african development bank african development fund … · cna capacity needs assessment cobra...

51
AFRICAN DEVELOPMENT BANK AFRICAN DEVELOPMENT FUND PROJECT: INCREASING CLIMATE CHANGE ADAPTIVE CAPACITY OF RWANDAN COMMUNITIES Increasing the adaptive capacity of vulnerable Rwandan communities to adapt to the adverse effects of climate change: Livelihood diversification and investment in rural infrastructures COUNTRY: RWANDA ONEC October 2016 Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 26-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

AFRICAN DEVELOPMENT BANK

AFRICAN DEVELOPMENT FUND

PROJECT: INCREASING CLIMATE CHANGE ADAPTIVE CAPACITY

OF RWANDAN COMMUNITIES

Increasing the adaptive capacity of vulnerable Rwandan communities to

adapt to the adverse effects of climate change: Livelihood diversification and

investment in rural infrastructures

COUNTRY: RWANDA

ONEC

October 2016

Pu

bli

c D

iscl

osu

re A

uth

ori

zed

P

ub

lic

Dis

clo

sure

Au

tho

rize

d

Table of contents

Acronyms and Abbreviations .................................................................................................... ii

Grant/Loan Information ........................................................................................................... iv

Project Summary ................................................................................................................... viii

1. INTRODUCTION ............................................................................................................. 1

2. INITIAL PROGRAM ....................................................................................................... 1

2.1 Description and Background Information ....................................................................... 1

2.2 Project Cost and Financing Arrangements ...................................................................... 2

2.3 Status of SEAP Implementation ...................................................................................... 3

3. PROJECT REAPPRAISED .............................................................................................. 3

3.1 Rationale for the Project ............................................................................................. 3

3.2 Justification of the LDCF Grant ...................................................................................... 4

3.2 Objectives and Description ......................................................................................... 4

3.3 Stakeholder Consultation ............................................................................................ 5

3.4 SEAP Revised Financing Arrangements and LDCF funded Project Costs Structure 6

4. Procurement Arrangement and Fiduciary Controls for LDCF Resources: ....................... 7

4.1 Procurement Arrangements ......................................................................................... 7

4.2 Financial Management, Disbursement and Audit Arrangements ................................... 7

5. PROJECT FEASIBILITY ................................................................................................. 8

5.1 Financial & Economic Performance ............................................................................... 8

5.2 Environmental and Social Impacts .................................................................................. 8

5.3 Project Sustainability....................................................................................................... 9

5.4 Key Risks and Mitigation Measures ............................................................................. 10

6. IMPLEMENTATION ..................................................................................................... 11

6.1 Implementation Arrangements ...................................................................................... 11

6.2 Other executing partners ............................................................................................... 12

6.3 Monitoring ..................................................................................................................... 13

6.4 Knowledge Building ..................................................................................................... 14

7. JUSTIFICATION IN RELATION TO BANK POLICIES FOR LDCF GRANT .......... 14

8. LEGAL INSTRUMENTS AND AUTHORITY ............................................................. 15

8.1 Legal Instruments .......................................................................................................... 15

8.2 Conditions associated with the Bank Intervention ........................................................ 15

8.3 Compliance with Bank Policies .................................................................................... 15

9. CONCLUSIONS AND RECOMMENDATIONS .......................................................... 16

Annex 1. Financial management and disbursement arrangements ............................................ I

Annex 2 – Procurement arrangements .................................................................................... III

Annex 3. Profile of Intervention Areas for Additional (LDCF) Financing............................. XI

Annex 4. Detailed Additional Program Activities and Costs ............................................... XIV

Project Document Annex 1: GEF PIF Approval ................................................................ XXIII

Project Document Annex 2: GEF CEO Approval............................................................. XXIV

Project Document Annex 3: Government Request to the Bank for Project Financing ....... XXV

i

Currency Equivalents

As of [22 September 2015]

1 USD = 745.456 RwF

1 UA = 1.41 US$

1 UA = 1,129.2167 RwF

Fiscal Year

1st July – 30th June

Weights and Measures

1 metric tonne = 2204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 metre (m) = 3.28 feet (ft)

1 millimetre (mm) = 0.03937 inch (“)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

ii

Acronyms and Abbreviations

ACNR Association pour la

Conservation de la Nature au

Rwanda

ACPC African Climate Policy Centre

AMAT Adaptation Monitoring and

Assessment Tool

ARAP Abbreviated Resettlement

Action Plan

AWP/B Annual Work Plans and

Budgets

BH Budget Holder

CC Climate Change

CEO Chief Executive Officer

CIP Crop Intensification Program

CNA Capacity Needs Assessment

CoBRA Community Based Resilience

Analysis

CPPR Country Portfolio Performance

Review

CSP Country Strategy Paper

CVCA Climate Vulnerability &

Capacity Assessment

DANIDA Danish International

Development Agency

DCC Department of Climate Change

DDP District Development Plan

DRC Democratic Republic of Congo

EARC East Africa Regional Resource

Centre

EARP Electricity Access Roll-out

Program

EDCL Energy Development

Corporation Ltd

EDPRS-II Economic Development and

Poverty Reduction Strategy II

2013-2018

EIRR Economic Internal Rate of

Return

ESIA Environmental and Social

Impact Assessment

ESMP Environmental and Social

Management Plan

FAO Food and Agricultural

Organization

FC Foreign Exchange Costs

FONERWA National Fund for Environment

and Climate Change

FSP Full Size Project

GEF Global Environmental

Facility

GIZ German Federal Enterprise

for International Cooperation

GMO Gender Monitoring Office

GoR Government of Rwanda

HH Household

ICCAC Increasing Climate Change

Adaptation of Rwandan

Communities

IDP Integrated Development

Program

IMS Information Management

System

IPRC Integrated Polytechnic

Regional Center

IWRMD Integrated Water Resources

Management Development

JPF Joint Partnership Fund

KAP Knowledge, Attitude and

Practices

LAFREC Landscape Approach to

Forest Restoration and

Conservation

LC Local Costs

LDC Least Developed Country

LDCF Least Developed Countries

Fund

LTO Lead Technical Officer

LTU Lead Technical Unity

LV Low Voltage

MIGEPROF Ministry of Gender and

Family Promotion

MINAGRI Ministry of Agriculture

MINICOFIN Ministry of Commerce and

Finance

MINICOM Ministry of Trade & Industry

MINILOC Ministry of Local

Government

MINIRENA Ministry of Environment and

Natural Resources

MININFRA Ministry of Infrastructure

M&E Monitoring and Evaluation

MoU Memorandum of

Understanding

MTE Mid-Term Evaluation

MTR Medium Term Results

MV Medium Voltage

iii

MVA Mega Volt Ampere

NAPA National Adaptation

Programs of Action

NCCP National Climate Change

Policy

NGO Non-Governmental

Organization

NISR National Institute of Statistics

of Rwanda

NPV Net Present Value

ONEC Department of Energy,

Environment, and Climate

Change (AfDB)

PAR Project Appraisal Report

PAREF Participatory forest

Management Project

PCR Program Completion Report

PERGP Integrated Project for

Ecosystem Rehabilitation and

Green Village Promotion

PIF Project Identification Form

PIR Project Implementation

Review

PLPA Participatory Learning,

Planning and Action

PM Project Manager

PMERL Participatory Monitoring

Evaluation Reflection and

Learning

PMU Project Monitoring Unit

PPG Project Preparation Grant

PPR Project Progress Report

ProDoc Project Document

PSC Project Steering Committee

PTF Project Task Force

RAB Rwanda Agricultural Board

RAP Resettlement Action Plan

RBCSP Results Based Country

Strategy Paper

REG Rwanda Energy Group

REMA Rwanda Environmental

Management Authority

RwF Rwandan Franc

SCCF Special Climate Change Fund

SEAP Scaling up Energy Access

Project

SHG Self Help Group

SME Small and Medium Enterprise

SPIU SEAP Project

Implementation Unit

ToR Terms of Reference

ToT Training of Trainers

TVET Technical and Vocational

Education and Training

UA Unit of Aid

UNDP United Nations Development

Program

UNEP United Nations Environment

Program

UNFCCC United Nations Framework

Convention on Climate

Change

USAID United States Agency for

International Development

US$ United States Dollar

VAT Value Added Tax

VfM Value for Money

iv

Grant/Loan Information Client’s information

RECIPIENT: Republic of Rwanda

EXECUTING AGENCY: The Energy development Corporation (EDCL)

Email: [email protected]

IMPLEMENTING UNIT: SCALING UP ENERGY ACCESS PROJECT

IMPLEMENTATION UNIT (SEAP-PIU)

REF DOCUMENTS SCALING-UP ENERGY ACCESS PAR

CEO ENDORSEMENT PROJECT DOCUMENT

Financing plan

Source Amount in USD (UA) Instrument

GEF/LDCF 8,824,749 (UA 6.259M) Grant

AfDB (15.494M) (Loan) approved already

AfDB (11.871M) (Grant) approved already

Government of Rwanda 3.932 (UA 2.595M) In Kind

TOTAL COST 51.58M (36.580M)

ADF’s key financing information

Loan/grant currency

USD

Interest type* N/A

Interest rate spread* N/A

Commitment fee* N/A

Other fees* N/A

Tenor N/A

Grace period N/A

EIRR, NPV (base case) N/A

*if applicable

Timeframe - Main Milestones (expected)

GEF PIF approval

February 2014

Project approval October 2016

Signing of Grant Agreement December 2016

Effectiveness December 2016

Mid-term Review October 2018

Last Disbursement June 2021

Completion December 2021

Last repayment N/A

v

Country and project name: RWANDA – Increasing the adaptive capacity of vulnerable Rwandan communities to adapt to the adverse

effects of climate change: Livelihood diversification and investment in rural infrastructures

Purpose of the project: To increase the adaptive capacity of vulnerable Rwandan communities to adverse effects of climate change through

livelihood diversification and investment in rural infrastructure

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/MITIGATION

MEASURES Indicator

(including CSI) Baseline Target

IMP

AC

T

Impact:

Improved

quality of life for

the Rwandan

People

- Per-capita income

- Human

Development

Indicator (HDI)

- % of population

living below

poverty line

US$ 700 in

2015

HDI = 0.433

in 2014

39.1% (2014)

US$ 900 by 2020 in

line with vision 2020

HDI = 0.5 in 2020

Less 30% by 2020 in

line with vision 2020

- IMF country

review report

- Human

Development

Reports and

National

economic

statistics

OU

TC

OM

ES

Outcome 1:

Diversified,

strengthened and

climate resilient

rural livelihood

opportunities for

vulnerable

women and men

in the project

area

% reduction in post-

harvest losses from

improved and

greened

infrastructure

35% 10% Project supervision

and M&E reports,

and Project

Completion report;

Government reports

at District levels

Risk 1: Climatic conditions

(destructive rains and

unpredictable seasons) hamper

project interventions (planting

etc.).

Mitigation Measures: The

project will build in flexibility

in terms of resource

disbursement to enable

communities to bring forward

project interventions if

necessary.

Risk 3: High costs and

insufficient supply of

electricity impedes livelihood

diversification.

Mitigation Measures: Project

will invest in a range of

livelihood opportunities with

varying power requirements

Risk 4: Inadequate political

and social support for

mainstreaming climate change

considerations into the

development processes,

Mitigation Measures: Project

to identify and secure the

services of a consultant to work

with communities and the

government in an participatory

monitoring

% increase in

knowledge of

livelihood

opportunities with

electricity access

% increase in

economic enterprises

for youth and women

from the new

enterprises

30% 80% of communities

aware of alternative

livelihood options

with electricity access

0 Over 30% of women

and 50% of youth in

the project

community have

increased income

from the new

enterprises

Outcome 2:

Community

driven

adaptation and

reduced

vulnerability to

climate change

% increase of HH

with knowledge on

vulnerability and

resilience to climate

change and gender

responsiveness

10% 80 % of HH in the

region will have this

knowledge by 2020

Project Supervision

and M&E reports;

National survey data

and District reports;

Completion Report

Number of

community groups

with capacity to plan,

implement and

monitor adaptation

programs

0 At least 15

community groups

with capacity

District level

development plans

and policies updated

with climate risk

management

provisions.

0 4 District level

programs,

development plans

and/or policies

updated with climate

risk management

provisions

vi

Outcome 3:

Increased

resilience of

small scale rural

infrastructure to

climate change

% of infrastructure

projects adopting

specifications that

takes into account

anticipated climate

risk for small rural

infrastructure

projects

0 100% and particularly

for community

markets, post-harvest

and agro processing

facilities.

Project Supervision

and M&E reports;

National data and

district reports

Designs reports

OU

TP

UT

S

Output 1.

Climate resilient

opportunities

developed for

rural Households

1. No of HH with

enhanced

understanding and

awareness of

livelihood

opportunities

resulting from

electrification

0 110,000 Project Supervision

and M&E reports;

National data and

District reports

2. No HH with

increased capacity to

participate in market

oriented enterprises

0 110,000

3. No of Value chain

development

activities

0 9

4. % of off-farm

economic

opportunities

increased

TBD Increase by 50% of

2015 figures with

30% women and 20%

youth involved

Output 2.

Community

driven

adaptation and

climate risk

reduction

processes

1. No of Training on

social dimensions of

vulnerability and

resilience to climate

change conducted.

0 8 (2 per year) with at

least split equally

between genders and

with 20% of

participants being the

youth

Project Supervision

& M&E reports

2. No of Awareness

campaigns on climate

change impacts and

promotion of gender-

responsive climate

adaptation

conducted.

0 8

3. No of Trainings for

district

administrations and

communities on

coordination and

support on climate-

resilient development

planning at the local

level conducted

0 4 (at least 30% of

participants being

women)

4. No of community

based planning,

implementation and

monitoring

adaptation programs

implemented

0 6

vii

Output 3.

Climate resilient

small scale rural

infrastructure

1. No of small

projects built with

specifications that

take into account

anticipated climate

risks

0 9 post-harvest

infrastructures built

and operational (3 per

district)

Project Supervision

and M&E reports;

Districts, Minutes of

market space

allocation and

training reports

2. No of markets

upgraded

0 6 – 2 per district with

30% of space

allocated to women

and 20% to youth.

3. No of trainings and

modules on climate

risks on the design

and construction of

small-scale rural

infrastructure

4 conducted for

District Engineers,

Administrators and

local contractors

Output 4:

Monitoring and

Evaluation

1. No of climate

change adaption

knowledge products

developed and

disseminated to the

community

0 6, including training

modules

Project Supervision

and M&E reports;

list of training

participants.

2. Conduct climate

change adaptation

practitioners event

0 2, with at least 30%

participants being

women and 20%

being youth

3. Project

Implementation

Reviews

0 Twice annually and

reports prepared

Components Inputs

AC

TIV

ITIE

S Component 1: Enhanced and diversified climate resilient rural livelihood:

Component 2: Strengthening awareness and ownership of adaptation & risk reduction process:

Component 3: Climate resilient small-scale rural infrastructure:

Component 4: Monitoring and Evaluation:

Component 5: Program Management Costs:

USD 3,000,000

USD 1,154,749

USD 4,000,000

USD 250,000

USD 420,000

viii

Project Summary Increasing Climate Change Adaptive Capacity of Rwandan Communities

Task Manager Humphrey N. Richard Grant Beneficiary Ministry of Infrastructure (MININFRA)

Division ONEC2 Grant Amount US$ 8,824,749

Project

Overview

The project for Increasing Climate Change Adaptive Capacity seeks to increase the adaptive

capacity of vulnerable Rwandan communities to the adverse effect of climate change through

livelihood diversification and investment in rural infrastructure. The project will maximize

the impact of an on-going AfDB funded project – Rwanda Scaling-up Energy Access Project

(SEAP), which provides infrastructure to distribute electricity for households and public

institutions and creates and expands opportunities for local populations to pursue non-

agricultural electricity-dependent income generating activities.

Project

Rationale

Climate variability and uncertainty inflicts significant negative impacts on the lives and

livelihoods of the Rwandan population. In the Northern and Western parts of the country,

climate data suggest that rainfall is likely to become more erratic with increasing intensity

and uncertainty, making rain-fed agriculture precarious and vulnerable. The livelihoods of

80% of mostly women and youth living in the rural parts of the country have largely

depended on agriculture as alternative livelihood opportunities are limited by the lack of

electricity, appropriate skills, and inadequate agro infrastructure facilities. The Baseline

Project, SEAP provides electricity services to the region, but last-mile productive activities

remains an issue as this was not factored in the project. The project financed with the GEF-

Least Developed Countries Fund (LDCF) is meant to address this gap. It will provides the

expertise and resources needed to maximize the impact of the SEAP by creating and

expanding opportunities for local populations to pursue value addition agricultural activities

and non-agricultural electricity dependent income-generating activities.

Project

Outcomes

The project will impact the lives of over 800,000 people and has the following key Outcomes

(i) Diversifying and strengthening climate resilient rural livelihood opportunities for

vulnerable communities in North and Western regions of Rwanda, (ii) Strengthening

awareness and ownership of adaptation and climate risk reduction processes, and (iii)

Increasing resilience of small scale rural infrastructure to climate change.

Development

Outcomes

The project is aligned with several national and local strategies related to climate change and

environmental management and builds on existing activities, such as Vision 2020, EDPRS II

(2013 - 2018), and Rwanda’s National Green Growth and Climate Resilience Strategy. The

project is also consistent with the Governments Energy Sector strategy Paper by promoting

productive use of electricity in rural areas.

Alignment with

GEF/LDCF

objectives

The GEF-LDCF priority focus is to finance projects that address the urgent and immediate

climate change adaptation needs of Least Developed Countries by seeking to reduce the

vulnerability of sectors and resources which are essential to social progress and national

development in the framework of National Climate Change Adaptation Program of Action

(NAPA). The goal of the project is aligned with this objective.

Cost Structure The GEF-LDCF grant of USD 8,824,749 will add resources to the ongoing SEAP funded by

the Bank and the Government in the amount of UA 29.961M which includes Government

contribution of over UA 2.596M (approximately US$ 4.0M at appraisal).

Implementation

arrangement

The Energy Development Corporation Ltd (EDCL) of the Rwanda Energy Group will be the

Executing Agency. The SEAP Project Implementation Unit established by EDCL will be the

Implementing Unit and will be strengthened with technical specialists assigned from the

Rwanda’s Fund for Environment and Climate Change (FONERWA).

Banks added

value

The Bank plays a lead role in Rwanda’s energy sector especially in regional power

integration and rural access to electricity. The Bank has also facilitated to country to access

several special funds particularly from Climate Investment Fund to support the country in

scaling up access to electricity services and promoting use of Renewable Energy. The

proposed project is consistent with the Bank’s 2013-2022 strategy of inclusive growth and

gradual transition to “green growth”. The project is also in sync with four of the Bank’s High

5 priority areas – light & Power Africa, Feed Africa, Industrialize Africa and Improving the

Quality of Life of the African people. The Project also supports the Bank’s new Strategy for

Jobs for Youths in Africa 2016 – 2025 that aims to creates millions of jobs for youth and

equip them to realize their full potential. It is also aligned with the Rwanda CSP 2012 – 2016

pillar 1 which aims at maximizing employment generation and gender responsiveness.

REPORT AND RECOMMENDATION OF MANAGEMENT CONCERNING A PROPOSAL FOR THE

INCREASING CLIMATE CHANGE ADAPTIVE CAPACITY OF RWANDAN

COMMUNITIES

Management hereby submits the following Report and Recommendation for

implementation of GEF/LDCF grant of US Dollars USD 8,824,749 (equivalent to UA

6.26 M) to the Government of Rwanda as additional funds to build community

resilience to climate change as part of the Scaling up Energy Access Project.

1. INTRODUCTION

1.1 The African Development Bank approved the Scaling Up Energy Access Project

(SEAP) for a US$ 45 million (loan+grant) on 26th June, 2013. The project, executed by

Energy Development Corporation Ltd (DECL) of the Rwanda Energy Group (REG), covers 6

districts in the Northern and Western provinces of Rwanda (Rusizi, Nyamasheke, Nyabihu

and Karongi districts in the Western Province and Rulindo and Gicumbi districts in the

Northern Province). The SEAP seeks to (i) improve access to electricity for households and

priority public institutions in the proposed project area and (ii) contribute to a sustained

reliable electricity supply.

1.2 The LDCF/SCCF Council approved the LDCF1 Work Program including the Project

Identification Form (PIF) for an LDCF grant of US $8,824,749 in May 2016. The additional

funding is to mainstream adaptation activities into the SEAP project.

2. INITIAL PROGRAM

2.1 Description and Background Information

2.1.1 Rwanda has one of the lowest per capita rates of electricity consumption in the world;

the country consumes about 42 kWh/year/capita, compared with the average of 478 kWh in

sub-Saharan Africa and 1,200 kWh for developing countries overall. The numbers make clear

Rwandans’ sizable need for additional electricity services. At the time of the SEAP appraisal,

the Electricity Master Plan of 2011, currently under review provided the basis of demand

projections under a scenario assuming that electricity access may reach 35% of the

population by 2017. The seven-year electricity development program used a more aggressive

growth rate for overall electricity consumption (based on a 2017 access target of 50%) to

arrive at an estimated peak demand of 350 MW for 2017. However, the government’s most

recent decision, to achieve 70% access by 2017/18, would imply total peak demand of up to

410 MW by 2017 and requiring a total of 563MW of installed and imported generation

capacity.

2.1.2 The Bank’s Country Strategy Paper (CSP) for Rwanda (2012–2016) seeks to support

two strategic pillars: (i) infrastructure development through interventions to address the

1 The Least Developed Countries Fund (LDCF) was established on directives to the Conference of the Parties to the United Nations

Framework Convention on Climate Change (UNFCCC) at its seventh session to address the needs of least developed countries (LDCs)

under the Convention on Climate Change. Absolute priority is accorded to adaptation and particularly the financing of the preparation and implementation of National Climate Change Adaptation Programs of Action (NAPAs). The Fund’s objective is to finance projects that

address the urgent and immediate climate change adaptation needs of LDCs by seeking to reduce the vulnerability of sectors and resources

which are essential to social progress and national development such as water, agriculture and food security, health, the management and prevention of catastrophic risks, and infrastructure, as have been identified and prioritized in NAPAs

2

country’s energy and transport bottlenecks, and (ii) enterprise and institutional capacity

development by supporting institutions that implement Rwanda’s policy on Small and

Medium Enterprises (SMEs). The GoR’s long-term development strategy (Vision 2020) and

medium term Economic Development and Poverty Reduction Strategy II (EDPRS II, 2013-

2018) focus on rapidly expanding access to electricity as the key means to achieving the

country’s vision of rescuing itself from poverty. This will alleviate infrastructure bottlenecks

in urban areas and improve limited access in rural areas. The SEAP project is also consistent

with the Bank’s energy sector policy approved in October 2012, where one of the core

principles is “ensuring energy security and increasing access for all.”

2.1.3 The SEAP’s development objective is to support “improvement of access to reliable

and cost effective electricity services for households and priority public institutions and

sustain the reliability of electricity supply in Rwanda and strengthen the institutional capacity

of key sector players in the project” in line with the Government’s long-term and short-term

development strategies and programs. The expected outcomes of the SEAP are (i) improved

access to electricity for households and priority public institutions in the proposed project

area and (ii) sustained reliable electricity supply.

2.1.4 The SEAP was a direct response to one of the three flagship programs called for in the

EDPRS—“economic transformation to create employment and generate exports”—and

responded to the key priority within this flagship theme of rapidly expanding access to

electricity. Moreover, the project contributes to the primary EDPRS target for the electricity

sector to reach an access ratio of 70% by 2017.

2.1.5 The SEAP project involves upgrading and rehabilitation of two substations in the

Northern Province, the Gifurwe substation to 10MVA capacity and the Rulindo substation to

20MVA capacity; building about 464 km of medium voltage (MV) and 710 km of low-

voltage (LV) distribution networks in both provinces; and connecting 25,438 households and

priority institutions (179 schools, 29 health centers and 25 sector administration offices) to

the grid in both the Northern and Western provinces.

2.2 Project Cost and Financing Arrangements

The total project cost, including physical contingency of 8% and price contingency of 5%

(excluding all taxes, duties, levies, and VAT in Rwanda), is estimated to be USD 45.384

million (UA 29.961 million), comprising foreign exchange costs of USD 35.128 (UA 23.189

million) and local costs of USD 10.256 million (UA 6.772 million). Table 2.1 presents the

foreign and local currency project cost by component.

3

Table 2.1: Project cost by component

Component USD million UA2 million

FC LC Total FC LC Total

A) Upgrading and rehabilitation of

substations 5.447 0.778 6.226 3.596 0.514 4.110

B) Access scale-up 22.181 5.117 27.358 14.643 3.418 18.060

C) Project administration and management

C1) Project supervision and

management 1.956 0.217 2.174 1.291 0.143 1.435

C2) Technical assistance 1.502 0.000 1.502 0.992 0.000 0.992

C3) Audit 0.000 0.027 0.027 0.000 0.018 0.018

C4) Operating expenses 0.000 0.974 0.974 0.000 0.643 0.643

D) ESMP /ARAP 0.000 1.903 1.903 0.000 1.256 1.256

Total base cost 31.087 9.076 40.163 20.552 5.992 26.513

Physical contingency (8%) 2.487 0.726 3.213 1.642 0.479 2.121

Price contingency (5%) 1.554 0.454 2.008 1.026 0.300 1.326

Total project cost 35.128 10.256 45.385 23.189 6.772 29.961

2.3 Status of SEAP Implementation

All the project components of the SEAP have commenced and all the project contracts have

been awarded and physical implementation begun. The project has disbursed 25% so far but

this is expected to increase rapidly as plant and equipment deliveries will start in September

2016. The SEAP project is Non-Potentially-Problematic with an IPR rating of above

Satisfactory.

3. PROJECT REAPPRAISED

3.1 Rationale for the Project

Climate variability and uncertainty inflicts significant negative impacts on the lives and

livelihoods of rural populations in Africa. In the Northern and Western parts of Rwanda,

climate data suggest that rainfall is likely to become more erratic with increasing intensity

and uncertainty, placing rain-fed agriculture in a precarious and vulnerable position. The

livelihoods of 80% of people living in Northern and Western provinces of Rwanda has

largely depended on agriculture as opportunities for alternative livelihoods are limited by the

lack of electricity, appropriate skills, inadequate infrastructure and other services such as

marketing facilities. The Baseline Project, SEAP provides electricity services to the region,

but last-mile productive activities remains an issue as this was not factored in the project. The

project financed with a grant from LDCF is meant to address this gap. It will provides the

expertise and resources needed to maximize the impact of the SEAP in the relevant

communities by creating and expanding opportunities for local populations to pursue value

addition agricultural activities and non-agricultural electricity dependent income-generating

activities. Considering most of the population in the rural areas comprise women and youth,

the project will ensure their involvement in all project activities and that they are allocated

adequate share in the resulting project benefits. The additional funding for “Increasing the

adaptive capacity of vulnerable Rwandan communities to adapt to the adverse effects of

2 The exchange rate used at project appraisal of 1.0 UA to 1.5148 US$ is used. Elsewhere in the current

exchange rate of 1.41 US$ to the UA is used.

4

climate change (ICCAC): Livelihood diversification and investment in rural

infrastructures” has been approved by the Global Environment Facility (GEF) in May

2016, to be implemented alongside the Scaling-Up Energy Access Project funded by the

Bank.

Recent initiatives by the Government of Rwanda to implement Climate Change Adaptation

and Mitigation program indicates their readiness to mainstream climate change resilience in

development activities. It has partnered with the Bank and other Development Partners

preparation of the Green Growth Costing tool-kit, the Sustainable Energy for All Action

Agenda, Green Mini-Grids, Scaling-up Renewable Energy and Forest Investment Programs.

3.2 Justification of the LDCF Grant

The additional funding will benefit people in the districts of Karongi, Nyamasheke and

Rusizi. The outcomes will contribute to the overall purpose of poverty reduction through

livelihood diversification, and will improve livelihoods for an additional 800,000

beneficiaries in these program areas. LDCF financing will maximize the improved access to

electricity made possible by the SEAP investment by reducing the vulnerability of current

economic development and livelihoods in the three districts, and complement climate change

adaptation and mitigation activities in the country such as the Integrated Green Villages in

Karongi.

3.3 Objectives and Description

The overall development objective of SEAP as elaborated in 2.1.3 has not changed but the

LDCF funded component will enrich it by increasing the adaptive capacity and resilience of

the Rwandan communities in the project area to climate change impacts. It will provide an

opportunity to integrate, the last-mile electricity provision with alternative livelihood

creation. The project will therefore facilitate communities to formulate, and pilot the

implementation of community based adaptation plans, informed by detailed vulnerability

assessments and technical knowledge of the risks and opportunities presented by the existing

enterprises and their services. This approach will lead to expansion of livelihood support

systems with climate smart measures. The project will be implemented as part of the on-

going SEAP project, utilizing as much as possible the SEAP PIU as already setup. The

National Fund for Environment and Climate Change (FONERWA) will support the PIU by

assigning some technical specialists to the project.

3.3.1 The expected outcomes from the additional funding include:

Diversifying and strengthening climate resilient rural livelihood opportunities for

vulnerable women and men;

Strengthening awareness and ownership of adaptation and climate risk reduction

processes;

Increasing resilience of small scale rural infrastructure to climate change.

3.3.2. The ICCAC Outputs will support the achievement of the resilience to climate change

by facilitating diversification of livelihoods away from traditional agricultural activities so as

to most efficiently utilize the new infrastructure created by an electricity access project, and

consequently increase local communities’ resilience and to adapt to the negative impacts of

climate change. The main outputs therefore include:

5

Output 1: Enhanced and diversified climate resilient rural livelihood opportunities: This

component will support the transition of target households from unsustainable, low-income

agriculture based into economically viable and market oriented livelihoods in rural areas that

benefit from the SEAP project. This will reduce the vulnerability of livelihoods and physical

assets to the adverse effects of climate change. In particular it will create Climate Change

Adaptation awareness finance development of decentralized village-based agriculture

processing centers.

Output 2: Strengthening awareness and ownership of adaptation and climate risk reduction

processes: Enhancing capacities for planning, coordinating and implementing climate change

adaptation activities at the community level.

Output 3: Climate resilient small-scale rural infrastructure: This component will focus on

investment in upgrading rural infrastructure, such as post-harvest storage facilities and market

centers that are connected to the electricity-grid through the SEAP.

Output 4: Monitoring and Evaluation: This component ensures that lessons learnt and

knowledge tools developed during project implementation are captured and appropriately

disseminated. Specialist from FONERWA will provide the PIU with the necessary support to

deliver this output.

The detailed analysis of the project outcomes, outputs, activities and performance indicators

is given in Annex 4 of this PAR.

3.4 Stakeholder Consultation

The preparation of this project was guided by a comprehensive and extensive participatory

process, where stakeholders included District-level leaders, officials from a number of

Ministries, special Government projects, cooperatives, community elders and local

communities. Consultations with the above mentioned stakeholders took place at both

national and local levels within the effected districts. Consultation methods included

interviews, focus group discussions, stakeholder workshop (held in Nyamasheke for all

effected districts) and a stakeholder validation workshop (held in Kigali for all effected

districts). Issues raised by stakeholders included the catastrophic impacts of climate change

(flooding being the most prevalent in the country and effected districts) and the need to adapt

or build resilience to climate change impacts. There was also a keen interest to explore

alternative livelihood opportunities, for which three proposals were put forward for each of

the three effected districts.

The executing agency supported by specialists from FONERWA has led the process, where

its experience in the effected districts was important in providing information on stakeholders

and their characteristics. They also contributed through making arrangements (information to

stakeholders and overall coordination) for interviews, the workshop in Nyamasheke and

validation meeting in Kigali. The participatory approach also followed a complementary

approach, building upon existing plans and program, including national action plans and

national sectoral policies. These interventions were also refined through discussions with

other development partners in the country including UNDP, FAO, GIZ, USAID, DANIDA

and a number of non-governmental organizations (NGOs).

6

3.5 SEAP Revised Financing Arrangements and LDCF funded Project Costs Structure

3.5.1 The total project cost is estimated to be USD 8,824,749 (UA 6.259 million),

comprising foreign exchange costs of USD 395,000(UA 280,000) and local costs of USD

8.430 million (UA 5.979 million) (government counterpart). Table 3.1 presents the foreign

and local currency project cost by component.

3.5.2 The project will be financed by the Bank and the GoR. The Bank’s financing will be

used to cover 100% of the total foreign cost and 68.2% of local costs of the project excluding

all taxes, duties, levies, and VAT in Rwanda.

Table 3.1: Sources of financing for foreign and local costs3

Component

UA million

% of total Foreign

costs Local costs Total

ADF 23.189 4.176 27.365 74.81%

Government of Rwanda 0.000 2.956 2.956 8.08%

Global Environment Facility (GEF) 3.222 3.037 6.259 17.11%

Total project costs 26.411 10.169 36.580 100%

The breakdown of the LDCF resources by sub-component and expenditure schedule are as

outlined below.

Table 3.2: Breakdown of LDCF Grant by sub-component and expenditure schedule

Sub-component USD UA

2016/17 2017/18 2018/19 2019/20 Total Total

(A) Enhanced and diversified

climate resilient rural livelihoods 255,000 445,000 1,880,000 420,000 3,000,000 2,127,660

(B) Strengthening awareness and

ownership of adaptation and

climate risk reduction processes 245,000 365,000 309,749 235,000 1,154,749 818,971

(C) Climate resilient small-scale

rural infrastructure 300,000 310,000 1,885,000 1,505,000 4,000,000 2,836,879

(D) Monitoring and Evaluation 50,000 35,000 75,000 90,000 250,000 177,305

Program management Cost 124,750 101,750 96,750 96,750 420,000 297,872

Total program costs 8,824,749 6,258,687

Table 3.3: Breakdown of LDCF Grant by categories

Project Category USD ‘000 UA ‘000

Goods 420 298

Works 5,905.00 4,188

Services 2,499.75 1,773

3 At the exchange rate of I.0 UA to 1.41 US$

7

4 Procurement Arrangement and Fiduciary Controls for LDCF Resources

4.1 Procurement Arrangements

4.1.1 All procurement of works, and acquisition of consulting services financed by Bank

resources will be in accordance with the Bank’s Procurement Policy dated October, 2015 as

amended from time to time, using the relevant Bank Solicitation Document , and the

provisions stipulated in the Financing Agreement. The implementing agency will be

responsible for all envisaged procurements in the project.

4.1.2. The SEAP PIU shall be the executing agency for carrying out the Procurement for the

Project. In this regard the existing SEAP Project Implementation Unit (PIU) will be used as

the implementation arrangement for this program. The EDCL has been assessed for its

capacity to carry out the project and their capacity has been found to be adequate. The

detailed procurement arrangements are presented in the Annex 2 and in the procurement plan.

4.2 Financial Management, Disbursement and Audit Arrangements

4.2.1 The Bank has carried out an assessment of the financial management system of the

Rwanda’s Energy Development Corporation Ltd (EDCL), as the executing agency, based on

Bank’s FM Implementation Guidelines-2014. The assessment concluded that the Financial

Management (FM) capacities are “Adequate” and the overall risk is “Moderate”.

4.2.2 The overall responsibility for financial management (including Budgeting, Accounting

system, Internal Control, Treasury Management/Funds Flow, Financial Reporting and External Audit

arrangements) will rest with the EDCL’s Electricity Access Rollout Programme (EARP)

implementation unit that is handling the first phase of the Scaling-up Energy Access Project (SEAP). To facilitate the implementation of the FM function of the Project, the current Chief Accountant for

the SEAP who has adequate knowledge and experience with Bank FM policies and procedures will be

designated as the Project Accountant and will report to the EARP Director of Finance.

4.2.3 The existing EARP financial manual detailing its accounting policies and procedures will be

used by the project. Consolidated Project Financial Statements will be prepared by the project chief

accountant under the supervision of the EARP Director of Finance. The project will prepare Interim

Financial Reports (IFR) as part of the quarterly progress report (QPR), as required by the Bank, not

later than 45 days after the end of each quarter. In line with the use of country system, the Rwanda

Energy Group (REG)’s Internal Audit Department will include the Project in its audit program and

audit regularly using a risk based audit methodology. The Project internal audit report will be shared

with the Bank during supervision missions or on a need basis.

4.2.4 The Project audit will be conducted by the Auditor General (AG) of State Finances of

Rwanda or a Private Audit firm appointed by AG and agreed with the Bank based on the Bank’s audit

terms of reference. The audit report, complete with a Management Letter, will be submitted to the

Bank not later than six months after the end of the financial year. The cost of the audit will be borne

by the project if undertaken by the Private Audit Firm.

4.2.5 The Project will mainly use the Direct Payment method and the Special Account method for

financing all eligible project expenditures. However, the other two disbursement methods may be

used where the need arises, but after consultation with Bank and obtaining prior approval. The details

of the disbursement methods are provided in the Bank Disbursement Handbook. The EDCL will open

a Special Account (SA) for the purpose of this project at the National Bank of Rwanda (BNR).

The detailed financial management assessment is provided in Annex 1.

8

5 PROJECT FEASIBILITY

5.1 Financial & Economic Performance

At its appraisal, the Baseline project was found financially sustainable and economically

viable. Its financial internal rate of return (FIRR) was estimated at 21.5% (real) while the

financial net present value (FNPV) discounted at a real rate of 10% was USD 40.15 million

based on a flat electricity tariff of RWF 134.40 per KWh charged to residential consumers

since August 2012. Today’s residential tariff is at Rwf 182/kWh. The additional grant will

improve the financial and economic performance of the SEAP project as the community

translate opportunities of electricity access into gainful economic activities in the process

increasing electricity uptake in the region. The improved economic status the rural

community also means more resources will be available for higher household electricity

consumption – improved quality of life.

5.2 Environmental and Social Impacts

5.2.1. At the micro level, the project is expected to benefit the whole Districts’ population

which is estimated at 800,000 people, working directly through cooperatives. The proposed

projects in each district are expected to provide incomes to individual members.

5.2.2 Based on the project description in the request for categorization memorandum

(RCM), the project was validated as a category 2 on July 4th 2016 and will require an ESMP

to address the issues associated with Agro processing and value addition enterprises.

5.2.3. Gender: It is estimated that women represent about 60% of the beneficiaries since

women lead most smallholder farming activities. Youth will also benefits directly from this

project as they have proposed a number of projects. In addition, the project will actively

empower women and other excluded groups, particularly those at high risk of suffering from

the effects of climate change vulnerabilities. This will be achieved through social

mobilization utilizing Women Self Help Groups (SHGs) and other such community based

structures. These groups will benefit particularly from skill development (education/training),

access to financial resources and markets for sustainably produced/harvested products. To

ensure that alternative adaptation options meet equality and equity criteria, with special

attention given to women and youth, a gender impacts assessment methodology was used to

complement the climate vulnerability and capacity assessment. This assessment reviewed the

impact of alternative adaptation options on women and men as well as on gender relations in

the project area. To address specific gender inequalities that impede women’s participation in

enterprise development and the jobs market, the project will identify gaps in gender equality

by consulting with men and women and developing skills and strategies to address these

gaps. The project will specifically target vulnerable youths (aged 15 to 21 years) from

unstable family backgrounds for vocational training and other support needed to enable them

to get productive employment and reduce youth disaffection and delinquency. The project is

designed to use staff and national institutions for capacity building activities. This will

permit scalable investments from the project budgets.

5.2.4. Involuntary resettlement: No involuntary resettlement is envisioned as a result of the

project.

9

5.3 Project Sustainability

5.3.1 The sustainability of the project will be in its ability to continue functioning at the end

of the project and learn from the lessons learnt and practices employed; the project can then

be replicated across other districts, and eventually the whole country.

The project proposed is integral for the environmental, social, institutional and financial

sustainability of not just the three Districts but for the whole of Rwanda. Without this LDCF

intervention, climate vulnerability will erode local economic development and resilient

livelihoods. The project activities in the field will be executed by the beneficiaries themselves

and knowledge products developed will be disseminated through training and workshops.

The high level of involvement of Government representatives at the local level and the

participation of a large number of women and youth will ensure project sustainability.

5.3.2 Social Sustainability: The project will address the problems of poverty, environmental

degradation and climate-led disasters in the project area and will serve as a model for scaling up in

neighboring districts facing similar problems. The project will ensure that diversification of

agriculture provides resilience of local economies and livelihoods and form the basis of community

based adaptation plans. Assisting the district environment teams to mainstream climate risk

considerations in the district development plans will further contribute to the target of mainstreaming

sustainable development principles in national development policies. The project will develop and

demonstrate practical enterprises, tools, technologies and capacities for non-agricultural income

generating activities, through community centred adaptation program, focusing heavily on promotion

of utilisation of electricity. These interventions will collectively lead towards environmental

sustainability and reduce vulnerability of livelihoods to climate risks and increase household welfare

(including incomes) of local communities. The purpose of the program is to promote climate resilient

development. In this regard, one component focuses on development of manpower in agriculture,

land, water, forestry and infrastructure engineers in climate resilient technologies. The program will

sensitize the planners and policy makers to incorporate climate resilience in development. An

aggressive advocacy campaign in this regard will be launched through print and electronic media to

influence the policy and development process. Thus the motivated and technically strong manpower

in teaching and extension institutions will sustain and disseminate the climate resilient programs at a

larger scale. This will ensure sustainability and up-scaling of the present and future interventions.

Policing to implement policies is not a solution; therefore, the community members will be sensitized

and trained in participatory approaches to discourage negative environmental approaches and promote

eco-friendly approaches. This will also ensure sustainability of the program interventions. In

addition the project will rely on existing national institutions such as FONERWA/ REMA/

MINALOC/ MINAGRI/ MININFRA/ CAPACITY BUILDING SECRETARIAT/ GENDER

MONITORING UNIT, etc. as a sustainable mechanism.

5.3.3 Financial Sustainability The financial sustainability of this project rests in part on

the improvement of economic capabilities for the local communities. All the infrastructure

investment financed by the project are of very basic technology and build with local

materials, and all inputs are locally produced and the outputs will be to a large extent locally

consumed or exported to the rest of the country. This increases the level of profitability of

the interventions. The program design also has several built-in options for scaling up

program interventions to ensure financial sustainability. The project will introduce measures

to expand economic opportunities for women and youth and promote their participation in the

labour force as this will reduce poverty, foster faster growth and increase resilience.

10

5.4 Key Risks and Mitigation Measures

An identification and ranking of risks by impact has been conducted as well as identification of

mitigation measures. Overall, the risks are not exceptionally high and should be manageable (Table

5.1).

Table 5.1: Ranking of Program Risks by Impact Description Ranking Mitigation measures

1 Low awareness and acceptance of the

need to tackle climate change among key

practitioners limits the support for action

on climate change within key sectors.

LOW Engage with co-operatives during implementation of

the program as they have been found to play an

important role in creating awareness and advocating

for changes in behavior and practices locally

Undertake detailed stakeholder analysis during the

initial stages of implementation, and develop an

effective advocacy strategy to win over influential

stakeholders.

2 District administrations lack the

resources and capacity to engage fully

with the project and integrate project

outputs with development plans.

LOW Inclusion of project deliverables in the District

Performance Contract where possible will also help

to ensure project activities become integrated and

sustainable with ongoing development at the local

level.

Project implementation will be supported with a

competent team of professionals that are dedicated

full time to the project.

3 Climatic conditions (destructive rains and

unpredictable seasons) hamper project

interventions (planting etc.).

MEDIUM Build in flexibility in terms of resource disbursement to

enable communities to bring forward project

interventions if necessary.

4 Limited capacity of partner organizations

to deliver project outputs.

LOW Carry out capacity assessments of community

institutions (co-operatives etc.) during the design phase

before finalizing the implementation arrangements and

incorporate capacity building where necessary.

5 Failure to create ownership of the project

at the local level to project interventions.

LOW Involve the key stakeholders in problem identification,

project design, implementation and phase out activities

to create ownership at the community level and build in

sustainability

6 People may fail to use the technologies

correctly, despite the knowledge and

advantages to be accrued from adopting.

LOW Continuous awareness targeting communities to

embrace the correct use of post-harvest management

technologies.

Linkages to the private sector; careful use of the

grants/credits to finance purchasing of energy efficient

technologies.

7 Unwillingness of engineers to embrace

new guidelines and designs.

LOW Timely implementation of project activities, Training

and generation of lessons

8 Inadequate political and social support

demonstrated by politicians, technical

staff and communities for mainstreaming

climate change considerations into the

development process

LOW Project to identify and secure the services of a

consultant with technical expertise, to work with

communities and the government in a participatory

monitoring role

9 High costs and insufficient supply of

electricity impedes livelihood

diversification

MEDIUM Project will invest in a range of livelihood

opportunities with varying power requirements.

10 Lack of coordination with other climate

change projects in Rwanda limits the

capacity of implementing agency to learn

from and build on the experience of

related projects.

LOW Review lessons from other projects during the design

phase.

Allocate resources for effective co-ordination

Project team will be multi-disciplinary

11

6 IMPLEMENTATION

6.1 Implementation Arrangements

6.1.1 Rwanda’s Energy Development Corporation limited (EDCL) will be the Executing Agency of

the LDCF funded project. The Project Implementation Unit (PIU) setup within EDCL for the Scaling-

up Energy Access Project will host the implementing team for the additional component. The PIU

Project Manager will be the accounting officer and responsible for the administration of the additional

fund. The PIU Project will report to the Project Steering Committee (PSC). FONERWA in

consultation with AfDB, shall second a senior staff member as a project focal point responsible for

ensuring the smooth execution of the project. FONERWA will Co-chair the multi-stakeholder Project

Steering Committee (PSC), which will bring together all key institutions including the Rwanda

Environment Management Agency (REMA), 3 NGOs Districts, and local community representatives.

The Chair of the PSC will be the Permanent Secretary in the Ministry of Infrastructure.

6.1.2 The Project Steering Committee will guide and oversee implementation of the project.

Specifically the PSC will:

Provide guidance to ensure that project implementation is in accordance with the

project document;

Review and approve any proposed revisions to the program - program results

framework and implementation arrangements;

Review, amend (if appropriate) and endorse all Annual Work Plans and Budgets;

Review program progress and achievement of planned results as presented in six-

monthly Program Progress Reports, annual Program Implementation Reviews (PIRs)

and Financial Reports; Advise on issues and problems arising from program implementation, submitted for

consideration by the Program Management Unit or by various stakeholders; and Facilitate cooperation between all program partners and facilitate collaboration

between the Program and other relevant programs, projects and initiatives in Rwanda.

6.1.3 The SEAP Project Manager (PM) will be the accounting officer of the additional fund and

will work closely with the PSC and FONERWA. The PM will also take the lead in communications

with government agencies and advocacy. The PM will also be responsible for providing technical

advice and guidance in his/her area of technical expertise. The PM will report on program progress to

PSC meetings, and will develop and submit semi-annual PPRs and annual PIRs with the support of

staff seconded to the PIU from FONERWA. As the accounting officer of the additional funds, the

Project Manager will be responsible for the financial execution, procurement and the overall

management of the of the project activities. This implies that the existing SEAP PIU will be

responsible for the procurement in consultation with FONERWA and in accordance with the work

plan and budget approved by the PSC and cleared by the Bank. The Project Manager may consider

recruiting additional staff to the PIU to ensure adequate fiduciary controls and accounting In addition

to technical and substantive duties, the PM will:

Act as secretariat to the PSC;

Organize project meetings and workshops, as required;

Prepare Annual Work Plans and detailed Budgets (AWP/B) and submit for PSC’s approval;

Coordinate and monitor the implementation of the approved AWP/B;

During program inception period, review the project’s M&E plan and propose refinements, as

necessary, and implement the plan;

Prepare the six-monthly Project Progress Reports (PPRs) and give inputs in the preparation of

12

the annual Project Implementation Review (PIR); Ensure that all co- financing partners

provide information on co-financing disbursed during the course of the year for inclusion in

the PIR;

Coordinate the program with other related on-going activities and ensure a high degree of

inter- institutional collaboration; and

Assist in the organization of mid-term and final evaluations.

6.1.4 The duties of the project Focal Point Person seconded to the PIU from FONERWA will

include (i) acting as the responsible focal point at the policy level within FONERWA; (ii) ensuring all

necessary support from FONERWA is provided for implementation of all of the proposed

components’ activities; (iii) reviewing and providing input to annual work plans and budgets in

consultation/collaboration with PIU before it is cleared by the Bank; and (iv) participating in the

selection of consultants. The focal point person will work closely with the District coordinator who

will be in-charge of the day to day activities of the climate change adaptation project in the field.

Other technical staff to be seconded whenever necessary will include; a knowledge Management

specialist and a Monitoring and Evaluation Specialist. In addition the Focal Point Person will:

Ensure real-time monitoring of project’s progress on the ground and alert PIU Project

Manager of potential problems that could result in delays in implementation;

Ensure the Project’s effective and efficient work with stakeholders in the pilot areas, and

aligning proposed activities with similar initiatives of the Government in the region;

Organize and supervise consultant inputs;

Oversee creation of the Project’s approach to managing and sharing knowledge, and to

identifying and disseminating lessons learned;

6.1.5 The District Coordinator will report to the Project manager through the project’s Focal

Point Person and will be in-charge of the day-to-day activities of the project. Further, he and will

coordinate all activities at the District level in close collaboration with FONERWA. Based at the

District level, the District Coordinator will ensure effective and efficient implementation of

activities by communities and other stakeholders.

6.2 Other executing partners

6.2.1 The program will work with a number of partners who will contribute to the execution

of specific components/outputs through Letters of Agreement. Letters of Agreement with

partners will be based on specific activities in each annual work plan and budget approved by

the Program Steering Committee.

13

Figure 6.1: Organization Chart for project implementation

6.2.2 AfDB’s Role: As the GEF implementing agency, AfDB will maintain project oversight

to ensure that GEF policies and criteria are adhered to and that the project meets its objectives

and achieves expected outcomes in an efficient and effective manner. AfDB will report on

project progress to the GEF Secretariat; financial reporting will be to the GEF Trustee. AfDB

will closely monitor and provide overall guidance to the project. In addition the AfDB will:

manage and disburse funds from GEF in accordance with the rules and procedures of

the Bank;

oversee project implementation in accordance with the project document, the work

plans and budgets, and the rules and procedures of the Bank;

carry out at least two supervision missions per year; and

report to the GEF Secretariat and Evaluation Office, through the annual Project

Implementation

review, on project progress and provide financial reports to the GEF Trustee.

6.2.3 The AfDB (GEF Coordination Unit) will submit annual project implementation report

(PIR) to GEF Secretariat and, in collaboration with the project Task Manager submit a request

for funds transfer for the project activities from the GEF Trustee based on 6 monthly

projections.

6.3 Monitoring

6.3.1. Quarterly and annual reporting arrangements will follow the current JPF framework.

The Coordinator with support of the JPF team will be responsible for the preparation of

quarterly and annual reporting. The Program Completion Reports (PCR) and additional

monitoring and evaluation activities on climate change resilience will be carried out by the

Department of Climate Change (DCC) to produce knowledge products of lessons learnt on

implementation of the NAPA for dissemination. Documentation of local knowledge on

Project Steering Committee REMA, MININFRA (Chair), MINILOC, MINICOFIN, Local Authorities, NGO, Private Sector and others, EDCL, FONERWA (Co-Chair)

SEAP PIU Project Implementation Unit (PIU)

Project Manager

FONERWA – Focal Point Person District Coordinator Other specialists seconded to the PIU Vendors for small infrastructure projects and consultancies and TAs

SEAP – Main Project Team

Contractor & Consultants for the Energy Access Project

14

adaption will enrich the Bank’s knowledge in this area DCC will also compile specific

quarterly and annual reports for the LDCF resources as well as monitor the implantation of

the ESMP. The LDCF Adaptation Monitoring and Assessment Tool will also be completed

during the mid-term review cycle and during the PCR preparation.

6.3.2. The overall monitoring setup includes Joint Sector Reviews held twice a year,

Technical reviews held in March/April and Joint Sector Reviews in Sept/October. In

additional the sector conducts regular technical reviews, surveys, Value for Money (VfM)

and tracking studies.

It is of utmost importance for the project to make use of internationally recognized results-

based monitoring and evaluation frameworks during its entire implementation. FONERWA

will be responsible for the monitoring and supervision activities in the field. This will be in

collaboration with the PIU Management. The project will document all problems encountered

and lessons learnt during implementation as a way of knowledge management. This will

ensure that successes are replicated while hindrances would be avoided early for similar

future projects or even other current projects. The component will look at knowledge

management and dissemination, monitoring (both internal and external). A detailed

elaboration of monitoring and evaluation plan including costing is outlined in Annex 4.

6.4 Knowledge Building

The associated knowledge dissemination framework will include communities as generators

of knowledge and promote peer-to-peer and lateral knowledge sharing across all stakeholders

in the climate change domain in Rwanda with specific focus on the project areas. To promote

both dissemination and interaction on a wider scale, mass and social media will be used to

facilitate broad knowledge sharing across significant portions of the communities that are and

will likely continue to be affected by climate change in the project areas. To achieve this,

various knowledge dissemination products will be developed such as; (i) Web and paper

based information booklets/brochures (ii) Posters (ii) Radio/television broadcasts (iv) Videos,

animations, still images and Policy briefs, etc. Information contained in the above knowledge

dissemination products will be generated from climate change relevant information available

from national, regional and global sources, including the differential impacts of climate

change across genders, classes, ages, abilities and ethnic groups. A detailed elaboration of

knowledge activities and costing are included in Annex 4.

7 JUSTIFICATION IN RELATION TO BANK POLICIES FOR LDCF GRANT

7.1. Agriculture is one of the primary sources of livelihoods for the majority of the

Rwandan population. In the face of increasing climate variability, it has become critical to

Rwanda’s development to develop alternative off-farm, income generating alternative

livelihoods to build resilience to increasingly unpredictable weather patterns. Climate change

is already increasing the frequency and intensity of extreme weather events, particularly

droughts, floods. Recent weather events clearly illustrate the magnitude of the problem,

which has been communicated in Rwanda’s National Adaptation Program of Action (NAPA)

and identified priority intervention areas, which include increasing resilience in agriculture

dependent populations. It is expected that funding of the NAPA identified priority

intervention areas will stimulate interest among key stakeholders and also lead to changes in

15

planning approaches resulting into integration of climate change issues into development

planning.

7.2 With the financing from LDCF, the impact of the SEAP project will be enhanced and

maximized, particularly with respect to resilience, sustainability of energy facilities and

infrastructure, as well as natural resource management in the face of climatic shocks. These

additional resources will contribute to improving the population’s living conditions and

diversifying livelihoods toward off farm activities, away from traditional agricultural

activities so as to most efficiently utilise the new infrastructure created by an electricity

rollout program, and consequently increase resilience to the negative impacts of climate

change.

7.3 Activities under the additional funding are directly aligned to the core objectives of

the Bank’s Strategy for 2013 – 2022 in particular the transition toward “green growth that

will protect livelihoods, improve water, energy and food security, promote the sustainable use

of natural resources and spur innovation, job creation and economic development. Project

activities will involve off-farm activities which will create economic opportunities for

farmers to shift livelihoods away from traditional agricultural activities. As highlighted

earlier, the LDCF funded component supports directly the Bank’s High 5’s.

8 LEGAL INSTRUMENTS AND AUTHORITY

8.1 Legal Instruments

8.1.1. The legal instrument is the grant agreement between the AFDB and the Government

of Rwanda for the LDCF additional funding to cover the incremental cost of climate

adaptation activities identified as additional to the SEAP investment.

8.2 Conditions associated with the Bank Intervention

8.2.1. Conditions Precedent to Entry into Force of the LDCF Grant: The LDCF Grant

Protocol Agreement shall enter into force on the date of its signature.

8.2.2. Conditions Precedent to First Disbursement of LDCF Grant: In addition to the entry

into force of the Grant, the first disbursement of LDCF Grant resources shall be subject to

fulfilment of the following conditions:

(i) Appointment of a focal point person from FONERWA in the SPIU

(ii) Opening of special accounts for LDCF

8.3 Compliance with Bank Policies

8.3.1 The proposed activities under LDCF resource complies with all applicable Bank

policies as well as the policies of the GEF’s LDCF.

16

9 CONCLUSIONS AND RECOMMENDATIONS

9.1. Management recommends that the Boards of Directors approve the implementation of

additional activities financed through the GEF/LDCF Grant for an amount not exceeding

USD 8,824,749 for the purpose and under the conditions set forth in this report.

I

Annex 1. Financial management and disbursement arrangements

The Bank has carried out an assessment of the financial management system of the Rwanda’s Energy

Development Corporation Ltd (EDCL), as the executing agency, based on Bank’s FM Implementation

Guidelines-2014. The assessment concluded that the Financial Management (FM) capacities are

“Adequate” and the overall risk is “Moderate”.

The overall responsibility for financial management (including Budgeting, Accounting system, Internal

Control, Treasury Management/Funds Flow, Financial Reporting and External Audit arrangements) will

rest with the EDCL’s Electricity Access Rollout Programme (EARP) implementation unit that is handling

the first phase of the Scaling-up Energy Access Project (SEAP) . The Project Manager, who is the head of

the SEAP Project Implementation Unit (PIU), will be assigned to manage the grant under the supervision

of the Programme Coordinator of EARP. To facilitate the implementation of the FM function of the

Project, the current Chief Accountant for the SEAP who has adequate knowledge and experience with

Bank FM policies and procedures will be designated as the Project Accountant and will report the EARP

Director of Finance. However, in order to match the anticipated additional workload and also strengthen

the internal controls, the project will recruit an Accountant, with qualifications and experience acceptable

to the Bank to, support the Chief Accountant.

The Project Manager shall cause the preparation of a consolidated annual work programme with

participation and input of key stakeholders including the FONERWA technical staff. The work

programme which will indicate activities by component, category and source of financing will be

reviewed and approved by REG and the Bank on an annual basis. The existing TOMPRO accounting

system will be configured to include the grant as a separate source of financing to enable the monitoring

of grant expenses and generation of project specific financial reports. The existing EARP financial

manual detailing its accounting policies and procedures will be used by the project. Consolidated Project

Financial Statements will be prepared by the project chief accountant under the supervision of the EARP

Director of Finance.

The project will prepare Interim Financial Reports (IFR) as part of the quarterly progress report (QPR), as

required by the Bank, not later than 45 days after the end of each quarter. In line with the use of country

system, the Rwanda Energy Group (REG)’s Internal Audit Department will include the Project in its audit

program and audit regularly using a risk based audit methodology. The Project internal audit report will

be shared with the Bank during supervision missions or on a need basis.

The external audit arrangement will entail the Project preparing and submitting consolidated financial

statements for audit within three (3) months after the closure of every financial year. The consolidated

financial statements will be prepared using the International Public Sector Accounting Standards

(modified cash basis) applied by EDCL. The Project audit will be conducted by the Auditor General (AG)

of State Finances of Rwanda or a Private Audit firm appointed by AG and agreed with the Bank based on

the Bank’s audit terms of reference. The audit report, complete with a Management Letter, will be

submitted to the Bank not later than six months after the end of the financial year. The cost of the audit

will be borne by the project if undertaken by the Private Audit Firm.

The Project will mainly use the Direct Payment method and the Special Account method for financing all

eligible project expenditures. However, the other two disbursement methods may be used where the need

arises, but after consultation with Bank and obtaining prior approval. The details of the disbursement

methods are provided in the Bank Disbursement Handbook. The EDCL will open a Special Account (SA)

for the purpose of this project at the National Bank of Rwanda (BNR). An initial deposit for an amount

corresponding to 6 months of activities as justified by a work program approved by the Bank will be

made in the SA. Subsequent replenishments of the SA will be subject to the Executing Agency having

II

provided sufficient justifications for the use of at least 50% of the most recent advance and 100% of the

other older advances, and upon production of an agreed work program for the next six months. The Bank

will issue a disbursement letter, which will provide specific guidelines on key disbursement procedures

and practices. The content of the disbursement letter will be discussed during negotiations. In regard to

approved activities implemented in the districts, payment documentations shall be reviewed, approved

and submitted by management of FONERWA to SEAP PIU for payment.

Conditions and Financial Covenants

Open a dedicated Special Account (SA) at the National Bank of Rwanda (BNR).

FM Action Plan

The action plan below indicates the actions to be taken for the project to strengthen its financial

management system and the due dates.

Action Date Due Responsibility

1

.

Recruit an Accountant with the necessary qualifications

and experience.

Before Project

effectiveness EDCL

2

.

Reconfigure the TOMPRO accounting system to include

the grant as a separate source of funding

Before the first

disbursement EDCL

3

. Agree on the External Audits Terms of reference By Negotiations AfDB

4

.

Organize a launch workshop with a training session on the

Bank’s FM and requirements and disbursement policies

and procedures

At Project launch EDCL and

AfDB

In conclusion, the proposed financial management arrangements put in place meet the Bank’s minimum

requirements as per its project financial management policies and guidelines and therefore are adequate

to provide, with reasonable assurance, accurate and timely information on the status of the Project

required by the Bank.

III

Annex 2 – Procurement arrangements

1. Procurement arrangements

1.1 National procedures and regulations—use of country procurement system

B.5.1.1 The Bank’s assessment of NCB procedures for Rwanda concluded that the legal and regulatory

framework and the national standard bidding documents (SBDs) for goods are considered essentially

acceptable for national competitive bidding under projects financed by the Bank. However, this can be

envisaged only when the deviations identified in the NPP are specified in the Bank’s Project Financing

Agreement and the SBDs are revised before they can be utilized under projects financed by the Bank. In

the case of the SBD for Small Works, the divergences are such that until the revisions have been

undertaken the Bank’s SBD for Small Works must be used. The deviations with respect to fundamental

principles relate either to the Bank’s fiduciary obligations or to internationally accepted best practices and

include among others; (i) application of local preference, methods of delivery of bids and price

adjustments; (ii) omissions in the SBD for Goods which are very minor concern provisions for incidental

expenses, spare parts and prohibition from contacting the purchaser during bid evaluation; and (iii)

omissions in the SBD for Small Works include provisions for the Letter of Bid and Bid Schedule, model

Contract Agreement, fraud and corruption, staff and labor standards, force majeur, options in the method

of delivery of bids, care and supply of bids, treatment of confidential details, joint and several liability and

the qualification tables in the Schedule of Forms.

B.5.1.2 The GOR has made some progress in reforming the system notably, (i) the issuance of manual for

Public Procurement (User’s Guide) for use by the procurement practitioners, (ii) the code of ethics for

public procurement practitioners. Furthermore, following the 2009 OECD/DAC assessment of the public

procurement, the Government has issued amendments to the laws, in order to address issues raised by the

assessment notably (i) the exit of RPPA from public procurement proceedings in 2011, (ii) Clarity of

responsibilities of RPPA in order to avoid conflict of interest and direct involvement in procurement (iii)

The establishment of the Independent review panel(s) at national and at district levels (iv) Procurement

planning has become part of budget formulation and contributes to multiyear planning.

B.5.1.3 Following the completion of the assessment of NCB procedures by the Bank, the Government has

agreed with the Bank on the findings, and committed itself to addressing them. Dialogue with the

Government continues to have all the shortcomings identified addressed before the use country systems is

finally agreed upon.

1.2 Procurement Arrangements

B.5.2.1 All procurement of goods, works and acquisition of consulting services financed by the Bank will

be in accordance with the Bank’s Procurement Policy dated October, 2015, as amended from time to

time, using the relevant Bank Solicitation Documents, and the provisions stipulated in the Financing

Agreement.

The various items under different expenditure categories and related procurement arrangements are

summarized in Table B.5.2 below. Each contract to be financed by the Fund, the different procurement

methods or consultant selection methods, the need for prequalification, estimated costs, prior-review

requirements, and time frame have been agreed between the Borrower and the Bank project team and are

provided in the Procurement Plan (see section B.5.5).

IV

Summary of Procurement Arrangements.

Project Categories

Amount in US$ '000 UA '000

Use of

Country

Procurement

Procedures

Use of

Bank’s

Procedures

Non-Bank

Financed Total Cost

1. Goods

1.1 Office Equipment & Consumables

80]

[80]

57

Sub-total of Goods [80] 57

2. Works

2.1 Upgrading of 6 rural markets (2

per District)

2.2 Construction/ rehabilitation of 9

post-harvest infrastructure (3 per

District)

[1,375]

[4,530]

[1,375]

[4,530]

975

3,213

Sub-total of Works [5,905] 4,188

3. Consulting Services

3.1 Technical assistance and capacity

building

3.2 Monitoring and evaluation

[2,249.749]

[250]

[2,249.749]

[250]

1,596

177

Sub-total of Services [2,499.749] 1,773

4. Operating Expenses 340 241

Sub-total 340 241

TOTAL [8,824.749] 6,259

1.3 Goods: There is one package for the Goods which shall be procured through OCB with national

publication. This is procurement of Office equipment and consumables.

1.4 Works: The procurement of Works identified in this project are: Upgrading of 6 rural markets (2 per

District) and Construction/ rehabilitation of 9 post-harvest infrastructure (3 per District) and will be

procured under the Open Competitive Bidding method with international publication.

1.5 Consulting Services: The consulting services required for the project are Technical assistance &

Capacity Building, and Monitoring and Evaluation. These services shall be procured under the method of

Quality and Cost Based Selection (QCBS) procedures.

B.5.2.2

2. Assessment of the Executing Agency

2.1 The REG SPIU will be responsible for the procurement of goods, works and consulting

services/training services. An assessment of the capacity of the Executing Agency to implement

V

procurement actions for the project has been carried out by the Bank. The assessment reviewed the

organizational structure for implementing the project and the interaction between the staff responsible for

procurement activities. The capacity of the SPIU is found to be adequate.

3. General Procurement Notice

3.1 The text of a General Procurement Notice (GPN) has been agreed with REG, and it will be issued for

publication in UNDB online and in the Bank’s Internet Website, upon approval by the Board of Directors

of the Financing Proposal.

4. Procurement Plan

The Borrower, at appraisal, developed a Procurement Plan (see annex procurement plan) for project

implementation which provides the basis for the procurement methods. This plan has been agreed

between REG and the Bank Team and is available at REG offices. It will also be available in the Project’s

database and in the Bank’s external website. This Procurement Plan will be updated by the Borrower’s

Project Team annually or as required to reflect the actual project implementation needs and improvements

in institutional capacity. Any revisions proposed to the Procurement Plan shall be submitted to the Bank

for prior review. The REG shall implement the Procurement Plan in the manner in which it has been

agreed with the Bank.

VI

Goods:

1 General

Country/Organisation: Rwanda

Project/Programme Name: Scaling up Energy Access Project - LDCF Financing

Project/Programme SAP Identification #:

Loan Number:

Executing Agency: EDCL

Approval Date of Procurement Plan :

Date of General Procurement Notice: 21-08-2016

Period Covered by this Procurement Plan:

2 Goods and Non Consulting Services: Prior/Post review

Thresholds

Procurement Method

Prior

review

Threshol

d

(UA)

Post review Threshold

(UA)

Frequency of

Review

ICB (Goods)

All contracts

None At all stages

NCB None All contracts At all stages

Non Consulting Service None None None

3. Procurement Packages Methods and Time Schedule

for 18 months

VII

Description

Lot

Number SPN/IFP

Received

SPN/IFP No-

Objectio

n Date

SPN/IFP

Publicati

on Date

(UNDB)

Estimated

Amount in UA

(000)

Procurement

Method

Pre-or

Post Qualification

Dom/Reg. Preference

(Y/N)

Prior or

Post

Review

Bid

closing

date

3.

1 Project Management - Goods (office equipment and

consumables)

56.74 OCBO(nation

al) N/A post

Project Management - Operating Expenses

241.14

Total Cost 297.87

Works:

1 General

Country/Organisation: Rwanda

Project/Programme Name: Scaling up Energy Access Project - Additional

Financing

Project/Programme SAP

Identification #

Loan Number:

Executing Agency: EDCL

Approval Date of Procurement

Plan :

Date of General Procurement

Notice: 21-08-2016

Period Covered by this

Procurement Plan:

VIII

3. Procurement Packages: Methods and Time Schedule for 18 months

Procurement Packages with

Methods and Time Schedule Basic Data

Description

Lot Number

SPN/IFP

Received

SPN/IFP

No-

Objection

Date

SPN/IFP

Publication

Date

(UNDB)

Estimated

Amount

in UA

Lumpsum or Unit

Rate

Procurement

Method

Pre-or Post

Qualification

Dom/Reg.

Preference

(Y/N)

Prior

or

Post Review

Bid

closing

date

Upgrading of 6 rural markets (2 per District)

975.18 Unit Rate

OCB

(International)

Pre

Qualification Prior

1-Mar-

17

Construction/ rehabilitation of 9

post-harvest infrastructure (3 per District)

3,212.77 Unit Rate OCB (International)

Pre Qualification Prior

1-Mar-17

Total Cost 4,187.94

Services:

1 General

Country/Organisation: Rwanda

Project/Programme Name: Scaling up Energy Access Project - LDCF Financing

Project/Programme SAP Identification #:

Loan Number:

Executing Agency: EDCL

Approval Date of Procurement Plan :

IX

Date of General Procurement Notice: 21-08-2016

Period Covered by this Procurement Plan: 2016-2018

2 Consulting Services: Prior/Post review Thresholds

Procurement Method

Prior review

Threshold

(UA)

Post review

Threshold

(UA)

Frequency of Review

QCBS (Firms) All contracts None At all stages

LCBS All contracts None At all stages

IC All contracts None At all stages

3 Consulting Services: Selection Method and Time

schedule for 18 Months

Basic Data

Description*

Date EOI

Received Date No-Objection

Selection

Method

Lumpsum

or Time-

Based

Estimated

Amount in

UA

Prior/Post

Review

Bid Closing

Date

Plan/

Revised/

Actual

Technical assistance and capacity building

Time-based 1,595.57 Prior Plan

Revised

Actual

Monitoring and evaluation

Time-based 177.31 Prior Plan

Revised

Actual

Total Cost 1,772.87

X

4.1 Frequency of Procurement Post Review Missions

In addition to the prior review supervision to be carried out from Bank offices, the capacity assessment of

the Implementing Agency has recommended 1 procurement supervision mission to visit annually the

project and carry out post review of procurement actions.

4.2 Global Action Plan for improvement to National Procurement Procedures.

The following discrepancies with the Bank’s Rules and Procedures: “Rules and Procedures for

Procurement of Goods and Works”, dated May 2008, revised July 2012 have been identified in the

national procurement law and regulation and shall not be used for procurement activities financed by the

Bank:

CONCERNS REQUIRED CHANGES

Principle of Eligibility:

Standard Forms and the Remaining Sections of the

SBD for Small Works exclude (i) Principle of

Eligibility,(ii) eligibility of goods and related

services, (ii)Documents establishing the eligibility of

goods and related services

Inclusion of appropriate standard Clauses reflecting best

practices with respect to all the missing items in the

Rwanda SBD for Small Works

Principle of Transparency:

Standard Forms and the Remaining Sections of the

SBD for Small Works exclude: (i) Letter of Bid and

Bid Schedule,(ii)Qualification tables (general and

specific experience forms, average annual turnover,

historical contract performance, current

commitments financial resources and situation

Inclusion of appropriate standard Clauses reflecting best

practices with respect to all the missing items in the

Rwanda SBD for Small Works

Principle of Fairness:

Instructions to Bidders and General Conditions of

Contract for Small Works exclude the following

Letter of Bid and Schedule

Contract Agreement

Compliance with Laws

Force Majeur

Staff and labor standards

Fraud and Corruption

Inclusion of appropriate standard Clauses reflecting best

practices with respect to all the missing items in the

Rwanda SBD for Small Works

Discrepancies identified in the National Standard Bidding Documents

Principle of Fairness:

Incidental expenses

Spare parts

Revision of the SBD for Goods to include appropriate

standard Clauses on:

Incidental expenses

Spare parts

XI

Annex 3. Profile of Intervention Areas for LDCF Financing

Description Participating Districts

Karongi District Nyamasheke District Rusizi District

Demography Karongi District is divided

into 13 administrative sectors

(Imirenge), and is subdivided

into 88 cells (Akagari) and

538 villages (Imudugudu).

The district is composed of

175,684 females and 155,886

males. The population density

is considered high, with 334

persons per square kilometer,

and an annual population

growth rate of 1.7%.

The District has a population

of 383,138 of which 47% are

male, while females

represent 53% of the

population. The population

density in the district is 326

persons per square

kilometer. The District has

fifteen (15) administrative

Sectors/Imirenge, 68 Cells

and 588 Villages

(Imidugudu).

The District has an area of

940.95 km2 and is populated

by 404,714 inhabitants, which

make a density population of

399 inhabitants per km2. The

low population density is

attributed to the natural forest

of Nyungwe National Park

occupies much of the district.

Map

Economic

Activities

Agriculture and livestock

farming are the key economic

activities in Karongi District.

To this end, at least 73.7% of

total households depend

mainly on revenues from

agricultural activities, and

11.5% of total households

earn wages from agriculture.

The export cash crops of

coffee, tea and macadamia are

produce, while food crops

include maize, sorghum,

beans, soya beans, peas, Irish

potatoes, bananas, cassava,

wheat, vegetables and fruit

trees. Livestock such as cows,

Agriculture is the main

economic activity in the

District. Slightly over 70%

of the population is

employed in agriculture

sector, 14% is waged labor

while 56.1% are independent

farmers. Livestock sub

sector is also notable with

12.2% of households in

possession of a cow

provided through either the

"One Cow" program or

through not for profit

organizations.

Rusizi district is very

productive, particularly in

food and industrial crops. The

main crops are rice, maize,

tea, coffee, beans, cassava,

banana, and a variety of fruits.

In addition, the district’s

proximity to Burundi and

DRC provides ample

opportunity in cross-border

trade, and has provided

capital for numerous

development projects within

the district

XII

Description Participating Districts

Karongi District Nyamasheke District Rusizi District

sheep, goats, pigs and poultry

are reared in the rural areas,

while bee-keeping and fish

farming are encouraged, but

are not very well developed.

Poverty High levels of poverty are

witnessed in the district, that

is, 61.7% poverty rate, and

39.8% extreme poverty rate.

Poverty is very high in

Nyamasheke District

(second highest in the

country), with 63.4% of the

population under the poverty

line, whereas poverty

reduced in Rwanda from

56.9% to 44.9% between

2007 and 2011.

Poverty rate is 45 against the

national 44.9

Socio-

economic

Challenges

Isolated habitat in the

district, leading to low levels

of development of

settlements (Imudugudu) and

difficulty in accessing social

amenities such as schools,

health facilities, clean

drinking water, waste

management facilities, etc.

Poor infrastructure

(including low access to

electricity at only 2.8%, ICT,

water and sanitation) and

undeveloped tourist sites

Small land size (57.9% of

households have less than

0.5 ha) vis-à-vis the number

of farmers, leading to low

productivity

Need for value addition of

agricultural and livestock

products, accompanied by

creation of off-farm jobs

Very high dependency on

wood energy (99.9%)

Low education levels and

high drop-out rates

Disabled persons head

21.7% of households.

Low productivity of

agriculture, especially

from poor quality of soils

and unfavorable climatic

conditions

Lack of diversification as

more than 70% are still

employed in unproductive

agriculture

Disaster risks to

livelihoods – loss of lives

from mud/landslides and

impassable roads affecting

economic activities

Inadequate settlement

patterns (such as isolated

rural housing) that hamper

provision of basic services

and increase vulnerability

to disasters

Low productivity of

agriculture, especially from

unfavorable climatic

conditions

Lack of diversification as

more than 70% are still

employed in unproductive

agriculture

Inadequate settlement

patterns (such as isolated

rural housing) that hamper

provision of basic services

and increase vulnerability to

disasters

Isolated habitat in the

district, leading to low

levels of development of

settlements (Imudugudu)

and difficulty in accessing

social amenities such as

schools, health facilities,

clean drinking water, waste

management facilities, etc.

Degraded natural resources

like watershed, wetland,

lakes and river band.

Lack of financial capital to

initiate off farm enterprises.

XIII

Description Participating Districts

Karongi District Nyamasheke District Rusizi District

Analysis Karongi District has been

observed as the third poorest

district in the Western

Province, a situation which is

increased by steep

topographic features that

hamper access to social

amenities and infrastructure.

In addition, agriculture, the

main economic activity in the

district, is adversely affected

by soil erosion arising from

the steep topography.

The purpose of this project,

which links climate change

adaptation to last-mile

connectivity, has the potential

to address the high

dependency on agriculture in

the district, which is

characterized by low

productivity. Specifically, this

project may contribute to

tourism development in the

district, which has great

potential, and provides a

ready market for local

agricultural and livestock

products. For these products

to sustainably supply the

tourist sites, however,

activities related to value

addition are required so as to

promote off-farm activities

and provide opportunities for

employment.

Productivity and

employment is one of the

thematic areas under the

‘District-led development

principle’ as presented in

EDPRS2, where an increase

in off-farm employment is

encouraged, with an aim of

about 50% of the population

engaged in non-farm

employment by 2018. Off-

farm agriculture-related

activities may arise from the

commercialization of

agriculture, and

improvement of post-harvest

handling and storage

services.

The baseline rural

electrification project

addresses a key development

constraint of low rate of

electricity access. In line

with the District focus, the

project’s emphasis on

trading centres encourages

the uptake of electricity as

well as supporting off-farm

agriculture-related activities.

However, the appropriate

use of electricity for

productive and income-

generating purposes has

been identified as a critical

need in the District.

The socio-economic

indicators of Rusizi district

are not too far off from the

national average. In addition,

the District’s proximity to

Burundi and DRC presents

great opportunities for cross-

border trade. This opportunity

so far remains largely

untapped, yet it would

provide employment

opportunities and sources of

income to households, and

also finance the district’s

development activities. The

DDP also identifies ‘access to

electricity’ and ‘agriculture

development’ as prerequisites

for integrated development,

sectors that are also

highlighted as priority areas

for the district, and pertinent

to the current project.

XIV

Annex 4. Detailed Additional Program Activities and Costs

In the tables below is a detailed description of Project activities to be undertaken under each component

as well as the unit cost in USD and total cost estimated per activity and component.

Table A: Component 1 outputs and activities

Component 1: Enhanced and diversified climate

resilient rural livelihoods

Cost (USD)

Outcome Output Activity Year 1 Year 2 Year 3 Year 4 Total

Outcome 1.1: Diversified,

strengthened

and climate

resilient rural

livelihood

opportunities

for vulnerable

women and

men

Output 1.1.1: Improved

knowledge,

understanding

and awareness

of livelihood

opportunities

resulting from

electrification

KAP baseline

survey

30,000 0 0 0 30,000

Development

of awareness

materials

0 20,000 10,000 0 30,000

Community

Awareness

Programs

0 10,000 5,000 5,000 20,000

Output 1.1.2:

Increased

capacity of

target

households to

participate in

market-

oriented

enterprises

Ministry of

Trade &

Industry

(MINICOM)

to determine

baseline

capacity

(Capacity

needs

Assessment)

20,000 0 0 0 20,000

MINICOM

Training -

Cooperatives

0 5,000 5,000 5,000 15,000

Facilitate

study tour to

working

enterprises

65,000 0 0 0 65,000

Output 1.1.3:

Increased

investment in

value chain

development

creating and

linking

demand to

supply

Nyamasheke

District - Fruit

processing

plant; Animal

feeds

production

plant; Pork

processing

unit

30,000 120,000 600,000 120,000 870,000

Karongi

District –

Ecotourism;

Banana value

chain;

Briquette

making

30,000 120,000 600,000 120,000 870,000

XV

Component 1: Enhanced and diversified climate

resilient rural livelihoods

Cost (USD)

Outcome Output Activity Year 1 Year 2 Year 3 Year 4 Total

Rusizi District

– Briquette

making;

Construction

of a modern

fruit market;

Fruit value

chain

promotion

30,000 120,000 600,000 120,000 870,000

Output 1.4.1: Increased

economic

opportunities

for women and

youth

Facilitate

Youth Fund

and Gender

Monitoring

Office (GMO)

of

MIGEPROF –

Ministry of

Gender &

Family

Promotion

50,000 50,000 60,000 50,000 210,000

Total 255,000 445,000 1,880,000 420,000 3,000,000

Output 1.1.1: Improved knowledge, understanding and awareness of livelihood opportunities resulting

from electrification.

The project will facilitate a Knowledge Attitude Practice survey as a baseline on the current knowledge

and understanding of livelihood opportunities. Based on the results of the baseline, awareness materials

will be developed both in electronic and print. Community radio will also be utilised. Community

awareness programs will also be designed. The programs will take opportunity of World International

days (World Environment day; World Wetland day, etc.) to create awareness to a wide range of

stakeholder.

Output 1.1.2: Increased capacity of target households to participate in market-oriented enterprises.

Almost 80% of the population in the three districts depend on subsistence agriculture as the main

livelihood. The project will facilitate MINICOM to undertake a baseline (Capacity Needs Assessment,

CNA) and provide capacity on the identified gaps. Through MINICOM the project will facilitate training

of cooperatives on viable enterprises. The project will also facilitate study tours both within and in

neighbouring countries to enable beneficiaries to learn from viable and profitable enterprises.

Output 1.1.3: Increased investments in value chain development creating and linking demand to

supply.

During the program development phase, each of the three districts presented preliminary off-farm

enterprises (Table B).

XVI

Table B: Priorities provided by community groups as possible livelihood alternatives

District Priority 1 Priority 2 Priority 3

Karongi Eco- tourism

Banana value chain Briquette making

Nyamasheke Fruit processing plant Animal feeds

production plant

Pigs processing unit

Rusizi

Briquette making from

waste products

Construction of a

modern fruit market

Fruits value chain

promotion

The project will work with stakeholders to identify viable and profitable livelihoods opportunities

resulting from electrification. A rapid assessment will be conducted in each District to ensure that all

ideas were captured during the stakeholder meeting. Other activities under this output will include; study

tours to viable enterprises within the country, development and implementation of a sensitization program

and initiating of an awards scheme. The project will provide funds (direct investment) to enable

establishment of the identified enterprises. Efforts will be made to work closely with the private sector.

This will ensure available market options and future sustainability.

Output 1.1.4: Increased economic opportunities for women and youth.

To ensure that women and youth benefit from the project, the project will put affirmative action with clear

quotas for women and youth during the formation of groups for each enterprise. The project will

facilitate existing institutions like Youth Fund and Gender Monitoring Office (GMO) of MIGEPROF –

Ministry of Gender & Family Promotion to ensure the affirmative action is realised during the life of the

project and beyond. The project will also establish access to financial support for women and youth.

Table C: Component 2 outputs and activities

Component 2: Strengthening awareness and

ownership of adaptation and climate risk reduction

Cost (USD)

Outcome Output Activity Year 1 Year 2 Year 3 Year 4 Total

Outcome

2.1:

Community

driven

adaptation

and reduced

vulnerability

to climate

change

improved

Output 2.1.1:

Increased

knowledge and

understanding of

the social

dimensions of

vulnerability and

resilience to

climate change

Development

of awareness

materials

0 50,000 24,749 0 74,749

Community

training

PLPA/Climate

Vulnerability

& Capacity

Assessment

(CVCA)

vulnerability

0 80,000 40,000 0 120,000

Output 2.1.2:

Increased

awareness of

climate change

impacts and

promotion of

gender-responsive

climate adaptation

Awareness

campaigns

50,000 50,000 50,000 50,000 200,000

Workshop –

Adaptation

activities

0 40,000 40,000 40,000 120,000

XVII

Output 2.1.3:

Increased

institutional

capacity of district

administrations to

coordinate and

support climate-

resilient

development

planning at the

local level

Facilitate

REMA and

MINILOC to

support

greening of

DDPs

125,000 125,000 125,000 125,000 500,000

Output 2.1.4:

Increased capacity

of communities to

plan, implement

and monitor

adaptation

programs

Training –

Participatory

M&E

20,000 10,000 10,000 10,000 50,000

Development

of M&E tools

40,000 0 10,000 0 50,000

Facilitate

communities

to carry out

planning an

monitoring

10,000 10,000 10,000 10,000 40,000

Total 245,000 365,000 309,749 235,000 1,154,749

Output 2.1.1: Increased knowledge and understanding of the social dimensions of vulnerability and

resilience to climate change

Using the cooperatives as the entry point, the project will use the PLPA (Participatory Learning Planning

and Action) to capture the social dimensions of vulnerability and resilience to climate change in a

participatory manner. The PLPA process will also establish the current knowledge attitude and practices

as a baseline (KAP Survey). Using the results from the two processes, the project will then design

training programs and develop both print, voice and electronic public awareness materials on social

dimensions of vulnerability and resilience to climate change.

Output 2.1.2: Increased awareness of climate change impacts and promotion of gender-responsive

climate adaptation

The project will ensure that the adaptation efforts are gender and age responsive and consider the specific

needs of men, women and youth as well as the gendered inequalities that may exacerbate the impacts of

climate change for poor women in particular, or prevent women from benefitting from adaptation

interventions.

The project will achieve this by identifying gender and age dimensions of vulnerability to climate change

as well as analyzing and addressing gender and age inequalities, risks and opportunities in the context of

the planned responses to climate change and promoting gender-aware responses to climate change.

The project will work with men and women and boys and girls to promote equal access to decision-

making processes in adaptation planning by making the capacity building processes transparent and

accessible. The project will also train women and youth organizations to take part in and lead these

processes.

XVIII

Output 2.1.3: Increased institutional capacity of district administrations to coordinate and support

climate-resilient development planning at the local level The Government of Rwanda through FONERWA has provided funds for REMA and MINILOC for

greening the District Development Plans. The project will enhance this effort through targeted capacity

building towards key staff in the local authority at District, Sector and Cell levels and promote a climate

extension service. At the District level this will include: Agronomist Officers, Environment Officers and

interns, Infrastructure Officers, Lands Officers, Forestry Officers, Extension Officers and RAB CIP

Officers. Agronomist Officers in each sector and Integrated Development Program (IDP) Officers at the

cell level will also be included.

Output 2.1.4: Increased capacity of communities to plan, implement and monitor adaptation programs

This output will use co-operatives as an entry point to strengthen the capacity of vulnerable communities

to plan and implement adaptation interventions recognizing that these processes must be founded on men

and women farmers’ knowledge and experiences. Using training materials manuals and materials

produced by the Adaptation Fund project, the project will progressively build capacity of communities to

plan, implement and monitor adaptation programs.

Component 3: Climate resilient small-scale rural infrastructure

This component will focus on investment in upgrading rural infrastructure, such as post-harvest storage

facilities that are connected to the electricity-grid by the AfDB baseline project.

In order to achieve the results of this component, a number of outputs and indicative activities are

summarized as Table D.

Table D: Component 3 outputs and activities

Component 3: Climate resilient small-scale rural

infrastructure

Cost (USD)

Outcome Output Activity Year 1 Year 2 Year 3 Year 4 Total

Outcome

3.1: Increased

resilience

of small

scale rural infrastructure

to climate

change

Output

3.1.1: Increased

investment

in small-

scale rural

infrastructur

e designed,

built and/or

rehabilitated

to a

specification

that takes

into account

anticipated

climate risks

Consultant –

Infrastructure audit

80,000 0 0 0 80,000

Small scale

infrastructure -

Karongi

0 40,000 300,000 300,000 640,000

Small scale

infrastructure -

Nyamasheke

0 40,000 300,000 300,000 640,000

Small scale

infrastructure - Rusizi

0 40,000 300,000 300,000 640,000

Output

3.1.2: Rural

markets

upgraded

with at least

30% of

space

Rehabilitation/Upgra

de markets-Karongi -

0 40,000 205,000 130,000 375,000

Rehabilitation/Upgra

de markets-

Nyamasheke -

0 40,000 205,000 130,000 375,000

Rehabilitation/Upgra

de markets - Rusizi

0 40,000 200,000 130,000 370,000

XIX

Component 3: Climate resilient small-scale rural

infrastructure

Cost (USD)

Outcome Output Activity Year 1 Year 2 Year 3 Year 4 Total

allocated to

women and

20% to

youth

Construct New

Market Rusizi

0 50,000 300,000 200,000 550,000

Meeting– Market

committees

10,000 10,000 10,000 5,000 35,000

Output

3.1.3: Increased

institutional

capacity of

district

administrati

ons to

coordinate

and support

climate-

resilient

development

planning at

the local

level

Training –Engineers

and Procurement

20,000 0 20,000 0 40,000

Consultant - Training

Modules

development

(Working with

Integrated

Polytechnic Regional

Centre (IPRC),

develop training

modules for Training

of Trainers)

40,000 0 25,000 0 65,000

Training – TOT on

Modules for IPRC

50,000 0 10,000 0 60,000

Support trainees to

deliver modules

0 10,000 10,000 10,000 30,000

Consultant –

Guidelines

development

50,000 0 0 0 50,000

Consultant –

Checklist

development

(Develop a checklist

for construction,

supervision and audit

to ensure future

compliance of future

infrastructure with the

new climate-proofed

design standards)

50,000 0 0 0 50,000

Total 300,00

0

310,00

0

1,885,00

0

1,505,00

0

4,000,00

0

Output 3.1.1: Increased investment in small-scale rural infrastructure designed, built and/or

rehabilitated to a specification that takes into account anticipated climate risks.

The main activity under this output is carrying out an infrastructure audit. The audit will list the number

and type of structures, which require climate proofing. Using communities and other stakeholders, a

selected number of infrastructure will be identified during the audit for upgrading, which will act as

models for future designs and building.

Output 3.1.2: Rural markets upgraded with at least 30% of space allocated to women and 20% to youth

During a stakeholder workshop conducted as part of program development, one market was identified for

construction.in Rusizi. The program will carry out a rapid assessment of the existing markets, by working

with key stakeholders to identify at least six markets for rehabilitation/upgrading of existing markets in

XX

other Districts. To ensure that women and youth benefit from these rural investments, the assessment will

recommend that the project work with sectors allocation committees to ensure that 30% and 20% of

women and youth are allocated spaces.

Output 3.1.3: Increased capacity of District engineers and local contractors to factor in climate risks to

the design and construction of small-scale rural infrastructure

The project will build capacity of district engineers and procurement officers on factoring of climate risks

in the design and construction of small-scale rural infrastructure. This will be achieved by first,

developing of training modules and conduct a TOT for IPRC (main college where rural engineers are

trained). The project will also develop guidelines for engineers and procurement officer on inclusion of

climate risks in tender documents. A checklist for construction, supervision and audit will also be

developed and capacity built for the main users.

Component 4: Monitoring and Evaluation

It is of utmost importance for the project to make use of internationally recognized results-based

monitoring and evaluation frameworks during the implementation of the entire project. FONERWA in

collaboration with EDCL will be responsible for the monitoring and evaluation. The project will also

document all problems and lessons encountered during the project’s implementation as a way of

knowledge management. This will ensure that successes are replicated while hindrances would be

avoided early for similar future projects or even other current projects. The component will look at

knowledge management and dissemination, monitoring (both internal and external). In order to achieve

the results of this component, a number of outputs and indicative activities are summarized as Table E1.

Table E: Component 4 outputs and activities

Component 4: Knowledge, Monitoring and Evaluation

Cost (USD)

Outcome Output Activity Year

1

Year

2

Year

3

Year

4

Total

Outcome 4: M&E

management and

lessons learnt are

captured and

appropriately

disseminated

Output 4.1.1:

Compile,

document and

disseminate

Knowledge

adaptation

products

Establish a

knowledge

management

strategy

5,000 0 0 0 5,000

Document

knowledge

adaptation products

and lessons learnt

(Write shops)

20,000 0 5,000 5,000 30,000

Dissemination of

lessons – electronic,

paper and

workshops

10,000 5,000 15,000 15,000 45,000

Output 4.1.2:

Participation

in adaptation

practitioners’

events

Facilitate seminars

and workshops

(Project team

participation and

presentation of

knowledge products

0 15,000 0 15,000 30,000

XXI

from the projects in

various forums)

Output 4.1.3:

Produce

Monitoring

and

evaluation

reports

Develop a project

M&E framework

and Information

Management

Systems (IMS)

5,000 0 0 0 5,000

Produce monitoring

reports per

component and as

annual project

reports

5,000 5,000 5,000 15,000

Mid Term Project

Evaluation

0 0 40,000 0 40,000

End of Project

Evaluation

0 0 0 40,000 40,000

Monitoring Travel -

Joint monitoring

and staff

10,000 10,000 10,000 10,000 40,000

Total 50,000 35,000 75,000 90,000 250,000

Output 4.1.1: Compile, document and disseminate Knowledge adaptation products

This output will focus on Knowledge Management and Dissemination: Knowledge sharing is central to

climate compatible development and plays a key role in ensuring stakeholder participation at all levels.

Knowledge production is often considered a shared experience between national level policy makers,

scientists and local community members.

The associated knowledge dissemination framework will include communities as generators of

knowledge and promote peer-to-peer and lateral knowledge sharing across all stakeholders in the climate

change domain in Rwanda with specific focus on the project areas. To promote both dissemination and

interaction on a wider scale, mass and social media will be used to facilitate broad knowledge sharing

across significant portions of the communities that are and will likely continue to be affected by climate

change in the project areas. To achieve this, various knowledge dissemination products will be developed

such as; (i) Web and paper based information booklets/brochures (ii) Posters (iii) Radio/television

broadcasts (iv) Videos, animations, still images and Policy briefs, etc. Information contained in the above

knowledge dissemination products will be generated from climate change relevant information available

from national, regional and global sources, including the differential impacts of climate change across

genders, classes, ages, abilities and ethnic groups.

Output 4.1.2: Participation in adaptation practitioners’ events

The project will facilitate participation of various stakeholders in practitioners’ events. Proceedings from

climate change seminars, stakeholder workshops, focus group discussions, progress reports and other

climate change relevant information and knowledge products. The knowledge dissemination products will

target both grassroot level and policy level stakeholders to bridge the gap between top-level (policy

makers) and bottom-level (portion of stakeholders most affected) stakeholders. The project will also

XXII

facilitate participation of various stakeholders in practitioners’ events. Proceedings from climate change

seminars, stakeholder workshops, focus group discussions, progress reports and other climate change

relevant information and knowledge products.

Output 4.1.3: Produce Monitoring and evaluation reports

The project will ensure that monitoring of the project is conducted and reported at various levels;

including internal, external and at community levels (participatory M&E). At the beginning of the project,

a project M&E framework will be developed together with a robust IMS (Information Management

Systems). The system will allow real time data input and analysis from internal and community

evaluation.

Internal monitoring: Internal monitoring will serve the purpose of ensuring that the proposed Knowledge

management and monitoring & evaluation (M&E) framework is adhered to using appropriate means and

approaches. Monitoring and evaluation personnel from REMA, MINIRENA, FONERWA, and EDCL

will be jointly responsible of the internal monitoring and evaluation of the project. The monitoring and

evaluation reports highlighting important issues that could impact on the delivery of the project will be

submitted to the PSC for review and decisions, and subsequently to the Bank as part of the quarterly

report.

The proposed monitoring parameters, frequency and time schedule should be followed to the later to

ensure effective implementation of proposed intervention measures. All experts involved in the project;

climate change adaptation and vulnerability expert, financial, procurement, & M&E expert, rural

infrastructure expert, and social development expert are expected to make at least two monitoring visits

yearly per project activity to observe pre-project situation, middle of activity and end of project status.

Progress reports will be prepared for each visit by each expert with collaboration with the implementing

agency (ies) to give finer details of the project at the time of evaluation. The progress reports will be

submitted to the PSC for review and decision and subsequently to the Bank.

Participatory M&E: Participatory Monitoring, Evaluation, Reflection and Learning (PMERL) formulated

and information gathered used in adaptive management and shared widely: The project will facilitate the

design and use of a Participatory Monitoring, Evaluation, Reflection and Learning for Community-based

Adaptation plans. As described in the Community Based Resilience Analysis, CoBRA (UNDP, 2013) and

PMERL Manual (by CARE International), the formulation and implementation of this system will

enhance participation of the communities in learning about the effectiveness of the adaptation measures

and the continuous modification of those measures as the circumstances change, to continually improve

their efficacy. Under this output, the project staff will monitor the climate / environment / development

indicators on yearly basis, and prepare annual plans based on these indicators and also facilitate the

publication of annual district report which at present is not produced by any district in Rwanda.

External monitoring: External monitoring will be executed by an independent monitoring expert who will

review the progress reports prepared by the internal monitoring process Vis a Vis the actual situation on

the ground. The external monitoring expert will evaluate reports, data, work and other activities related to

implementation of the project with the aim of ensuring that the proposed intervention measures are

implemented as planned in the Knowledge management and monitoring & evaluation (M&E) framework.

The independent monitoring expert will submit progress reports to the AfDB/GoR/GEF.

XXIII

Project Document Annex 1: GEF PIF Approval

XXIV

Project Document Annex 2: GEF CEO Approval

XXV

Project Document Annex 3: Government Request to the Bank for Project Financing