addendum no. 2 to the contract documents for w0502 …€¦ · addendum no. 2 addendum no. 2 to the...

35
Highway 99 Distribution System Improvements - 1 - Contract No. W0502 Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the attention of all Bidders for the above project: The following additions(s), deletions(s), revisions(s) and/or modifications(s) are made to the Contract Documents, Specifications, and Drawings for the construction of W0502 Highway 99 Distribution System Improvements. ITEM 1 CHLORINE INJECTION VAULT AT M&O SITE (SCHEDULE F) A chlorine injection vault and associated appurtenances is added to the water system improvements at the District’s M&O site (Schedule F). The work includes a revision to one of the connections to the existing system, and an increase in the quantity of restrained joint 16- inch DI water main. Volume 2 Special Provisions In Section 01025 Measurement and Payment, under lump sum Bid Item # 91 M & O Site Miscellaneous Improvements as revised in Addendum 1, add the following under B.2.: d. Installing the chlorine injection vault and appurtenances in conformance with the details shown on Drawing Sheet F-5 included with this Addendum No. 2. e. The 16-inch Ductile Iron pipe, both interior and exterior of the vault, shall be measured and paid for under the Bid Item #45 16-Inch DI Water Pipe, Class 52, Incl. Fittings (RJ). (The overall length of water main is increased due to this addition by approximately 80 lineal feet). f. The connection to the existing 16-inch DI water main, as shown on revised Detail 3/F-4 (as shown on replacement Drawing Sheet F-4 included with this Addendum No. 2), shall be measured and paid for under Bid Item #46 Connection to Existing Water Main. (The number of connections is not changed by the addition of this work). A revised Section 01025 is not included with this Addendum No. 2. Volume 5 Drawings The following Drawing Sheets are revised and replaced: Sheet F-2: Plan and profile notes have been revised and a new profile for the 16” connection & chlorine injection vault has been added. Sheet F-4: Detail 3/F-4 has been revised. Sheets G-3 and G-4: Sheet Indexes have been updated to reflect Item 2 addition and Addendum 1 changes. The following Drawing Sheet is added to the Contract: Sheet F-5 entitled Chlorine Injection Vault Details. Copies of revised Drawing Sheets F-2 and F-4, and new Drawing Sheet F-5 are included with this Addendum No. 2.

Upload: others

Post on 20-Jul-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Highway 99 Distribution System Improvements - 1 - Contract No. W0502

Addendum No. 2

ADDENDUM NO. 2 To The Contract Documents for

W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS

To the attention of all Bidders for the above project:

The following additions(s), deletions(s), revisions(s) and/or modifications(s) are made to the Contract Documents, Specifications, and Drawings for the construction of W0502 Highway 99 Distribution System Improvements.

ITEM 1 – CHLORINE INJECTION VAULT AT M&O SITE (SCHEDULE F)

A chlorine injection vault and associated appurtenances is added to the water system improvements at the District’s M&O site (Schedule F). The work includes a revision to one of the connections to the existing system, and an increase in the quantity of restrained joint 16-inch DI water main. Volume 2 – Special Provisions In Section 01025 Measurement and Payment, under lump sum Bid Item # 91 M & O Site Miscellaneous Improvements as revised in Addendum 1, add the following under B.2.:

d. Installing the chlorine injection vault and appurtenances in conformance with the details shown on Drawing Sheet F-5 included with this Addendum No. 2.

e. The 16-inch Ductile Iron pipe, both interior and exterior of the vault, shall be measured and paid for under the Bid Item #45 16-Inch DI Water Pipe, Class 52, Incl. Fittings (RJ). (The overall length of water main is increased due to this addition by approximately 80 lineal feet).

f. The connection to the existing 16-inch DI water main, as shown on revised Detail 3/F-4 (as shown on replacement Drawing Sheet F-4 included with this Addendum No. 2), shall be measured and paid for under Bid Item #46 Connection to Existing Water Main. (The number of connections is not changed by the addition of this work).

A revised Section 01025 is not included with this Addendum No. 2. Volume 5 – Drawings The following Drawing Sheets are revised and replaced:

Sheet F-2: Plan and profile notes have been revised and a new profile for the 16” connection & chlorine injection vault has been added. Sheet F-4: Detail 3/F-4 has been revised. Sheets G-3 and G-4: Sheet Indexes have been updated to reflect Item 2 addition and Addendum 1 changes.

The following Drawing Sheet is added to the Contract:

Sheet F-5 entitled Chlorine Injection Vault Details.

Copies of revised Drawing Sheets F-2 and F-4, and new Drawing Sheet F-5 are included with this Addendum No. 2.

Page 2: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Highway 99 Distribution System Improvements - 2 - Contract No. W0502

Addendum No. 2

ITEM 2 – REVISED COST ESTIMATE

The cost estimate is revised to reflect the deletion of Bid Schedule G (Sanitary Sewer) from the Contract and the addition of insertion valves pursuant to Addendum No.1 and the addition of the Chlorine Injection Vault per Item 1 of this addendum. Volume 1 - Bidding Requirements and Conditions In Section 00020 Invitation to Bid, revise the Cost Estimate to read:

$11.7 to $13.0M (excl. Wash. Sales Tax)

A revised Section 00020 is not included with this Addendum No. 2.

ITEM 3 – PRE-BID CONFERENCE

The Pre-Bid Conference was held at the District office on January 24, 201. The presentation slides for the project overview given at the conference and the attendance sheets are attached with this Addendum No.2.

The following questions and their corresponding answers are presented below:

1. Q: Will the estimated dollar amount of the deleted Schedule G sewer work be provided? A: Yes, a revised estimated amount reflecting the deletion of the sewer work will be shown in the next addendum.

2. Q: There is a requirement to pothole ahead of construction. Does the District “stand by” its potholing information? How accurate is the pothole information? Were the potholed utilities surveyed? If the pothole information is accurate why does the Contractor need to pothole? A: The existing utility locations shown on the plans are based on information collected from as-built drawings, field notes, and measurements obtained from pothole excavations. Some of the utility location information was verified by survey for design purposes only, and is not guaranteed. The information that the District has gathered is provided to the Bidders in the Drawings. The requirement to pothole existing utilities in advance of the construction per the requirements of Contract Specification Section 01055 is not waived. The Contractor shall carefully review and comply with all requirements of this specification section and include all associated costs of potholing in his Bid.

3. Q: Was a design locate done? A. Yes, locates were done and the utility pavement markings indicating utilities were surveyed during design. The surveyed locations are shown on the Drawings.

4. Q: The specifications say that the Contractor will provide the material testing. Will the District be doing any testing in addition to the contractor? A: No, the District is not planning to do additional testing. The District will have a geotechnical engineer under contract in case a need arises for review or additional testing.

Page 3: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Highway 99 Distribution System Improvements - 3 - Contract No. W0502

Addendum No. 2

5. Q: Some of the pothole information indicates concrete under pavement. Is the location of the concrete road under Highway 99 known? A: The location of the old concrete road under Highway 99 is unknown. The existing concrete road is much narrower than the current road width, and the proposed water main is located generally in the outside driving lane of Highway 99. The old concrete road section is not shown because the limits are not accurately known.

6. Q: Is the project located mostly in Snohomish County jurisdiction? A: Work to be performed in Highway 99 is located in WSDOT right-of-way, except there is a portion of work within the City of Everett on Highway 99 at and north of Airport Road. With the exception of those areas, the work is within Snohomish County jurisdiction. Also, easements on private property adjacent to Highway 99 are within Snohomish County jurisdiction.

7. Q: Does the District have a grading permit for work on private property (easement areas)? If so, does this also cover the Contractor’s staging areas? A: The District does have a Snohomish County Grading permit for work in easement areas (permit is included in Appendix B). The District does not have a grading permit for the Contractors’ staging areas since the locations(s) are unknown at the time of design and during the Bid period. The Contractor shall be responsible for obtaining and all costs associated with any and all Snohomish County grading permits required for the Contractor’s staging areas. A copy of these approved permits and a copy of all executed agreements with property owners associated with staging areas shall be submitted to the District.

ITEM 4 – CONTRACTOR’S PERFORMANCE AND PAYMENT BOND

Delete Section 00700 10.0, Contractor’s Performance and Payment Bond in its entirety, and replace it with the following: 10.0 Contractor’s Performance and Payment Bond

No later than ten days after notice of selection, the Contractor shall execute and deliver to the District a performance and payment bond for 100% of the Contract Price in compliance with RCW 39.08, on a form acceptable to the District with an approved surety company having an A.M. Best rating of A- or greater that also holds a U.S. Treasury Department certificate of authority as an acceptable surety. The Contractor’s sureties shall be listed in the most current version of the (US) Department of the Treasury's Listing of Approved Sureties (Department Circular 570) http://www.fms.treas.gov/c570/c570_a-z.html.

The Contractor shall promptly furnish additional bond security to protect the District and persons supplying labor or materials required by the Contract if:

1. The District has a reasonable objection to any surety;

2. Any surety fails to furnish reports on its financial condition pursuant to District’s request; or,

3. The Contract Price increases beyond the bond amount.

Page 4: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Highway 99 Distribution System Improvements - 4 - Contract No. W0502

Addendum No. 2

ITEM 5 – SECTION 00400, QUALIFICATIONS

Replace pages 7 and 8 of SECTION 00400, QUALIFICATIONS, in their entirety and replace with revised pages 7 and 8 plus new pages 9 and 10 of SECTION 00400, QUALIFICATIONS, which are attached with this Addendum No. 2.

ITEM 6 – USE OF, AND PAYMENT FOR, CRUSHED SURFACING

Volume 2 – Special Provisions In Section 02500 General Pipe Installation, under 2.01 A. and B. on pages 3 and 4:

Change the references to “Crushed Surfacing” to read “Crushed Surfacing Base Course unless otherwise shown on the Drawings or required by permit conditions or the right-of-way authority.”

In Section 02500 General Pipe Installation, under 2.01 B. on page 3, for Pipe bedding for rigid pipe:

Delete both “Pea gravel” and “Gravel Backfill for Pipe Zone Bedding” and replace with “ Crushed Surfacing Base Course”.

A revised Section 02500 is not included with this Addendum No. 2.

Volume 5 – Drawings

On Drawing Sheet K-21: Change all references in all of the trench details form “Crushed Surfacing” to “Crushed Surfacing Base Course” unless “Crushed Surfacing Top Course” is explicitly delineated in the notes.

On Drawing Sheet K-21, Detail F for Pavement/Sidewalk Areas on Private Property, for circled note 3 referring to Pipe Zone Backfill:

Delete the words “Gravel Backfill For Pipe Zone Bedding Or”.

A copy of revised Drawing Sheet K-21 is not included with this Addendum No. 2.

ITEM 7 – CLAIMS DISCUSSION MEETING

Volume 2 – Special Provisions In Section 01200 Contract Meetings, add the following to page 3:

1.08 CLAIMS DISCUSSION MEETING A. The Contractor, his insurance broker, and risk manager shall attend a meeting

with the District and its representatives for the purpose of discussing claims procedures. The meeting shall be held prior to the start of construction.

A revised Section 01200 is not included with this Addendum No. 2.

ITEM 8 – 48 INCH STEEL CASING FOR AUGER BORE AT STATION 420+66

Volume 5 – Drawings The following Drawing Sheets are revised:

Sheet A-6: In the plan view, at the callout note for Station 420+66, correct the diameter of the steel casing for the auger bore from 42” DIA. to 48” DIA. Sheet A-13, Detail HWY 99 CROSSING AT STA 420+66: in both the plan and profile

Page 5: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Highway 99 Distribution System Improvements - 5 - Contract No. W0502

Addendum No. 2

views, change the callout notes referencing the steel casing diameter from 42” to 48”. In the plan view note, change the length from 73 LF to 80 LF.

Copies of revised Drawing Sheets A-6 and A-13 are not included with this Addendum No. 2.

ITEM 9 – PSE GAS MAINS OR SERVICES – RELOCATIONS

Volume 2 – Special Provisions In Section 01195 Protection and Maintenance of Work, 1.06 M. Gas on page 6: Add the following:

5. For any PSE gas mains or services to be relocated, contact Keith Zornes, Engineering Specialist, Customer Construction Services at 425-424-6470, or by email at [email protected].

A revised Section 01195 is not included with this Addendum No. 2. ITEM 10 – PAYMENT FOR TEMPORARY POTABLE WATER SERVICES

Volume 2 – Special Provisions In Section 02512 Water Service Connections, 3.01.A.6, on page 6, add the following new paragraph:

Furnishing, installing and removing temporary potable water services to businesses that would be adversely affected by temporary water service interruptions, shall be considered incidental costs to Bid Items numbered 39 through 47 and numbered 50 through 63.

A revised Section 02512 is not included with this Addendum No. 3.

ITEM 11 – WRITTEN QUESTIONS

Question 1 (Grouped)

Could you please clarify the Snohomish County permit (and associated fees) that is/are required of the contractor? In the pre-bid conference, it was mentioned that AWWD has procured a “Grading Permit” for the project. However, you made it clear that many of the permits required for the project must be pulled by the contractor (especially those that will drive review and inspection of traffic control plans). Is this “Grading” permit the same as the D8 Type Permit that Snohomish County requires for major utility construction that charges the contractor by the Lineal Foot of utility installed? The question/answer is key information for bidders in that the D8 permit and related costs may necessitate overall costs to the contractor in excess of $25,000 that would be incidental to the bid.

Answer:

Permits are described in Section 01062. Related work is described in Sections 01500 and 01570. The permits obtained by the District are included in Appendix B.

For Snohomish County, the District has obtained the Right-of-Way D8 – Utility and the Grading Permit – Commercial for the water main construction. Other Snohomish County permits have also been obtained but are no longer applicable as they related to the sanitary sewer system construction which was deleted from the project as the result of Addendum No. 1.

Page 6: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Highway 99 Distribution System Improvements - 6 - Contract No. W0502

Addendum No. 2

The District will pay all fees associated with the Right-of-Way D8 - Utility Permit and Grading Permit – Commercial including renewal and inspection fees.

However, the Contractor is responsible for obtaining from Snohomish County Public Works Right-of-Way Use/Traffic Control Plans (Type B) for road/lane/closures. Refer to 1.02.D in Section 01062 and 1.04.G in Section 01550 for more information.

All traffic control plans, regardless of road agency jurisdiction, are to be prepared by the contractor per Section 01570.

Question 2 (Grouped)

Could you please clarify the intention of the Hot Mix Asphalt Pay Items as they relate to the payment for removal of temporary asphalt and the intended sequencing for pavement patching? When will bid item #16, Hot Mix Asphalt for Temporary Trench Patch be utilized vs. bid item #17, Hot Mix Asphalt for Pavement Repair?

Answer:

Bid item #16, Hot Mix Asphalt for Temporary Trench Patch, will be paid for all asphalt placed as an asphalt patch that is then removed by the Contractor at a later date. Bid item #17, Hot Mix Asphalt for Pavement Repair, will be paid for all hot mix asphalt placed as a permanent trench patch or pavement repair that will not be removed by the Contractor at a later date.

Question 3

The special provisions say that removal of the temporary asphalt patch of BI#16 is incidental to the bid item. So does this mean that whenever the contractor has installed temporary hot asphalt patching that is not of a suitable depth to match the existing asphalt depth of the adjacent road structure that BI #16, Hot Mix Asphalt for Temporary Patch will apply and of course have to be removed to accommodate the subsequent permanent paving of BI#17?

Answer:

Yes.

Question 4

In short, when does AWWD visualize Bid Item #16 will be utilized specifically?

Answer:

Bid item #16 will be utilized to compensate the Contractor for all hot mix asphalt placed that will subsequently be removed by the Contractor, at a later date, and then replaced with a permanent hot mix asphalt patch or pavement repair.

Question 5

Bid Item #21, Planing Bituminous Pavement: The special provisions state that this bid item relates to the planning of existing asphalt surfaces. Does this mean that BI#21 will not apply to the surfaces that have been paved and paid under BI#15, BI#16, BI#17, or BI#18?

Page 7: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Highway 99 Distribution System Improvements - 7 - Contract No. W0502

Addendum No. 2

Answer: Measurement for Bid Item #21, Planing Bituminous Pavement, will apply to surface areas paid under Bid Items #15, #17 and #18, but will not apply to surface areas paid under Bid item #16.

Question 6

Is it AWWD’s intention to plane the surfaces for paving covered by the overlay bid items #19 & #20 after or before the paving in BI#15, BI#16, BI#17, or BI#18 has occurred to match the adjacent surfaces?

Answer: The sequence is the choice of the Contractor and subject to requirements of the governing road authority. Planing would occur after permanent asphalt trench patch or pavement repair and immediately preceding asphalt overlay.

Question 7 (Grouped)

Regarding the trenching and paving work on Highway 99, is it AWWD’s intent to have the contractor install the necessary pipe, bring the grade up to the bottom of the paving section daily, steel plate the trench until the end of the week, remove the steel plates and pave back full depth to provide a flat travel surface for weekend traffic (since steel plates are not allowed during weekends)? However, with the restrictions on daily paving to maximum 3“ lifts whereas Hwy 99 is likely to be 12” thick, this sequence would be impossible as it would require 4 days of paving to reach the full section height. Could you please clarify the sequence for paving that AWWD has witnessed under similar specifications on past projects?

Answer:

Past projects are not reported here since each project is unique. Per 1.06.F of Section 02740, Asphalt Paving, daily paving is limited to 6 inches total compacted thickness (two or more compacted lifts). WSDOT has indicated it will allow limited, temporary use of steel plates if they are removed weekly. The District has included Bid Item #16, Hot Mix Asphalt for Temporary Trench Patch to compensate the Contractor for furnishing, placing and removing temporary trench patch, which is required to be three (3) inches thick for WSDOT ROW. As a point of clarification for performance requirement 1.07.M of Section 02740, the term “trench patching” was intended to include either temporary or permanent trench patching.

The District is relying on the Contractor to determine the most effective and efficient means of accomplishing the work. The District’s currently envisioned method of accomplishing the work in WSDOT Right-Of-Way is for the Contractor to perform the excavation, pipe laying and backfill during the work week, plating over the excavations until the last night (Friday night). The temporary hot patch thickness would be installed that night in one lift, allowed to cool and traffic opened up by the required time per the WSDOT permit conditions on Saturday morning. The permanent paving operation that requires the 12” patch thickness per detail K-21 and the approved permits will occur sometime later in the project. The permanent paving operation will include removal of the temporary hot patch and some asphalt paving on either side of the patch (planing is required in some locations), and install the required 12” minimum permanent patch and

Page 8: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Highway 99 Distribution System Improvements - 8 - Contract No. W0502

Addendum No. 2

required overlay over multiple days. The length of each segment of the final paving operations is up to the contractor with concurrence of WSDOT.

Laurie Fulton February 1, 2012

Attachments:

Revised Drawing Sheets (for Chlorine Injection Vault): F-2 and F-4

New Drawing Sheet (for Chlorine Injection Vault): F-5

Updated Drawing Sheets: G-3 and G-4

Presentation Slides for the project overview presented at the Pre-Bid Conference on January 24, 2012

Attendance sheets from the January 24, 2012 Pre-Bid Conference

Revised Pages 7 and 8 plus new pages 9 and 10, Section 00400 Qualifications

END OF ADDENDUM NO. 2

Page 9: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the
Page 10: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the
Page 11: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the
Page 12: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the
Page 13: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the
Page 14: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Highway 99 Distribution System Improvements

Contract No. W0502

Pre-Bid Meeting

January 24, 2012

1

Page 15: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Project Team

• AWWD

– Nancy Davidson

– Bob Hastings

• HWA

– Erik Anderson

• Roth Hill

– Laurie Fulton

– Jay Gibson

• Hainline & Associates

– Curt Quick

2

Page 16: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Meeting Agenda

• Sign In/Introductions (please be sure to sign in) • Project Overview • Roles During Construction • Bid Requirements • Permit Status/Requirements • Easements • Construction Concerns • Contractor Staging and Access • Available Information/Documents • Utilities Coordination • Construction Scheduling/Phasing • Site Review • Questions and Answers

3

Page 17: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Project Overview • Project Purpose

– Water Main Replacement – Distribution System Upgrades – Pressure Zone Adjustments

• Project is divided into schedules based primarily on location

• Project is primarily located in WSDOT and Snohomish County right of way with smaller portions in City of Everett right of way and easements

• 28,300 +/- lf of 16”, 12” and smaller water mains including 4 trenchless crossings of WSDOT right of way

• Addendum No. 1 issued 1/20/12 – Sewer work, lift station abandonments (Bid Schedule G) deleted – Insertion valves (3) added

4

Page 18: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

5

Page 19: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Roles During Construction

• AWWD is funding the project

• AWWD is the lead agency - Bob Hastings is the contact

• Construction Manager - Hainline & Associates

• Roth Hill, LLC - engineering support

• EADOCS will be used to manage information

6

Page 20: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Bid Requirements

• Bid Opening: February 14, 2012 at 1:30pm • Follow the Instruction to Bidders (Section 00100) • Checklist of Bidding Forms (Section 00200)

– Form of Bid (Section 00300 – including Acknowledgement of Addendums)

– Bid Guarantee Bond (5%)

• Qualifications (Section 00400), Specific subcontractor qualifications in other sections

• The Construction Schedules are combined into two Bid Schedules

• Bidder questions directed to Bob Hastings at AWWD • Prevailing Wage Project • Bid documents available from ARC’s PlanWell service.

7

Page 21: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Permit Status/Requirements Acquired Permits in Appendix B • Washington State DOE Construction Stormwater

General Permit • Snohomish County Noise Ordinance Variance • WSDOT Permit Utility Franchise and Amendments

– Amendment 3 is the most recent • Snohomish County Right of Way • Snohomish County Grading • City of Everett Right of Way Permits required to be obtained by the Contractor are identified in the Specifications

8

Page 22: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Easements

• All temporary and permanent easements are in Appendix C.

• Easement restrictions on: – Work Schedule – Completion Date – Constraints on the Use of Parking Lots

• Liquidated damage provisions are applicable (see Sections 00700 & 01014).

• Completion of Property Release forms required for all temporary and permanent easements. A copy of the form is in Appendix C.

• Working outside easement areas is not permitted unless there is a private agreement with the property owner.

9

Page 23: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Construction Concerns

• Lane Closure/Time of Day Restrictions – Night work on Highway 99 & State Route 525

• Traffic Control Plans – Contractor submittal required

• Construction Sequencing Plans (Water) – See sheet in drawings and Appendix F

• Four Trenchless Crossings – 3 Highway 99; 1 State Route 525

• Restoration/Paving Considerations – “K” Drawings

• Potholing in Advance of Construction – 6 Working Days

10

Page 24: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Contractor Staging & Access

• Temporary and permanent easements have been provided where the water mains cross private property

• Contractor is responsible for acquiring staging areas whether on road right of way or private property

• Refer to Specification Section 01500 for requirements to provide field offices

11

Page 25: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Available Information/Documents

• Potholing Data in Drawings

• Geotechnical Data Report Included in Appendix G for reference

• Corridor Study and Environmental Record Review Included in Appendix H

• Business Hours Included for Convenience in Appendix E

12

Page 26: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Utilities Coordination

• Water – Alderwood (AWWD)

• Sanitary Sewer – AWWD and property owners

• Power – Snohomish County PUD No. 1

• Gas – Puget Sound Energy

• Cable – Comcast/Frontier

• Communications/Fiber Optics – Property owners and Century Link

• Storm Drainage – WSDOT, Snohomish County, City of Everett, and property owners

• Traffic – WSDOT, City of Everett, and Snohomish County

• Traffic Signals – WSDOT & Snohomish County

13

Page 27: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Scheduling/Phasing

• Bid Opening: February 14, 2012 at 1:30pm

• Qualifications will be requested at the bid opening for the two lowest bidders

• Expected Construction (in field) start late March/early April 2012

• Initial Items

– Submittals/Meetings Required

14

Page 28: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Site Review

• Bidders are invited and encouraged to visit the pipe alignments

• All areas are visible from the road right of way/easements except SR 525 crossing only visible from Freeway and 148th Ave Bridge

15

Page 29: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

Questions/Answers

16

Page 30: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

ALDERWOOD WATER AND WASTEWATER DISTRICT

W0502 HWY 99 DISTRIBUTION SYSTEM IMPROVEMENTS

PRE-BID MEETING - JANUARY 24, 2012 -1:30 PM

SIGN-IN SHEET

NAME (Please Print) COMPANY/AGENCY CITY / STATE TELEPHONE E-MAIL ADDRESS

l ^ ^ u ^ v ^ o v A c ^ n . / to A

<^rvv

j

3 £o« ^ o - y / y £ _^ :

«0 Sj~^*S\*r\f

yvc_

4 Lr -745-46^

j d.f ^ V K ^ V A J (p g y cTfg- S L L Z ^ C . . Cg2 Id x

Page 31: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

ALDERWOOD WATER AND WASTEWATER DISTRICT

W0502 HWY 99 DISTRIBUTION SYSTEM IMPROVEMENTS

PRE-BID MEETING - JANUARY 24, 2012 -1:30 PM

SIGN-IN SHEET

NAME (Please Print) COMPANY/ AGENCY CITY / STATE TELEPHONE E-MAIL ADDRESS

f

i

Brckri I )<q jL-Aor 1 1 v

j

Page 32: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

4. List of past projects where the partners of the J V worked together in the past and indicate the roles and responsibilities of each member in relation to that project.

2.04 SUBCONTRACTORS.

A. Within 48 hours of bid opening identify the name and address for each subcontractor, designer or supplier; the type of work to be completed by it and information that the such entity meets the qualification requirements of this Section 00400. List past projects, provide each project's name, contract value, and owner's name and phone number and describe the subcontractor's responsibilities. Each entity's qualification may be reviewed and prior experience checked to verify that the entity identified are qualified and have adequate experience on projects similar in size, scope, and complexity to this project. Provide the qualifications information for the following:

1. Auger Bore Installation Subcontractor. Identify the name and address of the subcontractor responsible for auger bore scope of work (or the Bidder if doing the work itself). The subcontractor (or Bidder if self performing) shall have a minimum of five (5) years of experience in auger bore projects and have completed at least five (5) auger boring projects consisting of a minimum 36-inch diameter and greater than 50 feet in length between pits in the last two years using the type of equipment to be used in this Contract. The subcontractor shall have completed at least one (1) auger bore drive greater than 120 feet in length with a minimum diameter of 30 inches. All auger bore projects cited to meet these qualification requirements shall have been constructed in glacially derived granular soil similar to that indicated in the GDR.

2. Auger Bore Superintendent: Experience as a superintendant on at least three (3) auger bore projects in the past two (2) year using the type of auger bore system to be used in this Contract. All projects to have been constructed in glacially derived granular soil similar to that indicated in the GDR. Provide a description of the superintendent's responsibilities on each project.

Auger Bore Operator: Experience as a auger bore equipment on at least three (3) auger bore projects in the past two (2) years using the type of auger bore system to be used in this Contract. All projects to have been constructed in glacially derived granular soil similar to that indicated in the GDR.

3. Provide a list of the proposed equipment for the auger bore installation. Note any equipment differences that may apply to each auger bore location or resulting from auger boring locations at more than one location concurrently.

2.05 FINANCIAL RESPONSIBILITY, BOND FORFEITURE, LITIGATION AND CLAIMS

In addition to the criteria named above, the District requires the Bidder to be a contractor possessing demonstrated financial responsibility and skills of integrity, diligence, and honesty. To assist in the District's evaluation of this additional criterion, the Bidder shall provide information requested in Sections 2.05 through 2.08.

Highway 99 Distribution System Improvements Addendum No. 2

00400 - 7 Contract No.W0502

Page 33: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

2.06 FINANCIAL RESPONSIBILITY A responsible contractor shall be in a stable financial condition, such that this project can be successfully completed. Contractors shall provide evidence of qualifications by submitting the following: (a) provide the firm's current bonding capacity and state the ability of the firm to bond this project; (b) list the bonding company name, contact person, telephone number of your bonding agent, and include a statement from your bonding agent pertaining to the commitment to bond this project; and (c) provide proof that the surety proposed for this Project meets the requirements of 00700, Section 10.0.

For each bonding company used in the past 5 years, please list the bonding company name,

address, agent's name, and phone number.

Bonding Company Address Name of

Bonding Agent Agent's Phone

Number

At any time during the past five (5) years, has any surety company made any payments on

your current or past firm's behalf as a result of a default or to satisfy any claims made against

a performance or payment bond issued on your firm's behalf, in connection with a construction

project.

• Yes • No

If "yes," attach a separate signed/dated statement indicating the amount of each claim,

the name and telephone number of the claimant or bonding company, the date of the

claim, the grounds for the claim, the present status of the claim, the date of resolution

of claim if resolved, the method by which such was resolved if resolved, the nature of

the resolution and the amount, if any, at which the claim was resolved.

2.07 LAWSUITS A. Criterion: The Bidder shall not have lawsuits or arbitrations with judgments or

awards entered against the Bidder within five years of the bid submittal date that demonstrate a failure to meet the terms of contracts, unless there are extenuating circumstances acceptable to the Owner.

B. Documentation: The Bidder shall submit a list of lawsuits or arbitrations with judgments or awards entered against the Bidder within five years of the bid submittal date, along with a written explanation of the circumstances surrounding each such lawsuit. The Owner shall evaluate these explanations to determine whether the lawsuits demonstrate a failure to meet of terms of construction related contracts. The Owner may also evaluate lawsuits within the time period specified that are not reported by the Bidder.

Highway 99 Distribution System Improvements Addendum No. 2

00400 - 8 Contract No.W0502

Page 34: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

2.08 PREVAILING W A G E S

A . Criterion: The Bidder shall not have a record of prevail ing wage complaints filed against it within five years of the bid submittal date that demonstrates a pattern of failing to pay workers prevail ing wages , unless there are extenuating c i rcumstances acceptable to the Owner.

B. Documentat ion: The Bidder shall submit a list of prevail ing wage complaints filed against it within five years of the bid submittal date along with an explanation of each complaint and how it was reso lved. The Owner shall evaluate these explanat ions and the resolution of each complaint to determine whether the complaints demonstrate a pattern of failing to pay its workers prevailing wages as required. The Owner may also evaluate complaints filed within the time period speci f ied that were not reported by the Bidder.

2.09 CONTRACT HISTORY

A. Provide detailed information as to the following if within the past 15 years the Bidder has:

1. Had a contract terminated for cause or default;

2. Not been an active contractor;

3. Been in bankruptcy, reorganization and/or receivership;

4. Not been registered and licensed as a construction contractor; and

5. Been disqualified by any federal, state or local agency from being awarded and/or participating in public contracts.

6. Has failed to complete a project or Contract.

B. Explain the circumstances surrounding the event(s) identified above.

C. If the Bidder has not had any of the above six situations occur within the past 15 years, the Bidder shall state that "Contractor has not had contractual problems per Section 00400, Item 2.06.A. within the past 15 years."

2.10 CRIMINAL HISTORY

Identify all criminal convictions, including pleas of nolo contendere, of the Bidder and any officers of the Bidder. If the Bidder and its officers have no criminal convictions, including pleas of nolo contendere, the Bidder shall state that "Bidder and its officers have no criminal convictions."

2.11 ACCIDENT/INJURY EXPERIENCE

Submit the Bidder's accident/injury experience factor from the Department of Labor and Industries or other appropriate organization from the year 2000 to present. If the Bidder is a joint venture, provide information for members of the joint venture who will be performing and managing the Contract work. If a JV or BOS partner is only providing financial support, this information is not required and will not be evaluated with regard to this element.

Highway 99 Distribution System Improvements Addendum N o . 2

00400 - 9 Contract No.W0502

Page 35: ADDENDUM NO. 2 To The Contract Documents for W0502 …€¦ · Addendum No. 2 ADDENDUM NO. 2 To The Contract Documents for W0502 HIGHWAY 99 DISTRIBUTION SYSTEM IMPROVEMENTS To the

2.12 ACCIDENT PREVENTION PROGRAM Submit for approval, in accordance with Section 01063 Health and Safety, the Bidder's Accident Prevention Program ("APP") that meets the requirement of Washington Administrative Code (WAC) 296-155-110 and the applicable portions of W A C 296-24, W A C 296-62, W A C 296-67, W A C 296-155 and W A C 296-800 thru W A C 296-876. Pursuant to the W A C , the A P P is to be tailored to the Contractor's type of construction business. Specific types of hazards related to the work under this Contract shall be addressed in the site-specific Health and Safety Plan (HASP) which shall be submitted after Contract execution. The following W E B site provides additional information regarding the A P P :

http://www.lni.wa.gov/Safety/Basics/Programs/Accident/APPCoreRuleGuide.pdf

SECTION 3: ADDITIONAL INFORMATION

At the District's request, provide any other explanation or information, which would assist the District in evaluating the qualifications of the Bidder, the Bidder's key personnel, and proposed subcontractors.

END OF SECTION

Highway 99 Distribution System Improvements Addendum N o . 2

00400 - 10 Contract No.W0502