Experience from construction of a Smart Grid RD 2 Platform. Agenda Background System Design Experience Future work. Henrik Stomberg– Sweden – Session No 4 – Paper No 0325. Background. NOAA National Oceanic and Atmospheric Administration. Background. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/1.jpg)
Frankfurt (Germany), 6-9 June 2011
Agenda
1. Background
2. System Design
3. Experience
4. Future work
Henrik Stomberg– Sweden – Session No 4 – Paper No 0325
Experience from construction of a Smart Grid RD2 Platform
1
![Page 2: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/2.jpg)
Frankfurt (Germany), 6-9 June 2011
Background
NOAA National Oceanic and Atmospheric Administration
2
![Page 3: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/3.jpg)
Frankfurt (Germany), 6-9 June 2011
Background
3
![Page 4: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/4.jpg)
Frankfurt (Germany), 6-9 June 2011
Background: Power consumption pattern in private residence
4
![Page 5: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/5.jpg)
Frankfurt (Germany), 6-9 June 2011
Background: Global irradiance, Ludvika, Sweden
5
![Page 6: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/6.jpg)
Frankfurt (Germany), 6-9 June 2011
Agenda
1. Background
2. System Design
3. Experience
4. Future work
Henrik Stomberg– Sweden – Session No 4 – Paper No 0325
Experience from construction of a Smart Grid RD2 Platform
6
![Page 7: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/7.jpg)
Frankfurt (Germany), 6-9 June 2011
VINNOVA is a Swedish government agency
under the Ministry of Enterprise, Energy and Communications and the national contact agency for the EU Framework Programme for R&D
7
![Page 8: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/8.jpg)
Frankfurt (Germany), 6-9 June 2011
Project: Smart Grid Energy Storage
Solutions for optimized control in real time
of distributed renewable power production,
storage and demand response
8
![Page 9: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/9.jpg)
Frankfurt (Germany), 6-9 June 2011
Energy storage & Control
9
![Page 10: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/10.jpg)
Frankfurt (Germany), 6-9 June 2011
System Design, STRI Smart Grid RD2
Converter
AC system
Meter
Fuel cell
Truck chargereCar charg.
Wind
2 kW 3 kW 2 kW 1kW
PQualitySTRI 380 V
H2electro- lizer
BatteryCapacitor
48 V DC
230 VAC
H2fill.
Solar
10
![Page 11: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/11.jpg)
Frankfurt (Germany), 6-9 June 2011
“Cell Agent” LAB View Supervisory CS
11
![Page 12: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/12.jpg)
Frankfurt (Germany), 6-9 June 2011
CCR – Container Control Room
12
![Page 13: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/13.jpg)
Frankfurt (Germany), 6-9 June 2011
Control Modules and Control System
- Combined switching and measuring control modules (CM) (left) - Computer for the control system (right)
13
![Page 14: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/14.jpg)
Frankfurt (Germany), 6-9 June 2011
Single line diagram RD2
14
![Page 15: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/15.jpg)
Frankfurt (Germany), 6-9 June 2011
Homer optimization model
Jan Feb Mars April Maj Juni Juli Aug Sep Okt Nov Dec
3000
2500
2000
1500
1000
500
Jan Feb Mars April Maj Juni Juli Aug Sep Okt Nov Dec
3000
2500
2000
1500
1000
500
0 2 4 6 8 10 12 14 16 18 20 22
4 kW
3 kW
2 kW
1 kW
0 2 4 6 8 10 12 14 16 18 20 22
4 kW
3 kW
2 kW
1kW
Monthly consumption
Monthly production
Hourly production
Hourly consumption
15
![Page 16: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/16.jpg)
Frankfurt (Germany), 6-9 June 2011
System Design for the RD2
Grid-connected to a 10 kV/380 V multi-vender IEC 61850 station
Standardized communication and control of the RD2
AC and DC bus system backbone Remote operated AC/DC switch and
measurement sensors Ethernet communication
16
![Page 17: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/17.jpg)
Frankfurt (Germany), 6-9 June 2011STRI Active Substation
• 11 cubicles 10 kV switchgear• Integrated protection and control• IEC 61850 from 4 suppliers• Max 4 cells each for the IEDs (Intelligent
Electronic Device)• Connected to the control system for local
production and storage of energyAnalog values from the supplystation via IEC 61850-9-2
17
![Page 18: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/18.jpg)
Frankfurt (Germany), 6-9 June 2011
Agenda
1. Background
2. System Design
3. Experience
4. Future work
Henrik Stomberg– Sweden – Session No 4 – Paper No 0325
Experience from construction of a Smart Grid RD2 Platform
18
![Page 19: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/19.jpg)
Frankfurt (Germany), 6-9 June 2011
Power generation during 24 hours
19
![Page 20: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/20.jpg)
Frankfurt (Germany), 6-9 June 2011
20
Power generation during 24 hours
Serie 2 = PV power (W), Serie 1= Power delivery (W)
![Page 21: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/21.jpg)
Frankfurt (Germany), 6-9 June 2011
Our experience are to:
Specify the application and load Decide DC and/or AC Bus Communication standard decition Use Standarized equipment Optimize energy storage system; (battery, H2,
Fly-Wheel, biogas etc.) Energy conversion optimization Measuring equipment and software
21
![Page 22: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/22.jpg)
Frankfurt (Germany), 6-9 June 2011
Agenda
1. Background
2. System Design
3. Experience
4. Future work
Henrik Stomberg– Sweden – Session No 4 – Paper No 0325
Experience from construction of a Smart Grid RD2 Platform
22
![Page 23: Agenda Background System Design Experience Future work](https://reader035.vdocuments.net/reader035/viewer/2022062500/56815ab8550346895dc87277/html5/thumbnails/23.jpg)
Frankfurt (Germany), 6-9 June 2011
Future work1. Power Quality measurements
2. Energy storage test bench
3. Microgrid and virtual power plant
4. Interuniversity cooperation
5. Optimized solutions for DER and energy storage
6. Applications for residentials, office, shopping centers, regions etc
7. Verification of communication
8. Develpment of software forMicro Grid CA Controller
9. Development of algoritmes for the operation
23