Agile Contracts?

SDC 2012Johannes Brodwall, Principal Architect

Steria Norway

@jhannes

Page 2: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Motivation

Page 3: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Agile ManifestoIndividuals and interactions over processes and toolsWorking software over comprehensive documentation

Customer collaboration over contract negotiationResponding to change over following a plan

Page 4: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Customer collaboration over contract negotiation

Page 5: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Does «contract» make a difference?

Page 6: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Customer

Hold on, I expected a much fancier UI

for this.?

Page 7: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Most common contracts:Fixed price

Time and material

Page 8: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Customer

Hold on, I expected a much fancier UI

for this.

CrapCrap

Page 9: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Customer

Hold on, I expected a much fancier UI

for this.No problem, we’ll work some more

Page 10: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

«Time and material» creates the most happiness

Page 11: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

«Time and material» creates the most happiness

(Source: My best and worst projects)

Page 12: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Ability to adjust frequently creates happiness

(Source: My best and worst projects)

Page 13: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

So why care about the rest?

Page 14: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Do you pay taxes?

Page 15: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

How should your government handle:

• We’re running out of money for pensions• We need to change the rules!

• The current system is huge

Page 16: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

How should govt spend your money?

• A big, state-run project• Hire a random company to do it all

• Just pay consultants until it’s done

Page 17: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Can Agile help?

Page 18: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Customer collaboration over contract negotiation

Page 19: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

PS2000 + Agile

Page 20: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Typical Norwegian public sector project:

«We need to replace huge system X…

Page 21: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Typical Norwegian public sector project:

«We need to replace huge system X…

… we’d like to use Scrum»

Page 22: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

PS2000:«Target price»

Page 23: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

(Target price:Set a budget,

report cost.Supplier & client splits difference)

Page 24: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

PS2000 + agile:«Colocated»

«Sprints»

«Sprint reviews»

«Product owner»

«Product backlog»

Page 25: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

… but also«Negotation phase»

«Requirement phase»

«Acceptance test phase»

Page 26: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Whence PS2000?

Page 27: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Contract standard from Norwegian Computing

Association

Page 28: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

2001: PS2000 with target price

Page 29: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

2009: PS2000 + Agile

Page 30: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Norwegian trends:• 2 Agile user groups with 100+ people at

meetings from 2005• Conferences: Smidig 2007 + 2008

• Networking: Devs <-> PMs <-> customers• Meetups about contracts

• Scrum certifications• Large and diverse consultancy industry

Page 31: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Some project highlights

Page 32: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

In p

rogre

ssLARM: Domain: Electricity reserve power

Application: Operator UI

Internal Integration

Project size: 2 scrum teams plus support

Organization: Supplier + Customer teams

Colocated at customer site

Team size: 7 per team

Duration: 3 years (1,5 years left)

Sprint length: 3 weeks (customer present)

Releases: 3 times per year (in theory…)

Contract: Target pricing for whole scope

Page 33: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

?

Bid

Apr, 2010

Negotiation

Aug, 2010

Mar, 2010

Elaboration

Nov, 2010

Release 1Sprint Sprint Sprint Sprint Sprint

May, 2011

Acceptance Production

Sept, 2011

Elaboration Sprint Sprint Sprint

Sprint Sprint

Sprint

Page 34: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Smart move:Reliable product backlog using

scenarios

Page 35: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Big win:First release in use 1 year after contract, containing most used

screen

Page 36: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Big loss:Feature creep of individual user

stories

Page 37: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

CompletedPERFORM:

Domain: State pension fund

Application: Case worker UI

External Integration

Process flow

Project size: 12-14 scrum teams plus support

Organization: Three suppliers with 3-6 teams

Colocated at customer site

Team size: 10 per team

Duration: 3 years

Releases: 3 times per year

Sprint length: 3 weeks, with shared demo

Contract: First release: Time & materials

Subsequent:

Target pricing per release

Page 38: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Smart move:Contract on price per release

First release on T&M

«Competing» suppliers

Page 39: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Big win:Delievered what was needed

Government is happy

Users are happy

Page 40: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Big loss:Full time requirement spec

Hostile architecture team

Page 41: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Customer collaboration over contract negotiation

Page 42: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Reality:• We must compete

• We must commit

Page 43: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Pure fa

briactio

nIMAGINE:

Project size: Some scrum teams with independent

users and product owners

Organization: Colocated at customer site

Team size: 6-8 per team

Duration: 3 years

Sprint length: 2 weeks, with shared demo

Releases: Every month

Bidding: Performance competition

Contract: Target estimate per user story

Page 44: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Bidding: Competitive delivery

Page 45: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Supplier

Supplier

Supplier

Supplier

Customer

Project referenceResumesHourly rates

Supplier

Pre-qualification

Page 46: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Supplier

Supplier

Page 47: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Supplier

Supplier

6-10 weeks

Page 48: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Supplier

Analysis

CodingD

elivery

Analysis

Coding

Delivery

Analysis

CodingCoding

AnalysisDelivery

Delivery

Supplier

Page 49: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Supplier

Analysis

CodingD

elivery

Analysis

Coding

Delivery

Analysis

CodingCoding

AnalysisDelivery

Delivery

Supplier

Page 50: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Pricing: Customer sets budget

Page 51: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Menu:• Simple GUI: 2 kEUR• Complex GUI: 5 kEUR• GUI with customer

involvement: 10 kEUR• Etc…

(Or 2, 5, 20 story points)

Page 52: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Customer

I need a screen shot for X. We want something simple.

Ok. 2 kEURO

Page 53: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Customer

Do you have anything to show for it?

We’ve spent half the budget

It’s not tested yet.

Okay, I’m pulling the

plug

Page 54: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier

Customer

Stop!

We’ve spent the budget

Page 55: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Supplier Commitment:

Δ ☺

Δ $

Page 56: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Questions and discussions

Page 57: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Conclusion

Page 58: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Customer collaboration over contract negotiation

Page 59: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

We need an answer for large investments

Page 60: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

Norway’s answer ain’t half bad

Page 61: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

We can do better

Page 62: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes

We must do better

Page 63: Agile Contracts? SDC 2012 Johannes Brodwall, Principal Architect Steria Norway @jhannes