspector
Est Compl Date 4/22/2021
Project Status Notes
Utility Comments
100% plans recieved 10/25/2019 Cultural scan completed awaiting copy of license
agreement from Sawtoothlaw [ 12.04.19 JT)
45th St Bridge 1432
Replace bridge #1432 over the Thurman Mill Canal on 45th St as part of ACHD's Bridge
Maintenance Program .
Jason Tugby
ACHD Design
Kraig Wartman
Bill Nelson
12/31/2019 11:12 AM 29 of 91
Design & Construction Review (DCR)
GIS RD209‐11 Contract No
Prj No 517033 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 86 Prj Mgr
Notice to Proceed 2/23/2017 Consultant
Est Completion Date 1/6/2020 Contact
Right of WayEst Start 1/6/2020 ROW Agent
Completion Date 11/6/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 12/6/2021 Proj Inspector
Est Compl Date 7/25/2022
Project Status Notes
Utility Comments
Updated draft ROW plans submitted for review. Construction moving from 2020 to 2022
to bid with the State St/Eagle Rd project. (CH 12/05/19 )
Aikens St, Eagle Rd to 2nd St
Extend Aikens Rd east to 2nd St and add/replace curb, gu er, & sidewalks on both sides of
Aikens the length of the project in accordance with the Eagle Rd/State St Intersection
Concept Study. Street section to include parking on the south side of Aikens. 10 foot wide
sidewalks may be added where feasible with Cost Share with City of Eagle.
Cody Homan
Stanley Consultants
Jim Baker
Becca Randall
12/31/2019 11:12 AM 30 of 91
Design & Construction Review (DCR)
GIS IN205‐120 Contract No
Prj No 319049 ITD Key No
Project Description
Current Project Phase 06 Study
DesignStatus 11 Prj Mgr
Notice to Proceed 9/4/2019 Consultant
Est Completion Date 10/6/2020 Contact
Right of WayEst Start 10/6/2020 ROW Agent
Completion Date 10/5/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 2/3/2022 Proj Inspector
Est Compl Date 7/26/2022
Project Status Notes
Utility Comments
Intersec on analysis dra report submi ed, under review. (CH 12/09 /19)
Amity Rd and Maple Grove Rd Roundabout
Replace the Amity Rd and Maple Grove Rd with a roundabout or larger signalized
intersection.
Cody Homan
Six Mile Engineering PA
Jeff Jones
Dave Serdar
12/31/2019 11:12 AM 31 of 91
Design & Construction Review (DCR)
GIS CM215‐03 Contract No
Prj No 819015 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 11/20/2018 Consultant
Est Completion Date 8/26/2019 Contact
Right of WayEst Start 8/26/2019 ROW Agent
Completion Date 12/16/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 4/25/2022 Proj Inspector
Est Compl Date 7/6/2022
Project Status Notes
Utility Comments
ROW Cer ficate submi ed. (CD 12/16/19)
Bogart Ln, State St to Sloan St
Install an attached 7' asphalt pathway with extruded curb on the west side of Bogart Ln
between Caswell St and Pocono St. Construct a 5' attached sidewalk on the south side of
Sloan and a 7' attached sidewalk on the east side of Bogart Ln at the parcel and the SEC of
Bogart St and Sloan St. I nstall an RRFB across Bogart Ln on the south side of Sloan St.
Chris Dayley
ACHD Design
Matt Degen
Michele White
12/31/2019 11:12 AM 32 of 91
Design & Construction Review (DCR)
GIS CM213‐58 Contract No
Prj No 819040 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 99 Prj Mgr
Notice to Proceed 2/21/2019 Consultant
Est Completion Date 8/21/2019 Contact
Right of WayEst Start 11/21/2017 ROW Agent
Completion Date 12/26/2019 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 3/26/2020 Proj Inspector
Est Compl Date 6/5/2020
Project Status Notes
Utility Comments
ROW extended into FY20. Offers out to two properties. Construction in Summer. (CD
12/4/19)
Broadway Ave and Boise Ave
Improve safety for pedestrians at the intersec on of Boise Ave and Broadway Ave. Install
accessible pedestrian signals, remove and replace pedestrian ramps, and relocate lighting.
Chris Dayley
Precision Engineering LLC
Joel Grounds
Michele White
12/31/2019 11:12 AM 33 of 91
Design & Construction Review (DCR)
GIS MI218‐05 Contract No
Prj No 220011 ITD Key No
Project Description
Current Project Phase 12 Design In House
DesignStatus 4 Prj Mgr
Notice to Proceed Consultant
Est Completion Date 9/30/2020 Contact
Right of WayEst Start 9/30/2020 ROW Agent
Completion Date 6/7/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 11/1/2021 Proj Inspector
Est Compl Date 2/1/2022
Project Status Notes
Utility Comments
Field topo is complete, beginning development of boundry map. Design to start May
2020. (CD 12/16/19)
Bryson Ave Bridge 1134
Replace bridge #1134 over the South Slough‐lateral as a part of ACHD's Bridge
Maintenance Program. Design to accommodate future 7‐foot attached sidewalks on both
sides of the roadway.
Chris Dayley
ACHD Design
Pierson Dewit
Dave Serdar
12/31/2019 11:12 AM 34 of 91
Design & Construction Review (DCR)
GIS BK217‐03 Contract No
Prj No 818037 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 54 Prj Mgr
Notice to Proceed 4/1/2019 Consultant
Est Completion Date 4/1/2020 Contact
Right of WayEst Start 4/1/2020 ROW Agent
Completion Date 10/5/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 2/4/2021 Proj Inspector
Est Compl Date 8/3/2021
Project Status Notes
Utility Comments
50% review meeting was held 10/31/19. Open House is planned for 1/9/20. (BM 12-18-
19)
Cassia St Bikeway and Pedestrian Improvements
Bikeway and pedestrian improvements along Cassia St from Franklin Rd to Kootenai St
(includes portion of Robert St from Cassia St to Kootenai St). Project includes the following.
‐Sidewalk on north side and full width pavement rehabilitation from Franklin Park Dr to
Curtis Rd ‐Sidewalk on north side, full width pavement rehabilitation, and installation of
permeable pavers from Latah St to Shoshone St. ‐Mini roundabout at the intersection of
Cassia St and Shoshone St. ‐New bridge crossing at the Ridenbaugh Canal for
pedestrian/bike pathway connectivity through Cassia Park. ‐New PHB at Franklin Rd and
Liberty St ‐Modification/relocation of PHB at Cassia St and Orchard St ‐New RRFB at Cassia
Brian McCarthy
Kittelson & Associates
Becca Randall
12/31/2019 11:12 AM 35 of 91
Design & Construction Review (DCR)
GIS CM214‐44 Contract No
Prj No 819032 ITD Key No
Project Description
Current Project Phase 10 Ready DSN
DesignStatus 99 Prj Mgr
Notice to Proceed 2/8/2019 Consultant
Est Completion Date 10/25/2019 Contact
Right of WayEst Start 9/30/2019 ROW Agent
Completion Date 2/21/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 6/4/2020 Proj Inspector
Est Compl Date 9/21/2020
Project Status Notes
Utility Comments
99% design completed. IAA signed and returned from MLD for comission signiture on
November 13 2019. ROW phase awaiting Bill N. for updates ( 12.04.19 JT
Cherry Ln and Meridian Library Pedestrian Crossing
Install an enhanced pedestrian crossing (Pedestrian Hybrid Beacon) with a Z‐Crossing on
Cherry Lane midway between W 8th St and Linder Rd across from the library. This will
require relocating the existing school zone beacon to the west.
Jason Tugby
ACHD Design
JA
Bill Nelson, Dave Serdar
12/31/2019 11:12 AM 36 of 91
Design & Construction Review (DCR)
GIS IN215‐03 Contract No
Prj No 318006 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 12/11/2017 Consultant
Est Completion Date 9/10/2018 Contact
Right of WayEst Start 7/16/2018 ROW Agent
Completion Date 9/14/2020 Possession % 46
ConstructionStatus 0 Contractor
Notice to Proceed 1/12/2022 Proj Inspector
Est Compl Date 5/12/2022
Project Status Notes
Utility Comments
99% submittal received September 2018. R/W phase is programmed for 2019/2020.
(BM, 12-18-19)
Chinden Blvd and Curtis Rd
Add a right turn lane to southbound Veterans Memorial Parkway and Cur s Road. The
right turn lane will extend through the intersection to Ustick Road. Project includes new
curb, gutter, sidewalk, and retaining walls on the east side of Curtis Rd/Veterans Memorial
Pkwy.
Brian McCarthy
Six Mile Engineering PA
Larry White
Renee Jayo
12/31/2019 11:12 AM 37 of 91
Design & Construction Review (DCR)
GIS 103250 Contract No N/A
Prj No 520029 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 84 Prj Mgr
Notice to Proceed 10/11/2019 Consultant
Est Completion Date 1/3/2020 Contact
Right of WayEst Start 1/3/2020 ROW Agent
Completion Date 6/30/2020 Possession % 0
ConstructionStatus Contractor
Notice to Proceed Proj Inspector
Est Compl Date
Project Status Notes
Utility Comments
The Project is in the Design Phase and is on schedule. [JT III - 12/13/19]
Cloverdale Rd, Columbia Rd to Overland Rd Corridor Preservation
Acquire right‐of‐way for Idaho Power reloca ons on Cloverdale Road between Columbia
Road and Overland Road.
Joe Tate
T-O Engineers Inc
Steve Frisbie, 208-631-9655
Michele White
12/31/2019 11:12 AM 38 of 91
Design & Construction Review (DCR)
GIS IN205‐97 Contract No CT220‐02
Prj No 317005 ITD Key No
Project Description
Current Project Phase 19 Construction
DesignStatus 100 Prj Mgr
Notice to Proceed 1/13/2017 Consultant
Est Completion Date 8/8/2018 Contact
Right of WayEst Start 8/8/2018 ROW Agent
Completion Date 7/24/2019 Possession % 100
ConstructionStatus 9 Contractor
Notice to Proceed 11/14/2019 Proj Inspector
Est Compl Date 10/30/2020
Project Status Notes
Utility Comments
Construction NTP date was 11-14-19. Left turn restrictions onto Victory Rd to be
implemented starting early January. (BM 12-18-19)
Cole Rd and Victory Rd Intersection
Design intersec on of Cole Rd and Victory Rd in accordance with the 2016 CIP, widen Cole
Rd south to McGlochlin St to 5 lanes with bike lanes, sidewalks and/or pathways and
replace the structure of the Five Mile Creek.
Brian McCarthy
Precision Engineering LLC
Joel Grounds
Michele White
12/31/2019 11:12 AM 39 of 91
Design & Construction Review (DCR)
GIS CGS205‐20 Contract No CT219‐12
Prj No 816032 ITD Key No
Project Description
Current Project Phase 22 Complete
DesignStatus 100 Prj Mgr
Notice to Proceed 12/9/2015 Consultant
Est Completion Date 9/15/2016 Contact
Right of WayEst Start 9/15/2016 ROW Agent
Completion Date 2/22/2017 Possession % 100
ConstructionStatus Contractor
Notice to Proceed 2/21/2019 Proj Inspector
Est Compl Date 10/15/2019
Project Status Notes
Utility Comments
Central Paving Co Inc
Project is substantially complete. 11.16.19 RC
Columbus St, Overland Rd to Kootenai St
Construct curb, gu er & sidewalk on both sides of Columbus St from Overland Rd to
Kootenai St in accoradance with the Central Bench Neighborhood Plan. Project will provide
pedestrian connectivity & reduce the need for safety busing of Hawthorne Elementary
School.
Ryan Cutler
Six Mile Engineering PA
Jeff Jones
Michele White
12/31/2019 11:12 AM 40 of 91
Design & Construction Review (DCR)
GIS CM217‐27 Contract No
Prj No 819010 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 98 Prj Mgr
Notice to Proceed 10/25/2018 Consultant
Est Completion Date 3/11/2019 Contact
Right of WayEst Start 7/30/2019 ROW Agent
Completion Date 10/4/2019 Possession % 83
ConstructionStatus 0 Contractor
Notice to Proceed 5/4/2020 Proj Inspector
Est Compl Date 9/10/2020
Project Status Notes
Utility Comments
100% plans recieved Ready to bid with Addtional projects with JTIII (12.04.19 JT )
Deer Flat Rd and School Ave Pedestrian Crossing
Install an enhanced pedestrian crossing (Pedestrian Hybrid Beacon) on Deer Flat Rd at
School Ave.
Jason Tugby
Precision Engineering LLC
Joel Grounds
Bill Nelson
12/31/2019 11:12 AM 41 of 91
Design & Construction Review (DCR)
GIS 102730 Contract No
Prj No 8200091.0CD ITD Key No
Project Description
Current Project Phase 10 Ready DSN
DesignStatus 25 Prj Mgr
Notice to Proceed 11/18/2019 Consultant
Est Completion Date Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 5/12/2020 Proj Inspector
Est Compl Date 9/18/2020
Project Status Notes
Utility Comments
NTP for design signed 11/14 (JT 12/04)
Deer Flat Rd, School Ave to Deerhorn Rd
Jason Tugby
Precision Engineering LLC
Joel Grounds
Dave Serdar
12/31/2019 11:12 AM 42 of 91
Design & Construction Review (DCR)
GIS 102640 Contract No
Prj No 820097.0CD ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 39 Prj Mgr
Notice to Proceed 11/26/2019 Consultant
Est Completion Date Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 3/4/2020 Proj Inspector
Est Compl Date 5/5/2020
Project Status Notes
Utility Comments
30% Concept Design submitted 12-14/19. (12/16/19)
Division Ave, Highlands St to Hale St
Install 5' attached sidewalk to match existing with curb/gutter on the east side of Division
with ADA‐compliant ped ramps at crossings. Will require relocation of irrigation box at SE
corner of Division/Hale.
Chris Dayley
Civil Survey Consultants
Matt Hart
Dave Serdar
12/31/2019 11:12 AM 43 of 91
Design & Construction Review (DCR)
GIS RD207‐33 Contract No
Prj No 518040 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 1/29/2018 Consultant
Est Completion Date 6/28/2019 Contact
Right of WayEst Start 6/21/2019 ROW Agent
Completion Date 7/20/2020 Possession % 33
ConstructionStatus 0 Contractor
Notice to Proceed 11/19/2020 Proj Inspector
Est Compl Date 10/6/2021
Project Status Notes
Utility Comments
Project is in ROW. 11.26.19 RC
Eagle Rd, Amity Rd to Victory Rd
Widen Eagle Road to 5 lanes with curb, gu er, sidewalk and a Level 3 bike facility in
accordance with the 2016 CIP. Project inlcude enhanced pedestrian crossings at the
pedestrian pathway near the Tenmile Feeder Canal. In house design.
Ryan Cutler
ACHD Design
Jeremy Andree
Renee Jayo
12/31/2019 11:12 AM 44 of 91
Design & Construction Review (DCR)
GIS 103030 Contract No
Prj No 820095.0CD ITD Key No
Project Description
Current Project Phase 10 Ready DSN
DesignStatus 25 Prj Mgr
Notice to Proceed 1/3/2020 Consultant
Est Completion Date 3/25/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 6/16/2020 Proj Inspector
Est Compl Date 7/22/2020
Project Status Notes
Utility Comments
12/13 Finalizing SOW/PSA w WH Pacific 12/13/19 SMJ
Edgewood Ln, State St to Hill Rd
Install 7' detached asphalt pathways on east side of Edgewood to connect exis ng
infrastructure. Install 7' attached asphalt pathway with extruded curb in front of 220
Edgewood to connect to existing. Install 7' asphalt pathway on the west side of Edgewood
approximately 550' north from State St.
Seth Jarsky
WH Pacific
No R/W
12/31/2019 11:12 AM 45 of 91
Design & Construction Review (DCR)
GIS 101810 Contract No
Prj No 820021 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 57 Prj Mgr
Notice to Proceed 11/14/2019 Consultant
Est Completion Date 4/17/2020 Contact
Right of WayEst Start 4/17/2020 ROW Agent
Completion Date 9/30/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 6/7/2021 Proj Inspector
Est Compl Date 8/16/2021
Project Status Notes
Utility Comments
The Project is in the Design Phase and is on schedule. [JT III - 12-13-19]
Enhanced School Crossings ‐ Meridian Middle and Capital HS
Install enhanced pedestrian crossings (rectangular rapid flashing beacons) on W 8th St in
front of Meridain Middle School and on Milwaukee St next to Capital High School at the
existing crosswalks.
Joe Tate
CH2M Hill Engineers Inc
George Van Horn
Becca Randall
12/31/2019 11:12 AM 46 of 91
Design & Construction Review (DCR)
GIS IN217‐10 Contract No
Prj No 820018 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 7 Prj Mgr
Notice to Proceed 12/9/2019 Consultant
Est Completion Date 10/9/2020 Contact
Right of WayEst Start 10/9/2020 ROW Agent
Completion Date 4/27/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 8/5/2021 Proj Inspector
Est Compl Date 11/22/2021
Project Status Notes
Utility Comments
Awai ng NTP and signiture from Keller for contract. (JT 12/04)
Fairview Ave and Curtis Rd Accessible Pedestrian Signal
Jason Tugby
Keller Associates Inc
Rob Gronowski
Dave Serdar
12/31/2019 11:12 AM 47 of 91
Design & Construction Review (DCR)
GIS IN211‐05 Contract No
Prj No 320012 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 0 Prj Mgr
Notice to Proceed 12/12/2019 Consultant
Est Completion Date 9/30/2020 Contact
Right of WayEst Start 9/30/2020 ROW Agent
Completion Date 9/22/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 1/4/2022 Proj Inspector
Est Compl Date 9/19/2022
Project Status Notes
Utility Comments
Commission approved design contract on Dec. 11. Kickoff mee ng to be held early
January 2020. (BM 12-18-19)
Fairview Ave and Locust Grove Rd
Widen and reconstruct the intersec on of Fairview Ave and Locust Grove Rd with 9 lanes
on Fairview and 7 on Locust Grove. Project includes a concrete intersection, buffered bike
lanes, new curb, gutter, sidewalk, and traffic signals.
Brian McCarthy
Precision Engineering LLC
Joel Grounds
Dave Serdar
12/31/2019 11:12 AM 48 of 91
Design & Construction Review (DCR)
GIS IN217‐09 Contract No
Prj No 820019 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 6 Prj Mgr
Notice to Proceed 12/9/2019 Consultant
Est Completion Date 10/2/2020 Contact
Right of WayEst Start 10/2/2020 ROW Agent
Completion Date 3/9/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 6/25/2021 Proj Inspector
Est Compl Date 10/12/2021
Project Status Notes
Utility Comments
Awai ng NTP and signiture from Keller for Contract (JT 12/04)
Fairview Ave and Milwaukee St Accessible Pedestrian Signal
Jason Tugby
Keller Associates Inc
Rob Gronowski
Dave Serdar
12/31/2019 11:12 AM 49 of 91
Design & Construction Review (DCR)
GIS 102650 Contract No
Prj No 320093.0CD ITD Key No
Project Description
Current Project Phase 10 Ready DSN
DesignStatus 17 Prj Mgr
Notice to Proceed 11/18/2019 Consultant
Est Completion Date Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 5/12/2020 Proj Inspector
Est Compl Date 9/18/2020
Project Status Notes
Utility Comments
NTP signed 11-20 Precision Engineers (JT 12/04)
Five Mile and Seneca Pedestrian Crossing
Jason Tugby
Precision Engineering LLC
Joel Grounds
Dave Serdar
12/31/2019 11:12 AM 50 of 91
Design & Construction Review (DCR)
GIS 102342 Contract No
Prj No 320090.0CD ITD Key No
Project Description
Current Project Phase 10 Ready DSN
DesignStatus 18 Prj Mgr
Notice to Proceed 11/18/2019 Consultant
Est Completion Date Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 5/12/2020 Proj Inspector
Est Compl Date 9/18/2020
Project Status Notes
Utility Comments
NTP signed 11-20 Precision Engineers (JT 12/04)
Five Mile and Smoke Ranch Pedestrian Crossing
Jason Tugby
Precision Engineering LLC
Joel Grounds
Dave Serdar
12/31/2019 11:12 AM 51 of 91
Design & Construction Review (DCR)
GIS CM213‐15 Contract No
Prj No 819030 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 99 Prj Mgr
Notice to Proceed 2/19/2019 Consultant
Est Completion Date 8/30/2019 Contact
Right of WayEst Start 9/3/2019 ROW Agent
Completion Date 4/6/2020 Possession % 8
ConstructionStatus 0 Contractor
Notice to Proceed 7/27/2021 Proj Inspector
Est Compl Date 10/6/2021
Project Status Notes
Utility Comments
95% completed. Additional sidewalks to be designed with supplimental on Haines St with
storm water midigation. SME completed and in progress (12.04.19 JT)
Franklin St, McKinley St to Pierce St
Construct sidewalk on the north side of Franklin Street, between McKinley Street and
Pierce Street. Sidewalk will provide a safe walking route for students of Roosevelt School
and provide a connection to a public bus route on Haines St.
Jason Tugby
T-O Engineers Inc
Jeff Werner
Renee Jayo
12/31/2019 11:12 AM 52 of 91
Design & Construction Review (DCR)
GIS CM217‐29 Contract No
Prj No 819007 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 12/20/2018 Consultant
Est Completion Date 9/13/2019 Contact
Right of WayEst Start 9/13/2019 ROW Agent
Completion Date 8/27/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 2/16/2022 Proj Inspector
Est Compl Date 6/3/2022
Project Status Notes
Utility Comments
ROW underway. SMJ 12/13/19
Garden St Franklin Rd to Bethel St
Rebuild road to a 33’ cross sec on including curb, gu er, and sidewalk to Alpine Street.
Rebuild road to a 36’ cross section including curb, gutter, and sidewalk south of Alpine
Street. Design project to minimize and not disturb existing railroad crossing.
Seth Jarsky
Parametrix Inc
Harvin Flores
Renee Jayo
12/31/2019 11:12 AM 53 of 91
Design & Construction Review (DCR)
GIS MA212‐01 Contract No
Prj No 218049 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 69 Prj Mgr
Notice to Proceed 12/6/2018 Consultant
Est Completion Date 2/11/2020 Contact
Right of WayEst Start 2/11/2020 ROW Agent
Completion Date 9/30/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 2/7/2022 Proj Inspector
Est Compl Date 8/11/2022
Project Status Notes
Utility Comments
95% design submittal expected in December. (BM 11-20-19)
Gowen Rd Bridge 2110
Replace
existing bridge with a single span four lane bridge with curb,
gutter, attached sidewalks, and bike lanes. Install a 5 lane section with bike lanes and
attached
sidewalk on both approaches, connecting to the intersection of Gowen and
Eisenman to the east and the intersection of Gowen and Exchange on the west.
Replace the pedestrian ramps on Gowen at Eisenman with ADA compliant pedestrian
ramps.
Brian McCarthy
HDR Engineering Inc
Pete Eschbacher
Renee Jayo
12/31/2019 11:12 AM 54 of 91
Design & Construction Review (DCR)
GIS MA215‐01 Contract No CT219‐32
Prj No 217015 ITD Key No
Project Description
Current Project Phase 19 Construction
DesignStatus 100 Prj Mgr
Notice to Proceed 1/9/2017 Consultant
Est Completion Date 1/29/2018 Contact
Right of WayEst Start 11/20/2017 ROW Agent
Completion Date 12/18/2017 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 12/2/2019 Proj Inspector
Est Compl Date 5/1/2020
Project Status Notes
Utility Comments
Knife River
Herman
NTP December 1. Construction started, Bridge removed. (CD 12/16/19)
Gowen Rd Bridge 2173
Replace aging structure over New York Canal on Gowen Rd as part of ACHD's Bridge
Maintenance Program.
Chris Dayley
HW Lochner Inc
Vance Henry, Lochner
12/31/2019 11:12 AM 55 of 91
Design & Construction Review (DCR)
GIS CM211‐57 Contract No CT220‐03
Prj No 816002.008 ITD Key No
Project Description
Current Project Phase 17 Bid and Award
DesignStatus 100 Prj Mgr
Notice to Proceed 12/4/2015 Consultant
Est Completion Date 1/26/2017 Contact
Right of WayEst Start 11/21/2016 ROW Agent
Completion Date 5/31/2018 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 5/4/2020 Proj Inspector
Est Compl Date 7/31/2020
Project Status Notes
Utility Comments
Bid opening held on 12-18-19. Project will be packaged with Warm Springs, Glacier to
Glacier. DJR (12/17/19)
Holcomb Rd, Eastgate Dr to Amity Rd
Construct 5' detached sidewalk on the east side of Holcomb Rd between Mendota Dr and
Amity Rd in accordance with the Southeast Boise Neighborhood Plan. Stripe Bke lanes and
install wayfinding signage for a bike facility from Amity Rd to Mimosa Way. Project will
provide ped/bike connection from Oregon Trail Heights / Coulbia Village to Holcomb
path/bridge and Southeast Boise. In‐House Design
Dave Rader
ACHD Design
Pierson Dewit
Renee Jayo
12/31/2019 11:12 AM 56 of 91
Design & Construction Review (DCR)
GIS CM217‐22 Contract No
Prj No 820014 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 52 Prj Mgr
Notice to Proceed 11/21/2019 Consultant
Est Completion Date 3/6/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 4/27/2020 Proj Inspector
Est Compl Date 7/7/2020
Project Status Notes
Utility Comments
The Project is in the Design Phase as is on schedule. [JT III - 12-13-19]
Horseshoe Bend Rd and Shadowview Rd Ped Crossing
Install curb ramps, a striped pedestrian crossing, and refuge island on Horseshoe Bend Rd
on the north side of Shadowview St. In‐house design.
Joe Tate
ACHD Design
Jeremy Andree, David Sasso
Renee Jayo
12/31/2019 11:12 AM 57 of 91
Design & Construction Review (DCR)
GIS IN216‐01 Contract No
Prj No 320013 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 21 Prj Mgr
Notice to Proceed 9/30/2019 Consultant
Est Completion Date 11/6/2020 Contact
Right of WayEst Start 11/6/2020 ROW Agent
Completion Date 9/30/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 3/6/2023 Proj Inspector
Est Compl Date 9/8/2023
Project Status Notes
Utility Comments
The project is in the design phase and is on schedule. [J Tate III - 12-13-19]
Lake Hazel Rd and Eagle Rd
Widen and signalize intersec on to 4/5 lanes on Eagle Rd and 3/5 lanes on Lake Hazel Rd
as per the 2016 CIP. In‐house Design
Joe Tate
ACHD Design
Jeremy Andree
Michele White
12/31/2019 11:12 AM 58 of 91
Design & Construction Review (DCR)
GIS IN205‐59 Contract No
Prj No 318038 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 99 Prj Mgr
Notice to Proceed 1/17/2018 Consultant
Est Completion Date 3/1/2019 Contact
Right of WayEst Start 2/1/2019 ROW Agent
Completion Date 1/12/2023 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 10/16/2024 Proj Inspector
Est Compl Date 1/2/2025
Project Status Notes
Utility Comments
Plans have been delivered to the ROW team for acquisition and is on hold. 11.26.19 RC
Lake Hazel Rd and Five Mile Rd
Reconstruct intersec on to a 7x6 signalized intersec on.
Ryan Cutler
HDR Engineering Inc
Cameron Waite
Becca Randall, Dave Serdar
12/31/2019 11:12 AM 59 of 91
Design & Construction Review (DCR)
GIS 103080 Contract No
Prj No 820098.0CD ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 28 Prj Mgr
Notice to Proceed 12/23/2019 Consultant
Est Completion Date Contact
Right of WayEst Start 10/1/2019 ROW Agent
Completion Date 10/1/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 6/11/2020 Proj Inspector
Est Compl Date 8/7/2020
Project Status Notes
Utility Comments
Lake Hazel Rd, Cloverdale Rd to Five Mile Rd Pedestrian Improvements
Cody Homan
HW Lochner Inc
Justin Schwalbe
No R/W
12/31/2019 11:12 AM 60 of 91
Design & Construction Review (DCR)
GIS IN211‐01 Contract No
Prj No 313024 ITD Key No 13492
Project Description
Current Project Phase 16 Shelved/Bid Ready
DesignStatus 100 Prj Mgr
Notice to Proceed 5/16/2014 Consultant
Est Completion Date 9/29/2017 Contact
Right of WayEst Start 9/29/2017 ROW Agent
Completion Date 2/4/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 3/31/2020 Proj Inspector
Est Compl Date 9/30/2020
Project Status Notes
Utility Comments
The ROW Certification was received on 2/4/19. The plans are now shelf-ready.
Construction is planned for FY20. [JT III - 12/13/19]
Linder Rd and Deer Flat Rd
Federal aid project to improve intersec on of Linder Rd and Deer Flat Rd, including curb,
gutter, sidewalk, and bike facilities.
Joe Tate
Parametrix Inc
Cody Janson
Bill Nelson
12/31/2019 11:12 AM 61 of 91
Design & Construction Review (DCR)
GIS RD213‐16 Contract No CT220‐09
Prj No 516019 ITD Key No
Project Description
Current Project Phase 17 Bid and Award
DesignStatus 100 Prj Mgr
Notice to Proceed 2/1/2016 Consultant
Est Completion Date 12/22/2016 Contact
Right of WayEst Start 12/22/2016 ROW Agent
Completion Date 9/22/2017 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 2/6/2020 Proj Inspector
Est Compl Date 7/2/2020
Project Status Notes
Utility Comments
Responsive low bidder is Knife River Construction. Bid awarded January 8th. DJR
(12/17/19)
Linder Rd, Franklin Rd to Pine Ave
Widen Linder Road to 5 lanes with storm drain, curb, gutter, sidewalk and bike lanes in
accordance with the 2012 CIP. Project includes upgrade of the Union Pacific Railroad
crossing, irrigation crossings and Bridge #131. Project is the top priority safe routes to
school request (2015) from the West Ada School District.
Dave Rader
HW Lochner Inc
Vance Henry
Michele White
12/31/2019 11:12 AM 62 of 91
Design & Construction Review (DCR)
GIS IN209‐06 Contract No
Prj No 318048 ITD Key No 19944
Project Description
Current Project Phase 17 Bid and Award
DesignStatus 97 Prj Mgr
Notice to Proceed 8/1/2018 Consultant
Est Completion Date Contact
Right of WayEst Start 9/4/2018 ROW Agent
Completion Date 6/7/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 1/2/2020 Proj Inspector
Est Compl Date 8/18/2020
Project Status Notes
Utility Comments
Project to be constructed by ITD beginning January 2020. (BM 12-18-19)
Locust Grove Rd and Chinden Blvd Intersection
Widen Locust Grove Rd at the intersec on of Chinden and Locust Grove to three lanes on
the north side and five lanes on the south side to match the ITD cross‐section at this
intersection. North of Chinden install attached five foot sidewalks, curb and gutter, and
bike lanes. South of Chinden, install curb, gutter, and a detached 5' sidewalk on both sides
of Locust Grove. Purchase ROW for future buildout of a displaced left intersection and two
southbound receiving lanes.
Brian McCarthy
Parametrix Inc
Dave Serdar
12/31/2019 11:12 AM 63 of 91
Design & Construction Review (DCR)
GIS RD202‐44 Contract No
Prj No 519034 ITD Key No
Project Description
Current Project Phase 12 Design In House
DesignStatus 61 Prj Mgr
Notice to Proceed 12/5/2018 Consultant
Est Completion Date 5/18/2020 Contact
Right of WayEst Start 5/18/2020 ROW Agent
Completion Date 6/29/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 11/18/2021 Proj Inspector
Est Compl Date 2/3/2022
Project Status Notes
Utility Comments
Project in beginning phase of design with 50% plans an cipated in August and PIM #1 in
September. 8.26.19 RC
Locust Grove Rd, Victory Rd to Overland Rd
Widen Locust Grove Rd to five lanes in accordance with the 2016 Capital Improvements
Plan. Install 5’ detached sidewalks and buffered bike lanes. Relocate the Pedestrian Hybrid
Beacon (PHB) at Bassett Street. Install a Pedestrian Hybrid Beacon at Time Zone Dr.
Relocate impacted utility poles and the utility boxes at Doberman. Replace the bridge
#2087 over Nine Mile Creek with a stiff leg culvert to accommodate final cross section.
Ryan Cutler
ACHD Design
Renee Jayo, Dave Serdar
12/31/2019 11:12 AM 64 of 91
Design & Construction Review (DCR)
GIS RD207‐22 Contract No
Prj No 517039 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 12/14/2016 Consultant
Est Completion Date 6/21/2019 Contact
Right of WayEst Start 7/8/2019 ROW Agent
Completion Date 6/16/2020 Possession % 39
ConstructionStatus 0 Contractor
Notice to Proceed 11/4/2020 Proj Inspector
Est Compl Date 9/22/2021
Project Status Notes
Utility Comments
ROW phase in process. 11.26.19 RC
Maple Grove Rd, Victory Rd to Overland Rd
Widen Maple Grove Rd to 5 lanes with curb, gu er, sidewalk, & bike lanes in accordance
with the 2012 CIP. Project includes reconstruction/widening of Maple Grove bridges
#1237, #1238, and #1242 and installation of enhanced pedestrian crossings at Targee and
Maple Grove Elementary.
Ryan Cutler
Horrocks Engineers Inc
Heidi Carter
Michele White
12/31/2019 11:12 AM 65 of 91
Design & Construction Review (DCR)
GIS CM217‐23 Contract No
Prj No 819031 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 10/26/2018 Consultant
Est Completion Date 10/18/2019 Contact
Right of WayEst Start 10/18/2019 ROW Agent
Completion Date 1/20/2020 Possession % 27
ConstructionStatus 0 Contractor
Notice to Proceed 1/22/2020 Proj Inspector
Est Compl Date 4/9/2020
Project Status Notes
Utility Comments
12/13 ROW underway SMJ 12/13/19
McMillan Rd and Leather Way Pedestrian Crossing
Install an enhanced pedestrian crossing (pedestrian hybrid beacon) on McMillan Rd at
Leather Way. In‐house design .
Seth Jarsky
ACHD Design
Bill Nelson
12/31/2019 11:12 AM 66 of 91
Design & Construction Review (DCR)
GIS CM214‐01 Contract No
Prj No 816031 ITD Key No
Project Description
Current Project Phase 17 Bid and Award
DesignStatus 100 Prj Mgr
Notice to Proceed 11/5/2015 Consultant
Est Completion Date 9/6/2017 Contact
Right of WayEst Start 9/6/2017 ROW Agent
Completion Date 7/25/2018 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 2/27/2020 Proj Inspector
Est Compl Date 7/20/2020
Project Status Notes
Utility Comments
12/13 Schedule to bid January, NTP late February SMJ 12/13/19
McMillan Rd, Westview Dr to Maple Grove Rd
Complete sidewalk on the south side and an asphalt pathway on the north side of
McMillan Rd from Westview Dr to Maple Grove Rd. Project includes installation of an
enhanced pedestrian crossing (PHB) at Mitchell St.
Seth Jarsky
ACHD Design
Jeremy Andree
Michele White
12/31/2019 11:12 AM 67 of 91
Design & Construction Review (DCR)
GIS RD207‐23 Contract No CT220‐01
Prj No 516027 ITD Key No
Project Description
Current Project Phase 19 Construction
DesignStatus 59 Prj Mgr
Notice to Proceed 12/7/2015 Consultant
Est Completion Date 12/19/2016 Contact
Right of WayEst Start 12/19/2016 ROW Agent
Completion Date 8/5/2019 Possession % 100
ConstructionStatus 6 Contractor
Notice to Proceed 12/2/2019 Proj Inspector
Est Compl Date 9/1/2020
Project Status Notes
Utility Comments
Construction to begin November 12/2/19. Idaho Power has already begun with
relocations. Temporary road closure of Meridian Rd to take place in January for
replacement of the Settlers Canal culvert. (BM, 12-18-19)
U lity comments acquired.
Idaho Power IUE corrridor in project
Meridian Rd, Cherry Ln to Ustick Rd
Widen Meridian Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in accordance
with the 2012 CIP. Project includes reconstruction/widening of Meridian Rd Bridges #2045
and #126X and enhanced pedestrian crossings at James Ct and Woodbury Dr.
Brian McCarthy
Civil Survey Consultants
Tim Burgess
Renee Jayo
12/31/2019 11:12 AM 68 of 91
Design & Construction Review (DCR)
GIS CM215‐17 Contract No
Prj No 820016 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 57 Prj Mgr
Notice to Proceed 11/14/2019 Consultant
Est Completion Date 4/17/2020 Contact
Right of WayEst Start 4/17/2020 ROW Agent
Completion Date 9/30/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 6/7/2021 Proj Inspector
Est Compl Date 8/16/2021
Project Status Notes
Utility Comments
The Project is in the Design Phase and is on schedule. [JT III - 12/13/19]
Overland Rd and Phillippi St Ped Crossing
Install an enhanced crossing (pedestrian hybrid beacon) across Overland Rd at Phillippi St
as per the Central Bench Neighborhood Plan. In‐house design.
Joe Tate
CH2M Hill Engineers Inc
George Van Horn
Becca Randall
12/31/2019 11:12 AM 69 of 91
Design & Construction Review (DCR)
GIS NE204.01 Contract No
Prj No 816002.017 ITD Key No
Project Description
Current Project Phase 16 Shelved/Bid Ready
DesignStatus 100 Prj Mgr
Notice to Proceed 4/7/2016 Consultant
Est Completion Date 4/12/2017 Contact
Right of WayEst Start 4/12/2017 ROW Agent
Completion Date 8/7/2017 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 1/4/2021 Proj Inspector
Est Compl Date 7/14/2021
Project Status Notes
Utility Comments
The final submittal was received on 9/28/17 and the project is shelf-ready. [JT III -
12/13/19]
Phillippi St, Malad St to Targee St
Complete curb, gu er, & sidewalk improvements on both sides of Phillippi St between
Malad St and Targee St in accordance with the Central Bench Neighborhood Plan.
Joe Tate
Riedesel Engineering Inc
Pierson Dewit
Michele White
12/31/2019 11:12 AM 70 of 91
Design & Construction Review (DCR)
GIS CM210‐49 Contract No
Prj No 817021.001 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 100 Prj Mgr
Notice to Proceed 11/4/2016 Consultant
Est Completion Date 7/18/2018 Contact
Right of WayEst Start 9/6/2016 ROW Agent
Completion Date 7/2/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 2/5/2021 Proj Inspector
Est Compl Date 7/28/2021
Project Status Notes
Utility Comments
Re-design incorporating reduced street section is complete. Initiating cultural scan. DJR
(12/17/19)
Phillippi Street, Targee Street to Overland Road
Construct curb, gutter & sidewalk on the east side of Phillippi St between Targee St &
Overland Rd in accordance with the Central Bench Neighborhood Plan. Project includes a
partial pavement rehabilitation.
Dave Rader
ACHD Design
Jeremy Andree
Dave Serdar
12/31/2019 11:12 AM 71 of 91
Design & Construction Review (DCR)
GIS CM211‐34 Contract No CT220‐08
Prj No 818041 ITD Key No
Project Description
Current Project Phase 19 Construction
DesignStatus 100 Prj Mgr
Notice to Proceed 12/29/2017 Consultant
Est Completion Date 9/27/2018 Contact
Right of WayEst Start 9/28/2018 ROW Agent
Completion Date 9/30/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 5/29/2020 Proj Inspector
Est Compl Date 8/31/2020
Project Status Notes
Utility Comments
Compliance Solutions & Contract
Bids opened Nov 13, Compliance Solutons & Contracting is the apparrent low bidder.
Commision awarded 12/4/19 (CD 12/16/19)
Pierce St, Washington St to Shenandoah Dr
Reconstruct
Pierce St from Washington St to Shenandoah Dr, install 5‐foot wide sidewalk on
the west side of Pierce St, install pedestrian curb ramps, small section curb
and gutter, storm drain manholes and piping, catch basins, two seepage beds,
and associated appurtenances.
Chris Dayley
T-O Engineers Inc
Pat Colwell
Becca Randall, Dave Serdar
12/31/2019 11:12 AM 72 of 91
Design & Construction Review (DCR)
GIS CM211‐25 Contract No
Prj No 816002.016 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 11/25/2015 Consultant
Est Completion Date 6/22/2017 Contact
Right of WayEst Start 6/22/2017 ROW Agent
Completion Date 9/24/2018 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 12/16/2021 Proj Inspector
Est Compl Date 5/11/2022
Project Status Notes
Utility Comments
Construction has been reprogrammed for FY22. (BM, 2-19-19)
Roosevelt St, Rose Hill St to Emerald St (West Side)
Construct sidewalks on the west side of Roosevelt St between Rose Hill St & Emerald St in
accordance with the Central Bench Neighborhood Plan. Project will improve connectivity
for students attending Jefferson Elementary. Project also includes full width pavement
maintenance under project #517018.
Brian McCarthy
Precision Engineering LLC
Joel Grounds
Bill Nelson
12/31/2019 11:12 AM 73 of 91
Design & Construction Review (DCR)
GIS 102970 Contract No
Prj No 820092.0CD ITD Key No
Project Description
Current Project Phase 10 Ready DSN
DesignStatus 27 Prj Mgr
Notice to Proceed 1/2/2020 Consultant
Est Completion Date 4/21/2020 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 6/29/2020 Proj Inspector
Est Compl Date 7/28/2020
Project Status Notes
Utility Comments
12/13 Finalizing SOW/PSA w WH Pacific 12/13/19 SMJ
Royal Blvd, La Pointe St to Lusk St
Install 5‐foot wide detached asphalt pathway on Royal Blvd from La Pointe to Lusk St to fill
pedestrian gaps. Install ADA‐compliant ramps as necessary. Near multiple parks and BSU.
2020 Commission Directive Projects.
Seth Jarsky
WH Pacific
No R/W
12/31/2019 11:12 AM 74 of 91
Design & Construction Review (DCR)
GIS MI215‐09 Contract No
Prj No 219024 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 97 Prj Mgr
Notice to Proceed 1/17/2019 Consultant
Est Completion Date 7/15/2019 Contact
Right of WayEst Start 7/15/2019 ROW Agent
Completion Date 9/30/2020 Possession % 18
ConstructionStatus 0 Contractor
Notice to Proceed 1/21/2021 Proj Inspector
Est Compl Date 6/4/2021
Project Status Notes
Utility Comments
The project is in the ROW phase and is on schedule. [JT III - 12/13/19]
N/A
Shamrock Ave Bridge No 1424
Replace Bridge #1424 over the South Slough on Shamrock Avenue as part of ACHD's Bridge
Maintenance Program.
Joe Tate
Elite Edge Engineers
Pierson Dewit / Future Selected D
Michele White
12/31/2019 11:12 AM 75 of 91
Design & Construction Review (DCR)
GIS BK213‐04 Contract No
Prj No 818014 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 2/1/2019 Consultant
Est Completion Date 10/14/2019 Contact
Right of WayEst Start 10/14/2019 ROW Agent
Completion Date 2/26/2020 Possession % 4
ConstructionStatus 0 Contractor
Notice to Proceed 6/12/2020 Proj Inspector
Est Compl Date 9/30/2020
Project Status Notes
Utility Comments
12/13 ROW underway SMJ 12/13 /19
Shoshone St Bikeway, Canal St to Capital Blvd
Improve Shoshone St as part of the regional low stress bikeway network from Canal St to
Capital Blvd. Project includes cycle track at Overalnd and Shoshone intersection, RRFB at
Rose Hill and Shoshone intersection, bulb outs at Nez Perce and Shoshone intersection,
bikeway wayfinding and markings.
Seth Jarsky
Kittelson & Associates
Bill Nelson
12/31/2019 11:12 AM 76 of 91
Design & Construction Review (DCR)
GIS IN210‐03 Contract No
Prj No 317044 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 85 Prj Mgr
Notice to Proceed 1/2/2018 Consultant
Est Completion Date 5/24/2019 Contact
Right of WayEst Start ROW Agent
Completion Date 9/1/2020 Possession % 30
ConstructionStatus 0 Contractor
Notice to Proceed 1/12/2021 Proj Inspector
Est Compl Date 10/22/2021
Project Status Notes
Utility Comments
The project is in the ROW phase and is on schedule. Re-design to add a south leg to the
intersection is also now underway. [JT III - 12/13/19]
State St and Pierce Park Ln
Rebuild the State Street and Pierce Park Ln intersec on in accordance with the State Street
Transit and Traffic Operations Plan (TTOP). The State Street TTOP call for expanding State
Street to three lanes in each direction with bike lanes and a center turn lane. The two
outermost vehicular lanes would eventually be reserved for buses and high occupancy
vehicles. The Pierce Park leg of the intersection will need to be reconfigured to intersect
State Street at between 75 and 90 degrees.
Joe Tate
Parametrix Inc
Cody Janson
Bill Nelson
12/31/2019 11:12 AM 77 of 91
Design & Construction Review (DCR)
GIS MIS216‐02 Contract No
Prj No 717040 ITD Key No 20275
Project Description
Current Project Phase 19 Construction
DesignStatus 100 Prj Mgr
Notice to Proceed 1/26/2018 Consultant
Est Completion Date 11/5/2018 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 8/8/2019 Proj Inspector
Est Compl Date 1/31/2020
Project Status Notes
Utility Comments
The project is in the Construc on Phase and is ahead of schedule. [JT III - 12/13/19]
State St, 16th to 23rd Street Lighting Improvements
This Local Highway Safety Improvement Project (LHSIP) is a federal aid safety project to
install continuous street lighting to improve visibility and reduce nighttime crashes.
Joe Tate
Precision Engineering LLC
Joel Grounds
No R/W
12/31/2019 11:12 AM 78 of 91
Design & Construction Review (DCR)
GIS IN205‐03 Contract No
Prj No 308004 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 12/2/2016 Consultant
Est Completion Date 9/11/2018 Contact
Right of WayEst Start 9/11/2018 ROW Agent
Completion Date 10/11/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 12/13/2021 Proj Inspector
Est Compl Date 5/6/2022
Project Status Notes
Utility Comments
R/W is complete. Awaiting Bureau of Reclamation and Army Corps permits/agreements
Construction is currently programmed for FY22. (BM, 12-18-19)
Ten Mile Rd and Amity Rd
Construct a multi‐lane roundabout at the intersection of Ten Mile Rd and Amity Rd to
maintain efficient and safe traffic operations. Project includes Ten Mile Bridge #1182.
Brian McCarthy
ACHD Design
Jeremy Andree
Bill Nelson
12/31/2019 11:12 AM 79 of 91
Design & Construction Review (DCR)
GIS CM217‐52 Contract No
Prj No 819039 ITD Key No
Project Description
Current Project Phase 20 Construction In House
DesignStatus 100 Prj Mgr
Notice to Proceed 2/25/2019 Consultant
Est Completion Date 8/30/2019 Contact
Right of WayEst Start 8/30/2019 ROW Agent
Completion Date 11/5/2019 Possession % 100
ConstructionStatus 77 Contractor
Notice to Proceed 11/12/2019 Proj Inspector
Est Compl Date 2/18/2020
Project Status Notes
Utility Comments
12/13 Construction to be substantially complete week of Dec 16. SMJ 12/13/19
Ten Mile Rd and Crenshaw St Pedestrian Crossing
Install an enhanced pedestrian crossing (pedestrian hybrid beacon) on Ten Mile Rd at
Crenshaw St. In‐house design and build.
Seth Jarsky
ACHD Design
Jeremy Andree
Dave Serdar
12/31/2019 11:12 AM 80 of 91
Design & Construction Review (DCR)
GIS IN214‐03 Contract No
Prj No 319038 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 60 Prj Mgr
Notice to Proceed 1/21/2019 Consultant
Est Completion Date 2/26/2020 Contact
Right of WayEst Start 2/26/2020 ROW Agent
Completion Date 9/14/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 12/23/2020 Proj Inspector
Est Compl Date 8/26/2021
Project Status Notes
Utility Comments
Design of the phased mul -lane roundabout ongoing. Online PIM underway with the Ten
Mile, Victory to Overland project, comment period ends Dec. 20th. (CH 12/09/19)
Ten Mile Rd and Victory Rd
Widen the intersec on or replace with a roundabout. A traffic analysis will be done to
determine the ultimate lane configuration based on growth above projections in the area.
Includes the replacement/widening of the bridge over the irrigation lateral on Ten Mile Rd,
north of Victory Rd.Design will be coordinated with the Ten Mile Rd, Victory Rd to Overland
Rd project to widen Ten Mile Rd to 5‐lanes (In‐house design). These project are planned to
be bid together.
Cody Homan
Six Mile Engineering PA
Jeff Jones
Dave Serdar
12/31/2019 11:12 AM 81 of 91
Design & Construction Review (DCR)
GIS RD202‐31 Contract No
Prj No 518030 ITD Key No
Project Description
Current Project Phase 19 Construction
DesignStatus 100 Prj Mgr
Notice to Proceed 11/6/2017 Consultant
Est Completion Date 12/7/2018 Contact
Right of WayEst Start 9/5/2017 ROW Agent
Completion Date 7/10/2019 Possession % 100
ConstructionStatus 23 Contractor
Notice to Proceed 9/16/2019 Proj Inspector
Est Compl Date 10/13/2020
Project Status Notes
Utility Comments
Construction is underway. DJR (12/17/19)
Pothole 4-15-2018 SCB
Ten Mile Rd, McMillan Rd to Chinden Blvd
Widen Ten Mile Rd to five lanes with curb, gutter, sidewalk and bike lanes in accordance
with the 2016 CIP.
Dave Rader
ACHD Design
Kraig Wartman
Bill Nelson
12/31/2019 11:12 AM 82 of 91
Design & Construction Review (DCR)
GIS RCO299 Contract No
Prj No 519041 ITD Key No
Project Description
Current Project Phase 12 Design In House
DesignStatus 60 Prj Mgr
Notice to Proceed 1/4/2019 Consultant
Est Completion Date 2/26/2020 Contact
Right of WayEst Start 2/26/2020 ROW Agent
Completion Date 9/14/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 12/23/2020 Proj Inspector
Est Compl Date 8/26/2021
Project Status Notes
Utility Comments
Design ongoing, In-house. Online PIM underway with the Ten Mile/Victory project,
comment period ends Dec. 20th. (CH 12/09/19)
Ten Mile Rd, Victory Rd to Overland Rd
Widen Ten Mile Rd to 5 lanes with curb, gu er, sidewalk and a Level 3 bike facility in
accordance with the 2016 CIP and Master Street Map. In‐house design.
Cody Homan
ACHD Design
Jeremy Andree
Bill Nelson
12/31/2019 11:12 AM 83 of 91
Design & Construction Review (DCR)
GIS RD202‐32 Contract No CT220‐07
Prj No 518001 ITD Key No
Project Description
Current Project Phase 19 Construction
DesignStatus 46 Prj Mgr
Notice to Proceed 10/18/2017 Consultant
Est Completion Date 10/16/2018 Contact
Right of WayEst Start 10/16/2018 ROW Agent
Completion Date 9/16/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 12/30/2019 Proj Inspector
Est Compl Date 9/14/2020
Project Status Notes
Utility Comments
Bid awarded on 12/4/19 to Central Paving. Utility preconstruction meeting held on
12/9/19. DJR (12/17/19)
Ten Mile Road, Ustick Road to McMillan Road
Widen Ten Mile Road from 2 to 5 lanes with curb, gu er and sidewalk and bike lanes in
accordance with 2016 CIP. Five detached sidewalks will be constructed on each side of the
street. New pedesterian hybrid beacons will be installed at both the Five Mile Creek
Pathway and just south of Vecenza way. The project alson includes replacing bridge #2044
over the Five Mile Creeek and bridge #1103 over the Creason Lateral.
Dave Rader
Civil Survey Consultants
Matt Hart
Renee Jayo
12/31/2019 11:12 AM 84 of 91
Design & Construction Review (DCR)
GIS MDR218‐02 Contract No
Prj No 220003 ITD Key No
Project Description
Current Project Phase 10 Ready DSN
DesignStatus 7 Prj Mgr
Notice to Proceed 1/6/2020 Consultant
Est Completion Date 8/11/2020 Contact
Right of WayEst Start 8/11/2020 ROW Agent
Completion Date 7/27/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 11/1/2021 Proj Inspector
Est Compl Date 1/18/2022
Project Status Notes
Utility Comments
12/12 Meeting w Legal, resume w FY20 Design and FY21 ROW SMJ 12/13/19
Thurman Mill Bridge Projects
Provide water quality and quan ty mi ga on for a series of bridge projects being
reconstructed in or near the Thurman Mill drainage area.
Seth Jarsky
J-U-B Engineers Inc
Dave Serdar
12/31/2019 11:12 AM 85 of 91
Design & Construction Review (DCR)
GIS CM217‐53 Contract No
Prj No 819014 ITD Key No
Project Description
Current Project Phase 15 Right of Way
DesignStatus 100 Prj Mgr
Notice to Proceed 12/6/2018 Consultant
Est Completion Date 5/10/2019 Contact
Right of WayEst Start 6/5/2019 ROW Agent
Completion Date 9/4/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 5/28/2020 Proj Inspector
Est Compl Date 8/7/2020
Project Status Notes
Utility Comments
Project is in right-of-way. DJR (12/17/19)
Ustick Rd and Milwaukee St School Zone
Pavement rehabilita on and upgrade pedestrian ramps on specified residen al street
segments. Segments identified as part of ACHD's Pavement Management Program. Project
funded or in part through House Bill 312 funding.
Dave Rader
Six Mile Engineering PA
Larry White
Michele White
12/31/2019 11:12 AM 86 of 91
Design & Construction Review (DCR)
GIS CM214‐61 Contract No CT220‐12
Prj No 819027 ITD Key No
Project Description
Current Project Phase 17 Bid and Award
DesignStatus 90 Prj Mgr
Notice to Proceed 1/14/2019 Consultant
Est Completion Date 8/12/2019 Contact
Right of WayEst Start 8/12/2019 ROW Agent
Completion Date 11/19/2019 Possession % 100
ConstructionStatus 0 Contractor
Notice to Proceed 6/15/2020 Proj Inspector
Est Compl Date 8/11/2020
Project Status Notes
Utility Comments
Construc on phase has been moved to FY 20. ROW Cert submi ed. 100% plans
submitted. Scheduled to bid in Jan. (CD 12/16/19)
N/A
Valley St, Lake Hazel Rd to La Grange St
Install approximately 860LF of new curb, gu er, sidewalk, and remove and replace
approximately 385LF of sidewalk on the west side of Valley Street in front of the school.
Upgrade and install 7 curb ramps, a seepage bed, driveway approach, crosswalk and
luminaire.
Chris Dayley
Six Mile Engineering PA
Leah Kelsey
Renee Jayo, Dave Serdar
12/31/2019 11:12 AM 87 of 91
Design & Construction Review (DCR)
GIS IN215‐06 Contract No
Prj No 319043 ITD Key No
Project Description
Current Project Phase 12 Design In House
DesignStatus 58 Prj Mgr
Notice to Proceed 12/5/2018 Consultant
Est Completion Date 4/30/2020 Contact
Right of WayEst Start 4/30/2020 ROW Agent
Completion Date 7/19/2021 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 11/18/2021 Proj Inspector
Est Compl Date 2/3/2022
Project Status Notes
Utility Comments
Project is in 95% design phase. (RC 11.30.19)
Victory Rd and Locust Grove Rd Roundabout
Replace intersec on of Victory Rd and Locust Grove Rd with a two lane roundabout in
accordance with the 2016 Capital Improvements Plan. Shift the roundabout slightly to the
northeast of the center of the existing intersection to minimize right‐ of‐way impacts.
Ryan Cutler
ACHD Design
Renee Jayo, Dave Serdar
12/31/2019 11:12 AM 88 of 91
Design & Construction Review (DCR)
GIS CM215‐19 Contract No
Prj No 318032 ITD Key No
Project Description
Current Project Phase 16 Shelved/Bid Ready
DesignStatus 100 Prj Mgr
Notice to Proceed 1/11/2018 Consultant
Est Completion Date 7/20/2018 Contact
Right of WayEst Start 4/23/2018 ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 5/26/2020 Proj Inspector
Est Compl Date 8/26/2020
Project Status Notes
Utility Comments
The project is shelved / bid ready. [JT III- 12/13/19]
Victory Rd and Standing Timber Ave Pedestrian Crossing
Installation of a Pedestrian hybrid beacon (PHB) on the west side of Standing Timber Ave.
across from Victory Rd. Install directional ramps on both sides of intersection and place
ramps just west of the existing crossing to avoid impacts to storm drain infrastructure.
Joe Tate
CH2M Hill Engineers Inc
George Van Horn
No R/W
12/31/2019 11:12 AM 89 of 91
Design & Construction Review (DCR)
GIS CM214‐47 Contract No
Prj No 820017 ITD Key No
Project Description
Current Project Phase 11 Design
DesignStatus 20 Prj Mgr
Notice to Proceed 11/15/2019 Consultant
Est Completion Date 4/30/2020 Contact
Right of WayEst Start 4/30/2020 ROW Agent
Completion Date 9/16/2020 Possession % 0
ConstructionStatus 0 Contractor
Notice to Proceed 4/26/2022 Proj Inspector
Est Compl Date 6/22/2022
Project Status Notes
Utility Comments
Executed PSA with design consultant. Held kick-off mee ng on Oct 22. Design started.
30% design due Jan 23, 2020. (CD 12/16/19)
Vista Ave and Nez Perce St Ped Crossing
Design
and install a marked crosswalk and HAWK, including bike push buttons on Vista
at Nez Perce (South side of the intersection). Remove and install ADA compliant
directional curb ramps. Install bus stops closer to Nez Perce.
Chris Dayley
Precision Engineering LLC
Joel Grounds
Becca Randall
12/31/2019 11:12 AM 90 of 91
Design & Construction Review (DCR)
GIS CM217‐01 Contract No CT220‐03
Prj No 819023 ITD Key No
Project Description
Current Project Phase 17 Bid and Award
DesignStatus 100 Prj Mgr
Notice to Proceed 1/7/2019 Consultant
Est Completion Date 9/30/2019 Contact
Right of WayEst Start ROW Agent
Completion Date Possession %
ConstructionStatus 0 Contractor
Notice to Proceed 5/4/2020 Proj Inspector
Est Compl Date 7/31/2020
Project Status Notes
Utility Comments
The project is in the bid and award phase and is on schedule. [JT III - 12/13/19]
N/A
Warm Springs Ave, Glacier Dr to Glacier Dr
Construct sidewalk on the north side of Warm Springs Avenue from 320' northwest of
Glacier Drive to the southeast corner of Riverland Terrace Subdivision. Priority request
from the Boise School District.
Joe Tate
Precision Engineering LLC
Pierson Dewit / Future Selected C
No R/W
12/31/2019 11:12 AM 91 of 91