african development bank group senegal …
TRANSCRIPT
AFRICAN DEVELOPMENT BANK GROUP
SENEGAL
REHABILITATION OF THE SENOBA – ZIGUINCHOR - MPACK ROAD
AND OPENING UP OF THE SOUTHERN REGIONS
PICU/RDGW/COSN DEPARTMENTS
June 2018
Translated Document
P
ub
lic
Dis
clo
sure
Au
tho
rize
d
Pu
bli
c D
iscl
osu
re A
uth
ori
zed
TABLE OF CONTENTS
I PROJECT STRATEGIC THRUST AND RATIONALE............................................................. 1 1.1 Project Linkages with National and Regional Strategies and Objectives.................................................. 1 1.2 Main Development Issues ......................................................................................................................... 2 1.3 Rationale for Bank’s Involvement ............................................................................................................ 3 1.4 Donors’ Coordination ............................................................................................................................... 3
II PROJECT DESCRIPTION ........................................................................................................... 4 2.1 Project Objectives and Components ......................................................................................................... 4 2.2 Technical Solution Retained and other Alternatives Explored ................................................................. 4 2.3 Project Type .............................................................................................................................................. 5 2.4 Estimated Project Costs ............................................................................................................................ 5 2.5 Financing Arrangements ........................................................................................................................... 6 2.6 Project Target Area and Beneficiaries ...................................................................................................... 8 2.7 Participatory Process for Project identifications, Design and Implementation ......................................... 9 2.8 Bank Group Experience,Lessons Reflected in the Project Design ............................................................ 9 2.9 Key Performance Indicators .....................................................................................................................10
III PROJECT FEASIBILITY ........................................................................................................... 10 3.1 Economic and Financial Perfromance .....................................................................................................10 3.2 Environmental and Social Impacts ...........................................................................................................11
IV IMPLEMENTATION .................................................................................................................... 15 4.1 Implementation Arrangements .................................................................................................................15 4.2 Monitoring and evaluation .......................................................................................................................17 4.3 Governance ................................................................................................................................................. 4.4 Sustainability ............................................................................................................................................18 4.5 Risk Management ....................................................................................................................................19 4.6 Knowledge Building ................................................................................................................................19
V LEGAL FRAMEWORK ............................................................................................................... 20 5.1 Financing Instrument ...............................................................................................................................20 5.2 Conditions associated with Bank Group intervention ..............................................................................20 5.3 Compliance with Bank Policies ...............................................................................................................22
VI RECOMMENDATION ................................................................................................................. 22
APPENDIX I: SOCIO-ECONOMIC INDICATORS FOR SENEGAL
APPENDIX II: TABLES ON BANK’S PORTFOLIO IN SENEGAL
APPENDIX III: MAIN RELATED PROJECTS FINANCED BY THE BNAK AND OTHER DEVELOPMENT
PARTNERS IN SENEGAL
APPENDIX IV: MAP OF PROJECT AREA
APPENDIX V: SUPPORT FOR REPORT’S KEY ARGUMENTS
LIST OF TABLES
No. TITLE Page
Table II.1 -Project components ............................................................................................................................................................. 4 Table II.2 - Alternative solutions explored and reasons for rejection .................................................................................................... 5 Table II.3- Estimated cost by component for the entire project ............................................................................................................. 6 Table II.4- – Costs by expenditure ctegory for the entire project .......................................................................................................... 6 Table II.5– Source of financing by component for the entire project .................................................................................................... 7 Table III.1- Summary of economic analysis ....................................................................................................................................... 10 Table III.1– Project monitoring and supervision schedule .................................................................................................................. 17
i
Currency Equivalents
March -2018
UA1
1UC
= USD1.446
UA1 = EUR 1,184
UA1 = CFA776.515
Fiscal Year 1 January - 31 December
Weights and Measures
1 metric tonne = 2204 lbs.
1 metre (m) = 3.28 feet
1 millimetre (mm) = 0.03937 inches
1 kilometre (km) = 0.621 miles
1 hectare (ha) = 2.471 acres
Acronyms and Abbreviations
AADT : Average Annual Daily Traffic
ADF : African Development Fund
AFD : French Development Agency
AfDB : African Development Bank
AGEROUTE : National Road Works and Management Agency
ANRAC : National Agency for the Recovery of Economic and Social Activities in Casamance
ANSD : National Agency for Statistics and Demography
APU : Agricultural Processing Unit
BPW : Buildings and Public Works
CIB : Consolidated Investment Budget
CSF/BTP : Vocational Training Centre/Building and Public Works
CSP : Country Strategy Paper
DCFE : Cooperation and External Financing Department
DD : Detailed designs
DEEC : Environment and Classified Establishments’ Department
DTR : Road Transport Department
ECOWAS : Economic Community of West African States
EIB : European Investment Bank
EIG : Economic Interest Group
ESMP : Environmental and Social Management Plan
ESP : Emerging Senegal Plan
EU : European Union
FERA : Autonomous Road Maintenance Fund
HDM 4 : Highways Development and Maintenance version 4
ILO : International Labour Organisation
IRI : International Roughness Index
IRR : Internal rate of return
IsDB : Islamic Development Bank
JBCP : Juxtaposed Border Control Post
MCC : Millenium Challenge Corporation
ii
MEFP : Ministry of Economy, Finance and Planning
MIPMI : Ministry of Industry and Small and Medium-Sized Industry
MITTD : Ministry of Infrastructure, Land Transport and Opening Up
NPV : Net Present Value
PAD : Autonomous Port of Dakar
PD : Preliminary designs
PDAI : Project Direct Area of Influence
PEAI : Project Extended Area of Influence
RBCSP : Results-Based Country Strategy Paper
RONET : Road Network Evaluation Tools
RUC : Road User Costs
UA : Unit of Account
UNDB : United Nations Development Business
USD : United States Dollar
Veh/D : Vehicles per day
VOC : Vehicle Operating Cost
WAEMU : West African Economic and Monetary Union
iii
PROJECT INFORMATION SHEET
Client information
Donee/Borrower : Senegal
Project Name : Rehabilitation of the Sénoba-Ziguinchor-Mpack road
and opening up of the Southern Regions
Location : Regions of Ziguinchor and Sédhiou
Executing Agencies : Ministry of Infrastructure, Land Transport and Road Access
(MITTD)/Road Works and Management Agency
(AGEROUTE)
Financing Plan
Source Amount in
million UA
Amount in
million CFAF
Amount in
million US$
Amount in
million Euros Instrument %
AfDB LOAN 71.80 55 756.37 103.83 85.00 Project loan 49.85%
EU GRANT 21.12 16 398.92 30.54 25.00 Grant 14.66%
EIB LOAN 50.68 39 357.42 73.29 60.00 Project loan 35.19%
Gov. of SENEGAL 0.43 333.23 0.62 0.51 CIB 0.30%
TOTAL 144.04 111 845.93 208.28 170.51 100.00%
ADB’s Key Financing Information
Loan currency : EUROS (EUR)
Loan type: Fully flexible loan
Tenor: To be determined (not exceeding 25 years including the grace period)
Grace period To be determined (not exceeding 8 years)
Loan average maturity**: To be determined (depending on the depreciation profile
Repayments: To be determined (semi-annual payments after the grace period)
Interest rate: Base rate + Funding margin +Lending spread + Maturity premium
Base rate : Floating rate (6-month EURO EURIBOR to be reset on the applicable reset date). A
free-fixing option is offered to fix the base rate
Funding margin : Bank’s funding margin resets on 1 January and 1 July and applied on 1 February and
1 August with the base rate
Lending spread : 80 basis points (0.8%)
Maturity premium:
To be determined as follows: (i) 0% if the average weighted maturity <= 12.75
years; (ii) 0.10% if average weighted maturity<=15 years ; and (iii) 0.20% if
average weighted maturity >15 years
Front-end fee : 0.25% of the loan amount to be paid no later than on the loan signature date
Commitment fee : 0.25% per year on the undisbursed amount. It starts to accrue 60 days after loan
signature and is payable on interest payment dates
Base rate conversion option *:
In addition to the free-fixing option for fixing the base rate, the Borrower is now
offered the possibility of returning to the floating rate or re-fixing all or part of the
disbursed amount of its loan.
Transaction fees are payable
Interest rate cap or collar
option * :
The Borrower is offered the possibility of establishing base rate caps or collars for
all or part of the disbursed amount of its loan
Transaction fees are payable
Lending currency conversion
option *:
The Borrower is offered the possibility of converting the lending currency for all or
part of its disbursed or undisbursed loan into another Bank-approved lending
currency.
Transaction fees are payable
iv
* The conversion options and transaction fees are governed by the Bank’s Guidelines for Loan Terms available
which can be accessed through the following link: http://www.afdb.org/fr/documents/document/guidelines-for-
conversion-of-loan-terms-july-2014-87643/
FRR ; NPV (baseline scenario) : Not applicable
ERR ; NPV (baseline scenario) : 28.70%; 125.51 billion CFAF
Timeframe – Main Milestones (expected)
Activities (month, year)
Concept note approval March-2018
Project approval June-2018
Effectiveness Sept-2018
Completion of activities Dec.-2021
Last disbursement Dec.-2022
Last repayment- AfDB Loan July-2038
v
PROJECT SUMMARY
Project Overview
1. In June 2016, the Government of Senegal requested a contribution from the Bank to the
financing of the Project to rehabilitate the Gambian border--Sénoba-Ziguinchor–Mpack–Guinean
Guinea Bissau Border section of National Road 4 which forms part of the Dakar-Lagos Trans-African
Highway 7 corridor. Implementation of this integrated project will, through its access dimensions and
support to the activities of the most vulnerable segments of the population will contribute to the revival
of tourism in Casamance, the reduction of agricultural and fruit production losses and to the
strengthening of trade and sub-regional integration. The expected outcomes are the growth of transit
traffic and trading, country-wide reduction of transport costs, the reduction of customs control points
and time spent for controls on the Dakar - Bissau road corridor as well as improved accessibility and
conditions for the conduct of socio-economic activities in the project area of influence, especially those
of the most vulnerable groups (women and youth).
2. The project will comprise: (i) the rehabilitation of 165 km of roads in compliance with
ECOWAS standards; (ii) the improvement and asphalting of 100km of access roads. There are also
plans to carry out related improvement works comprising socio-economic and commercial
infrastructure, urban roads and support to women’s and youth groupings, in particular to increase
agricultural output. The project will also will also help to build the executing agency’s capacities and to
improve the availability of statistical data on transport facilitation indicators.
3. The Sénoba-Ziguinchor road section as well as the project roads and rural access roads are
located in the Ziguinchor and Sédhiou regions, mainly in the Departments of Bounkiling, Bignona and
Ziguinchor. These three Departments comprise the Project Direct Area of Influence (PDAI). However,
since the Sénoba-Ziguinchor road section forms part of the Dakar-Lagos Trans-African Highway 7, its
Extended Area of Influence (PEAI) mainly covers other regions of The Gambia, Guinea Bissau and
Guinea. The PEAI covers an area of 9277.38 km2, i.e. 4.72% of the country’s surface area with, a
population estimated in 2016 at 666,551 people, i.e. almost 4.50% of the country’s population. The
proportion of women in the PDAI is 48.79%. The project’s direct beneficiaries are transport users as
well as people living in the PDAI who were consulted and sensitised for the project design on the basis
of a participatory process that will be maintained until the project has been implemented. The project
will be implemented over a 4-year period at a total cost, excluding taxes and duties, including physical
and financial contingencies of UA 144.04 million, equivalent to EUR 170.51 million. The Bank’s
contribution is UA 71.80 million, i.e. equivalent to EUR 80 million. The rest of the financing will be
jointly provided by the EU to the tune of UA 21.12 million i.e. EUR 25.00 million, and at the same
time the EIB, to the tune of UA 50.68 million, i.e., EUR 60 million and the Government of Senegal
(UA 0.43 million, i.e. EUR 0.51 million).
Needs Assessment
4. Senegal’s southern regions, especially those of Sédhiou and Ziguinchor are among the
country’s main areas of fragility. The Casamance conflict which lasted for years in those regions caused
the destruction of part of the socio-economic infrastructure resulting in inadequate tapping of its strong
economic potential. The economic recovery programmes for these regions established since 2003 did
not achieve the expected results. These regions also have a high incidence of poverty exceeding 60%.
The internal and external isolation of these regions is one of the main causes. In addition, these regions
are part of the border areas. Trade between these two regions and the country’s other regions and also
with neighbouring countries (mainly The Gambia, Guinea Bissau and Guinea) have been affected by
this situation. Implementation of this project will bring these regions closer to the country’s key
consumption and processing centres for its products and more effectively exploit this potential and trade
with neighbouring countries.
vi
5. The project is also justified by its alignment with the Bank’s Hi-5 priorities by helping to
address the challenges of regional integration, reducing agricultural and fruit production losses by
improving the conditions for processing this production, improving the population’s living conditions,
addressing youth unemployment, inequalities and gender issues. Finally, the project is justified by its
alignment with the Bank’s 2014 – 2019 strategy for addressing fragility and building resilience in
Africa. Indeed, the sources of fragility in Casamance include its geographical isolation which worsens
the local populations’ feeling of exclusion, the infrastructure gap, the porousness of its borders and its
regional involvement.
Bank’s Added Value
6. In the sub-region, the Bank is considered to be a strategic partner in the transport sector due to
its different previous and current operations. In addition to its national projects, the Bank plays a key
role in financing transport sector projects in Senegal and improving service levels in West Africa’s
corridors, especially the Nouakchott-Dakar-Banjul-Bissau-Conakry-Abidjan-Lagos corridor
(construction of the Rosso bridge over the Senegal River, on the rehabilitation of the Dinguiraye – Nioro
- Keur Ayib road in Senegal, construction of the bridge over the Gambia River and improvement of the
Lola - Danané between Guinea and Côte d’Ivoire). The Bank’s experience has facilitated the effective
mobilisation for this project of EU co-financing in the form of a grant of 25 million Euros. By
intervening in this project, the Bank will strengthen its leadership role for the development of regional
infrastructure in the Continent. Apart from the road works on the corridor financed with the other
donors, the Bank has taken into account in its financing the other improvements as well as issues
pertaining to transport facilitation, axle load control and road safety.
Knowledge Management
7. The project will provide the Bank with a good opportunity to build its knowledge on the impact
of transport infrastructure projects, on access to production areas, strengthening industrial strategies by
bringing production areas closer to the consumption and processing areas for such production as well
as the development of trade and sub-regional integration. In order to learn effective lessons from this
project, a monitoring and evaluation mechanism will be established by the executing agency which will
include, in particular, monitoring of the project’s impact on the creation of direct and indirect jobs. The
establishment of key impact indicators prior to project commencement and impact assessment on project
completion will help produce useful information on the project outcomes. The project will support the
preparation of the regional social accountability matrix which will help to assess the expected impacts
of infrastructure investment in the project area. The lessons to be learned and experience and knowledge
gained from the implementation of this project will be managed from a database at the executing agency
and disseminated in annual reports and through the Bank’s website. This database will effectively
facilitate management of all the knowledge built during the project’s implementation.
vii
Programme Results-Based Logical Framework Country and Project Name: Senegal – Project to Rehabilitate the Sénoba-Ziguinchor-Mpack Road and Open up the Southern Regions
Project Goal: Contribute to reducing internal and external isolation and strengthening regional integration
RESULTS CHAIN
PERFORMANCE INDICATORS MEANS OF
VERIFICAT
ION
RISKS/
MITIGATION MEASURES Indicators
(including CSI) Baseline situation Target
IMP
AC
T
Contribute to an
increase in sub-
regional trade and to
poverty reduction
(i) traffic volume
between Senegal
and Guinea Bissau ;
(ii) poverty rate in
the PDIA
In2016 : (i) 810,111
tonnes of goods ; (ii)
Sédhiou 68.3% and
Ziguinchor 66.8%
From 2025 : (i) 1,569,331 tonnes of goods ; (ii)
Sédhiou 58% and Ziguinchor 56%
Source :
ANDS
statistics
Impact risks
Failure to control the security situations and weaknesses in the implementation of industrial
strategies and policies
Mitigation measures
Country’s industrial policies and strategies are implemented and the security situation in Senegal
continues to improve
OU
TC
OM
ES
Outcome 1 : The
level of service is
improved on the
Sénoba-Ziguinchor
road
(i) Generalized
transport costs (VOC
and time) between
Sénoba, Ziguinchor
and Mpack; (ii)Average Annual
Daily Traffic
(AADT) trend ; and
(iii) number of
control points on the
corridor; and (iv)
average time for
assistance provision to victims of road
accidents
In 2017 : (i) Average user
cost on project roads of
CFAF 364/km for light
vehicles and CFAF 975
/km for heavy duty vehicles; travel time of 2.5
h for LV and 3.75 h for
HDV (ii) Average daily
traffic of 438 vehicles, 12%
of which are HDV; (iii) 13
checkpoints and; (iv) 4
hours
From 2022: (i) Average user cost on project roads is
CFAF 210/km for light vehicles and CFAF for heavy
duty vehicles ; travel time of 1.5 hours for LV and
2.15 hours for HDV ; and (ii) average daily traffic of 750 vehicles, 18% of which are HDV ; (iii) 3
checkpoints; and (iv) 45 mn
Sources :
AGEROUTE
and OPA
statistics
Outcome Risks :
(i) The sustainability of investments is not guaranteed because of the (a) failure to secure adequate
resources for road maintenance; and the failure to fully apply Rule 14 on the control of axle loads; (ii)
WAEMU decisions on limitation of checkpoints and eradication of illegal levies on Inter-State
corridors are not enforced; and (iii) the autonomous body responsible for road safety has not yet been established.
Mitigation measures:
(i) (a) Maintenance for project roods, streets and tracks is eligible for the Autonomous Road
Maintenance Fund (FERA), but resources are insufficient and, moreover, the proportion of these
resources from the annual government subsidy (CFAF 5 billion per year) is difficult to recover. The
leveraging of resources through loans in the national market is not sustainable in the short to medium
term with the current level of the Road User Tax (RUT.) It is necessary to stabilize the RUT and make
it more autonomous by: (i) transforming it into a levy instead of a tax (road marketing principle); (ii) by including it in the middle section of the hydrocarbon price structure; and (iii) gradually removing
the budgetary allocation in favour of an increase in the RUT. Implementation of these provisions will
be a loan condition; (b) Partial implementation of Regulation 14 (shedding for overloads above 40%)
which has begun at sub-regional level is not yet satisfactory even though it represents progress. Senegal
can take the initiative of considering the possibility of starting the full enforcement of Regulation 14
for loads intended for national consumption from the cement works and the Autonomous Port of Dakar
since, in no way does this jeopardize the competitiveness of these economic actors and identify all the
platforms that generate over 200,000 tonnes of freight annually and ensure that they have axle load scales and dimension checking gauges .Implementation of these measures will be a Bank condition for
the project ; (ii) implementation of the WAEMU Decision on limiting checkpoints is a Bank loan
condition for the project, (iii) establishment of the autonomous safety body is loan condition for the
project.
Outcome 2 : fruit
crop production
losses because of
transportation
difficulties reduced
Percentage of fruit
production lost in
the PDAI
In 2017: (i) 40% of
mango production 20% of
which is due to the lack of
a transportation system
From 2022: losses reduced by 50% Sources :
ANSP
statistics and
Regional
Services
viii
RESULTS CHAIN
PERFORMANCE INDICATORS MEANS OF
VERIFICAT
ION
RISKS/
MITIGATION MEASURES Indicators
(including CSI) Baseline situation Target
Outcome 3 :
Accessibility as well
as the activities,
conditions and living
environment in the
PDAI are improved
(i) Rural Access
Index (percentage of
the population
within a 2km radius
of a passable road);
(ii) yields of
women’s and youth
groupings ; and (iii) number of jobs
induced in the
project
In2017: (i) 20%; (ii) 60mn
per kg of agricultural
products processed and
(iii) no jobs created by the
project
From 2022: (i) 40%; (ii) 10 mn per kilo of agricultural
products processed; and (iii) 400 jobs created under the
project
AGEROUTE
statistics
OU
TP
UT
S
Output 1:
Rehabilitated and/or
upgraded roads and
improved urban roads.
Length of roads In 2017:(i) 165 km of
paved roads in poor
condition and able to bear
intense heavy traffic; (ii) earth urban roads not
improved; (iii) 72 km de
rural access roads of
crushed stone slightly
improved
In 2022: (i) 165km of paved roads rehabilitated ; (ii)
14 km of earth roads upgraded to paved roads with
public lighting ;and (iii) 52 km of tracks of the
Kalounayes loop, widened, improved and paved; (iv) 100 km of rural roads upgraded
Project
supervision,
status and
impact monitoring
evaluation,
audit and
completion
reports
Output Risks
(i) Increase in the cost of works due to: (a) the fact that the technical solution proposed for the Tobor
road pavement is not a sustainable solution; and (b) lags between the PD and award of contracts; (ii) difficulties relating to the mobilisation and provision of counterpart funds by the country, taking into
account commitments made over the same period; and (iii) the security situation does not allow sufficient
competition of firms during competitive bidding.
Mitigation measures These risks are mitigated by (i) (a)(b) an additional study is being conducted on the 7 kilometres of the
Tobor road pavement in order to reach a consensus on the technical solution to be adopted and because the successful bidder will be requested to submit comprehensive implementation studies ;and (c) the use
of APA in order to reduce the lead time between conduct of studies and award of contracts and (ii)
limitation of counterpart funds for components financed by the Bank, to the coverage of compensation
and environmental monitoring costs, i.e. UA 0.42 million ;and (iii) an agreement will be signed between
AGEROUTE and the defence forces for the secondment of teams to ensure the security of the work zone
and related costs will be incorporated in the project cost.
Output 2: Socio-
economic
infrastructure and
equipment
established
Quantity of socio-
economic
infrastructure
In 2017:NA In 2022: (i) 3 motor parks/stations and a parking area
for heavy duty vehicles upgraded or rehabilitated; (ii)
150 APU and or small implements for processing
agricultural, forestry and fishery products, provided to
women’s and youth groups ; (iii) 6 market gardening areas upgraded ; (iv) 7 markets rehabilitated and /or
constructed ; (v) 1500 lm of enclosures constructed;
(vi) 10 class rooms rehabilitated and/or constructed;
(vii) 4 health centres and 4 training centres
rehabilitated, 3 medicalized ambulances delivered and
one trauma unit rehabilitated ; (viii) one equipped
weighing station constructed and; (ix) 10 portable axle scales delivered
Output 3: Training Number of people
trained and hours of
work per day
In 2017: NA In 2022: At least 300 young people trained in road
maintenance, 85,000 pers./days of direct work, of
which 35% for young people and 15% for women, at
least 5,000 temporary jobs created and at least 1,000
people sensitised
Output 4 : Studies
conducted and services provided
Number of reports
validated In 2017: NA In 2022:(i) 1PD report for related infrastructure ; (ii)
3 impact monitoring and evaluation reports; (iii) 3
accounting and financial audit reports; and (iv) 3
technical audit reports and one procurement audit
report ; (v) 8 quarterly status reports and one final
report; (vi) 3 training reports; and (vii) 3 sensitisation
reports
K E Y
A T C I V I T I E S
COMPONENTS
ix
RESULTS CHAIN
PERFORMANCE INDICATORS MEANS OF
VERIFICAT
ION
RISKS/
MITIGATION MEASURES Indicators
(including CSI) Baseline situation Target
COMPONENTS
Components
A - Rehabilitation and/or improvement of roads and rural
access roads
B – Integrated activities
C – Transport facilitation and road safety
D- Project management
INPUTS IN MILLIONS
Components In MUA In Million
Euros
Source in Million Euros
AfDB
LOAN
EU
GRANT
EIB
LOAN Gov.
A - Rehabilitation and/or improvement of roads and rural access roads 119.69 141.69 64.85 22.36 54.02 0.46
B - Integrated activities 7.86 9.31 9.31 0.00 0.00 0.00
C - Transport facilitation and road safety 1.00 1.18 1.18 0.00 0.00 0.00
D- Project Management 1.12 1.33 1.18 0.15 0.00 0.00
Physical and financial contingencies 14.36 17.00 8.48 2.49 5.98 0.05
Total inputs 144.04 170.51 85.00 25.00 60.00 0.51
x
xi
1
REPORT AND RECOMMENDATIONS OF MANAGEMENT TO THE BOARDS OF
DIRECTORS ON A PROPOSED AFDB LOAN AND AFIF GRANT TO THE REPUBLIC OF
SENEGAL TO FINANCE THE PROJECT TO REHABILITATE THE SENOBA-
ZIGUINCHOR-MPACK ROAD AND OPEN UP THE SOUTHERN REGIONS/
Management submits this report and recommendations on a proposed (i) AfDB Loan of EUR 85.00
million to Senegal; and (ii) a European Union AfIF Grant of EUR 25.00 million to the Republic of
Senegal to finance the project to rehabilitate the Sénoba-Ziguinchor-Mpack road and open up the
southern regions.
I PROJECT STRATEGIC THRUST AND RATIONALE
1.1 Project Linkages with National and Regional Strategies and Objectives
1.1.1 The project road is part of the Dakar-Lagos Trans-Africa Highway (TAH 7) corridor identified
as the backbone for the sub-region’s economic and social development. This corridor is considered to
be one of the top priorities of the Programme for Infrastructure Development in Africa (PIDA) of the
African Union (AU) and the ECOWAS Regional Transport Facilitation Programme under CWTR-
38/99. For several years, several road improvement and upgrading activities in accordance with
ECOWAS standards have been initiated on this corridor and financing is being prepared for
improvement of the missing section (Boké-Québo). Rehabilitation of the road under this project will
upgrade the road in anticipation of a significant increase in expected traffic following the commissioning
of the bridge over the Gambia River planned for 2019.
1.1.2 The project, which is consistent with the Emerging Senegal Plan (PSE) is the new reference
framework for economic and social policy over the medium-to-long term and, therefore, for the
operations of Senegal’s Technical and Financial Partners. It comprises three thrusts: (i) structural
transformation of the economy and growth; (ii) human capital, social protection and sustainable
development; and (iii) governance, institutions, peace and security. This project is included in the PSE
Priority Action Plan (2014-2018 PAP) and constitutes a key element thereof given its importance in
support to agricultural and fruit production activities and improvement of the population’s living
conditions.
1.1.3 In general, the project is in keeping with: (i) the Bank’s Development Strategy for the 2013 to
2022 period designed to improve Africa’s growth through infrastructure development, among others;
(ii) the ‘Integrate Africa’, ‘Improve the quality of life of the people of Africa’, ‘Feed Africa’ priorities
of the Bank’s Hi-5s, one of whose objectives is to remove barriers in order to take advantage of the
benefits of a large African market; (iii) Pillar 1 of the Regional Integration Strategy and Policy (RISP):
support to the development of regional infrastructure; and (iv) actions planned under the Programme
for Infrastructure Development in Africa (PIDA). Moreover, by easing access to the Southern regions
of Senegal considered to be the country’s breadbasket, the project will contribute to implementation of
the Government’s strategy (bolstering the processing of agricultural resources) by significantly reducing
the transport costs of these resources. In this respect, the project is in line with the Bank’s priorities
aimed at (i) helping to double Africa’s industrial GDP by 2025 and (ii) including employment as a
crosscutting objective of its sector interventions (Pillar 1 of the 2016-2020 Jobs for Youth in Africa)
strategy. Finally, the project is justified by its alignment with the Bank 2014-2019 Strategy for
Addressing Fragility and Building Resilience in Africa. Indeed, the drivers of fragility in Casamance
include its geographical isolation which worsens the local communities’ feeling of exclusion, the
infrastructure gap, and more specifically, the porousness of its borders and its regional involvement.
1.1.4 More specifically, the project builds on Pillar 2 of the Bank’s Country Strategy Paper (CSP)
for Senegal covering the 2016-2020 period. This CSP is focused on 2 Pillars: (i) Pillar 1: Support to
agricultural transformation; and (ii) Pillar 2: Strengthening of production and competitiveness
support infrastructure (energy and transport). The main objective of Pillar 2 is to meet the population’s
demand in terms of accessibility and mobility as well as of businesses in order to improve access to
2
transport services with a view to strengthening their competitiveness. This project is in keeping with the
CSP’s Indicative Lending Programme.
1.2 Main Development Issues
1.2.1 The southern regions of Senegal, in particular, the regions of Sédhiou and Ziguinchor are
among the country’s main areas of fragility despite their economic potential. Indeed, the conflict in
Casamance, which has lasted for over three (3) decades has caused the destruction of the region’s social
and economic infrastructure resulting in weak development of its socio-economic potential and a high
poverty rate (exceeding 60%). In May 2003, the Government of Senegal designed the Programme for
the Revival of Economic and Social Activities in Casamance (PRAESC). This programme received
support from several donors including the Bank, through the Casamance Rural Development Support
Project (PADERCA). PRAESC’s implementation did not achieve the expected results. In addition,
trade between these two regions and the country’s other regions was affected by this situation. The
internal and external isolation of these regions is one of the main obstacles.
1.2.2 Agricultural development is the main focus of the Emerging Senegal Plan (PSE) through the
Programme to Accelerate the Pace of Senegalese Agriculture (PRACAS). Casamance produces almost
everything but processes nothing. In the region there is no industrial unit worthy of the name that could
support the unemployment reduction strategy. Throughout Senegal, the level of agricultural product
processing (13.2%) remains very low which is why, every year, at least 30% of harvest is lost. In order
to reverse this trend, the Government has initiated the Programme for Integrated Agri-hubs, the first of
which should be established in Casamance in 2018. The construction of access roads under this
project should contribute to the achievement of the set objectives in this area.
1.2.3 In this context, the main drivers of fragility identified in Casamance may be summarised as
follows: (i) geographical isolation which worsens the local communities’ feelings of exclusion, (ii) the
infrastructure gap, (iii) illegal trafficking of cocaine, timber and fire-arms (iv) porousness of the
country’s borders and its regional involvement, and (v) the complexity of its natural resource
management policy.
1.2.4 Other social and demographic –related factors also play a fragility accelerator role and should
be taken into account under this project, namely (i) the different forms of gender-based violence, (ii)
land conflicts linked to the resettlement of people displaced by the conflict (iii) the youth job creation
gap and clandestine immigration, which represent a real threat to stability and are jeopardizing the
region’s peace process and economic development. The main challenge to be addressed in Casamance
is to build institutional, economic and social resilience, while reducing gender disparities, and supporting
the accelerated decentralization process, with the establishment of key infrastructure to ensure lasting and
definitive peace. The region has a wide infrastructure gap which greatly impedes the sustained and inclusive
growth of Casamance’s economy, on the one hand, and regional integration, on the other. Rural-urban
migration towards the city of Ziguinchor, in which 81% of the citizenry are concentrated, and whose
population doubled between 1976 and 2014, was not supported by corresponding investments. There
were no infrastructure investments or access to basic services, thereby limiting any development
initiatives in both urban and rural areas, and slowing down the supply of goods and services by the
government within the region. In Sédhiou, the combined unemployment and under-employment rate is
33% and at the same time, the proportion of young people either unemployed or without training is
36.8%. These situations of youth vulnerability in terms of employment is a driver of fragility and a
concern for the Senegalese authorities which have made employment a key objective of the Emerging
Senegal Plan.
1.2.5 In order to reach Dakar, the main area of product consumption and industrial processing, it is
necessary to travel 875 km via Tambacounda or 450 km through The Gambia. The Government of
Senegal has prioritized the opening up of these regions. Thus: (i) the improvement, asphalting and
rehabilitation works on the Tambacounda-Kolda-Ziguinchor road were recently completed; (ii) the
rehabilitation works on the Kaolack-Dinguiraye-Nioro road on ADF financing were recently completed;
3
(iii) the construction work on the bridge over the Gambia River on ADF financing is expected to be
completed by June 2019; and (iv) the Dakar-Ziguinchor sea link has been improved with the
commissioning of two new ships (Aguène and Diambone). Rehabilitation of the Sénoba-Ziguinchor-
Mpack road should complete the external opening up of these two regions and the related roads and
rural access roads the internal opening up.
1.2.6 The road which is the subject of this project, forms part of the Dakar-Bissau-Abidjan-Lagos
Trans-African 7 road corridor identified as the sub-region’s economic and social development
backbone. This corridor is considered to be the top priority of the Programme for Infrastructure
Development in Africa (PIDA) of the African Union (AU) and ECOWAS’s Regional Transport
Facilitation Programme. Its implementation is expected to boost intra-regional trade, especially between
Senegal and the neighbouring countries, in particular The Gambia, Guinea Bissau and Guinea.
1.3 Rationale for Bank’s Involvement
1.3.1 In the sub-region, the Bank is considered to be a strategic partner in the transport sub-sector as
a result of its different previous and current interventions. The Bank plays a major role in financing
corridor development projects in West Africa (10 regional projects since the 2000s) thereby helping to
narrow the infrastructure gap. It plays a key role in financing transport projects in Senegal and in
improving service levels on the Nouakchott-Dakar-Banjul-Bissau-Conakry-Abidjan-Lagos corridor
(construction of the Rosso Bridge over the Senegal River, rehabilitation of the Dinguiraye-Nioro-Keur-
Ayib road in Senegal, construction of the bridge over the Gambia River, improvement of the Lola-
Danané road between Guinea and Côte d’Ivoire). The Bank’s experience has facilitated the effective
mobilisation of EU co-financing of EUR 25 million for this project. By intervening in this project, the
Bank has strengthened its leadership role for regional infrastructure development on the Continent. This
project will also strengthen the Bank’s agricultural development interventions and future interventions
such as the establishment of agricultural transformation areas in order to achieve the objectives set by
the Government in terms of North, South and Centre agri-hubs.
1.4 Donor Coordination
1.4.1 The main active donors in Senegal’s transport sector are the World Bank, European Union,
Millennium Challenge Corporation (MCC), French Development Agency (AFD), BADEA, Islamic
Development Bank (IsDB), WADB and bilateral donors. Regular coordination/consultation on the
sector is carried out between the Bank and these TFPs. Through its country office (COSN), the Bank
is an active member of the Extended Group of Technical and Financial Partners (or Group of 50) and
of several thematic groups. In particular, since 2011, the Bank is the Vice-chair of four thematic groups.
In Senegal, there is no formal thematic group on transport but periodic meetings and exchanges take
place between the TFPs involved in the sector. For this project, it was agreed with the potential donors
(EU and EIB) to regularly exchange information on the sector and to carry out joint missions as part of
its preparation and the monitoring of its implementation.
1.4.2 During the project’s implementation, this coordination will continue with (i) the participation
of experts from Headquarters and the Bank’s representation in the country in working meetings of TFPs
operating in the sector (ii) the different joint supervision missions and (iii) the involvement of
stakeholders in the approval of reports produced on the different studies planned.
4
II PROJECT DESCRIPTION
2.1 Project Objectives and Components
2.1.1 The project’s strategic objective is to help strengthen sub-regional integration and trade and
reduce food production losses in the primary sector as a consequence of the opening up of Senegal’s
southern regions.
2.1.2 More specifically, the project will help to: (i) improve the service level on the Sénoba-
Ziguinchor-Mpack- Guinea Bissau border road by reducing general transport costs, customs
checkpoints and the time taken to provide care for victims of road accidents; (ii) build agricultural
product processing capacity; and (iii) improve access and living conditions in the Project Direct Area
of Influence (PDAI). In order to achieve these objectives, the project is focused on activities broken
down into four components summarised in the following Table.
Table II.1
Project components
Component name Cost in
MUA Description
A - Rehabilitation
and/or improvement of
roads and rural feeder
roads
132.95
(i) Rehabilitation of 165 km of road between Sénoba and Mpack in asphalt concrete
including 13km of roads surfaced with paving stones in Bounkiling, Bignona and
Ziguinchor and a parking area for heavy duty vehicles in Ziguinchor, green areas and
support to ensure security of the area during works implementation; (ii) improvement
and asphalting of 52 km of the Kalounayes loop including 1 km of urban roads surfaced
with paving stones in Coubanao; (iii) improvement of 100 km of rural feeder roads;
(iv) works control and supervision; (v) sensitisation on HIV/AIDS, nutrition, social
mobilisation, environmental protection and road safety; (vi) planting of 33,000 trees;
(vii) construction of a weighing station; (ix) inclusion in contracts and agreements of
the employment of young engineers or technicians on internships; and (viii) clearing
of rights-of-way and monitoring of ESMP implementation.
B – Integrated activities 8.73
(i) Improvement and/or rehabilitation of social and commercial infrastructure (10 class
rooms including school canteens, 4 health centres and 4 training centres, 7 markets, 4
motor parks, 1 parking area for heavy duty vehicles, 6 market gardening areas, 1500
lm of enclosures; (ii) support to youth and women’s associations with the supply of
150 APUs and/or small tools for processing agricultural, forestry and fishery products;
(iii) support to improve youth employability through youth work training programmes
and rehabilitation/equipping of an agricultural or BPW training centre; (iv) control and
supervision of integrated works including support for the introduction of integrated
activities; (v) detailed designs and BDs for integrated activities and (vi) a study on the
comprehensive assessment of the drivers of fragility and opportunities for resilience
in the southern regions.
C – Transport
facilitation and road
safety 1.11
(i) Support for the Observatory on Abnormal Practices (OPA); (ii) road safety support
by providing resources for the rapid treatment of victims of road accidents 3
medicalized ambulances and a rehabilitated trauma centre; (iii) support for axle-load
control through the purchase of 10 portable axle scales.
D- Project management 125
(i) Monitoring and evaluation of socio-economic impacts and project facilitation; (ii)
technical and road safety audit; (iii) accounting and financial audit; (iv) procurement
audit; (v) communication; and (vi) operation of executing agency.
2.2 Technical Solution Retained and Other Alternatives Explored
2.2.1 The Sénoba – Ziguinchor – Mpack road section is a paved road with a pavement width of
between 6 and 7 m and 1.5 metre wide shoulders. The existing pavement has never over time been the
subject of major strengthening or recharging works. The technical solution retained for the road’s
rehabilitation is the widening of the platform at certain points to bring it into line with certain ECOWAS
standards (10.2 m platform width, 7.20 m pavement width, 2 x 1.5 width of shoulders and 80 km/hour
reference speed). The pavement structure will comprise a foundation layer obtained by scarification of
5
the existing pavement and possibly adding laterite for upgrading and compacting to OPM standard, a
23-cm thick base layer of cement-treated laterite, an 8-cm thick bond coating of crushed stone across
the entire width and a 5-cm thick wearing course in 0/14 asphalt concrete (AC). For the 7 km located in
the Tobor marshland, the structure comprises a 2-layer backfill of 25 cm of untreated natural gravel, 10
cm of interlocking pavers for the coating, but this solution could be improved because of the expertise
of the contractor retained to carry out the works. It is worth noting that the 105 hydraulic structures and
the canal in Ziguinchor identified on the Sénoba-Ziguinchor-Mpack section are in fairly good condition
and will be retained. Extensions to the heads of some structures could become necessary in areas where road
widening is being carried out.
2.2.2 The alternative technical solution and the reasons for its rejection are summarised in Table 2.2
below.
Table II.2
Alternative solution explored and reasons for rejection Alternative
solution Brief description Reason for rejection
A pavement
structure
without paved
stone.
In addition to the characteristics
of the platform and the
foundations which are similar to
the solution retained, the
structure of the alternative
solution comprises a 25-cm thick
base course of cement-treated
laterite and a 6-cm thick wearing
course of 0/14 asphalt concrete
(AC).
The pavement body is considered to be less durable than that of the
solution retained. First signs of degradation (cracking of the
improved cement laterite gravel layer) appears only 4 years after
works completion. If in addition, measures are not taken to enforce
axle load controls such degradation could accelerate more rapidly.
This solution is not consistent with the preventive road maintenance
strategy developed by the project owner on the main roads of the
classified network (no refill before 7 to 8 years on a new road or a
fully rehabilitated road).
2.2.3 The diversity of the planned activities reflects the integrated nature of this road project. Indeed,
in addition to the roadworks, related improvements are planned in order to strengthen its socio-economic
impacts. These improvements concern the following sectors: agriculture, water, gender, social
protection and vulnerability, basic health and education and vocational training, as well as support to
youth employability. Special emphasis has been placed on support to actions in favour of women.
2.3 Project Type
2.3.1 This is a national stand-alone investment operation. Donors’ interventions in transport
infrastructure in Senegal are usually made through this type of investment (investment project. The
funds allocated to the project will be disbursed for clearly defined and specific investments. Thus the
project has adopted the most suitable approach for the Bank’s intervention in this project.
2.4 Estimated Project Costs
2.4.1 The total project cost excluding taxes and custom duties, including physical and financial
contingencies, is estimated at 144.04 million Units of Account (MUA), equivalent to EUR 170.51
million at an exchange rate of UA1 = 𝐸𝑈𝑅1.184. Provisions for physical contingencies represent 9.00%
of the base cost while the provision for financial contingencies equals 0.98% of the base cost and the
provision for physical contingencies.
6
Table II.3
Estimated costs by component of the entire project
COMPONENTS
Million CFAF Million UA Million Euros
F.E. L.C. Total F.E. L.C. Total F.E, L.C. Total
A - Rehabilitation and/or
improvement of roads and rural
feeder roads
74 112.37 18 828.09 92 940.46 95.44 24.25 119.69 112.98 28.70 141.69
B – Integrated activities 4 883.74 1 220.93 6 104.67 6.29 1.57 7.86 7.45 1.86 9.31
C –Transport facilitation and
road safety 620.00 155.00 775.00 0.80 0.20 1.00 0.95 0.24 1.18
D- Project management 268.00 604.92 872.92 0.35 0.78 1.12 0.41 0.92 1.33
Base cost 79 884.11 20 808.95 100 693.05 102.88 26.80 129.67 121.78 31.72 153.51
Physical contingencies 7 988.41 2 080.89 10 069.31 10.29 2.68 12.97 12.18 3.17 15.35
Price escalation 859.65 223.93 1 083.58 1.11 0.29 1.40 1.31 0.34 1.65
TOTAL COST 88 732.16 23 113.77 111 845.93 114.27 29.77 144.04 135.27 35.24 170.51
Table II.4
Costs by Expenditure Category of the Entire Project
EXPENDITURE CATEGORIES Million UA Million Euros
% F.E. L.C. Total F.E. L.C. Total
A –Works 96.80 24.20 121.00 114.59 28.65 143.23 84.00%
B – Services 5.95 1.75 7.70 7.05 2.07 9.12 5.35%
C – Other 0.12 0.85 0.97 0.15 1.01 1.15 0.68%
BASE COST 102.88 26.80 129.67 121.78 31.72 153.51 90.03%
Physical Contingencies 10.29 2.68 12.97 12.18 3.17 15.35 9.00%
Financial Contingencies 1.11 0.29 1.40 1.31 0.34 1.65 0.97%
TOTAL COST 114.27 29.77 144.04 135.27 35.24 170.51 100.00%
2.5 Financing Arrangements
2.5.1 Following the joint project appraisal mission and working sessions between donors, it emerged
that, in view of the conditions of eligibility for AfDB financing and the possibility for AfDB to use the
national procurement system, parallel financing with EIB was retained. The road works including rural
access roads and urban roads were broken down into 4 lots: (i) lot 1: Sénoba-PK40 and lot 2: PK 40-
PK80 on AfDB and EU financing; (ii) lot 3: PK80-Ziguinchor-Mpack on EIB financing; and (iii) lot 4
concerning the 52 km of the Kalounayes loop on AfDB financing. Works control and supervision will
be broken down into three lots: (i) lot 1, financed by AfDB and EU for the supervision of works under
lots 1 and 2; (ii) lot 2 financed by EIB for the supervision of lot 3 works; and (iii) lot 3 financed by
AfDB for the supervision of the works on the Kalounayes loop. In order to take into consideration EIB’s
concerns a provision will be included in the contract of the lots control mission for the NR4 works to
be financed by AfDB requiring the contracting party to directly respond to all requests from the EIB.
2.5.2 The project will be jointly financed by the Bank (AfDB Loan), the EU through a grant from
the resources of the African Investment Facility (AfIF), the Government of Senegal, and at the same
time with the European Investment Bank (EIB). The Bank’s contribution is UA 71.80 million, i.e. EUR
85.00 million. The EU contribution is UA 21.12 million, i.e. EUR 25.00 million and the EIB
contribution is UA 50.66 million, i.e. EUR 60.00 million. The Senegalese counterpart is UA 0.43
million, i.e. EUR 0.5 million. The ADB window’s contribution is below 50% of the project cost.
The submission of the EIB financing agreement to the Bank will be required as an undertaking by the
Republic of Senegal.
2.5.3 Tables 2.5 and 2.6 below set out the detailed costs by source of financing and provide a
summary of the financing plan.
7
Table II.5
Source of financing for the entire project
SOURCES Million CFAF Million UA Million Euros
% F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total
AfDB LOAN 44 159.08 11 597.28 55 756.37 56.87 14.94 71.80 67.32 17.68 85.00 49.85%
EU 13 087.15 3 311.77 16 398.92 16.85 4.26 21.12 19.95 5.05 25.00 14.66%
EIB 31 485.94 7 871.48 39 357.42 40.55 10.14 50.68 48.00 12.00 60.00 35.19%
GOV. 0.00 333.23 333.23 0.00 0.43 0.43 0.00 0.51 0.51 0.30%
Project total 88 732.16 23 113.77 111 845.93 114.27 29.77 144.04 135.27 35.24 170.51 100.00%
Table II.6
Source of financing by component of the Entire Project
Components In MUA In million
Euros
Source in million Euros
AfDB LOAN EU GRANT EIB LOAN Gov
A – Rehabilitation and/or improvement of roads and rural access roads
119.69 141..69 64.85 22.36 54.02 0.46
B – Integrated activities 7.86 9..31 9..31 0.00 0.00 0.00
C – Transport facilitation and road safety 1.00 1..18 1..18 0.00 0.00 0.00
D-Project management 1.12 1..33 1.18 0.15 0.00 0.00
Physical and financial contingencies 14.36 17.00 8.48 2.49 5.98 0.05
Total resources 144.04 170.51 85.00 25.00 60.00 0.51
Table II.7
Expenditure Schedule by Component for the Entire Project (in million UA)
Components 2018 2019 2020 2021 Total
A - Rehabilitation and/or improvement of Roads
and Rural access roads 17.87 .344 53.76 4.61 119.69
B – Integrated activities 0.00 2.41 3.50 1.95 7.86
C – Transport facilitation and road safety 0.17 0.37 043 0.03 1.00
D- Project management 0.22 0,28 0.38 0.24 1.12
Base cost 18.26 46.50 58.07 6.84 129.67
Physical contingencies 1.83 465 5.81 0.68 12.97
Price escalation 0.20 0.50 0.62 0.07 1.40
Total 20.29 51.65 64.50 7.59 144.04
Table II.8
Expenditure schedule by source of financing for the entire project (in million UA)
Source 2018 2019 2020 2021 Total
AfDB LOAN 9.47 27.60 32.02 2.71 71.80
EU GRANT 3.15 8.43 9.48 0.05 21.12
EIB LOAN 7.60 15.45 22.81 4.83 50.68
Gov. of. SENEGAL 0.06 0.17 0.19 0.00 0.43
Project Total 20.29 51.65 64.50 7.59 144.04
Total as % 14.08% 35.86% 44.78% 5.27% 100%
Table II.9
Expenditure schedule by expenditure category for the entire project (in million UA)
Categories 2018 2019 2020 2021 Total
A – Works 19.05 48.19 60.48 6.68 134.40
B – Consulting services 1.09 2.97 3.77 0.72 8.56
C- Other 0.15 0.49 0.25 0.19 1.08
TOTAL 20.29 51.65 64.50 7.59 144.04
8
2.5.4 With regard to the provisions relating to financing of the Africa Investment Facility (AfIF), on
12 July 2017, the Boards approved (Resolution No. B/BD/2017/124 - F/BD/2017/87), the cooperation
framework between the European Commission (EC) and the Bank, called ‘Pillar-assessed grant of
delegation agreement’ (PAGODA)’. In this context, the Bank and European Commission, on 5
December 2017, signed a Delegation Agreement for an amount of EUR 25.600 million relating to the
project (including an amount of EUR 600,000 owed to the Bank in respect of management and
administration costs). This Delegation Agreement defines the activities entrusted to the Bank for project
implementation. It determines the implementation arrangements, sets out the rules governing payment
of the EU contribution and defines the relations between the Bank and EC. The resources thus mobilised
from AfIF will be disbursed and managed by the Bank. The AfIF resources approved on 24 February
2017 are not allocated but some indications are given (see Appendix VI for further details).
Table II.10
AfDB and EU financing by expenditure category AfDB Loan EU Grant
EXPENDITURE
CATEGORIES
Million Euros
F.E. L.C. Total
B –Works 57.62 14.41 72.03
C – Services 2.84 0.96 3.80
D – Other 0.15 0.55 0.70
BASE COST 60.61 15.92 76.52
Physical
contingencies 6.06 1.59 7.65
Financial
contingencies 0.65 0.17 0.82
TOTAL COST 67.32 17.68 85.00
EXPENDITURE
CATEGORIES
Million Euros
F.E. L.C. Total
B –Works 15.81 3.95 19.76
C – Services 2.15 0.59 2.75
D – Other 0.00 0.00 0.00
BASE COST 17.96 4.55 22.51
Physical contingencies 1.80 0.45 2.25
Financial contingencies 0.19 0.05 0.24
TOTAL COST 19.95 5.05 25.00
2.6 Project Target Area and Beneficiaries
2.6.1 The roads targeted under the project are located in the Sédhiou and Ziguinchor regions,
especially the Departments of Bounkiling, Bignona and Ziguinchor. These three Departments constitute
the Project Direct Area of Influence (PDAI). However, since this road section is part of the Dakar-Lagos
Trans-African 7 road corridor, the Project Extended Area of Influence (PEAI) covers the regions of
Dakar, Thies, Kaolack in Senegal, the Gambia and Guinea Bissau. The PDAI covers an area of 9277.38
km2, i.e. 4.72% of the country’s area and, in 2016, had an estimated population of 666,551 people, i.e.
almost 4.50% of the country’s population. The proportion of women in the PDAI is 48.79%. The
proportion of the population living in rural areas represents 57/74%. The structure by age group shows
that, in the PDAI, the proportion of 15-35 year-olds commonly known as ‘youth’ is 67.50%. The
incidence of poverty in the PDAI (67.55%) is above the national average (46.70%). The PDAI’s
economy is mainly agriculture-oriented.
2.6.2 The PDIA has several types of soils suitable for agriculture. Through its wealth in forestry
resources, its agricultural production, its livestock and tourism potential, it is often considered as
Senegal’s breadbasket. Average annual rainfall is around 1,000 mm. Over 4/5 of households practise
agriculture. The dominant crops are groundnuts, millet and rice. Forest exploitation and tree- growing,
in particular, fruit trees, provide an alternative source of income for the populations. In addition, there
are abundant fishery resources (oysters, shrimps and fish) and other agricultural products such as cashew
nuts, the production of which is steadily rising. Industrial–scale cultivation which concerns the plant
species grown in order to supply processing industries with raw materials, including in the agro-food
sector (groundnuts for oil, sesame, hibiscus and cassava) has experienced contrasting performances
(72.6% drop for sesame and 87.2% for cassava and a 41.5% increase for groundnuts). Remoteness is
one of the obstacles to increased production and the competitiveness of industrial processing units.
9
2.7 Participatory Process for Project Identification, Design and Implementation.
2.7.1 The involvement of all stakeholders was a concern at every stage of this project’s appraisal.
Indeed, as part of the studies and preparation of this project, plenary information and consultation
sessions were held throughout the project’s direct area of influence, with the authorities and centralised
and devolved administrative and technical services, road hauliers, business operators and the
populations. Similarly, as part of updating of the ESIA and RAPs, public consultations were held. These
working sessions helped to gather and incorporate in the project design, the main needs and expectations
of the population and key stakeholders. The Bank’s project preparation and appraisal missions held
working sessions with all the stakeholders in the PDAI that were grouped together in Bounkiling, then
Bignona, Coubanao and Ziguinchor. This approach will be continued during this project’s
implementation. To this end, a budget allocation has been made for the conduct and implementation of
consultation activities for the implementation of the ESMP and RAPs.
2.8 Bank Group’s Experience and Lessons Reflected in Project Design
2.8.1 As at 30/04/2018, the Bank’s active public sector portfolio in Senegal included twenty-two
(22) operations, representing total net commitments of UA 54 million. The public sector portfolio
comprised four (4) multinational projects representing a cumulative amount of UA 75.43 million. The
overall disbursement rate for public sector operations is 20.50%. The respective disbursement rates for
national projects are 20.62% and 19.52%, for the multinational operations. The sector distribution of
national projects is presented as follows: transport & ICT 70.31%; water and sanitation 13.31%; rural
sector 11.55%; and social sector 4.05%; and governance 0.78%. For their part, multinational operations
are dominated by the energy sector followed by the transport and ICT sectors, 85.84%. As regards the
Bank’s private sector window in Senegal, total commitments represent about UA 130.32 million and
concern five (5) operations. The private sector window disbursement rate is 96.36%. The performance
of the Bank’s national public sector portfolio in Senegal is considered to be satisfactory: (i) the portfolio
has been greatly rejuvenated in recent years. The average age of operations fell from 5.5 years in 2011
to 3.47 years in 2018; (ii) the portfolio does not contain any problem project (PP) or potentially
problematic project (PPP). The ongoing transport sector portfolio comprises 4 national projects
and 2 multinational projects. For these 6 operations, the conditions precedent to first
disbursement have been fulfilled, commitments total about UA 385.62 million, the average age is
2.66 years and the average disbursement rate is 14.45%.
2.8.2 Project completion and supervision reports for Senegal are regularly prepared and lessons
learned. The main lessons learned from project implementation in the sector are : (i) the need to have
high quality PDs in order to enhance project quality at entry; (ii) the need to adhere to procurement
project implementation and audit preparation dates in order to prevent additional costs and the risk of
suspension of disbursements; and (iii) the failure to carry out impact monitoring and evaluation
activities and monitor them following project completion prevents any assessment of the impact of the
Bank’s operations on the country’s development. Furthermore, in the report prepared by IDEV on the
evaluation of the Bank Group’s Strategies and Programmes in Senegal over the 2004-2013 period, it is
recommended to safeguard and guarantee the autonomy of the resources of the Road Maintenance Fund
(FERA) in order to ensure infrastructure sustainability. These lessons were taken into consideration
under this project by the fact that: (i) PDs were prepared and individual consultants will be recruited to
review them before the programme appraisal mission : (ii) procurement deadlines will be shortened
as the national procurement system will be used for a large part of the activities planned under
this project; (iii) the project includes the cost of impact monitoring and evaluation services;
AGEROUTE has a unit responsible for carrying out continuing monitoring of the project impacts; and
(iv) guaranteeing FERA resources will be loan condition for this project.
10
2.9 Key Performance Indicators
2.9.1 The key performance indicators identified and expected outcomes at project completion which
appear in the results-based logical framework are grouped together as follows (i) trend in volume of
trade between Senegal and Guinea–Bissau and agricultural production losses; (ii) general transport
costs (VOC and time), trend of average annual daily traffic (AADT) on the project road sections,
reduction in the number of checkpoints and time required for customs control and reduction in the time
taken to provide care for victims of road accidents; (iii) the percentage of agricultural output lost as a
result of inaccessibility; (iv) the Rural Access Index, i.e. the percentage of the population within a radius
of 2 km of a passable road; and (v) yield of activities of women’s groupings; and vi) the number of jobs
created. The exact values of different impact indicators retained for this project will be established at
the baseline situation prior to works commencement) and an assessment will be carried out by the
service provider at mid-term and at project completion.
2.9.2 In addition to these outcome and output indicators which appear in the logical framework, there
are also project implementation performance indicators that will be monitored. They were selected on
the basis of the Bank’s corporate performance indicators. These mainly concern: (i) the time required
for effectiveness and fulfilment of the conditions precedent to first disbursement; (ii) procurement
timeframes; (iii) the average project IP indicator; and (iv) the disbursement rate trend on the basis of
the expenditure schedule. These indicators will be monitored during supervision missions and in the
project’s routine management.
III PROJECT FEASIBILITY
3.1 Economic and Financial Performance
3.1.1 The socio-economic study update report covers the Sénoba-Ziguinchor-Mpack road and the
Kalounayes loop. On the Sénoba-Ziguinchor road, according to 2015 traffic count data, the average
annual daily traffic (AADT) varies from 300 veh/d and 568veh/d depending on the sections, i.e. an
average of 438 veh/d.
3.1.2 In order to carry out the economic analysis, the following factors were taken into consideration:
(i) a 20-year analysis period, a residual value of 60% and a traffic growth rate of 4% for passenger traffic
and 5% for freight traffic; and (ii) investments and maintenance costs before and after the project
(periodic maintenance triggered on the basis of the IRI. The value of agricultural losses of 20% of
production in the PAI due to transportation difficulties of movement have been taken into consideration.
The economic analysis was carried out using the HDM model. Brought closer by the surpluses achieved
from vehicle operating cost savings and in passenger and goods travel times, a rate of return (EIRR) of
28.7% was obtained and the sensitivity analysis (+ or – 20% of costs and traffic) gave an EIRR that
varies between 28.7% and 21.6%. These rates are higher than the opportunity cost of capital which is
12%. The project is, therefore, economically viable. The Table below summarises the projects economic
analysis. The detailed analysis is provided in Technical annexes to this report.
Table III.1
Economic analysis summary
Economic parameters analysed Basic
assumptions
Sensitivity analysis
Assumption (-
20% of traffic)
Assumption (+
20% investment
cost.)
Assumption (-20% of
traffic and + 20% of
investment cost.)
Economic rate of return (ERR) 28.70% 24.70% 25.30% 21.60%
Net Present Value (NPV) in billion CFAF 125.51 89.83 112.46 76.77
11
Transport Facilitation
3.1.3 The financing request submitted to the Bank included the construction and equipping of the
juxtaposed border control post (JBCP) at Mpack located on the border with Guinea Bissau. WAEMU
indicated that it had signed a concession contract with a private firm for the construction and
management of the Mpack JBCP (see draft convention in annex). The construction of the JBCP is not
included in the cost of this project. AGEROUTE will contact WAEMU to obtain the JBCP
implementation schedule.
3.1.4 During the field visit it was noted that on the Dakar-Kaolack-Sénoba-Ziguinchor-Mpack
corridor, there were several checkpoints (customs, police, gendarmerie and forestry) and security-
related checkpoints. The activities of the Observatory of Abnormal Practices (OPA) on the corridors
managed by the Road Transport Directorate (DTR) only cover the Dakar-Kaolack section. The project
will provide support for the OPA to include among its activities monitoring of the entire Dakar-Mpack-
Bissau-Québo-Guinea Bissau border corridor to regularly determine the trend of transport facilitation
monitoring indicators.
3.2 Environmental and Social Impacts
Environment
3.2.1 In accordance with the requirements of the Bank’s Integrated Safeguards System (ISS), the
project is classified in category 1 because of its size (over 50 km), and the potential impact on the
sensitive ecosystems along the right-of-way (classified forests and mangroves). A detailed
environmental and social impact assessment has been carried out. The ESIA of the Sénoba-Ziguichor
section culminated in the award of a DEEC certificate of compliance issued on 21 September 2016.
This assessment was attuned to the Bank’s requirements following the preparation mission. The
environmental management measures concerning the Ziguinchor-Mpack section were integrated when
the assessment was updated and the related costs included in the ESMP. Since the asphalting of the
Kalounayes loop section was included in the project following the preparation mission, the ESIA
previously prepared by AGEROUTE was updated and submitted to DEEC. This ESIA received
environmental clearance on 23 February 2018. An abbreviated Resettlement Action Plan (ARAP) was
also prepared under the project. The ESIA for the entire project as well as the ARAP were published on
the Bank’s website on 26 February 2018.
3.2.2 Positive Environmental and Social Impacts. During the works phase, the positive impacts
will concern the creation of temporary jobs and increase in commercial activity in the regions crossed
by the project (about 85,000 work hours per day during the project and the creation of jobs with 35%
for under-35 year old youths and 15% for women.) In the project road operational phase, it is expected
that at least 400 jobs will be induced as a result of (i) higher penetration among the local communities
of government or non-governmental programmes concerning, in particular, water supply, public health,
and education; (ii) the many types of positive socio-economic fallouts with local and regional or even
national reach and improved trade between the different Departments of Ziguinchor and Sédhiou and
the capital, Dakar and, on a wider scale, with The Gambia and Guinea Bissau. In addition, people living
close to the paved roads and related rural access roads will benefit from faster and less expensive access
to social and health facilities: schools, health posts and hospitals, administrative buildings, as well as to
places for commercial transactions such as daily or weekly markets (loumas) and shops. Furthermore,
the project will contribute to increased marketing of agricultural and fishery production and tourism in
the regions of Ziguinchor and Sédhiou, in particular, through the establishment of storage and
processing techniques. Finally, the construction of enclosures and health facilities, especially for the
schools along the road, will impact positively on children’s security, hygiene and health. Enhancement
measures are included in the project, on the basis of concerns and wishes of the communities consulted.
The related projects were identified, prepared and finalized during the project’s appraisal. They mainly
concerned the construction of community infrastructure such as feeder or access roads, the rehabilitation
and construction of school enclosures, training and health centres and markets, as well as the
12
construction or relocation of motor parks. The total amount allocated to these related facilities is CFAF
6.78 billion, i.e. 6.06% of the total project cost.
3.2.3 Negative Environmental and Social Impacts. The main environmental impacts caused by
the project will be: (i) modification of the soil structure by subsidence on a fairly wide strip of about
20m on either side of the roads and rural feeder roads and the erosion of stripped surface areas in the
borrow areas; (ii) chemical pollution of soil and water by waste products and potential spillage of
chemical products (iii) air pollution from the movement of site machinery, in particular, the opening of
borrow pits and diversions, slashing and clearing of the right-of-way, living quarters and emissions
from the asphalt plant (iv) noise pollution from the site machinery. The biological impacts mainly
concern the destruction of vegetation due to diversions and borrow areas, but also the rehabilitation of
urban roads. The destruction of vegetation will impact on wildlife and wildlife habitats. On the social
front, the project will result in: (i) the displacement of 177 people currently settled along the road right-
of-way and engaged in commercial activities at the entrances to the towns of Bounkiling, Bignona and
Mpack; (ii) the project will also have an impact on the local population’s well-being and quality of life
since people will be exposed to site nuisances; (iii) the influx of workers could increase the risk of
sexually transmitted diseases such as HIV/AIDS which already has a worrisome prevalence rate in the
project area; (iii) the works will also affect the movements and security of people due to the movement
of site machinery and excavation required for the urban roads and borrow areas; and (iv) lastly, potential
conflicts could break out between site workers and local communities.
3.2.4 Environmental and Social Management Plan (ESMP). In order to control the negative
environmental impacts, mitigation and compensation measures have been prepared. An ESMP was
prepared summarising the recommended mitigation measures, monitoring indicators, monitoring
responsibilities, supervision and control as well as the implementation schedule for the measures.
Environmental supervision will be carried out by the Control Bureau of AGEROUTE’s Management
Unit. The regional division of the Environment and Classified Establishments Directorate (DREEC)
and the Regional Environmental Monitoring Committee (CRSE) will be responsible for monitoring. A
memorandum of understanding will be signed to that effect with DEEC. The cost of the ESMP is CFAF
2.7 billion excluding the ARAP; this cost will be borne by the project.
Resettlement
3.2.5 The abbreviated resettlement plan summary was (ARAP) was published on the Bank’s website
on 26 February 2018 at the same time as the ESIA summary in compliance with the Bank’s requirements
and after approval by DEEC and issuance of an environmental compliance certificate. However,
following claims, the ARAP approval process was resumed between 20 and 23 March and evidence of
this approval was submitted to the Bank. This led to an update of the number of PAP. Thus, the number
of affected people rose from 145 to 177 broken down as follows: 62 people in Bounkilling Department,
101 people in Bignona Department and 14 people in Ziguinchor Department. The PAPs are chiefly petty
traders and owners of 4 small stalls. The estimated budget for the resettlement, including livelihood
restoration measures is CFAF 319,434,500. The construction of new markets and associated budget for
the displacement of PAPs is included under related works. The construction of this infrastructure and
the displacement of PAPs will be carried out prior to commencement of works on the road sections
concerned. In the case of the Kalounayes loop, the works could affect the enclosures, plantations and
fields. A provision of CFAF 300 million is planned under the ESMP to cover damage during the works
including quarries and diversions, for the entire project. An environmental and social development
specialist will be recruited by AGEROUTE to monitor compensation before and during the works. The
Government has given its commitment to:(i) implement the project and have it implemented by
contractors in accordance with the rules and procedures of the Bank, under national law and the
recommendations, provisions and procedures contained in the project’s Environmental and Social
Management Plan (ESMP); and (ii) provide half-yearly reports on the implementation of the ESMP and
ARAP, including, as necessary, weaknesses and corrective actions taken or to be taken.
13
Climate Change
3.2.6 The project has been classified in climate category 2 according to the Bank’s CCS since it
shows sensitivity to the impacts of climate fluctuations, namely floods and wind deposits of sand. It is
anticipated that there will be an increase in greenhouse gas emissions such as CO2, mainly due to
increased traffic and deforestation during the works. Also, the planting of 65,000 roadside trees and 30
ha of mangroves have been planned as compensatory measures but also with a view to mitigating the
aforementioned emissions. A reforestation plan will be required for contractors that bid and the NGOs
responsible for the plantation and long-term monitoring. The latter will work under the control of the
competent authorities of the Forestry Department with which a memorandum of understanding will be
signed. The cost of restoring vegetation and its monitoring is estimated to be CFAF 692 million and
will be included in the works’ contracts.
Gender
3.2.7 As regards gender, in 2015, the Government of Senegal adopted a National Strategy for Gender
Equality and Equity (SNEEG). Through this strategy, it intends to make gender equality one of the
pillars for boosting economic development. In 2017, this strategy was revisited (SNEEG2) in order to
anchor it in the PSE. The socio-economic situation of women remains precarious with wide disparities
in several areas. Despite their significant contribution to the agriculture sector and trade, women are
faced with discrimination in access to productive resources (access to credit, land, etc.) thereby limiting
their productivity.
3.2.8 The project is classified in Category II according to the Gender Marker System. Difficulties
of access to the project area highlight this imbalance of disparities. Women represent 48.79% of the
PDAI’s total population. They will be the main beneficiaries of this project due to the : (i) facilitation
of access for transporting their produce with the related improvements to rural access roads; (ii) the
reduction of distances for the drudgery of fetching water as a result of boreholes and (iii) development
of wetlands for market gardening, support in terms of small agricultural implements to increase yields
and the processing of agricultural and fishery products, conservation, construction of market sheds for
marketing as well as training to build their organisational capacities in order to more effectively
participate in negotiations on the selling prices of their produce.
Support to Youth Employability
3.2.9 The Senegalese labour market is characterized by the vulnerability of women faced with
unemployment and under-employment. At the national level the combined unemployment and under-
employment rate is 26% for adults and 31% for youths. In the Ziguinchor region, it is noted that this
combined rate for youths is 26%, an average which is below that observed at the national level. Rural-
urban migration of young people explains this low rate. Indeed, the analysis of the age pyramid shows
a drop in the number of young people from 15 years old in this region with the number of 15-19 year-
olds dropping from 38 000 to 30 000 among 20 to 24 year-olds and to 22,000 for the 25-39 year-olds
(RGPHAE). In the region of Sédhiou, there is a high unemployment and under-employment rate of
33%, coupled with a high poverty rate of 63.8%. The situation of young people is also marked by a high
rate of idleness i.e. the proportion of young people who are neither in employment, nor in training, nor
unemployed a rate which is 36.8% (compared with 4% in Ziguinchor). This population is often
considered to be a population at risk. In the region of Ziguinchor it only represented 4%
3.2.10 These situations of youth vulnerability in terms of employment are a concern for the Senegalese
authorities who have made employment a major objective of the Emerging Senegal Plan. The Bank in
2016 adopted the 2016-2020 Jobs for Youth in Africa Strategy which involves under Pillar II the
mainstreaming of employment in all the Bank’s sector operations. The BPW sector which absorbs a
high proportion of Senegal’s investment budgets should, therefore, participate strongly towards the
achievement of this strategy’s objectives.
14
3.2.11 The project’s implementation will have a significant impact in terms of direct and indirect job
creation. The planned monitoring and evaluation system will make it possible to exactly measure the scale.
However, on the basis of the experience gained from other projects of the Bank’s Transport Department,
there are plans to create at least 85,000 pers/days of direct jobs (of which 35% for young people under
35 years old and 15% for women).
3.2.12 In addition to these jobs inherent in the works, the project provides for actions to improve the
employability of young unemployed engineers and senior technicians. Indeed, in the works control
contracts, provision will be made for covering the cost of job training for young people over the works
implementation period (24 months). These young people will be placed on the project sites with
contractors (10 per contract) and consulting firms for works control (03 per contract). This would make
62 young people at least 30% of whom would be women. They will be integrated in the teams of
contractors and control missions in order to familiarise themselves with management of large-scale
works. They will be required to produce a quarterly report in which they will indicate the activities in
which they have participated over the period. These reports, approved by the contractor or control
mission, depending on the case will be submitted to the executing agency. On completion of the works,
the engineers trained could either join the administration, or be recruited to large enterprise or consulting
firms or become self-employed. In any event, the experience acquired could help them to join
professional circles. In the bidding documents and requests for proposals bidders will be required
to indicate the method for supervising young people during works implementation and supporting
them after works completion.
3.2.13 The project will also extend the experiment which is being conducted through the vocational
training programme for at least 500 young people from the regions of Ziguinchor, Sédhiou and possibly
Kolda in the BPW (for all trades), agricultural (market gardening, agricultural product processing,,
poultry farming, etc.) services (catering and sewing, tourism etc.). This training in particular targets
young school drop-outs or those who have never been enrolled in school or displaced youth or those
with reduced mobility as a result of the armed rebellion. Following the training, craft kits will be given
to them to make them more operational and supportive action provided (training in the management of
activities, support to business/EIG start-ups and financing of micro-enterprises. The works on
constructing access roads with pavers will provide an opportunity for young people using a labour-
intensive works approach with apprenticeship training linked to a training centre in the project area.
3.2.14 The project has also identified support to a training centre in the isolated region of the
Kalounayes loop which allows this centre to expand the availability of its training to promising trades
in the territory (agriculture, agricultural processing, BPW, etc.). The diversification of training methods
makes it possible to enrol a significant number of young people (600 instead of 100 at present) while
anchoring training on the needs identified by enterprises and producer organisations in the area.
Sensitisation Campaigns on HIV/AIDS, Nutrition, Environmental Protection and Road
Safety
3.2.15 The project includes actions aimed at raising incomes and improving health coverage as well
as the well-being of the population, in particular vulnerable people including women and children in the
PFAI. These will, among others: (i) improve production in rural areas; (ii) reduce gender-related
inequalities; (ii) promote women’s literacy education, especially in rural areas; (iii) alleviate the burden
of women’s domestic chores; (iv) strengthen the promotion and diversification of economic and income-
generating activities in favour of women in production, processing and marketing in the value chain of
growth-bearing agricultural subsectors; and (iv) build the population’s adaptation and resilience
capacities in the PDAI by strengthening the role of women in the prevention and management of illness-
related risks, etc.
3.2.16 There are plans to conduct sensitisation campaigns on environmental protection, nutrition, road
safety and on sexually transmitted disease prevention. To that end, specialised NGOs in that area will
be recruited to carry out local proximity work. More specific themes will be agreed upon during the
15
implementation of this sub-component, in liaison with these NGOs, specialised structures, the technical
Ministries concerned as well as with the project team. They will be able to cover communication for
behaviour change (CBC) aspects as well as those linked to the transmission of practical and specific
knowledge. These campaigns will be organised during and after the works and will target around 20,000
people about at least 50% of whom will be women.
Road Safety
3.2.17 The issue of road safety is of great concern to the populations which require the installation of
speed bumps where the road crosses any localities. In the absence of speed bumps, the populations erect
barriers on the road with tree trunks, which only worsens road safety. Serious accidents have occurred
on the road because vehicles which, in order to avoid frequent hold ups, travel at high speed in order to
leave the road before night fall. This fear continues even though the security situation has improved. In
order to reconcile the road’s main function and road safety requirements, it will be necessary to step up
sensitisation campaigns and security force patrols, but also to establish rest areas. The project intends
to purchase ambulances in order to improve emergency care for victims of road accidents. Measures
will be taken by AGEROUTE to ensure that the road safety audit consultant is recruited at works
commencement in order to ensure that he/she can review the bidding documents and ensure that road
safety is more closely taken into account during the implementation of road works.
3.2.18 Senegal is one of the rare countries in West Africa not to have completed the implementation
of necessary provisions and mechanisms to achieve the goals of the Decade of Action for Road Safety
(2011-2020) aimed at stabilizing, then halving the number of road traffic fatalities in accordance with
the relevant WAEMU Directives. In 2011, Senegal prepared a road safety strategy and action plan to
improve road safety and one of its strong recommendations concerns the establishment of a National
Road Safety Management and Coordination Unit (OGESER). On 19 February 2018, a workshop was
organised to review the recommendations of that study. It is expected that the law establishing this body
will be submitted to the National Assembly by 31 December 2019 at the latest.
IV IMPLEMENTATION
4.1 Implementation Arrangements
4.1.1 The project owner is the Ministry of Infrastructure, Land Transport and Road Access (MITTD)
backed by the Road Works and Management Agency (AGEROUTE) which has sound experience
concerning the implementation of similar projects. A Project Management Team (PMT) will be
established responsible for steering and controlling general project implementation. The PMT’s main
duties will be to perform the following tasks: (i) ensure compliance with central government’s
commitments in the financing agreements; (ii) prepare documents that will allow the Government to
fulfil the loan conditions; (iii) prepare bidding documents for submission to the Bank for its no-
objection; (iv) ensure compliance with the project implementation schedule; (v) prepare project status
reports; (vi) prepare counterpart fund budgets and ensure their timely availability; (vii) carry out the
project’s financial management (checking of cost statements, transmission to the Bank of direct
payment requests and see to the timely submission of the project’s accounting and financial audits) ;
(viii) ensure impact monitoring and evaluation, etc. The PMT will be composed of: 1 Civil Engineer,
the Coordinator, 3 civil engineers responsible for the works Lot assigned to the field, 1 procurement
specialist, 1 monitoring and evaluation specialist and 1 accountant and 1 environmentalist. The CVs of
of this Team were submitted to the Bank.
Procurement Arrangements
4.1.2 In view of the scope and complexity of some works and consulting services planned under the
project, the Bank’s procurement methods and procedures will be used; this may present a significant
fiduciary risk. The following contracts will be awarded using the Bank’s Procedures and Measures
16
(BPM) in accordance with the ‘Procurement Policy and Methodology for Bank Group-funded
Operations dated October 2015 using the relevant Bank standard bidding documents (SBD).
4.1.3 The assessment of the Senegalese public procurement system (SPPS) produced a “moderate”
procurement risk rating. This generic country risk was reassessed in the context of all the activities
included under the Project to Rehabilitate the SENOBA-Ziguinchor Road and Open up the Southern
Regions in order to be taken into account in determining the project’s overall procurement risk. The
overall project procurement risk rating (PPRR) at the time of the assessment is considered to be
moderate. Most of the problems/risks have been identified and mitigation measures proposed and
incorporated in the PERCA action plan are set out in Paragraph B.5.9 of the technical annexes. All the
costs associated with the implementation of this action plan are included under this project. Also, the
services to be acquired using this method are : (i) sensitisation on HIV/AIDS, social mobilisation,
environmental protection and road safety, (ii) fragility assessment, (iii) technical and road safety audit;
and (iv) communication services and (v) the procurement of different services related to the operation
of the executing agency which will be carried out in compliance with the provisions of the Bank’s
Administrative, Accounting and Financial Procedures Handbook for the project with the Bank’s prior
approval.
4.1.4 The project will be implemented by AGEROUTE within which will be established a Project
Management Team (PMT). Project procurements will be carried out by the PMT which will be
supported by the procurement unit of AGEROUTE which employs several procurement specialists with
sound experience of Bank-financed projects. For further information, the procurement methods and
procedures (PMP) are set out in detail in the Annex to the Programme Appraisal Report and in the
procurement plan.
Financial Management
4.1.5 The project’s financial implementation will be carried out in compliance with AGEROUTE’s
existing procedures. While not exhaustive, these include the budgeting procedures, the expenditure
implementation procedures and accounting procedures. AGEROUTE will be responsible for the
implementation of all the necessary controls to ensure: (i) the use of project funds only for the planned
purposes by giving considerations of economy and yield the importance they deserve; (ii) preparation
of accurate, reliable and timely information for the periodic financial reports and (iii) the safeguarding
of project assets. In 2015, the Bank reviewed the financial management of AGEROUTE for a road
project that it is financing..
4.1.6 The project annual financial statements established by the PMT, as well as the internal control
system, will be submitted for auditing by an independent external audit firm, on the basis of terms of
reference approved by the Bank. Four audits are planned for the project for the 2018, 2019, 2020 and
2021 fiscal years. The audit reports must be transmitted by the PMT to the Bank within six months of
the fiscal year-end. The audits will be performed in compliance with the international standards of
auditing (ISA). The first year audit will cover the first 18 months, if the first disbursement is made in
the second half (after 30 June) of the year. The external audit should be adapted to the project’s specific
risks. The auditor’s contract will be concluded for a one-year period, renewable on the basis of the
quality of service delivery and for a duration not exceeding 3years.
17
Disbursement
4.1.7 The direct payment and reimbursement methods will be mainly used in the context of this
programme for Bank-financed activities. Similarly, to cover certain minor operating expenses, the
revolving fund method will be used. For that purpose, a special account will be opened by the Borrower,
on behalf of the project, in an acceptable commercial bank. The purpose of this account for the payment
of the Bank’s resources intended for the operation of the PMT. The PMT accounting and financial
officer will be responsible for project financial management.
Financial and Accounting Auditing
4.1.8 The project will be submitted for annual verification of its accounts by an independent external
auditor recruited on the basis of terms of reference approved by the Bank. The auditor shall be recruited
within 6 months of the project loan’s effectiveness. The duration of the auditor’s contract shall not
exceed three successive years, and the continuation of the auditing services will depend on the Bank’s
approval of the first audit report. Audit reports must be submitted to the Bank no later than six months
after the closing of the accounting period audited, and the audit costs will be paid directly by the Bank
after approval of each report.
4.2 Monitoring &Evaluation
4.2.1 The programme’s monitoring and evaluation will include internal and external monitoring,
Bank supervision missions, a mid-term review and a final evaluation including the completion report
prepared by the executing agencies. Works implementation will be the subject of monthly and quarterly
reports established by the works control and supervision agencies. The executing agency will provide
the Bank with quarterly programme implementation reports. Special attention will be paid to
consideration of the effectiveness of the proposed measures under this programme in order to address
the main lessons learned from the implementation of previous projects (quality of PDs, procurement
timeframes, realism of programme loan conditions, mechanism established for the continuing
monitoring and evaluation of outputs over a long period after project completion and guaranteeing and
increasing road maintenance resources).
4.2.2 Monitoring the programme impacts will help to identify and analyse the outcome indicators
consequent upon the programme’s implementation and contribute to the achievement of the expected
outcomes. It will be carried out by a consulting firm to be recruited by the executing agency.
Table IV.1
Project monitoring and supervision schedule
Approximate
date Activity Mission composition
Person-
weeks
22/07/2018 Launch Project officers (Transport economist and civil engineer),a disbursement officer, a procurement officer, a social sector specialist and an environmental expert
6
23/03/2019 Supervision Project officers (Transport economist and civil engineer) infrastructure officer from the Bank’s country offices and social sector specialists
7
22/09/2019 Supervision Infrastructure and procurement officers from the Bank’s country offices and a social
sector specialist 5
23/03/2020 Supervision Project officers (Transport economist and civil engineer) and infrastructure officers from
the Bank’s country offices and a social sector specialist 7
22/09/2020 Project Mid-Term
Review
Project officers (transport economist and civil engineer), a disbursement officer,, a
procurement officer, an environment expert and a social sector specialist 9
20/04/2021 Supervision
Project officers (Transport economist and civil engineer),a disbursement officer, a
procurement officer, an environmentalist and infrastructure officers from the Bank’s country offices and a social sector specialist
11
21/03/2022 Completion Report Transport economist, a civil engineer and a social sector specialist 6
Total 51
18
4.3 Governance
4.3.1 As regards governance, the Senegalese authorities are resolutely committed to the fight against
impunity and the promotion of economic governance. The economic and budgetary transparency
measures taken include the
adoption of Law No. 2012-22
establishing the Public Finance
Management Transparency Code,
Law No. 2012.30 establishing the
National Anti-Fraud and
Corruption Bureau (OFNAC),
Law No. 2014-17 governing the
declaration of property followed
by Decree No. 2014-1463
determining the list of persons
subject to the property declaration.
The country is ranked 9th among
African countries according to the 2016 Ibrahim Index for African Governance and in 66th position out
of 180 countries in the 2017 Corruption Perceptions Index calculated by Transparency International.
An assessment recently carried out by the Bank concluded that the existing procurement procedures in
Senegal take into account principles of economy, efficiency and transparency in procurement and may
be applied to international competitive bidding processes to be carried out in the context of projects
financed by the Bank in Senegal.
4.3.2 The project design also incorporates specific measures to mitigate the governance risk in order
to ensure that resources are used efficiently and for the purposes for which they are intended. Prior or
post review by the Bank of all the procurement activities will be required. In addition, the Programme
makes provision for independent auditors who perform project financial and procurement audits.
4.4 Sustainability
4.4.1 The sustainability of project investments depends on the quality of the works and the measures
that will be taken to provide maintenance and ensure the renewal of investments. The road pavement
structures retained can accommodate traffic that is also aggressive. The project roads, urban roads and
rural access roads are eligible for maintenance under the Autonomous Road Maintenance Fund (FERA).
However, FERA’s resources are insufficient (71% of needs covered) and difficulties in mobilising
expected revenue are frequent. While revenue from the Road User Tax (RUT) is easily mobilised, the
same does not apply for the CFAF 25 billion/yr. budget allocation from the Consolidated Investment
Budget (CIB). Submission to the Bank of FERA’s annual activity reports is a project loan condition.
4.4.2 In order to finance the Three-Year Rolling Programme (TYRP) whose road maintenance
requirements are estimated to be CFAF 186.2 billion, FERA has secured a bank loan. A first financing
agreement for CFAF 102.5 billion was signed on 30 December 2016 with ECOBANK and UBA.
However, this borrowing solution is not sustainable in the medium-to-long term with the current level
of the RUT. It will be necessary to make the RUT more stable and more autonomous by: transforming
it into a levy instead of a tax (road marketing principle); (ii) by including it in the middle section of the
hydrocarbon price structure; and (iii) gradually removing the budgetary allocation in favour of an
increase in the RUT.
4.4.3 With regard to axle load control, Senegal’s road network in October 2017 had 17 weighing
stations, two of which are on the Sénoba-Mpack road (one at Bignona and one at Ziguinchor). These
weighing stations are operated by Afrique Pesage Sénégal Ltd. Since 15 December 2012, the control is
effective and penalties are applied with a tolerance of 20% which are variable depending on whether
the overload is excessive (above 40%) or not excessive (below 40%). According to statistics, a
downward trend in the percentage of overloaded vehicles has been observed year-on-year. In October
0,00
10,00
20,00
30,00
40,00
50,00
60,00
70,00
80,00
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
I
n
d
e
x
Senegal- Mo Ibrahim Index Trend
OverallGovernance
Security and Ruleof Law
Participation andHuman Rights
SustainableEconomicDevelopment
HumanDevelopment
19
2017, an average of 46.51% of all vehicles were overloaded and most of the excessively overloaded
trucks (0. 51%) came from the Autonomous Port of Dakar. Integral application of Regulation 14 has
been postponed. In accordance with the decision by the Ministers at a meeting held on 28 October 2017
in Abidjan. Senegal which had started offloading excessive loads in November 2017, but had to
renounce it following consultations with Mali.
4.4.4 Progress in axle load control has been made, but only the effective and comprehensive
application of Regulation 14 will be able to ensure the sustainability of investments. It is recommended
that the government should start enforcing the Regulation in accordance with the effective decisions of
the Ministers in charge of Transport.
4.5 Risk Management
4.5.1 The main risks identified are: (i) the security situation in southern Senegal which could have
an impact on the number of bidders or on the amount of bids; (ii) the sustainability of investments is not
guaranteed because of (a) insecurity, insufficient resources for road maintenance; and (b) the failure to
fully apply Regulation 14 on axle load control; and (iii) the WAEMU Decisions on the limitation of
checkpoints and the abolition of illegal levies are not enforced.
4.5.2 In order to mitigate these risks: (i) there are plans under this project to cover costs related to
the deployment on the works sites of detachments of defence and security forces; (ii) the mission
recommended a mechanism to gradually lower the subsidy to FERA and increase the RUT in the same
proportions and bolster the Government’s decision concerning the offloading of axle overloads in April
2018. Implementation of these recommendations will constitute a project loan condition. In order to
limit checkpoints on the corridor, the project is counting on sensitisation through the dissemination of
the findings of the OPA surveys which will be backed by the project
4.6 Knowledge Building
4.6.1 The knowledge which should be gained from the project’s implementation will concern good
practices in the management of regional-oriented transport projects that will improve access to
production areas and impact monitoring and evaluation. The project will provide a good opportunity for
the Bank to implement its regional integration policy and strategy covering the 2014-2023 period and
to expand its knowledge on the impact of transport corridor projects on sub-regional trade and economic
development. Good practices will be disseminated to all project stakeholders through periodic meetings
and summary notes. The emphasis placed on the project’s socio-economic impact aims, in particular, to
meet knowledge building needs. Indeed, establishment of the baseline situation before the
commencement of project activities provides a basis for comparison in order to realistically assess the
level of achievement of this project’s impacts. The data for comparison are derived from the assessment
of the project outcomes to be carried out on works completion. The holding of a national workshop will
contribute to the dissemination of knowledge acquired from these studies.
4.6.2 The main knowledge and lessons learned will be managed from a relational database at
AGEROUTE. This database will effectively facilitate the management of knowledge accumulated on
activities, outputs, the main outcomes and lessons learned from this project. Summaries could be
published on the Bank’s website.
20
V LEGAL FRAMEWORK
5.1 Financing Instrument
An AfDB loan agreement will be signed between the Republic of Senegal and the African Development
Bank. And a second grant agreement, granted on the resources of the AfIF, will be signed between the
Republic of Senegal and the African Development Bank.
5.2 ADB loan conditions
A. Conditions precedent to effectiveness of the AfDB Loan
5.2.1 Effectiveness of the AfDB Loan Agreement shall be subject to fulfilment by the Borrower to
the satisfaction of the Bank, of the conditions set out in section 12.01 of the General conditions
applicable to AfDB Loan and Guarantee Agreements.
B. Special condition precedent to disbursement of loan resources for works involving
expropriation
5.2.2 In addition to effectiveness of the Loan Agreement, the disbursement of resources of the loan
for works involving expropriation shall be subject to fulfilment by the Borrower, to the satisfaction of
the Bank, of the following conditions:
(i) Provide gradually and before any work begins on a concerned area, evidence of compensation
and / or displacement of persons affected by the Project on said area, in accordance with the
Environmental and Social Management Plan (ESMP), the Abridged Resettlement Action Plan
(ARAP), and the Bank's rules and procedures on this matter, including the Involuntary
Resettlement Policy and its Disclosure System Integrated safeguards. It is specified that when
this compensation or resettlement is not possible, either totally or partially, because of the
impossibility to identify the beneficiaries or in case of litigation or other impossibility beyond
the control of the Duly substantiated borrower acceptable to the Bank (hereinafter referred to
as "Contentious Cases"), the condition may be considered to be met if the Borrower provides
evidence that the resources allocated to the compensation and / or relocation of the Litigious
Cases deposited in a bank account acceptable to the Bank specifically earmarked for such
compensation and / or relocation, or remittances to a trusted third party acceptable to the Bank
C. Other AfDB loan conditions
5.2.3 The other conditions are as follows
(i) Submit to the Bank, no later than December 31, 2019, the proof of the submission for adoption
to the National Assembly of the draft law yet creation of the autonomous body responsible
for road safety (paragraph 3.2.18)
(ii) Submit to the Bank FERA’s annual activity reports
(iii) Submit to the Bank FERA’s annual activity reports Provide the Bank, no later than
31/12/2020, (i)with the decree transforming the Road Usage Tax (RUT) into a levyfor the
benefit of the Autonomous Road Maintenance Fund (FERA), (ii) the order authorizing direct
transfer of the levy resources in a commercial bank account of the FERA; and (iii) the
measures taken for the gradual suppression of the annual public allocation of 25 billion CFAF
for road maintenance in favour of an increase of the RUT (Paragraph 4.4.2)
21
(iv) Communicate to the Bank, no later than 31/12/2019, the proof of the integral application of
WAEMU Regulation 14 concerning axle load control for loads intended for national
consumption originating from cement factories and the Autonomous Port of Dakar
D. Undertakings
The Borrower further undertakes, to the satisfaction of the Bank, to:
(i) Submit to the Bank the project financing agreement with the European Investment Bank
(EIB)
(ii) Execute the Project, the ESMP, the ARAP and have it executed by its contractors in
accordance with Bank rules and procedures, national law and the recommendations,
requirements and procedures contained in the ESMP and the ARAP of the Project; and
(iii) Provide semi-annual reports on the implementation of the ESMP and the ARAP, including
any deficiencies and corrective actions initiated or to be initiated (Paragraph 3.2.5).
5.3 AfIF Grant conditions
A. Conditions precedent to effectiveness of the AfIF Grant
5.3.1. The entry into force of the Grant Agreement will be subject to signature by both parties.
B. Special condition prior to disbursement of loan resources for works involving expropriation
5.3.2. In addition to effectiveness of the Loan Agreement, the disbursement of the Loan resources for
works involving expropriation is subject to the fulfilment by the Borrower, to the satisfaction of the
Bank, of the following condition:
(i) Provide, as and when work progresses, and before any work begins on a concerned area,
evidence of compensation and / or displacement of persons affected by the Project on said
area, in accordance with the Environmental and Social Management Plan (ESMP), the
Resettlement Action Plan (ARAP), and the Bank's rules and procedures in this area,
including the Involuntary Resettlement Policy and its Disclosure System; built-in backups.
It is specified that when this compensation or resettlement is not possible, either totally or
partially, because of the impossibility to identify the beneficiaries or in case of litigation or
other impossibility beyond the control of the Duly substantiated borrower acceptable to the
Bank (hereinafter referred to as "Contentious Cases"), the condition may be considered to
be met if the Borrower provides evidence that the resources allocated to the compensation
and / or relocation of the Litigious Cases deposited in a bank account acceptable to the Bank
specifically earmarked for such compensation and / or relocation, or remittances to a trusted
third party acceptable to the Bank
D Other FIAf grant conditions
5.3.3. The other conditions are as follows
(i) Submit to the Bank, no later than December 31, 2019, the proof of the submission for
adoption to the National Assembly of the draft law yet creation of the autonomous body
responsible for road safety (paragraph 3.2.18)
(ii) Submit to the Bank FERA’s annual activity reports
(iii) Submit to the Bank FERA’s annual activity reports Provide the Bank, no later than
31/12/2020, (i)with the decree transforming the Road Usage Tax (RUT) into a levy for
22
the benefit of the Autonomous Road Maintenance Fund (FERA), (ii) the order
authorizing direct transfer of the levy resources in a commercial bank account of the
FERA; and (iii) the measures taken for the gradual suppression of the annual public
allocation of 25 billion CFAF for road maintenance in favour of an increase of the RUT
(Paragraph 4.4.2)
(iv) Communicate to the Bank, no later than 31/12/2019, the proof of the integral application
of WAEMU Regulation 14 concerning axle load control for loads intended for national
consumption originating from cement factories and the Autonomous Port of Dakar
5.4 Compliance with Bank’s Policies
This project complies with all applicable Bank policies.
VI RECOMMENDATIONS
Management recommends that the Boards of Directors:
(i) Approve the proposition for an AfDB loan for an amount of EUR 85.00 million and grant
for a total amount of EUR 25.600 million from the resources of the AfIF grant (including
EUR 25.00 million in favour of the Republic of Senegal) for the project financing, in
accordance with the conditions set out in this appraisal report and the General Conditions
applicable to African development Bank Loan Agreements and to AfIF Grant Agreements;
(ii) Exceptionally grant a waiver to the rule of origin in Article 17 (1) (d) of the Agreement
establishing the African Development Bank, and authorize, for procurements to be made
using the national procurement system of the Republic of Senegal, the application of the
rules of eligibility contained in that system coupled with the provisions of Paragraph 5.3
(c) of the Procurement Policy for Bank Group-funded operations, October 2015 Edition.;
and
(iii) Decide that the procurements of goods, works and services that are financed from the
resources of the AfIF grant will be open to non-members of the Bank
I
APPENDIX I: Senegal: COMPARATIVE SOCIO-ECONOMIC INDICATORS
Year Senegal Africa
Develo-
ping
Countries
Develo-
ped
Countries
Basic Indicators
Area ( '000 Km²) 2017 197 30 067 94 716 35 018Total Population (millions) 2017 16,1 1 244,8 6 252,1 1 190,0Urban Population (% of Total) 2017 43,8 40,5 49,2 81,4Population Density (per Km²) 2017 83,4 42,4 66,0 34,0GNI per Capita (US $) 2016 950 1 836 4 442 41 208Labor Force Participation *- Total (%) 2017 57,5 65,8 62,3 60,3Labor Force Participation **- Female (%) 2017 45,3 55,3 47,8 52,5Sex Ratio (per 100 female) 2017 96,7 100,2 107,5 105,3Human Dev elop. Index (Rank among 187 countries) 2015 162 ... … …Popul. Liv ing Below $ 1.90 a Day (% of Population) 2011 38,0 ... 16,3 0,6
Demographic Indicators
Population Grow th Rate - Total (%) 2017 3,0 2,5 1,3 0,6Population Grow th Rate - Urban (%) 2017 3,6 3,5 2,4 0,9Population < 15 y ears (%) 2017 43,7 40,8 27,9 16,6Population 15-24 y ears (%) 2017 19,4 19,2 16,7 11,9Population >= 65 y ears (%) 2017 2,9 3,5 6,8 17,4Dependency Ratio (%) 2017 87,2 79,6 54,6 52,0Female Population 15-49 y ears (% of total population) 2017 24,1 24,0 25,6 22,6Life Ex pectancy at Birth - Total (y ears) 2017 67,7 61,9 70,2 80,7Life Ex pectancy at Birth - Female (y ears) 2017 69,5 63,3 72,3 83,5Crude Birth Rate (per 1,000) 2017 36,2 33,9 20,6 10,9Crude Death Rate (per 1,000) 2017 5,6 9,0 7,5 8,6Infant Mortality Rate (per 1,000) 2016 33,6 49,3 33,1 4,5Child Mortality Rate (per 1,000) 2016 47,1 72,6 44,3 5,3Total Fertility Rate (per w oman) 2017 4,9 4,4 2,6 1,7Maternal Mortality Rate (per 100,000) 2015 315,0 444,1 237,0 10,0Women Using Contraception (%) 2017 22,5 37,6 62,1 ...
Health & Nutrition Indicators
Phy sicians (per 100,000 people) 2005-15 6,1 41,6 121,6 293,5Nurses and midw iv es (per 100,000 people) 2005-15 43,0 120,9 211,3 873,4Births attended by Trained Health Personnel (%) 2010-16 53,2 55,9 76,6 98,9Access to Safe Water (% of Population) 2015 78,5 71,6 89,4 99,5Access to Sanitation (% of Population) 2015 47,6 39,4 61,5 99,4Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2016 0,4 3,6 1,1 ...Incidence of Tuberculosis (per 100,000) 2016 140,0 221,7 163,0 12,0Child Immunization Against Tuberculosis (%) 2016 97,0 82,1 84,9 95,8Child Immunization Against Measles (%) 2016 93,0 74,4 84,0 93,7Underw eight Children (% of children under 5 y ears) 2010-15 18,1 15,3 0,9Prev alence of stunding 2010-15 19,4 33,3 25,0 2,5Prev alence of undernourishment (% of pop.) 2015 11,3 17,5 12,3 2,7Public Ex penditure on Health (as % of GDP) 2014 2,4 2,6 3,0 7,7
Education Indicators
Gross Enrolment Ratio (%)
Primary School - Total 2010-16 82,2 101,7 103,8 102,6 Primary School - Female 2010-16 86,9 98,8 102,2 101,8 Secondary School - Total 2010-16 49,6 51,8 ... 106,6 Secondary School - Female 2010-16 49,1 49,7 ... 106,4Primary School Female Teaching Staff (% of Total) 2010-16 32,4 46,0 51,3 81,0Adult literacy Rate - Total (%) 2010-16 42,8 68,6 ... ...Adult literacy Rate - Male (%) 2010-16 52,8 76,0 ... ...Adult literacy Rate - Female (%) 2010-16 33,6 61,7 ... ...Percentage of GDP Spent on Education 2010-16 7,4 4,9 4,1 5,2
Environmental Indicators
Land Use (Arable Land as % of Total Land Area) 2015 16,6 8,0 11,3 10,1Agricultural Land (as % of land area) 2015 46,1 37,4 38,1 35,1Forest (As % of Land Area) 2015 43,0 21,0 31,4 28,8Per Capita CO2 Emissions (metric tons) 2014 0,6 1,1 3,5 11,0
Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :
UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.
Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)
** Labor force participation rate, female (% of female population ages 15+)
COMPARATIVE SOCIO-ECONOMIC INDICATORS
Senegal
January 2018
0
10
20
30
40
50
60
70
80
90
100
20
00
20
06
20
10
20
11
20
12
20
13
20
14
20
15
20
16
Infant Mortality Rate( Per 1000 )
Sen egal Af r ica
0
500
1000
1500
2000
2500
20
00
20
06
20
10
20
11
20
12
20
13
20
14
20
15
20
16
GNI Per Capita US $
Sen egal Af r ica
0,0
0,5
1,0
1,5
2,0
2,5
3,0
3,5
20
00
20
06
20
10
20
11
20
12
20
13
20
14
20
15
20
16
Population Growth Rate (%)
Senegal Af ri ca
01020304050607080
20
00
20
06
20
10
20
11
20
12
20
13
20
14
20
15
20
16
Life Expectancy at Birth (years)
Sen egal Af r ica
APPENDIX II
II
Portfolio of Ongoing Bank Projects in Senegal as at 30/04/2018
Project Name Status Age (Year) Source of Financing
Approval Date Approved amount in MUA
Closing Date Disbursed amount in MUA
Undisbursed amount in MUA
Disbursement rate
WATER AND SANITATION
Project to Reinforce Multiple-Use Water Supply along the Louga-Thiès-Dakar Road from the Keur Momar Sarr Treatment Plant - AfDB
Ongoing 1.44 AfDB 18/11/2016 54.59 30/06/2021 2.94 51.65 5.39%
Project to improve faecal sludge management and re-use in the town of Ziguinchor - FAE
Ongoing 5.01 AWF 23/04/2013 1.06 25/06/2018 1.06 0 100.00%
Water and sanitation sector project (PSEA) Ongoing 4.01 ADF 23/04/2014 20.00 31/12/2018 7.67 12.33 38.35%
Ongoing 4.01 RWSSI 23/04/2014 5.04 31/12/2018 2.09 2.95 41.47%
Sub-total 80.69 13.76 66.93 17.05%
TRANSPORT & ICT
Dinguiraye-Nioro-Keur-Ayib (DNK) Road Rehabilitation Project
Ongoing 3.92 ADF 28/05/2014 23.77 31/12/2019 15.75 8.02 66.26%
Project to rehabilitate RN2 and open up access to Morphil Island
Ongoing 2.37 BAD 16/12/2015 101.47 31/12/2019 16.51 84.96 16.27%
Digital Technology Park Project Ongoing 2.52 AfDB 21/10/2015 51.2 31/12/2020 1.53 49.67 2.99%
Urban Modernization Programme (PROMOVILLES)
Ongoing 1.08 AfDB 29/03/2017 96.04 31/12/2021 5.79 90.25 6.03%
Dakar Regional Express Train Project (TER) Ongoing 0.86 AfDB 21/06/2017 153.66 31/12/2021 17.64 136.02 11.48%
Sub-total 426.14 57.22 368.92 13.43%
AGRICULTURE
Community Roads Project in support of
PNDL (PPC/PNDL)
Ongoing 4.78 ADF 17/07/2013 15.00 31/12/2018 13.19 1.81 87.93%
Ongoing 4.37 OPEP 11/12/2013 6.97 30/06/2019 3.69 3.28 52.94%
Ongoing 4.64 ADF 04/09/2013 15.00 31/12/2018 9.85 5.15 65.67%
APPENDIX II
III
Project to Restore the Ecological and Economic Functions of Lake Guiers (PREFELAG)
Ongoing 4,64 GEF 04/09/2013 0.92
31/12/2018 0.49 0.43 53.26%
Food Security Support Project in Louga, Matam and Kaffrine Regions
Ongoing 5,00 ADF
26/04/2013 2.00 31/12/2018 1.23 0.77 61.50%
Ongoing 5,00 GAFSP 26/04/2013 27.88 31/12/2018 17.05 10.83 61.15%
PPF Rice Value Chain Development Project in the Senegal River Valley (PDCV Riz)
Ongoing 1,95 PPF 18/05/2016 0.55 31/03/2018 0.02 0.53 3.64%
PPF Youth entrepreneurship development project in the agricultural and agro-food subsectors (PDEJAS)
Ongoing 1,91 PPF 01/06/2016 0.81 31/05/2018 0.78 0.03 96.30%
Project to improve the quality of climate information to build community resilience in Senegal (CDSF)
Ongoing 1,12 ADF 17/03/2017 0.85 31/12/2019 0.01 0.84 1.18%
Sub-Total 69.98 46.31 23.67 66.18%
GOVERNANCE
Private Sector Promotion Support Project (PAPSP)
Ongoing 5,62 ADF 10/09/2012 4.04 30/06/2018 2.98 1.06 73.76%
Legal assistance to the legal sector (ALSF) Ongoing 1,58 ADF 30/09/2016 0.69 31/12/2018 0 0.69 0.00%
Sub-total 4.73 2.98 1.75 63.00%
SOCIAL
Project to Support the Promotion of Employment for Youth and Women (PAPEJF)
Ongoing 4,51 ADF 23/10/2013 21.19 30/06/2019 3.45 17.74 16.28%
Senegal Virtual University Support Project (PAUVS)
Ongoing 4,36 ADF 18/12/2013 3.38 30/06/2019 1.28 2.1 37.87%
Sub-Total 24.57 4.73 19.84 19.25%
MULTINATIONAL
Gambia/Senegal: Multinational project for the construction of the Trans-Gambia Bridge and cross-border improvement (Senegal loan)
Ongoing 6,36 ADF 16/12/2011 3.18 31/12/2019 0.014 3.166 0.44%
APPENDIX II
IV
Rosso Bridge construction project (Senegal loan)
Ongoing 1,39 ADF 09/12/2016 7.5 31/12/2020 0 7.5 0.00%
Programme to build resilience in Sahel (P2RS)
Ongoing 3,12 ADF 16/03/2015 22.25 30/06/2020 7.02 15.23 31.55%
OMVG Energy Project Ongoing 2,58 ADF 30/09/2015 42.5 31/12/2020 7.69 34.81 18.09%
Sub-total 75.43 14.72 60.71 19.52%
MULTISECTOR
Portfolio of Bank’s Ongoing Transport Sector Projects in Senegal as at 30/04/2018
Project name Status Age (Year) Source of Financing
Approval date
Approved amount in MUA
Closing date Disbursed amount in MUA
Undisbursed amount in MUA
Disbursement rates
Dinguiraye-Nioro-Keur-Ayib (DNK) Road Rehabilitation Project Ongoing 3.92 ADF 28/05/2014 23.77 31/12/2019 15.75 8.02 66.26%
Project to rehabilitate RN2 and open up access to Morphil Island Ongoing 2.37 AfDB 16/12/2015 101.47 31/12/2019 16.51 84.96 16.27%
Urban Modernization Programme (PROMOVILLES) Ongoing 1.08 AfDB 29/03/2017 96.04 31/12/2021 5.79 90.25 6.03%
Dakar Regional Express Train Project (TER) Ongoing 0.86 AfDB 21/06/2017 153.66 31/12/2021 17.64 136.02 11.48%
Gambia/Senegal: Multinational project for the construction of the Trans-Gambia Bridge and cross-border improvement (Senegal loan) Ongoing 6.36 ADF 16/12/2011 3.18 31/12/2019 0.01 3.17 0.44%
Rosso Bridge Construction Project(Senegal Loan) Ongoing 1.39 ADF 09/12/2016 7.50 31/12/2020 0.00 7.50 0.00%
APPENDIX II
V
Portfolio of Bank’s Ongoing Private Sector Projects in Senegal as at 30/04/2018
Senegal : Active Private Sector Window
Projects in Senegal as at 30/04/2018
Sector / Operation Status Age Source of financing
Approval date
Approved amount in MUA
Closing date Disbursed amount in MUA
Undisbursed amount in MUA
Disbursement rate
Blaise Diagne International Airport (AIBD)
17/12/2010 58.79 05/03/2029 58.79 0 100.00%
Dakar Toll Motorway Project (Senior loan) Ongoing AfDB 19/07/2010 7.95 31/12/2025 7.95 0 100.00%
Sendou Power Plant Project
- Senior loan Ongoing AfDB 25/11/2009 46.19 31/12/2024 46.19 0 100.00%
- Supplementary Loan Ongoing AfDB 30/10/2015 4.2 10/12/2027 4.2 0 100.00%
Rice Project of the Compagnie Agricole de Saint-Louis (CASL)
Ongoing 1.88 AfDB 22/06/2016 13.19 23/03/2022 8.45 4.74 64.06%
TOTAL 130.32 125.58 4.74 96.36%
APPENDIX III
VI
MAIN RELATED PROJECTS IN THE TRANSPORT SUB-SECTOR FINANCED BY THE BANK
AND DEVELOPMENT PARTNERS IN SENEGAL
DONORS PROJECTS
INVESTMENT
AMOUNT (in
million CFAF)
AFD Construction of the Seaplane Port Road 1 200
Austria Kédougou Bridge Construction Works 3 000
AfDB The Gambia River Bridge Construction Project 45 000
AfDB Rehabilitation of the Dinguiraye-Nioro-Keurayib Road + 6 km of urban roads in Nioro 12 004
AfDB Project to rehabilitate RN2 and open up access to Morphil Island 101 824
AfDB The Gambia River Bride Control Post 2 623
AfDB Promovilles 75 000
AfDB Rosso Bridge
ABEDA Blouf Loop Road, ThionkEssyl – Balingor Section Improvement Works 7 780
ABEDA Joel -Samba Dia-Djiffer Road Improvement 12 488
World Bank Greater Niaye restoration works between Rufisque and Lompoul LOT1 LOT2, LOT3 14 700
World Bank Greater Niaye restoration works between Rufisque and Lompoul LOT 2 + LOT 3 8 100
EIB Rosso Bridge
IsDB VDN LOT 2: CICES - Golf Club 37 917
IsDB Rehabilitation of Ndioum-Thilogne N2 44 100
IsDB Rehabilitation of Dialocoto-Mako - Lot 2 : KP120-Mako 21 000
ABEDA Rehabilitation of Dialocoto-Mako - Lot 1 : Dialocoto – KP 120 14 000
ADF/WAEMU Boundou-Fourdou Juxtaposed Border Control Post Construction Works 2 800
ADF/WAEMU Moussala Juxtaposed Border Control Post Construction Works 5 600
EDF Passy-Sokone Road Improvement 6 897
KFAED Touba-Dahra-Linguère Rehabilitation : Lot 2 - Dahra-linguére 9 253
KFAED Touba-Dahra-Linguère Rehabilitation : Lot1 Touba - Dahra (including the Dahra by-
pass) 14 789
KFAED Construction and Improvement Works on VDN section 3: Golf - Tivaouane Peulh
section including access road to Tivaouane Peulh village 32 000
Abu Dhabi Fund and
OPEC Rehabilitation of Ourossogui- HamdiOunaré N2 14 500
MCA RN6 Rehabilitation Works, Kounkandé-Vélingara section 6 500
MCA RN6 Rehabilitation Works, : Tanaff-Kolda Section 24 000
MCA RN6 Rehabilitation Works, Ziguinchor – Tanaff Section 45 000
EU Rosso Bridge
APPENDIX IV
VII
Map of Project Area
This map has been provided by the staff of the African Development Bank Group exclusively for the use of the readers
of the report to which it is attached. The names used and the borders shown do not imply on the part of the Bank Group
and its members any judgment concerning the legal status of the territory nor any approval or acceptance of these
borders.
APPENDIX V
VIII
ANNEXES: SUPPORT FOR REPORT’S KEY ARGUMENTS
A.1 Estimated Project Costs (Details)
Cost by component of entire project
COMPONENTS Million CFAF UA Million Million Euros
F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total
A – Rehabilitation and/or improvement of
roads and tracks
Rehabilitation of Sénoba- KP40 section including
4km of urban roads in Bounkiling (lot 1) 12 525.48 3 131.37 15 656.85 16.13 4.03 20.16 19.09 4.77 23.87
Rehabilitation of PK40 - PK 80 section including the 8 km of urban roads in Bignona (lot 2)
14 770.20 3 692.55 18 462.75 19.02 4.76 23.78 22.52 5.63 28.15
Rehabilitation of PK 80 - Ziguinchor – Mpack section including Tobor road pavements and the
parking area for heavy duty vehicles in
Ziguinchor (lot 3)
26 996.45 6 749.11 33 745.56 34.77 8.69 43.46 41.16 10.29 51.44
Improvement of KalounayesLoop 12 199.65 3 049.91 15 249.56 15.71 3.93 19.64 18.60 4.65 23.25
Rural access road improvements 4 000.00 1 000.00 5 000.00 5.15 1.29 6.44 6.10 1.52 7.62
Works control and supervision 3 524.59 881.15 4 405.74 4.54 1.13 5.67 5.37 1.34 6.72
Sensitisation on HIV/AIDS, social mobilisation
environmental protection, nutrition and road
safety
96.00 24.00 120.00 0.12 0.03 0.15 0.15 0.04 0.18
Clearing of rights-of-way (Expropriations) and
environmental monitoring 0.00 300.00 300.00 0.00 0.39 0.39 0.00 0.46 0.46
B – Integrated Activities 0.00 0.00 0.00
School and similar infrastructure 1 588.32 397.08 1 985.40 2.05 0.51 2.56 2.42 0.61 3.03
Urban infrastructure (motor parks commercial
infrastructure, waste management, etc.) 1 360.00 340.00 1 700.00 1.75 0.44 2.19 2.07 0.52 2.59
Support to women’s groups 1 200.00 300.00 1 500.00 1.55 0.39 1.93 1.83 0.46 2.29
Support to strengthening youth employability and to the reintegration of displaced persons as a
result of the armed rebellion
480.00 120.00 600.00 0.62 0.15 0.77 0.73 0.18 0.91
Studies on and control and supervision of related
works 207.42 51.85 259.27 0.27 0.07 0.33 0.32 0.08 0.40
Fragility assessment 48.00 12.00 60.00 0.06 0.02 0.08 0.07 0.02 0.09
C – Transport facilitation and road security 0.00 0.00 0.00
Support to OPA 96.00 24.00 120.00 0.12 0.03 0.15 0.15 0.04 0.18
Support to road safety 204.00 51.00 255.00 0.26 0.07 0.33 0.31 0.08 0.39
Portable axle-load scales 320.00 80.00 400.00 0.41 0.10 0.52 0.49 0.12 0.61
D- Project management
Monitoring and evaluation of project socio-
economic impact 90.00 90.00 180.00 0.12 0.12 0.23 0.14 0.14 0.27
Technical and road safety audit 65.00 65.00 130.00 0.08 0.08 0.17 0.10 0.10 0.20
Accounting and financial audit 40.00 40.00 80.00 0.05 0.05 0.10 0.06 0.06 0.12
Procurement audit 25.00 25.00 50.00 0.03 0.03 0.06 0.04 0.04 0.08
Communication 48.00 48.00 96.00 0.06 0.06 0.12 0.07 0.07 0.15
EA operation 0.00 336.92 336.92 0.00 0.43 0.43 0.00 0.51 0.51
Base cost 79 884.11 20 808.95 100 693.05 102.88 26.80 129.67 121.78 31.72 153.51
Physical contingency 7 988.41 2 080.89 10 069.31 10.29 2.68 12.97 12.18 3.17 15.35
Price escalation 859.65 223.93 1 083.58 1.11 0.29 1.40 1.31 0.34 1.65
TOTAL COST 88 732.16 23 113.77 111 845.93 114.27 29.77 144.04 135.27 35.24 170.51
APPENDIX V
IX
Cost by Category of Expenditure for the Entire Works
Categories
In million CFAF In million UA Ian million Euros
F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total
A – Works
Rehabilitation of the Sénoba-PK40 road including the urban roads, rural access roads, landscaping, support to road safety and support to
axle load control (LOT 1) 13 74748 3 43687 17 18435 1770 443 2213 2096 524 2620
Rehabilitation of the PK40 to KP80 road including the urban roads, rural access roads, landscaping, support to road safety and support to
axle load control (LOT 2) 15 91220 3 97805 19 89025 2049 512 2561 2426 606 3032
Rehabilitation of the PK80-Ziguinchor- Mack road including urban roads, rural access roads, landscaping (LOT3) 26 99645 6 74911 33 74556 3477 869 4346 4116 1029 5144
Improvement and asphalting of the Kalounayes loop including urban roads and rural access roads 14 35965 3 58991 17 94956 1849 462 2312 2189 547 2736
Social and commercial infrastructure including support to women 4 14832 1 03708 5 18540 534 134 668 632 158 791
Total Works 75 16410 18 79103 93 95513 9680 2420 12100 11459 2865 14323
B – Consulting services
Control and supervision of road, urban road and rural access roads works (LOT1) 67427 16857 84284 087 022 109 103 026 128
Control and supervision of road, urban road and rural access roads works LOT 2) 78251 19563 97814 101 025 126 119 030 149
Control and supervision of road, urban road and rural access roads works (LOT3) 1 34982 33746 1 68728 174 043 217 206 051 257
Control and supervision of Kalounayes Loop works 71798 17950 89748 092 023 116 109 027 137
Study and control and supervision of related works 20742 5185 25927 027 007 033 032 008 040
Sensitisation on HIV/AIDS, social mobilisation, environmental protection and to road safety 9600 2400 12000 012 003 015 015 004 018
Fragility assessment 4800 1200 6000 006 002 008 007 002 009
Youth employability and reintegration of people displaced by armed rebellion 48000 12000 60000 062 015 077 073 018 091
Monitoring and evaluation of project socio-economic impact 9000 9000 18000 012 012 023 014 014 027
Technical and road safety audit 6500 6500 13000 008 008 017 010 010 020
Accounting and financial audit 4000 4000 8000 005 005 010 006 006 012
Procurement audit 2500 2500 5000 003 003 006 004 004 008
Communication 4800 4800 9600 006 006 012 007 007 015
Total consulting services 462401 135700 598101 595 175 770 705 207 912
C- Others
Operation of Executing Agency 0.00 336.92 336.92 0.00 0.43 0.43 0.00 0.51 0.51
Clearing of rights-of-way and (expropriations) and monitoring of ESMP implementation by DEEC 0.00 300.00 300.00 0.00 0.39 0.39 0.00 0.46 0.46
Support to OPA 96.00 24.00 120.00 0.12 0.03 0.15 0.15 0.04 0.18
Total others 96.00 660.92 756.92 0.12 0.85 0.97 0.15 1.01 1.15
Base cost 79884.11 20808.95 100693.05 102.88 26.80 129.67 121.78 31.72 153.51
Physical contingencies 7 988.41 2 080.89 10 069.31 10.29 2.68 12.97 12.18 3.17 15.35
Financial contingencies 859.65 223.93 1 083.58 1.11 0.29 1.40 1.31 0.34 1.65
APPENDIX V
X
Total 88 732.16 23 113.77 111 845.93 114.27 29.77 144.04 135.27 35.24 170.51
Financing Plan for Project Expenditure Categories and Sources of Financing in MUA
Categories AfDB LOAN EU GRANT EIB LOAN GOV. SENEGAL Total
F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total
A - Works
Rehabilitation of the Sénoba-PK40 road including the urban
roads rural access roads landscaping support to road safety
and support to axle load control (LOT 1)
1158 289 1447 613 153 766 000 000 000 000 000 000 1770 443 2213
Rehabilitation of the PK40 to KP80 road including the urban
roads rural access roads landscaping support to road safety
and support to axle load control (LOT 2)
1327 332 1658 723 181 903 000 000 000 000 000 000 2049 512 2561
Rehabilitation of the PK80-Ziguinchor- Mpack road
including urban roads rural access roads landscaping (LOT3) 000 000 000 000 000 000 3477 869 4346 000 000 000 3477 869 4346
Improvement and asphalting of the Kalounayes Loop
including urban roads and rural access roads 1849 462 2312 000 000 000 000 000 000 000 000 000 1849 462 2312
Social and commercial infrastructure including support to
women 534 134 668 000 000 000 000 000 000 000 000 000 534 134 668
B – Consulting Services
Control and supervision of road urban road and track works
(LOT1) 006 002 008 081 020 101 000 000 000 000 087 022 109
Control and supervision of road urban road and rural access
road works LOT 2) 006 001 007 095 024 119 000 000 000 101 025 126
Control and supervision of road urban road and rural access
road works (LOT3) 000 000 000 000 000 174 043 217 174 043 217
Control and supervision of Kalounayes Loop works 092 023 116 000 000 000 000 000 000 000 000 000 092 023 116
Study and control and supervision of related works 027 007 033 000 000 000 000 000 000 000 000 000 027 007 033
Sensitisation on HIV/AIDS social mobilisation
environmental protection and to road safety 012 003 015 000 000 000 000 000 000 000 000 000 012 003 015
Fragility assessment 006 002 008 006 002 008
Youth employability and reintegration of people displaced by
armed rebellion 062 015 077 062 015 077
Monitoring and evaluation of project socio-economic impact 012 012 023 000 000 000 000 000 000 000 000 000 012 012 023
Technical and road safety audit 008 008 017 000 000 000 000 000 000 000 000 000 008 008 017
Accounting and financial audit 005 005 010 000 000 000 000 000 000 000 000 000 005 005 010
Procurement audit 003 003 006 000 000 000 000 000 000 000 000 000 003 003 006
Communication 000 000 000 006 006 012 000 000 000 000 000 000 006 006 012
C- Others
Operation of Executing Agency 000 043 043 000 000 000 000 000 000 000 000 000 000 043 043
Clearing of rights-of-way and (expropriations) and monitoring of
ESMP implementation by DEEC 000 000 000 000 000 000 000 000 000 000 039 039 000 039 039
Support to OPA 012 003 015 000 000 000 000 000 000 000 000 000 012 003 015
APPENDICE V
XI
A.2 Procurement Arrangements
The Different Procurement Methods and Contract Amounts in MUA are set out in the table below.
SPM Sénégal BMP
Not
financed by
the Bank
TOTAL
OCB LCB Others OCB LCB Others
WORKS
Rehabilitation of the Sénoba-PK40 road
including the urban roads rural access roads
landscaping support to road safety and
support to axle load control (LOT 1)
2458 [1607] 000 2458 [1607]
Rehabilitation of the PK40 to KP80 road
including the urban roads rural access roads
landscaping support to road safety and
support to axle load control (LOT 2)
2845 [1842] 000 2845 [1842]
Rehabilitation of the PK80-Ziguinchor-
Mpack road including urban roads rural
access roads landscaping (LOT3)
000 [000] 4827 4827 [000]
Improvement and asphalting of the
Kalounayes loop including urban roads and
rural access roads
2568 [2568] 000 2568 [2568]
Social and commercial infrastructure
including support to women 742 [742] 000 742 [742]
TOTAL 1 000 [000] 000 000 000 000 8613 [6759] 000 [000] 000 [000] 4827 13440 [6759]
SPM Sénégal BMP
Not
financed by
the Bank
TOTAL
QCBS LCS / CQS Others SBQC SMC / SQC Others
SERVICES
Control and supervision of road urban road
and rural access road works (LOT1) 121 [009] 000 121 [009]
Control and supervision of road urban road
and rural access road works LOT 2) 140 [008] 000 140 [008]
Control and supervision of road urban road
and rural access road works (LOT3) 000 [000] 241 241 [000]
Control and supervision of Kalounayes loop
works 128 [128] 000 128 [128]
Study and control and supervision of related
works 037 [037] 000 037 [037]
Sensitisation on HIV/AIDS social
mobilisation environmental protection and to
road safety
017 [017] 000 017 [017]
Fragility assessment 009 [009] 000 009 [009]
Youth employability and reintegration of
people displaced by armed rebellion 086 [086] 000 086 [086]
APPENDICE V
XII
Monitoring and evaluation of project socio-
economic impact 026 [026] 000 026 [026]
Technical and road safety audit 019 [019] 000 019 [019]
Accounting and financial audit 011 [011] 000 011 [011]
Procurement Audit 007 [007] 000 007 [007]
Communication 014 [000] 000 014 [000]
OTHER OPERATION 000 [000]
Operation of executing agency 048 [048] 000 048 [048]
Clearing of rights-of-way (expropriations)
and monitoring of ESMP implementation by
DEEC
000 [000] 043 043 [000]
Support to OPA 017 [017] 000 017 [017]
TOTAL 2 058 [044] 000 000 000 000 433 189 011 011 177 177 284 964 [422]
058 044 000 000 000 000 9046 6948 011 011 177 177 5111 14404 7180
Legends: Other* =Shopping among suppliers; Direct negotiation; Operating expenses;
Figures in [ ] are those financed by the Bank
APPENDICE VI
XIII
6.1 Financing Arrangements of the Africa Investment Facility (AfIF):
6.1.1 Introduction
On 12 July 2017 (Resolution B/BD/2017/124 - F/BD/2017/87), the framework for cooperation
between the European Commission (EC) and the Bank, called ‘the Pillar-assessed Grant or
Delegation Agreement’ (PAGODA)’ In this context, the Bank and European Commission on 5
December 2017 signed a Delegation Agreement for an amount of EUR 25.600 million relating to the
Project (including an amount of EUR 600,000 due to the Bank in respect of management and
administration costs). This Delegation agreement defines the activities entrusted to the Bank for project
implementation. It determines the implementation modalities, sets out the rules governing the payment
of the EU contribution and defines the relations between the Bank and EC. The resources thus mobilised
from the AfIF will be disbursed and managed by the Bank. See Annexes.
6.1.2 Co-financing of the AfIF
The AfIF resources approved on 24 February 2017 are not allocated. However, by way of indication,
they will contribute to the implementation of the following investment activities and with the following
specific social nature: (i) construction and equipping of juxtaposed border control posts at Mpack ; (ii)
improvement of urban roads and related rural access roads; (iii) rehabilitation of school and health
facilities; (iv) construction of urban infrastructure (motor park, waste management, commercial
equipment) ; (vi) support to women, young people and vulnerable people. The AfIF funds will also
contribute to the implementation of technical assistance activities and the following studies: (i) control
and supervision of related improvement works; (ii) studies on the design and operationality of
juxtaposed border control posts (JBCP); (iii) services for the control and supervision of JBCP; (iv)
training/sensitisation of border services and users v) harmonisation of the customs procedures of the
two countries; (vi) preparation of border control post procedures handbook.
Indicative breakdown of AfIF funding by component and by expenditure category is presented in the
following Tables (in EUR millions):
6.1.3 Estimated Cost
Estimated Project Costs by component (in EUR millions)
Components Amount
Rehabilitation and/or improvement of roads and rural access roads 20.00
Improvements and related measures 3/00
Transport facilitation and toad safety 2.00
Administrative and management costs 0.60
Total resources 25.60
Expenditure categories financed by the AfIF grant (in EUR millions)
Expenditure categories Amount
Works 21,95
Services 3.05
Total 25.00
APPENDICE VI
XIV
6.1.4 Implementation
To successfully implement the project activities financed by the AfIF grant, the Bank: (i) shall apply its
own accounting, internal control and audit procedures, which were positively rated during the prior
pillar assessment by the EC; and (ii) apply its own procedures, in particular its procurement procedures.
6.1.4.1 Financial management, disbursement and financial and accounting audit rules: the
applicable financial management, disbursement and financial and accounting audit rules will be those
stipulated in the PAGODA general conditions, the appraisal report and technical annexes.
6.1.4.2 Procurement Rules: There are plans to request the Boards of Directors to grant a waiver to
the Bank’s rule of origin, so that procurements of goods, works and services financed from the resources
of the AfIF grants are open to non-member countries. Also, arrangements for the procurement of goods,
services and works as set out in the appraisal report, the technical annexes and the procurement plan
will apply to the AfIF grant.
6.1.4.3 Legal Instruments: It should be pointed out that all obligations contracted by the Bank with
respect to the EC, both pursuant to the framework agreement concluded between the Bank and EC
approved by the Boards on 12 July 2017, and the PAGODA General Conditions and the delegation
agreement relating to the above-mentioned project and its annexes (concerning in particular financial
management, disbursement, financial and accounting audit, visibility or communication, etc.), will be
fully transferred for the Republic of Senegal. A grant agreement will be signed to that effect between
the Republic of Senegal and the Bank (‘Grant Agreement)’.
Conditions and Undertakings: the conditions precedent to effectiveness, first disbursement of
resources, the other conditions and undertakings set forth in the Grant Agreement will be identical to
the conditions and undertakings to be signed between the Republic of Senegal and AfDB.