african development fund · 33/11kv substations in bo and kenema, (ii) the rehabilitation and...

36
AFRICAN DEVELOPMENT FUND SIERRA LEONE REHABILITATION AND EXTENSION BO-KENEMA DISTRIBUTION SYSTEM APPRAISAL REPORT ONEC/GECL DEPARTMENTS December 2016 Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 05-Apr-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

AFRICAN DEVELOPMENT FUND

SIERRA LEONE

REHABILITATION AND EXTENSION BO-KENEMA

DISTRIBUTION SYSTEM

APPRAISAL REPORT

ONEC/GECL DEPARTMENTS

December 2016

Pu

bli

c D

iscl

osu

re A

uth

ori

zed

Pu

bli

c D

iscl

osu

re A

uth

ori

zed

Page 2: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

TABLE OF CONTENTS

1. STRATEGIC THRUST & RATIONALE .......................................................................... 1

1.1. Project linkages with country strategy and objectives ................................................ 1

1.2. Rationale for Bank’s involvement............................................................................... 2

1.3. Donors coordination .................................................................................................... 3

2. PROJECT DESCRIPTION ................................................................................................ 4

2.1. Project Components .................................................................................................... 4

2.2. Technical solution retained and other alternatives explored ....................................... 5

2.3. Project type .................................................................................................................. 5

2.4. Project cost and financing arrangements ..................................................................... 6

2.5. Project’s target area and population ............................................................................ 7

2.6. Participatory process for project identification, design and implementation .............. 8

2.7. Bank Group experience, lessons reflected in project design ....................................... 8

2.8. Key performance indicators ........................................................................................ 9

3. PROJECT FEASIBILITY .................................................................................................. 9

3.1. Economic and financial performance .......................................................................... 9

3.2. Environmental and Social impacts Environment ...................................................... 10

4. IMPLEMENTATION ...................................................................................................... 12

4.1. Implementation arrangements ................................................................................... 12

4.2. Monitoring ................................................................................................................. 14

4.3. Governance................................................................................................................ 15

4.4. Sustainability ............................................................................................................. 15

4.5. Risk management ...................................................................................................... 15

4.6. Knowledge building .................................................................................................. 16

5. LEGAL INSTRUMENTS AND AUTHORITY .............................................................. 17

5.1. Legal instrument ........................................................................................................ 17

5.2. Conditions associated with Bank’s intervention ....................................................... 17

5.3. Compliance with Bank Policies ................................................................................ 18

6. RECOMMENDATION .................................................................................................... 18

Appendix I: Country’s comparative socio-economic indicators ................................................I

Appendix II: Table of ADF’s portfolio in the country ............................................................. II

Appendix III: Key Projects Financed By the Bank and other Development Partners ............. IV

Appendix IV: Map of the Project Area ..................................................................................... V

Appendix V: Justification below 10% of project cost financing by the Government ............. VI

Page 3: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

i

Currency Equivalents November 2016

1 UA = 1.39434 USD

1 UA = 8761.9001 SLL

Fiscal Year

1st January – 31st December

Weights and Measures

1 metric tonne = 2204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 metre (m) = 3.28 feet (ft)

1 millimetre (mm) = 0.03937 inch (“)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

Page 4: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

ii

Acronyms and Abbreviations

AfDB African Development Bank

ADF

ARAP

African Development Fund

Abbreviated Resettlement Action Plan

CLSG Cote D'Ivoire, Liberia, Sierra Leone & Guinea

CSI Core Sector Indicator

CSP

DACO

DFID

Country Strategy Paper

Development Assistance Coordination Office

Department for International Development

DPs

E&S

ECOWAS

Development partners

Environmental and Social

Economic Community of West African States

EDSA

EGTC

Electricity Distribution and Supply Authority

Electricity Generation and Transmission Company

EIB

EIRR

European Investment Bank

Economic rate of return

ESAP Environmental and Social Assessment Procedures

EVD

EWRC

FIRR

FNPV

Ebola Virus Disease

Electricity and Water Regulatory Commission

Financial internal rate of return

Financial Net Present Value

GoSL Government of Sierra Leone

GDP

IsDB

Gross Domestic Product

Islamic Development Bank

ISS AfDB’s Integrated Safeguards System Policy of 2013

JICA Japanese International Cooperation Agency

km Kilometer

kV Kilovolt

LV

MAF

MoE

MoFEC

Low Voltage

Mutual Accountability Framework

Ministry of Energy

Ministry of Finance and Economic Development

MoU Memorandum of Understanding

MV

MW

Medium Voltage

Megawatt

NPA National Power Authority

OHL Overhead Line

O&M

PAP

PERP

PPE

Operations and Maintenance

Project Affected Persons

Post Ebola Recovery Program

Personal protective equipment

PPP Public Private Partnerships

PIU Project Implementation Unit

PRSP Poverty Reduction Strategy Paper

RAP Resettlement Action Plan

RMC

RoW

SA

SME

Regional Member Countries

Right of Way

Special Account

Small and Medium Enterprise

UA Units of Account

UNIDO United Nations Industrial Development Organization

USD

WB

United States Dollar

World Bank

Page 5: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

iii

Loan Information

Client’s information

COUNTRY: Sierra Leone

BORROWER: Republic of Sierra Leone

EXECUTING AGENCY: Ministry of Energy

IMPLEMENTING AGENCY: Electricity Distribution and Supply Authority

Financing plan

Source Amount (UA

million)

Instrument

ADF

4.621

Loan

ADF

4.688

Grant

Government of Sierra Leone* 0.93 Equity

DFID 27.84 Grant

TOTAL COST 38.08

ADF’s key financing information

Loan / grant currency

Unit of Account

Interest type* Not Applicable

Interest rate spread* Not Applicable

Commitment fee* 0.5% per annum on the un-disbursed loan balance

Service Charge 0.75% on the amount disbursed and outstanding

Other fees* Not Applicable

Tenor 40 years

Grace period 10 years

FIRR, NPV (base case) (9.3%, USD 1.3 million )

EIRR (base case) (20.4%%)

*if applicable

Timeframe - Main Milestones (expected)

Concept Note approval ADF

August 2016 DFID

Project approval December 2016 December 2016

Effectiveness January 2017

Disbursement Closing Date March 2020

Last Disbursement Date June 2020

Completion January 2020

Last repayment December 2056

Page 6: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

iv

Project Summary

Project Overview

The proposed project aims at upgrading and extending the Bo and Kenema

distribution network in order to increase its power transfer capacity and increase the

reliability and availability of power supply within the Bo-Kenema area of Sierra

Leone. More specifically, the project will enable (i) the upgrade and construction of

a 70 kilometre (km) overhead 33 kilovolt (kV) line between Bo and Kenema along

with the construction of two primary substations and rehabilitation of 2 city centres

33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of

Medium Voltage (MV) and Low Voltage (LV) distribution networks within the two

cities, (iii) the implementation of a end-user connection campaign with the objective

to connect 37,000 additional households to the grid (iv) the provision of service for

preparation of designs and bid documents (v) the provision of capacity building to

the Electricity Distribution and Supply Authority (EDSA) relevant stakeholder,

and (vi) the provision of temporary generation during the construction works.

The total project cost is estimated at UA 38.08 million of which, the Bank will

contribute UA 9.309 million, the Department for International Development

(DFID) UA 27.84 million and the Government of Sierra Leone (GoSL) UA 0.93

million. The Bo and Kenema area population, particularly those in rural areas and

low income groups, will benefit from this project as well as small businesses.

Through the provision of increased electricity access, the project will contribute to

improving targeted households’ standards of living in terms of education, health

and access to information. In addition, the project will help increase the

competitiveness of small businesses and expand their activities.

Needs Assessment

In the Bo-Kenema area as in other parts of the country, the limited and dilapidated

power infrastructure base continues to be one of the major constraints to expansion

of electricity access (15%) in the country. The distribution networks supply power

to 10,509 customers in Bo and 6,762 customers in Kenema including Blama’s 250

customers, leaving more than 75% of the population area without access to

electricity. The current peak demand is estimated to be around 7.5 Megawatt (MW), being supplied by a 4 MW diesel generator located in Bo and a 3 MW hydro

power plant in Goma which is however available only during the wet season. This

distribution system is severely constrained due to obsolete equipment, lack of

maintenance coupled with high losses that reach over 38 percent. The components

for the distribution networks were installed in the mid-1980s and many parts of the

system are currently in a very poor state from a health and safety perspective. At

the same time, the Cote D'Ivoire, Liberia, Sierra Leone & Guinea (CLSG)

interconnection is expected to be commissioned in 2018, providing more than 40

MW of firm and relatively low priced electricity to the insulated network. Increasing

the transfer capacity and reliability of the network will be necessary to make profit

from this new supply.

The proposed project is aimed at supporting the Government’s Post Ebola Recovery

Program (PERP) which cited unreliable and limited energy services in urban areas

and the near absence of energy services in rural areas as one of the major obstacles

that adversely impact the rapid response to the EVD crisis.

Bank’s Added Value

The national electricity access rate is 15% and per capita electricity consumption of

130 kWh against 550 kWh on average for Sub-Saharan Africa. The Bank has

extensive experience in conducting the implementation of infrastructure projects in

the region including National and regional Transmission Projects, as well as last

mile connectivity programs. In addition, the Bank is directly involved in the CLSG

project, and will play an instrumental role in adequately phasing the two projects to

leverage economic returns in the area.

Page 7: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

v

Knowledge

Management

The project will include a capacity-building component which includes training for

technical staff of PIU of EDSA and relevant stakeholders in operating and

maintaining the distribution system. The project will provide technical assistance

for the revamping and rehabilitation of the Joint EDSA/Electricity Generation and

Transmission Company (EGTC) training center that trains 20 Electrical Engineers

and 20 Mechanical Engineers at any given academic year. The graduates are

expected to strengthen the planning and operations departments of the respective

utilities and address the shortage of skilled capacity in the energy sector.

Page 8: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

vi

African Development Bank – RESULTS-BASED LOGICAL FRAMEWORK

Country and project name: Sierra Leone – Rehabilitation and Extension of Bo-Kenema Distribution System

Purpose of the project : Ensure reliability of electricity supply and increase access to electricity

RESULTS CHAIN

PERFORMANCE INDICATORS

MEANS OF VERIFICATION RISKS/MITIGATION MEASURES Indicator

(including CSI)

Baseline

(2015)

Target

(2019)

IMP

AC

T

Contribution to socio-economic

growth through improved access

to reliable and quality electricity

services

- # of non-

manufacturing SMEs

Established

- # of

manufacturing units

established

NIL

NIL

200

50

- National Economic Statistics

- EDSA’s Annual Statistical

Reports

OU

TC

OM

ES

Outcome 1:

Improved availability and

reliability of power supply

Average System Power

interruption duration

3 hrs.

2 hrs.

- Ministry Energy

- EDSA’s Annual Statistical

Reports

- Project progress and

completion report

- Project monitoring and post-

evaluation reports

- The risk of failure to achieve operational efficiency

that contributes to sector financial sustainability risk

will be mitigated through implementation of ,state-of-

art smart meters as a commercial management system

(metering and billing collection) and revenue

protection program to reduce the non-technical losses.

Outcome 2:

Reduced power losses and

improved revenue collection of

power utility

Distribution Losses

Bill Collection rate

40%

88%

20%

90%

Page 9: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

vii

OU

TP

UT

S

Component A

New distribution lines constructed

Distribution lines rehabilitated

New substations constructed

New transformers installed

Employment Created

Increased electricity access

- Length of new 33 kV

lines

- Length of new 11 kV

lines

- Length of new 0.4 kV

lines

- Length of 11 kV

rehabilitated

- # of new 33/11 kV

substations

- # of 33/11 kV

substations rehabilitated

- # of new 33/11 kV

transformers

- # of new 11/0.4 kV

transformers

- # of direct and indirect

jobs created during

construction

- # of additional

customers

NIL

35

NIL

2

NIL

NIL

NIL

NIL

- 70 km

- 115 km

- 150 km

35 km

2

2

4

93

- 200 (175 semi/low-

skilled), of which 60

women (30%)

Urban 36,000

Rural 1000

Progress reports from the

EDSA and project supervision

consultant

Bank’s supervision mission

reports

Disbursement and financial

reports from EDSA

Project completion report

- The sector’s technical sustainability risks will be

mitigated though the support of development partners

for the required capacity building program and

recruiting technical staffs for the operation &

maintenance activities.

- Risk of project completion delay will be mitigated by

selecting of well-experienced and reputable contractors

on the basis of EPC contract as well as the involvement

of the supervision consultant to augment project staff as

needed in order to ensure delivery efficiency.

- Risks of delay in procurement process, long approval

processes and contract management will be mitigated

by procuring the supervision consultant to assist

EDSA’s team. Risk: Timely selection of the consultant

-

- Risk of CLSG implementation delay will be Mitigated

through selecting of well-experienced and reputable

contractors on the basis of EPC contract as well as the

involvement of the supervision consultant to augment

project staff as needed in order to ensure delivery

efficiency

- Risk of Co-Financing being cancelled Mitigated by an

Administration Agreement/ Memorandum of

Understanding with clear milestones and disbursement

schedule on DFID contribution

Page 10: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

viii

Component B

Project Administration and

Management enhanced

- # of project progress

reports and

environmental and social

compliance reports

submitted

- # of financial audit

report

- # of environmental audit

reports

- # HIV/AIDS awareness

and prevention and

Health & Safety sessions

conducted

- 4 progress reports / year

including E&S

compliance reporting

- 1 financial report within

6 months after end of

each fiscal year and

- 1 environmental

report/year

- Monthly sessions held for

contractor workers

(100% participation) and

affected communities

Component C

Technical Assistance and

Capacity Building

- #of school rehabilitated

- #of engineers and

technicians trained

- # Sex-disaggregated

impact monitoring

indicators set up and

incorporated in EDSA

studies/reports

- Gender sensitive project

documents developed

using in-house capacity

1

NIL

1

40

Implemented sex-

disaggregated impact

monitoring indicators in

EDSA reports

All EDSA project

documents are

developed using a

gender sensitive

approach with in-house

capacity

Component D

Temporary Generation

Installed capacity

NIL

3.2MW

KE

Y A

CT

IVIT

IES

COMPONENTS INPUTS

A. Rehabilitation and Extension of Distribution Networks (Bo and Kenema)

B. Project Management & Engineering supervision services

C. Technical assistance and Capacity building

D. Temporary generation

Budget (UA Million)

Component A. 30.41

Component B. 1.79

Component C. 2.15

Component D. 3.73

Total 38.08

Financing Plan (UA Million)

ADF 9.309

DFID 27.84

GoSL 0.93

Total 38.08

Page 11: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

ix

Project Timeframe

Year

Quarters 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1

2

3

4

5

6

7

8

9

10

11

Operational acceptance

Last Disbursement date

Description

Appraisal

Project approval

Effectiveness

Selection of consultants

Bid preparation

No

Bidding period

Evaluation, Contract

award and mobilization

Construction

Commissionning

2016 2017 2018 2019 2020

Page 12: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

1

REPORT AND RECOMMENDATION OF THE MANAGEMENT OF THE ADF GROUP

TO THE BOARD OF DIRECTORS ON A PROPOSED LOAN/GRANT TO [SIERRA

LEONE] FOR THE [BO KENEMA DISTRIBUTION SYSTEM REHABILITATION AND

EXTENSION]

Management submits the following Report and Recommendation on a proposed ADF Loan

and ADF Grant of UA 4.621 million and 4.688 million respectively to finance the Bo Kenema

Distribution System Rehabilitation and Extension project in Sierra Leone.

1. STRATEGIC THRUST & RATIONALE

1.1. Project linkages with country strategy and objectives

1.1.1. The proposed project, through the rehabilitation, construction and expansion of the

distribution system, is in line with one of the two pillars of the Bank’s Country Strategy Paper

(CSP) for Sierra Leone’s (2013-17), which seeks to support transformational and sustainable

infrastructure development. The project is also aligned with Sierra Leone’s Agenda for

Prosperity (2013-2018) and the Energy Sector Strategy (2014-2017) which articulate that

energy access is a top priority.

1.1.2. The project is identified as a key deliverable of the Government’s Post Ebola

Recovery Program (PERP) a refocusing of A4P. The PERP cited unreliable and limited energy

services in urban areas and the near absence of energy services in rural areas as some of the

major obstacles to the rapid response during the Ebola crisis. It recognises that improved energy

services in targeting health centres will not only be required for the containment of any future

disease outbreak, but also for the strong economic growth and infrastructure development in

the country.

1.1.3. The project is directly aligned with the Bank’s ‘High 5s’1 goals, in particular

Lighting Up and Powering Africa and indirectly with Industrializing, Feed Africa, Integrating

Africa and Improving the Quality of Life of Africans. In addition, it is consistent with the Bank’s

New Deal on Energy for Africa, that relate to which focuses on tackling the energy shortages,

high cost and poor access that are impeding Africa’s continued social and economic progress.

The strategy’s flagships programs will support respective countries in developing an energy

value chain that is available, reliable, affordable and sustainable. In particular, the project aligns

to the Power Utility Transformation, Bottom of the Pyramid and Energy Efficiency flagships.

The Project is also well aligned with the inclusive growth objective of the Bank’s Ten Year

Strategy (“TYS”) which has core priorities areas, such as infrastructure development and

universal access to electricity in Africa by 2025. It will also help to implement the Bank’s

Energy Sector Policy approved in 2012, which has a two-fold objective: (i) support efforts of

Regional Member Countries (RMC) to improve access for the population and production

sectors to modern, reliable and affordable energy infrastructure and services; and (ii) assist

RMCs to develop an energy sector that is viable at the social, economic and environmental

levels. Lastly, the project is also in line with the Bank Group’s Strategy on addressing Fragility

and Building Resilience in Africa. A key focus of the strategy is strengthening state capacity,

establishing effective institutions and promotion of inclusiveness to build resilient societies

11 The High-5, an emphasis within the Ten Year Strategy framework intended to scale up investments in some

key areas of the TYS, are: Light Up and Power Africa, Integrate Africa, Industrialize Africa, Feed Africa and

Improve the Quality of Life for African.

Page 13: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

2

1.1.4. The proposed project is aligned with the vision and goals of the sector which is to

ensure a reliable supply of electricity to contribute to poverty alleviation through economic

development.

1.2. Rationale for Bank’s involvement

1.2.1. Sierra Leone experienced a decade long civil war (1991-2001) that damaged

physical infrastructure, particularly electricity, water, and sanitation. Despite peace and strong

economic growth since 2002 (end of civil conflict), the Ebola Virus Disease (EVD) outbreak

in 2014 proved a major setback to commendable progress towards reconstruction and national

development in the country. As of 2015, Sierra Leone ranked 181 out of 188 countries in the

United Nations (UN) Human Development Index and had an estimated gross national income

per capita of US$1,780 (current prices), placing it in the bottom third of countries in Sub-

Saharan Africa.

1.2.2. Electricity access and consumption in Sierra Leone are among the lowest in Africa

at less than 15% against an average rate of 40% in 2013 for the continent. The limited and

dilapidated power infrastructure base continues to be a major constraint to expand electricity

access in the country. Tariffs are high at US$ 0.22 per kWh (estimated for 2015), generating

capacity is insufficient, electricity services are of poor quality, and sector management is weak

which leads to inefficient operations. The main distribution network extends to Freetown and

the surrounding Western Area, covering only about 40% of the residents. Isolated systems (Bo-

Kenema, Lungi, Lunsar, Kono, and Makeni) provide limited services in delimited areas in other

parts of the country. In rural areas, where the bulk of the population resides, electricity access

is practically non-existent. During the dry season, when the available hydropower drops to

extremely low levels, the use of captive power generation is widespread and imposes high cost

of production. The industrial and commercial business sector has to rely on expensive captive

diesel-fired generators.

1.2.3. The electricity sector is undergoing a fundamental change. The National Electricity

Act, 2011 (the Electricity Act) repealed the National Power Authority Act, 1982, and

unbundled the National Power Authority (NPA) into (i) the Electricity Generation and

Transmission Company (EGTC); and (ii) the Electricity Distribution and Supply Authority

(EDSA). Implementation of the unbundling was delayed until January 2015 when EGTC and

EDSA became operational. EGTC is in charge of electricity generation and transmission at

high voltage levels (66kv and above) whilst EDSA is responsible for sub-transmission and

electricity distribution (33kV and below). EDSA supplies about 75,000 customers mainly

located in the Western Area (around Freetown).The majority of the staff has been transferred

from NPA to EDSA and EGTC but the transfer of assets and obligations, while ongoing, is yet

to be completed. Oversight of the sector falls under the Ministry of Energy (MoE). Tariff

setting is governed by the Electricity and Water Regulatory Commission Act 2011 that also

established the regulatory authority, the Electricity and Water Regulatory Commission

(EWRC) with the mandate to determine and review tariffs.

1.2.4. Current power generation capacity is inadequate to meet power demand. The

installed system’s capacity serving the Freetown Capital totals 84 MW, predominantly

hydroelectric in nature. This includes the Bumbuna hydroelectric power plant (50 MW), the

two thermal power plants at Kingtom (10 MW) and Blackhall Road (16.5 MW) and

containerized generation units installed at Kingtom. An additional 35 MW feeds the isolated

Bo-Kenema, Lungi, Lunsar, Kono, and Makeni systems. The mining sector and large industrial

Page 14: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

3

companies relies entirely on captive generation estimated at 76MW and 83MW respectively to

meet their power needs. Hydropower from Bumbuna is highly seasonal with production

fluctuations from about 15 MW in the dry season to 30-40 MW in the rainy season. Most

commercial and industrial customers are currently not connected to the grid because of

inadequate and unreliable electricity supply. Electricity demand growth, which is mainly driven

by the development of new industrial and residential areas, is projected to reach 350 MW and

934MW for the domestic and mining sector by 2020.

1.2.5. More specifically, in the project target area around Bo and Kenema towns, an

insulated power system covers an area populated by slightly more than 500,000 inhabitants.

The distribution networks supply power to 10,509 customers in Bo and 6,762 customers in

Kenema, and 250 customers in Blama leaving more than 75% of the population area without

access to electricity. The current peak demand is estimated to be around 7.5 MW, being

supplied by a 4 MW diesel generator located in Bo and a 3 MW hydro power plant in Goma

connected to Kenema which is however available only during the wet season. This distribution

system is severely constrained due to obsolete equipment, lack of maintenance coupled with

high losses of over 40%. A single circuit 33kV interconnector allows the load to flow from Bo

to Kenema during the dry season when Goma is not producing, but any fault in this line leaves

Kenema in the dark. The components for the distribution networks were installed around the

mid-1980s and many parts of the system are now in a very poor state from a health and safety

perspective.

1.2.6. The proposed project is expected to upgrade the Bo – Kenema interconnector into

a 33 kV double circuit 70 km overhead line within the existing Right of Way (RoW) that will

increase the transfer capacity between the two towns. The project also intends to construct new

substations located on the outskirts of Bo and Kenema to help manage voltage issues and help

improve load growth. System availability will be further increased through the construction of

11kV ring distribution lines that will feed the low voltage transformers to supply both domestic

and commercial customers.

1.3. Donors coordination

1.3.1. Sierra Leone is highly dependent on foreign aid with transfers approaching 6% of

the national GDP in 2015. Within the context of the Busan New Deal, the aid framework is

structured around the Mutual Accountability Framework (MAF)2 adopted in 2014 between

Government of Sierra Leone (GoSL) and the Development Partners (DPs). The Development

Assistance Coordination Office (DACO) in the Ministry of Finance and Economic

Development (MoFED) spearheads the formulation of aid policy3. The most active DPs in the

energy sector in Sierra Leone are the AfDB, World Bank (WB), Department for International

Development (DFID), Islamic Development Bank (IsDB), Japan International Cooperation

Agency (JICA), European Investment Bank (EIB), Millennium Challenge Corporation and

Economic Community of West African States ECOWAS. The Bank jointly with these

development partners is supporting the sector in the region. In Sierra Leone for example, the

Bank, the WB and the EU are financing the Cote d’Ivoire – Liberia – Sierra Leone – Guinea

2 It sets out the partnership required for the successful implementation of the Agenda for Prosperity (2013-

2018), including the formulation of steps towards enhanced alignment and harmonization and increased use of

country systems. 3 Dialogue with the DPs is conducted through the Development Partnership Committee (DEPAC), co-chaired by

the Minister of Finance and Economic Development and by the United Nations and the World Bank. DEPAC

convenes on quarterly basis, and once a year the Presidential DEPAC is held which is chaired by the President

of the Republic. Coordination and collaboration of development partners in Sierra Leone continues to be strong.

Page 15: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

4

Interconnection Project; The Bank’s comparative advantage lies in its vast experience in the

infrastructure sectors. (Appendix II).

2. PROJECT DESCRIPTION

2.1. Project Components

2.1.1. The project’s ultimate development objective is to provide reliable electricity

supply and access through the complete rehabilitation, upgrade and expansion of the Bo and

Kenema distribution network expected to cater for the newly developed communities who do

not have access to electricity. More specifically, the project will enable construction of

distribution lines, substations and end user connection campaign in Bo and Kenema. It will also

include (i) the upgrade and construction of a 70 km overhead 33kV line between Bo and

Kenema along with the construction of primary substations and rehabilitations in each city (ii)

the rehabilitation and expansion of MV and LV distribution networks within the two cities (iii)

the implementation of a end-user connection campaign with the objective to connect 37,000

additional households to the grid (iv) the provision of service for preparation of designs and

bid documents (v) the provision of capacity building to EDSA relevant stakeholder and (vi) the

provision of temporary generation during the construction works

Table 2.1: Project Components

Project Components

Estimated

cost (million

UA)

Component Description

A

Rehabilitation and

Extension of Distribution

Networks

30.40

Distribution lines : (i) the upgrade and construction of a 70 km

overhead 33kV line between Bo and Kenema (ii) the construction

of 115 km of 11 kV line and the rehabilitation of 35km of 11 kV line

(iii) the construction of 150 km LV 0,4kV distribution line in Bo and

Kenema.

Substations : (i) the construction of 2 new 33/11kV substations in

Bo an in Kenema, the rehabilitation of 2 city centres 33/11kV

substations in Bo and Kenema; the construction of 4 new 33/11kV

transformers between the two cities and (ii) installation of 93 new

11/0,4kV transformers in the distribution system.

End-user connections : Launching awareness campaigns about

access to energy and providing funding for 37,000 end-user

connections to the network

B

Project Management &

Engineering supervision

services

1.79

Provision of service for preparation of bidding documents, assisting

the client in the bidding process, supervision of construction

activities and project management.

Provision of Capacity building to EDSA Project Implementation

Unit and relevant stakeholder to enhance project implementation

effectiveness

C Technical assistance and

Capacity building 2.15

.Capacity and Skill Enhancement Program

Assisting EDSA and EGTC to revamp the joint training centre to

improve technical operations in the long run.

D Temporary generation4 3.73 Providing temporary generation in the city of Kenema during the

construction works of the 33kV line occurring in dry season.

Total 38.08

4 Temporary generation is required to support the power supply during the overhead line rebuild. It is estimated

that 3.2MW will be required for a period of approximately six months in accordance with the project construction

programme

Page 16: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

5

2.2. Technical solution retained and other alternatives explored

2.2.1. Constructing a 33kV double circuit overhead line between Bo and Kenema along

the route of the existing 33kV single circuit was chosen as the preferred option. This option

would require the disconnection of the 33kV supplies between Kenema and Bo during the

construction works. Building the new double circuit within the existing wayleave allows for

new structures to be built on line. The construction of the overhead line will require

disconnecting the power supply between Bo and Kenema. This will need temporary generation

to ensure Kenema dependent on Bo for power supply, shall not be without electricity. The

option was chosen due to; (i) availability of existing data for the existing overhead line profile

sheets and route plans for the complete route; (ii) an existing way leave is in place for the route;

(iii) this route will minimise environmental and social impacts and will facilitated the access

to the line for maintenance; (iv) overhead line design to allow future upgrading to 66kV; (v) a

33kV ring can be developed in future years when the demand necessitates additional growth.

2.2.2. Several project alternatives were considered, however, the reasons for their

subsequent rejection as provided in Table 2.2 below.

Table 2.2: Project Alternatives Considered and Reason for Rejection

Alternative name Brief description

Reasons for rejection

1 Single-circuit 66kV Construction of a single circuit 66 kV

overhead line, enabling to increase the

transfer capacity between Bo and

Kenema

• Technical studies

highlighted that a 33kV double

circuit OHL is suitable for the

predicted demand/load flows

• A 33kV double circuit

OHL is a more resilient design in

case of fault of one circuit; and

• A 66kV single circuit

has an estimated cost 60% higher.

2 33kV Offline build new route Development of a new overhead line

following a corridor running parallel

with the Bo–Kenema highway,

therefore reducing the need for

temporary generation to be located in

Kenema during the rebuild of the

existing overhead line.

• By taking a new

overheard line, this will result in

more environmental and in

particular social impacts (such as

resettlement). The project will

require a full RAP which could

impact the project

implementation from a timeline

and costs basis as a result of new

wayleaves.

3 33kV Underground Cable Construction of a new 70km 33kV

express circuit underground

• It will create switchgear

rating issues associated with

capacitive switching.

• It will be difficult to

upgrade at a later date and would

levy a greater capital cost.

2.3. Project type

2.3.1. The proposed intervention is a standalone investment project. The project is

intended to benefit 17,521 customers (10,509 in Bo, 6,762 in Kenema including 250 in Blama)

and provide 37,000 additional connections to the grid network. Other villages and communities

Page 17: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

6

along the project corridor notably Baoma, Yamandu, Gerehun, Mano Junction and Panguma

shall be connected to the distribution line.

2.4. Project cost and financing arrangements

2.4.1. The project costs, including a physical contingency of 10% and a price contingency

of 15% but excluding customs and duties, is estimated at UA 38.08 Million (approximately

equivalent to USD 53.08 Million). The project is financed at 24% by the Bank, 74% by DFID

and 2% by the GoSL5. The total costs incurred in foreign and local currency amount to UA

32.22 Million and UA 5.85 Million respectively, which accounts for 84.60% and 15.40% of

the project costs. Project cost estimates by component, category and by source of financing are

shown in the tables below.

Table 2.3: Project cost estimates by component [amounts in million UA equivalents]

Project Components FC LC Total % foreign

A Rehabilitation and Expanding Distribution Networks 20.67 3.65 24.32 85.0%

B Project Management & Engineering supervision services 1.26 0.17 1.43 88.0%

C Technical assistance and Capacity building 1.31 0.41 1.72 76.0%

D Temporary generation 2.54 0.45 2.98 85.0%

Base cost 25.78 4.68 30.46 84.6%

Physical contingency (10%) 2.58 0.47 3.05 84.6%

Price contingency (15%) 3.87 0.70 4.57 84.6%

Total project cost 32.22 5.85 38.08 84.6%

Table 2.4: Source of financing [amounts in million UA equivalents]

Project Components AfDB DFID GoSL Amount (UA M)

A Rehabilitation and Expanding Distribution Networks 7.53 21.95 0.93 30,41

B Project Management & Engineering supervision services 1.79 - - 1,79

C Technical assistance and Capacity building - 2.15 - 2,15

D Temporary generation - 3.73 - 3,73

Total 9.309 27.84 0.93 38.08

Note: Exchange rates are provided in the introduction of this report - page (i).

Table 2.4: Sources of financing [amounts in million UA equivalents]

Sources of funding FC LC Total % foreign

ADF 7.94 1.34 9.28 85.6%

DFID 23.50 4.37 27.87 84.3%

GoSL 0.79 0.14 0.93 85.0%

Total project cost 32.22 5.85 38.08 84.6%

Table 2.5: Project cost by category of expenditure [amounts in million UA equivalents]

Categories FC LC Total % foreign

Works 29.01 5.12 34.13 85.0%

Services 3.21 0.73 3.94 81.5%

Total project cost 32.22 5.85 38.08 84.6%

5 Appendix V - Justification to finance 10% of project cost financing by the Government

Page 18: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

7

Table 2.6: Expenditure schedule by component [amounts in million UA equivalents]

Project Components 2017 2018 2019 2020 Total

A Rehabilitation and Expanding Distribution Networks - 9.12 15.20 6.08 30,40

B Project Management & Engineering supervision services 0.45 0.45 0.45 0.45 1,79

C Technical assistance and Capacity building 0.54 0.54 0.54 0.54 2,15

D Temporary generation - 2.24 - 1.49 - 3,73

Total 0.99 10.11 18.42 8.56 38.08

Table 2.7: Project cost by category of expenditure ADF Loan [amounts in million UA

equivalents]

Categories FC LC Total % foreign

Works 3.928 0.693 4.621 85.0%

Services - - - 0.0%

Total project cost 3.93 0.69 4.621 85.0%

Table B.2.8: Project cost by category of expenditure ADF Grant [amounts in million UA

equivalents]

Categories FC LC Total % foreign

Works 2.461 0.434 2.895 85.0%

Services 1.524 0.269 1.793 85.0%

Total project cost 3.985 0.703 4.688 85.0%

2.4.2. The Bank’s financing, representing 24% of the total project cost estimates, will be

sourced from Sierra Leone’s Performance Based Allocation (PBA) under ADF-13. The GoSL

counterpart financing for the project is applied on the Bank’s financing component.

Justification to finance more than 90% is based on the country’s commitment to implement its

overall development program; (ii) the financing allocated by the country sectors targeted by

Bank assistance; (iii) the country’s budget situation and debt level (see Appendix V)

2.5. Project’s target area and population

2.5.1. The project will cover the population living in the towns of Bo and Kenema and the

villages in the area between the two towns. The project area is populated by slightly more than

500,000 inhabitants who will benefit from enhanced electricity supplies in a variety of ways

more generally. The proposed project seeks to enhance reliability of supply for existing

consumer connections approximately 17,521 customers (10,509 in Bo, 6,762 in Kenema

including 250 in Blama6) and provide 37,000 additional connections to the grid network. The

direct beneficiaries of the project are households, small businesses and manufacturing units

located in the towns of Bo-Kenema as well as Blama.

6 Blama is a town located between Bo and Kenema expected to benefit from the project.

Page 19: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

8

2.6. Participatory process for project identification, design and

implementation

2.6.1. Bank’s Identification, Preparation and Appraisal missions consulted widely with

the stakeholders, at national and local levels. Development Partners who are active in the

energy sector were also consulted, resulting in the co-financing from DFID. During the

identification, preparation and appraisal phases, the Bank’s objective was to ensure that all

stakeholders and interested parties, are fully informed of the proposed project consultations

were held with relevant stakeholders and their concerns were documented. The stakeholders

consulted included; Bo and Kenema District Local Government Officials such as the Chief

Administration Officers, District Environment Officers (DEOs), District Development Officers

(DDOs) and the district engineers amongst others. Meetings were also held with statutory

agencies which included; Environment Protection Agency (EPA-SL), HIV/AIDS Secretariat

and Electricity Generation and Transmission Company (EGTC).

2.6.2. In addition, meetings were held with staff of Ministry of Finance and Economic

Development (MoFED), Ministry of Energy (MoE), Ministry of Tourism and Cultural Affairs

(MoTCA), Ministry of Agriculture, Forestry and Food Security (MoAF&FS) Ministry of

Health and Sanitation(MoHS) and Ministry of Gender, Social Welfare and Children Affairs

(MoGSWCA). The consultant also met and held discussions with the paramount chiefs of

Kakua and Gerihum chiefdoms. Other meetings were held with women conducting roadside

trading in the areas of Bandajuma, Gerenum, Boama, and Blama areas along the Bo-Kenema

highway.

2.7. Bank Group experience, lessons reflected in project design

2.7.1. As of 10 October 2016, the Bank portfolio is comprised of 12 national operations

for a total commitment of UA 111.22 million. This includes 10 ADF/Transitional States Fund

(TSF) funded operations for the total sum of UA 88.71 million and 2 ADB funded operations

totalling UA 22.51 million representing respectively 79.76% and 20.24% of the ongoing

portfolio. Investments represent 92.20% of the total commitment, the rest being institutional

support (7.80%). 4 operations are co-financed with Global Environment Fund (GEF), DfID,

OPEC Fund for International Development (OFID) and Rural Water Supply and Sanitation

Initiative (RWSSI) to the tune of UA 49.97 million.. Infrastructure accounts for 90.22% of total

operations - with energy, transport and water and sanitation sharing respectively 21.71%,

28.84% and 49.45% of total commitments in Infrastructure. The remaining investment include

governance and finance (7.15%) and social including gender (2.63%). (see Appendix II).

2.7.2. In October 2016, cumulative disbursement reached UA 21.14 million, representing

a disbursement ratio of 19.01%. This significant drop compared to 36.48% in January 2016

which was due to the fast-tracked disbursement of Ebola related operations, signifies the

normalization of activities in Sierra Leone. The portfolio is on average 2.63 years old with no

ageing projects and no projects at risk. It is globally deemed satisfactory with average

Development Outcome (DO) and Implementation Progress (IP) ratings are 2.75 and 3.05,

respectively.

2.7.3. Lessons Learnt: In the energy sector, important lessons can be drawn from the

Bank’s past interventions in Sierra Leone mainly the Bumbuna Hydro project. The project was

successfully implemented after a civil war, however, the long lead times in finalizing contracts

Page 20: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

9

led to supplementary financing to address the cost overruns. For improved fiduciary

compliance, closer Bank staff monitoring and support was required during implementation,

and where compliance is not achieved, the Bank may need to invoke sanctions such as

withholding additional disbursements to ensure compliance with financial reporting and audit

requirements. Subsequently, it was noted that weak implementation capacity due to limited

expertise and insufficient staffing to implement projects; ensuring participatory approach of

community involving elected local councils, Paramount Chiefs and communities; ensuring

effective communication with all relevant stakeholders; providing technical support to the

Project Implementation Unit (PIU) is key in ensuring sustainable implementation of Bank

projects.

2.8. Key performance indicators

2.8.1. The project will result in (i) improving availability and reliability of power supply

thus resulting in an increase in economic activities which are currently impaired by the lack of

reliable electricity supply; and (ii) reduced power losses and improved revenue collection of

power utility. The project also includes a technical assistance to revamp and rehabilitate the

EGTC training school and capacity building enhancement program. The Result Based

Logframe of the project reflects the performance indicators for the project at input, output and

outcome levels. Key among them are :(i) for the outputs: number of switching gears

rehabilitated; kms of 33kV constructed, 0.4Kv, 11kV and 33kV line rehabilitated; number of

substations upgraded and rehabilitated ; (ii) for the outcomes: reduced average power

interruption duration per year on distribution network and reduced distribution loses,

HIV/AIDS awareness and prevention and Health & Safety sessions conducted, # Sex-

disaggregated impact monitoring indicators set up and incorporated in EDSA studies/reports,

Gender sensitive project documents developed using in-house capacity

3. PROJECT FEASIBILITY

3.1. Economic and financial performance

3.1.1. Following project implementation, it is expected that the power transfer capacity

will be significantly increased enabling 37,000 residential consumers to be connected to the

Bo-Kenema grid by 2020 and improving the reliability for the 16,000 existing consumers. This

translates into electricity access to approximatively additional 215,000 people, and an increase

in supply of 80 GWh in the area.

3.1.2. The financial benefits for the company will accrue from increased revenues from

electricity consumption charges, whilst the financial costs include mainly power purchase costs

and operating costs. The average weighted power purchase cost is very high in the insulated

Bo and Kenema network (more than 0.26 USD/kWh, more than current tariff averaging 0.22

USD/kWh) due to reliance on very expensive diesel engines, with a variable cost of 0.35

USD/kWh. However, new supplies from CLSG and solar farm are expected to replace diesel-

based generation and dramatically decline the average weighted power purchase cost to 0.15

USD/kWh by 2020.

3.1.3. The financial and economic assessment of the project is undertaken over an

operating period of twenty years starting in 2020. The investment is carried out over three years

(2017 to 2020). The financial assessment of the proposed project estimated a financial internal

rate of return (FIRR) and a financial net present value (FNPV) of 9.3% and USD 1.3 million

(at a 5% real discount rate) respectively, showing that the project is financially viable. This,

Page 21: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

10

however, relies on an increase of average step - tariff of 25% before 2020 when the project is

fully operational based on data from the project technical feasibility studies conducted by the

consultants and completed in August 2016. The regulator has approved the tariff adjustment.

3.1.4. The project will further enable a rehabilitation and upgrade of the MV and LV

distribution system. The bulk of the benefits are expected to derive from more reliable and

expanded electricity supply to the benefit of end-consumers. The benefits of extended access

to consumers is generally assessed through their willingness to pay (WTP) which is estimated

to be 0.30 USD / kWh in Sierra Leone. The economic assessment of the project reflected an

economic rate of return (EIRR) of 20.4% and economic net present value (ENPV) of USD 13.4

million (discounted at 12%, real).

3.1.5. Table 3.1 summarizes up the main financial and economic indicators of the project.

The complete analysis and assumptions are detailed in the Technical Annex B.6.

FIRR, NPV (base case) 9.3%, USD 1.3

million

EIRR (base case) 20.4%

NB: detailed calculations are available in Annex B7

3.1.6. The financial and economic returns of the project have been tested against the

possible risk parameters during the construction and operation phases. The identified key risks

include investment costs overrun, a delay in CLSG in-feed to the network, the failure to align

tariff with the cost structure of EDSA leading to a reduction in revenues, and the number of

additional households connected. The sensitivity analyses show that the financial and economic

returns are robust under identified adverse conditions concerning cost overruns. The analyses

also reveal that the economic and financial performance deeply relies on the timely

construction of the CLSG interconnection, or the availability of any cheaper supply than current

diesel engines. A two year- delay in CLSG construction would reduce the EIRR to 11.8%

(below the hurdle rate of 12%) and the FIRR to 1.7%. This highlights that the project makes

economic and financial sense only if closely phased with the CLSG investment. Financial

sustainability of the project relies on an increase of step-tariff of at least 25% to enable a

financial return above zero. The details of the sensitivity analysis are shown in the Technical

Annex B.7.

3.2. Environmental and Social impacts Environment

3.2.1. Environment: The project is a category 2 type since its infrastructure works will be

undertaken within the existing 33kV RoW whose vegetation is routinely cleared to allowable

heights while densification works will be undertaken along existing roads within the towns. The

2 new sub-stations will be on vacant lands without any vegetation and about twenty two (22)

housing structures, one (1) makeshift blacksmith workshop and twenty (20) trees will be lost

with an estimated one hundred and fifteen (115) Project Affected Persons (PAPs) to be

impacted. In line with the Bank’s Integrated Safeguard System requirements an Environmental

and Social Management Plan (ESMP) as well as an Abbreviated Resettlement Action Plan

(ARAP) were prepared for the project and finalized in October 2016. The E&S reports were

further submitted to the Compliance Division for review, approved and disclosed on the Bank’s

website on November 8th, 2016. The approval was undertaken and the license granted in

November 2016.

Page 22: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

11

3.2.2. The positive outcomes of the project include an increase in the number of people

connected to the electricity supply, creation of employment opportunities, improved local

socio-economic conditions through value addition on agricultural products, development of

SMEs, and improved delivery of health services especially ante-natal services as well as

improved security in the trading centers. The negative impacts of the project will include

mainly, loss of vegetation, soil erosion arising from excavations of pole foundations to be

mitigated through compaction of loose soil surfaces, management of construction waste, site

restoration, and safety concerns to be addressed through use of personal protective equipment

(PPE).

3.2.3. Mitigation Measures such as integration of the project Bill of Quantities,

monitoring by the EPA-SL, supervision missions by the Bank, conducting environmental

audits, and continued awareness on safety by EDSA alongside building capacity of the utility’s

Environmental Unit and the PIU, will support enhancement of mitigation measures.

3.2.4. Climate change: Lighting, storm impacts and temperature fluctuations constitute

some of the likely risks of climate change on electricity distribution infrastructure. These

impacts will be mitigated through installation of aluminum types of lightning arresters on

electricity facilities; routine clearance of vegetation along the RoW thereby eliminating risks

of tall trees falling on the power lines and use of approved steel poles which will be sunk 1.0-

2.0m deep for stability against impacts of storms and spaced at 50-60m apart to avoid sagging

of conductor cables during expansion and contraction without breakages. Changes in rainfall

patterns which triggers use of thermal generation resulting into carbon emissions is to be

mitigated through tree planting around thermal power plants and use of technologies which

reduce acoustic impacts from the plants.

3.2.5. Gender: In accordance with Bank Group Policies the project will ensure inclusion

of women, marginalized people and develop their communities. The Bo and Kenema

Distribution System Rehabilitation and Expansion Project aims to minimize the power supply

crisis in these towns and country as a whole. The project will maintain security of electricity

supply, satisfy short-term demand and improve electricity access, reliability, and quality of

supply to consumers. The main socio-economic impact of the proposed project is to supply

adequate and reliable power for customers, industrial development and businesses in the Bo

and Kenema area and strengthening of power supply to the surrounding cities (Goma) where

the lack of supply and frequent power interruption has significantly affected the provision of

vital social services, including health delivery and water supply.

3.2.6. During project implementation about 30% of the workers on the project will be

women alongside men which is in line with the national gender affirmative action. Along the

road in the project areas, women are involved in small-scale trading and though their operations

to a large extent, are hampered by availability of affordable and reliable electricity. Most of

them claim they cannot engage in the selling of cold drinks in their retail shops due to high

energy costs of acquiring and running petrol generators. It is proposed that funds be earmarked

for women operating roadside businesses in Baoma junction, by setting up roadside market

shelter and associated facilities for storage of their produce awaiting transit to Freetown. The

improvement will include providing separate toilets for male and female and area local chiefs

are in support of this proposal and are willing to offer land for the development.

3.2.7. Social: The power project will promote the development of agro-processing

activities such as rice and maize milling and packaging, processing of palm oil, cassava and

Page 23: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

12

kola nuts amongst others. Such interventions will lead to value addition which is likely to

translate into better incomes at household levels. These activities once enhanced will provide

means of livelihoods to both men and women and bring about growth and development in the

community on many fronts. It is also envisaged to support mining operations and a range of

cottage industries. It is further expected to create some estimated 200 jobs across its various

activities and based on the national gender laws, 30% of these jobs will be availed to the women

and this will give them alternate sources of incomes to support their households. The project

will also lead to improved delivery of social services especially ante-natal i.e. vaccination

which will improve child survival. The availability of electricity will lead to growth of small-

scale enterprises such as restaurants and salons which will provide additional sources of

livelihoods for the operators.

3.2.8. HIV/AIDS and EVD: It is reported that, though there is awareness in the country

on risks of HIV/AIDS and STIs\STDs, large part of the communities have very little knowledge

about its effects. Therefore, interactions between the project workers and the local communities

could likely lead to some sexual relationships thereby triggering infections. Furthermore,

available information indicates that, there is a lot of unknown information on EVD and it is

clear, the disease will not completely disappear from the region, as such, there will be few cases

re-occurring in a less virulent manner. In light of the above, EVD and HIV/AIDS, STI/STDs

prevention measures have been mainstreamed into the project with a focus on sensitization and

awareness of the workers and the neighboring communities as well as VCT services and

condom distribution on HIV/AIDS.

3.2.9. Involuntary resettlement: The 2 new sub-stations will be on vacant lands without

any unique vegetation and about twenty two (22) housing structures, one (1) makeshift

blacksmith workshop and twenty (20) trees will be lost with an estimated one hundred and

fifteen (115) Project Affected Persons (PAPs) to be impacted. In such circumstances, EDSA

will compensate affected persons in accordance with the Bank’s Policy of Involuntary

resettlement and by applying the principles stipulated in ARAP developed based on AfDB

guidelines

4. IMPLEMENTATION

4.1. Implementation arrangements

4.1.1. The Government of Sierra Leone shall be the Borrower of the loan and grant. The

Ministry of Energy will be the Executing Agency, and EDSA, the Implementing Agency of the

project.

4.1.2. Institutional Arrangements: A Steering Committee (SC) will be established to

provide strategic oversight on project execution and implementation through coordinated

monitoring and evaluation of major milestones. The SC shall be under the Chair of the Ministry

of Energy and consists of the Ministry of Finance and Economic Development, the Chairperson

of EPA, the Director General of EDSA and the Director General of EGTC.

Page 24: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

13

4.1.3. EDSA has a dedicated Project Implementation Unit (PIU) established under the

WB Energy Sector Utility Reform Project7. The PIU shall have the mandate to implement the

Bo Kenema project and subsequent donor funded projects. The PIU comprises of a Project

Manager, a Procurement Officer, an Environmental Officer, a Social Officer, a Project

Engineer and a Financial Management Specialist. The PIU shall be staffed with EDSA internal

staff, however, cognisant of the lack of skilled experts, key specialists shall be recruited

competitively to enforce EDSA capacity. In particular, a project management and supervision

specialist, financial management specialist and procurement specialist shall be engaged to

assist EDSA in the preparation of bidding documents for the project; provide support in the

project supervision. The PIU shall be under the guidance of the Director of Corporate Planning

and Project within EDSA’s organization structure.

4.1.4. Implementation Schedule: Overall, the project will be implemented over a period

of 36 months. The project time frame is included and the implementation timelines are

summarised in Annex B.9.

4.1.5. Procurement Arrangements: “Procurement of works and the acquisition of

consulting services, financed by the Bank for the project, will be carried out in accordance with

the “Procurement Policy and Methodology for Bank Group Funded Operations” (BPM), dated

October 2015 and following the provisions stated in the Financing Agreement. Specifically,

Procurement would be carried out following:

4.1.6. Bank Procurement Policy and Methodology (BPM): Bank standard PMPs, using

the relevant Bank Standard Solicitation Documents (SDDs), will be used for International

Competitive Bidding (ICB) contracts for both works and Acquisition of Consulting Services

as indicated in the Technical Annex B5, Para. B.5.3.2.

4.1.7. Borrower Procurement System (BPS): The utilization of BPS will not apply to

this project as it is envisaged that large contracts will evolve from the various procurement

processes as the associated risk for the use of BPS for large contracts is high.

4.1.8. Procurement Risks and Capacity Assessment (PRCA): the assessment of

procurement risks at the Country, Sector, and Project levels and of procurement capacity at the

Executing Agency (EA), were undertaken for the project and the output have informed the

decisions on the procurement regimes (BPS and Banks PMP) being used for specific

transactions or groups of similar transactions under the project. The appropriate risks mitigation

measures have been included in the procurement PRCA action plan proposed in Annex B5.

4.1.9. Financial Management: The general observation of the latest Country Fiduciary

Risk (CFR) of Sierra Leone has shown positive transformation in regulatory framework for

Public Financial Management (PFM) including significant gains recorded in external scrutiny

and aspects of financial reporting as a result of the continued implementation and roll out of

the Integrated Financial Management Information System (IFMIS). Pervasive weaknesses

however continues with budget credibility and predictability, expenditure control (including

payroll) and continued low levels of transparency. Significant lags still exist in the development

of Internal Audit into a modern and effective unit, maintenance of adequate government fixed

assets records, and slow progress towards introduction of a necessary treasury single account.

7 The Energy Sector Utility Reform Project is supporting the GoSL in the recruitment of a management contractor for EDSA

who will be responsible for implementing a business plan for EDSA, improving collections, re-organizing the utility to focus

on commercial performance, and building capacity for a period of three years.

Page 25: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

14

Overall, CFR was rated Substantial. EDSA is in its second year of effective operation with first

audit report expected by October 2016. The healthiness of EDSA’s financial position cannot

be determine at this stage as the financials are subject to audit currently.

4.1.10. Project accounting is manual, based on excel, along with the non-use of EDSA’s

budget and financial operating manuals for preparing, validating and executing the project’s

annual work plan and budget. EDSA is expected to develop a project implementation manual

to guide project operations, including revision and validation of the draft financial operating

manuals. Thus, it is recommended, overall responsibility for project accounting remain with

EDSA Financial Controller including absorbing standalone projects in to the Great Plains

accounting software. Submission of quarterly interim financial reports to the Bank and

quarterly coverage by EDSA’s internal audit unit would act as an ex-poste mitigation of the

existing risks.

4.1.11. Disbursement: The project is expected to consist of few major contracts, direct

payment arrangements will be used for this purpose, and if required, (condition upon a formal

request to the Bank) the use of a reimbursement guarantee method may also be used alongside

for imports. The project is expected to operate a Special Account (SA) for operational expenses,

and EDSA will open a segregated USD "Special Account” at a commercial bank acceptable to

the Bank. Management of the SA will follow EDSA’s financial operations manual with

approval signatories restricted to EDSA’s Director General, Deputy Director General, and

Financial Controller. All disbursement including replenishments of the SA will be in

accordance with the Bank’s Disbursement Handbook.

4.1.12. Audit: The Audit Service Sierra Leone (ASSL), has primary responsibility for

external audit of all government funds (including funds from donors), and has direct

involvement in the procurement and selection of firms to be engaged as auditors for projects

financed by development partners (including the Bank). The ASSL or an independent audit

firms will conduct the audit on terms of reference acceptable to the Bank. The audited financial

statements and associated management letter shall be submitted to the Bank within six months

of the end of each financial year audited.

4.1.13. Overall Conclusion: The assessment concluded that, EDSA’s FM capacity along

with the proposed mitigations, will have the capacity to ensure: (a) that project funds are used

only for the intended purposes in an efficient and economical way; (b) the preparation of

accurate, reliable and timely periodic and annual financial reports; (c) that any assets purchased

using project funds are adequately safeguarded. The detail FM assessment is attached as Annex

B

4.1.14. DFID financing shall be administered through the DFID/Technical Cooperation

Framework Arrangement as per the Template Administrative Agreement (Annex A-

Framework)

4.2. Monitoring

4.2.1. Monitoring will be based on the Project’s Results-Based Logical Framework,

including the key indicators for monitoring progress towards achievement of project outcomes.

Monitoring and Evaluation (M&E) activities will be undertaken at national and local levels as

appropriate, with EDSA shouldering the overall responsibility in line with its institutional

mandate. EDSA shall ensure consolidation and integration of the routine results monitoring

reports in the Quarterly Progress Reports to be prepared by the PIU with the assistance of the

Page 26: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

15

project supervision and management consultant, The M&E for outcome and impact indicators

will be undertaken in liaison with Statistics Sierra Leone (SSL), Ministry of Energy and

Ministry of Finance and Economic Development.

4.2.2. The Bank will lead supervision missions jointly undertaken with DFID. Two

supervision missions will be undertaken every year. The coordination of the missions will be

done by the Ministry of Finance and Economic Development in collaboration with the Ministry

of Energy and EDSA.

4.2.3. A Project Mid-Term Review will be undertaken at the mid cycle of the project

whilst the Project Completion Report will be prepared after 85% disbursement is achieved to

evaluate progress against outputs and outcomes and draw lessons for follow-up operations

4.3. Governance

4.3.1. This project will be implemented by EDSA a State entity governed by the National

Electricity Act 2011. Moreover, the Board of Directors (BoD) appointed by the President on

the recommendation of the Minister of Energy provides strategic direction and guidance to

EDSA. The project will comply with the Government's Anti-Corruption Act 2008 and the

National Anti-Corruption Strategy (NACS). The Internal Audit Department of EDSA will

assist in monitoring and evaluating the internal controls. External audit will be provided by the

Sierra Leone Auditor General. The Bank and MoFED will provide some oversight and carry

out periodic financial management assessments of the project and other assessments to review

the controls systems of the Implementing Agency. Subsequently, the TA will be required to

strengthen systems, procedures, staff skills and capability and adequate governance.

4.4. Sustainability

4.4.1. The project is technically, economically, financially, environmentally and socially

sustainable. The technical sustainability is ensured by the use of standard state-of-the-art

technology, which will replace obsolete equipment. The commitment and cooperation

demonstrated by the Government during the preparation and appraisal of the project represents

a key underlying factor for the sustainability of this project. In addition, the Management

Contractor appointed to manage EDSA, as part of its assignments, will review and strengthen

the internal control systems of EDSA and this project. Similarly, the Contractor will strengthen

EDSA’s internal audit unit to ensure effective risk-based internal audit of all activities

including those related to this project. Subsequently, the capacity building and skill

enhancement program will ensure availability of skilled labor for the implementation of future

projects.

4.5. Risk management

4.5.1. The project overall risk is rated as moderate. Table 4.5.1 discusses the envisaged

risks and mitigation measures.

Page 27: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

16

Table 4.5.1: Project Risks

Risk Description Mitigation

- Change in level of political support, or political

risk,

Mitigated by government support for the energy sector

rehabilitation program and the involvement of

development partners in Sierra Leone. - Sector’s technical sustainability risks

Mitigated though the support of development partners for

the required capacity building program and recruiting

technical staffs for the operation & maintenance activities. - Risk of project completion delay

Mitigated by selecting of well-experienced and reputable

contractors on the basis of EPC contract as well as the

involvement of the supervision consultant to augment

project staff as needed in order to ensure delivery

efficiency. Risk of failure to achieve operational efficiencies

that contributes to sector financial sustainability

risk

Mitigated through implementation of ongoing state-of-art

commercial management system (metering and billing

collection) and revenue protection program to reduce the

non-technical losses.

Risks of delay on procurement process, long

approval processes and contract management.

Mitigated by procuring the supervision consultant to assist

EDSA’s team in preparation of bidding documents and

contract reviews Risk of CLSG implementation delay Mitigated through selecting of well-experienced and

reputable contractors on the basis of EPC contract as well

as the involvement of the supervision consultant to

augment project staff as needed in order to ensure delivery

efficiency

Risk of Co-Financing being cancelled. Mitigated by an Administration Agreement/ Memorandum

of Understanding with clear milestones and disbursement

schedule on DFID contribution.

Risk of Disbursement Delay Mitigated by provision of quarterly advance disbursement

notifications by the PIU and disbursement indicators

considered by the Bank’s Delivery Accountability and

Process Efficiency Committee (DAPEC)

4.6. Knowledge building

4.6.1. The implementation of the project components will generate vital knowledge that

will be useful for continuous improvement of performance and execution of similar distribution

system improvement and power services to other similar socio-economic population. The

technical assistance activities will build technical capacity and rehabilitate and revamp the

EDSA/EGTC joint training centre to improve the technical capacity and operations of the MoE,

EDSA, EGTC in the long run. The NPA/GTZ Training Centre, as it was called when

established in 1985, was among the most equipped institution in Sierra Leone. Today it is

totally handicapped on tools, machines and equipment as the workshop tools, machines and

equipment are obsolete and lack of spares have made them irreparable and unserviceable. The

Training Centre is used exclusively to train young men and women in addition to the training

of young graduates and technicians in specialized skills required for generation, transmission

distribution segments. The Training Centre has the infrastructure (in terms of Classrooms,

laboratories and workshops) that can train up to a maximum of 20 Electrical Engineers and 20

Mechanical Engineers. The technical assistance co-financing from DFID will be utilized for

in-house technical skill enhancement programs that will be beneficial to in the long run. The

project implementation review, quarterly progress reports, audit, sector M&E and completion

reports will also provide information on various aspects of the project for further diagnosis.

The knowledge obtained will be shared within the Bank and other development partners as

well as with RMCs.

Page 28: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

17

5. LEGAL INSTRUMENTS AND AUTHORITY

5.1. Legal instrument

The legal instruments used for the project are a loan and grant agreements to be entered into

between the Republic of Sierra Leone and the Bank for ADF resources; and an on-lending

agreement between GoSL and EDSA.

5.2. Conditions associated with Bank’s intervention

(A) Conditions Precedent to Entry into Force

The entry into force of the Loan Agreement shall be subject to the fulfilment by the Borrower

of the provisions of Section 12.01 of the Bank’s General Conditions Applicable to the African

Development Fund Loan Agreements and Guarantee Agreements (Sovereign Entities).

a) The entry into force of the Loan Agreement shall be subject to the fulfilment by the

Borrower of the provisions of Article XII, Section 12.01 of the General Conditions

Applicable to the African Development Fund Loan Agreements and Guarantee

Agreements (Sovereign Entities).

b) The Protocol of Agreement shall enter into force on the date of its signature by the Fund

and the grant recipient under Article X, section 10.1 of the General Conditions

Applicable to Protocols of Agreement for Grants of the African Development Fund.

(B) Conditions Precedent to First Disbursement of the Loan and the Grant

The obligation of the Bank to make the first disbursement of the Loan and the Grant shall be

conditional upon the entry into force of the Loan and the Grant Agreements, and the fulfilment,

in form and substance satisfactory to the Fund, of the following conditions:

For the Loan

i) Provide evidence that a subsidiary financing agreement with terms and conditions

acceptable to the Fund, has been executed between the Borrower and EDSA for the

purpose of on-lending the proceeds of the loan;

ii) Provide evidence to the Fund of the opening of a Special Account for the Project in a

bank acceptable to the Fund.

For the Grant

i) Provide evidence to the Fund of the opening of a Special Account for the Project in a

bank acceptable to the Fund.

(C) Undertakings

The Borrower undertakes to implement the Environmental and Social Management Plan

(ESMP) and report to the Bank on a quarterly basis, as part of the quarterly progress report.

Page 29: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

18

5.3. Compliance with Bank Policies

This project complies with all applicable Bank policies, particularly the Public Sector Lending

Policies, Integrated Environmental and Social Assessment Guidelines, Bank’s Policy on

Resettlement and Involuntary Displacement, and Bank’s crosscutting themes of Gender and

Poverty.

6. RECOMMENDATION

Management recommends that the Board of Directors approve the proposed ADF Loan and

ADF Grant of UA 4.621 million and 4.688 million to the Government of Sierra Leone for the

purposes and subject to the conditions stipulated in this report.

Page 30: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

I

Appendix I: Country’s comparative socio-economic indicators

Page 31: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

II

Appendix II: Table of ADF’s portfolio in the country List of active projects (loans and grants) by Sector:

Age

6-Oct-16

1 ADF P-SL-EA0-001 Water and

sanitation

Three Towns Water Supply Project OnGo 26-Oct-10 5.95 30-Jun-18 28.50 21.36 74.94%

2 ADF P-SL-K00-006 Governance Public Financial Management & Business Enabling Support

Project

OnGo 30-Sep-11 5.02 30-Dec-16 4.00 3.37 84.17%

3 ADF P-SL-DB0-005 Transport Matotoka - Sefadu Road Rehabilitation Project OnGo 5-Apr-12 4.51 31-Dec-17 22.00 16.39 74.48%

4 ADF P-SL-E00-003 Water and

sanitation

Rural Water Supply & Sanitation Project OnGo 18-Sep-13 3.05 31-Dec-18 20.39 2.89 14.18%

5 ADF P-SL-KF0-009 Governance Technical Assistance And Capacity Building Support To

Ministry Of Energy & MCC - (TCB- ERPU & MCC)

OnGo 18-Dec-13 2.80 30-Jun-17 0.45 0.07 15.85%

6 ADF P-SL-KF0-008 Governance Technical Assistance And Capacity Building To Support

Minerals And Extractive Revenues Governance

OnGo 20-Dec-13 2.80 31-Dec-17 1.20 0.24 19.74%

7 ADF P-SL-K00-007 Governance PFM Improvement And Consolidation (PFMIC) OnGo 8-May-14 2.42 30-Sep-18 2.30 0.35 15.11%

8 ADF P-SL-IBE-003 Social Strengthening West Africa’s Public Health Systems Response

(SWAPHS)

OnGo 18-Aug-14 2.14 30-Mar-17 1.20 1.20 100.00%

9 ADB/SFR P-SL-I00-003 Social Emergency Humanitarian Relief Assistance To Flood Victims APVD 16-Nov-15 0.89 31-Dec-17 0.73 0.73 100.00%

10 ADB P-SL-F00-008 PS-Power CECASL Heavy Fuel Oil Power Project and accompanying Credit

Enhancement Facility

APVD 17-Dec-15 0.81 15-Jun-17 21.78 - 0.00%

11 ADF P-SL-DB0-010 Transport Mano River Union Rehabilitation of Bo-Bandajuma Road

Project

APVD 17-Dec-15 0.81 1-May-20 6.94 - 0.00%

12 ADF P-SL-KB0-001 PS- Social Youth Entrepreneurship and Employment Program (YEEP) APVD 4-May-16 0.42 15-Jan-19 1.73 - 0.00%

2.63 111.22 46.59 41.89%

Amount

approved (UA

million)

Cumulative

disbursement as

at 31st May

2016

Cumulative

disbursement %

as at 31st May

2016

Window ID Sector Project TitleStatus of

ProjectApproval date Completion date

Page 32: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

III

Age

6-Oct-16

Social Post Ebola Recovery Social Investment Fund Project’ (PERSIF) APVD 21-Oct-15 0.96 31-Dec-18 9.00 - 0.00%

Social Crisis Response : TA To Fight Ebola* OnGo 1-Oct-14 2.02 31-Dec-16 1.80 1.43 79.62%

Social Ebola Fight Back Programme Sierra Leone OnGo 1-Oct-14 2.02 31-Dec-16 33.00 33.00 100.00%

Power CLSG Interconnection -Sierra Leone OnGo 6-Nov-13 2.92 31-Dec-18 16.04 - 0.00%

Power CLSG Sierra Leone- Rural Electrification OnGo 6-Nov-13 2.92 31-Dec-18 4.88 0.12 2.40%

Social Institutional Support - Mano River Union II OnGo 1-Oct-13 3.02 31-Dec-16 0.94 0.62 65.49%

2.31 65.66 35.17 53.56%

Cumulative

disbursement as

at 31st May

2016

Cumulative

disbursement % as at

31st May 2016

Sector Project TitleStatus of

ProjectApproval date Completion date

Amount

approved

(UA million)

Page 33: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

IV

Appendix III: Key Projects Financed By the Bank and other Development Partners

Project/Framework Development

Partner

Amount Sector Contribution

Rehabilitation of T&D network in the

Western Area

JICA US$ 3.8 M Rehabilitation of the Goderich substation and extension of 11kv

network to Wilberforce

Energy Access Programme (EAP) DFID US$16 M

Rehabilitation Kingtom, Wilberforce, Black Hall Road & Wellington

Solar& Renewable Energy rollout to 14 villages and roadmap for

renewable technologies in rural areas. :Nationwide

Energy Sector Utility Reform

Project(ESURP)

World Bank US$40 M

EDSA Management Contract

Network improvements

Project implementation & generation studies

Low and Medium Voltage Network

Project

IsDB US$10.70

Network improvements restricted to Western Area Freetown

ECOWAS Emergency Electricity

Supply for Freetown

ECOWAS US$21M

T&D in Western Area

Revolving fund for fuel

Meters

Cote d’Ivoire, Liberia, Sierra Leone

and Guinea (CLSG) interconnection

WAPP,

AFDB, WB,

EU

US$489M 525Km energynetwork interconnecting Cote d’Ivoire, Liberia,

Sierra Leone and Guinea

Energy Access to 115 communities within 5 km of the line

4,700 Prepaid Meters provided to 115 communities

Page 34: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

V

Appendix IV: Map of the Project Area

Source: Feasibility Report - Bo Kenema Distribution Network , Atkins, 2016

Page 35: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

VI

Appendix V: Justification to finance 10% of project cost financing by the

Government

The GoSL counterpart financing for the project is applied on the Bank’s financing

component. Justification to finance more than 90% is based on the country’s commitment

to implement its overall development program; (ii) the financing allocated by the country

sectors targeted by Bank assistance; (iii) the country’s budget situation and debt level

(Refer to Annex II)

Introduction: GoSL made a request for this financing plan during appraisal of the program.

This appendix provides the justification for waiver for the Bank financing more than 90%

of the proposed operation financing as indicated in the financing plan depicted in the table

below.

Source

Total

Amount

Million UA

% Total

Million UA

ADF 9.31 24.45%

DFID 27.84 73.11%

GoSL 0.93 2.44%

Total 38.08 100%

i. Country Commitment to Overall Development: Sierra Leone's economy has

experienced boom years (2012 13), with real GDP growth reaching a peak of around

21% in 2013, were largely driven by rapid expansion in the mining sector, which

remains a key source of government revenue. A post-Ebola resumption of iron ore

mining and pick-up in investor confidence will produce real GDP growth of 4.9% in

2016. As iron ore activity is ramped up, GDP growth will accelerate to 6.8% in 2017.

Inflation will remain broadly stable in 2016, at 8.2%, as currency weakening is offset

by low oil prices. Sharply rising oil prices in 2017, along with continued currency

weakening, will push inflation up to 9.5% next year. The current-account deficit is

forecast to narrow from 36% of GDP in 2015 to 25.9% of GDP in 2016 as Ebola-

related imports fall. Despite a sharp rise in exports in 2017, the deficit will widen to

28.4% of GDP as oil prices rise. There have been significant gains in the Human

Development Index (HDI) from 0.344 in 2005 to 0.413 in 2014 (an improvement of

more than 20%), and this will most likely be reversed due to the impact of the EVD

on health (i.e. life expectancy at birth), education (years of schooling) and standard of

living (gross national income per capita). Having failed to achieve most Millennium

Development Goals (MDGs) by 2015, government authorities and development

partners on the ground are now aware of the pertinence and inseparability of the 17

Sustainable Development Goals (SDGs) which essentially means that development

work should be across all sectors. Government needs to do more on poverty reduction

using the new poverty-related data and information which will be generated by the

population and housing census conducted in December 2015.

Page 36: AFRICAN DEVELOPMENT FUND · 33/11kV substations in Bo and Kenema, (ii) the rehabilitation and expansion of Medium Voltage (MV) and Low Voltage (LV) distribution networks within the

VII

ii. Financing allocated by Sector Targeted by the Bank: The need to address

infrastructure gaps and exploit natural resources requires major and multi-year

contracts. GoSL aspiration plan laid out in the Agenda for Prosperity (A4P) is

underpinned by eight strategic pillars which would serve as the foundation for

achieving middle income country status. Through pillars 1 and 4, the authorities

envision to implement a number of large-scale projects in agriculture, energy and

transportation. The cost of the airport alone is estimated at US$312 million (6.6

percent of 2013 GDP); significant related expenses—light rail linking the airport to

the port, a port upgrade—are also planned. Energy related projects have been costed

at over US$1.2 billion. Coping with the resource implications of these will be

challenging given limited domestic resource mobilization and expenditure pressures.

The government plans to resort to external borrowing to fill the financing gap, and it

is also favorably disposed toward public private partnership (PPP) arrangements. PPP

arrangements could be less costly, both in terms of debt burden and debt service

payments. But large non-transparent concessions for PPP operators could create fiscal

risks that could outweigh the lower explicit fiscal cost. In this regard, the 2016

approved budget engulfs the target sectors of the Bank (energy, roads, basic services

and governance). The commitment in the energy sector is even stronger,

iii. Budget and Debt Situation: Sierra Leone has maintained favorable debt dynamics,

mostly due to debt reliefs in the mid-2000s provided for the Heavily Indebted Poor

Countries (HIPC) and Multilateral Debt Relief Initiative (MDRI). International

Monetary Fund (IMF) 2016 Debt Sustainability Analysis reflected that the nominal

stock of public and publicly guaranteed external debt amounted to 32 percent of GDP

in 2016, up from 26 percent at end-2013. The creditor profile is largely favorable: most

is concessional debt. owed to multilaterals, while the remainder is non-concessional

debt at commercial and semi commercial terms. Interest on external debt remains

below 2 percent of GDP. Domestic debt, which is 14 percent of GDP, is mostly

government securities, over 90 percent of which are held by commercial banks, other

financial institutions and the pension fund.

Sierra Leone’s budget often faces both anticipated and unanticipated financing risks.

Higher than forecast revenue in some years has been more than offset by expenditures

that exceeded budget appropriations due to spending pressures and poor cash flow

planning, resulting in unplanned and unexpected financing needs. Exogenous factors,

such as commodity price declines and the Ebola epidemic outbreak interacted with

these existing limitations, thus magnifying the fiscal risk. In fiscal year 2016 for

example, wage overruns and spending pressures from subvented agencies contributed

to larger than anticipated financing gaps early in the fiscal year, which could not

readily be filled because of the low market appetite for treasury instruments.