![Page 1: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/1.jpg)
Advanced Reactors and New Reactors Topics
BriefingCommission Meeting
February 6, 2020
1
![Page 2: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/2.jpg)
Opening Remarks
Margaret Doane
Executive Director for Operations
![Page 3: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/3.jpg)
Vision and Direction for Regulatory Reviews of
New and Advanced Reactors
Robert Taylor
Deputy Office Director for New Reactors
![Page 4: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/4.jpg)
UNIFIED NRR
RESEARCH AND TEST REACTORS
SUBSEQUENT LICENSE RENEWAL
OPERATING REACTORS
ADVANCED REACTORS
NEW REACTORS
MEDICAL ISOTOPES
We Make SAFE Use of Nuclear Technology POSSIBLE
4
![Page 5: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/5.jpg)
SAFE, TIMELY, AND EFFECTIVE LICENSING & OVERSIGHT OF VOGTLE 3&4
Closing ITAAC
Overseeing Vogtle Construction
Resolving
License Amendment
Requests 5
Photos Courtesy of Southern Nuclear Operating Company
![Page 6: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/6.jpg)
SUSTAINING SMALL MODULAR REACTOR (SMR) PROGRESS
Phase 2
Phase 3
Phase 4
Phase 5
Phase 6
Rulemaking
Phase 1
Design Certification
on Schedule
Standard Design
Approval
ON THE HORIZON
BWRX-300 SMR
Construction
Permit
Combined License
HITACHI
6
![Page 7: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/7.jpg)
ADVANCED REACTORS STAKEHOLDERS
NEIMA NEICA
PUBLIC
7
![Page 8: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/8.jpg)
Commitment
Execution
Execution
ENABLING the SAFE Use of
New NUCLEARTechnologies
COMMITMENT
PREPARATION EXECUTION
SUCCESS
8
![Page 9: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/9.jpg)
Michael King, Director
Vogtle Project Office
Office of Nuclear Reactor Regulation
9
Photo Courtesy of Southern Nuclear Operating Company
![Page 10: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/10.jpg)
Leveraging technology and innovation to ensure safe oversight of Vogtle project
10
ITAAC CLOSURE
Photos Courtesy of Southern Nuclear Operating Company
![Page 11: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/11.jpg)
11
![Page 12: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/12.jpg)
0
10
20
30
40
50
60
0
50
100
150
200
250
2013 2014 2015 2016 2017 2018 2019
Nu
mb
er o
f LA
Rs
Day
s
Fiscal Year
Modern Risk-Informed Licensing for Faster Decision-Making
12
![Page 13: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/13.jpg)
13
0
10
20
30
40
50
60
70
JUN JULY AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT
2019 2020 2021
All Vogtle UINs Are Accepted
Enabling Efficient ICN Reviews
UNIT 3 ICNs UNIT 4 ICNs UINs
![Page 14: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/14.jpg)
14
Continuously Adapting Inspection to Incorporate Lessons Learned from First Part 52
Construction
![Page 15: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/15.jpg)
Initiatives to Modernize Advanced Reactor Licensing
John Segala
Chief, Advanced Reactor Policy Branch
![Page 16: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/16.jpg)
Executing the Vision
16
![Page 17: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/17.jpg)
Facilitating Innovation with an Integrated Safety Approach
Fuel
Performance
Functional
Containment
Siting
Emergency
Preparedness
Environmental Insurance
SSC
Classification
& Event
Selection
Holistically
Considering
Consequences &
Safety Margins
17
![Page 18: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/18.jpg)
Developing a Modern Risk-Informed Framework
SECY-19-0117NEI-18-04
DG-13536 LMP Pilots
LicensingModernizationProject (LMP)
18
![Page 19: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/19.jpg)
Risk-Informing the Content of Applications
Application
LMPBDBE
Safety-Related SSCs
Non-Safety-RelatedSSCs
Non-Safety-Related SSCs With Special Treatment
Safety ClassificationAdvanced Reactor Design
19
![Page 20: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/20.jpg)
Working Group on the Safety of Advanced Reactors (WGSAR)
Cooperating Internationally
Sharing Regulatory Experience
Advancing Risk-Informed and Performance-Based Licensing Approaches
Memorandum of Cooperationwith Canada
20
![Page 21: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/21.jpg)
Implementing NEIMA Provisions
Nuclear Energy Innovation and
Modernization Act (NEIMA)
• Issued Reports to Congress- Staged Licensing Process - Risk-Informed Guidance
• Developing Guidance within Existing Framework- Source Term- Event Selection- Containment Performance- Emergency Preparedness
• Developing a Technology-Inclusive, Risk-Informed and Performance-Based Regulatory Framework- 10 CFR Part 53
21
![Page 22: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/22.jpg)
Readiness to ReviewNon-LWR Applications
Ben Beasley, Chief
Advanced Reactor Licensing Branch
![Page 23: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/23.jpg)
Readiness: Staff Preparations
Guidance
for industry
Guidance for
NRC Staff
Training for
NRC Staff
23
![Page 24: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/24.jpg)
• Pre-application interaction:
– White paper, audit
– Topical report, Preliminary Safety
Information Document
• Integrated approach to reasonable assurance
of adequate protection
• Environmental reviews
Write SER
No SER
24
Readiness: New Approaches
![Page 25: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/25.jpg)
25
Readiness: Project Team
![Page 26: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/26.jpg)
Potential Applicants
26
High-Temperature Gas-
Cooled Reactors
(HTGR)
Liquid Metal Cooled Fast
Reactors
(LMFR)
Molten Salt Reactors
(MSR)
GE-H PRISM (VTR)
ARC
TerraPowerWestinghouse
Columbia Basin
Hydromine
Framatome
X-energy
StarCore
General Atomics
Kairos
Terrestrial
Thorcon
Flibe
TerraPower
Elysium
Liquid Salt Fueled
TRISO FuelSodium-Cooled
Lead-Cooled
Alpha Tech
Muons
Micro
Reactors
Oklo
Stationary
Transportable
Others
Others
Westinghouse
Liquid Salt Cooled
Developers that have submitted a RIS response
![Page 27: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/27.jpg)
Current and Anticipated Work
27
![Page 28: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/28.jpg)
Oklo Review Status
Oklo Aurora PowerhousePhoto Courtesy of Oklo, Inc
28
![Page 29: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/29.jpg)
• AOO – anticipated operational occurrence
• BDBE – beyond design basis event
• CFR – Code of Federal Regulations
• COL – combined license
• DBA – design basis accident
• DBE – design basis event
• DG – draft guide
• GE-H – GE Hitachi Nuclear Energy
• HTGR – high-temperature gas-cooled reactor
Acronyms
29
![Page 30: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/30.jpg)
• ICN – ITAAC closure notification
• ITAAC – inspections, tests, analyses, and acceptance
criteria
• LAR – license amendment request
• MSR – molten salt reactor
• NEICA – Nuclear Energy Innovation Capabilities Act
• NEIMA – Nuclear Energy Innovation and Modernization Act
• NRR – Office of Nuclear Reactor Regulation
• LMP – licensing modernization project
30
Acronyms
![Page 31: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/31.jpg)
• LMFR – liquid metal cooled fast reactor
• LWR – light-water reactor
• NEI – Nuclear Energy Institute
• NRC – U.S. Nuclear Regulatory Commission
• QA – quality assurance
• PISD – preliminary safety information document
• RIS – regulatory issue summary
• SER – safety evaluation report
• SMR – small modular reactor
31
Acronyms
![Page 32: Advanced Reactors and New Reactors Topics Briefing · 2020-02-04 · ARC Westinghouse TerraPower Columbia Basin Hydromine Framatome X-energy StarCore General Atomics Kairos Terrestrial](https://reader034.vdocuments.net/reader034/viewer/2022042205/5ea6a81e41b8b14f031d20df/html5/thumbnails/32.jpg)
• SSC – systems, structures and components
• TRISO – tristructural-isotropic
• UAMPS – Utah Associated Municipal Power Systems
• UIN – uncompleted ITAAC notification
• VPO – Vogtle Project Office
• VRG – Vogtle Readiness Group
• VTR – versatile test reactor
• WGSAR – Working Group on the Safety of Advanced
Reactors
32
Acronyms