ahmed el antary - pmp part 5 - scope 4th ed - general

Upload: ahmed-el-antary

Post on 30-May-2018

225 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    1/24

    Project Management Professional

    PMP Exam Preparation Course

    Prepared By: Eng. Ahmed El Antary, PPM, MSPMEngineering & Management Technologies LLC

    Delaware, USA

    [email protected]

    Project Scope Management

    PMBOK 4th Ed

    Ahmed El Antary: [email protected]

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    2/24

    The Course Leader

    Ahmed El Antary, PPM, MSPM Engineering and Management Consultant

    Certified Professional Project Manager (PPM), WCU, USA PhD Learner with concentration on Project Management - PhD-

    BA program. NorthCenteral University, AZ, USA Master of Science in Project Management, Colorado Technical

    , , , B. Sc. Civil Engineering, Al Azhar University, Cairo, Egypt Project Management Certificate & PMP Preparation Course, WCU,

    USA Business Management Certificate GL, CTU, CO, USA

    Change Management Certificate GL, CTU, CO, USA Project Management Certificate GL, CTU, CO, USA Team Member of the Construction Extension Project for the

    PMBOK 3rd Ed. By (PMI) and (ANSI)

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    3/24

    Project Scope Management

    It is the processes required to ensure that the project

    includes all the work required, and only the work requiredto complete the project successfully

    It is primarily concerned with defining and controlling what

    Deliverables are products produced as part of a project,such as hardware or software, planning documents, or

    meeting minutes

    The project team and stakeholders must have the sameunderstanding of what products will be produced as aresult of a project and how theyll be produced

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    4/24

    Project Scope Management Processes

    Collect Requirements: The process of defining and

    documenting stakeholders needs to meet the projectobjectives

    Define Scope: The process of developing a detailed

    Create WBS: The process of subdividing projectdeliverables and project work into smaller, more

    manageable components

    Verify Scope: The process of formalizing acceptance for thecompleted project deliverables

    Control Scope: The process of monitoring the status of the

    project and product scope and managing changes to thescope baseline

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    5/24

    Collect Requirements

    InputsInputs

    ProjectProject CharterCharter

    Stakeholder RegisterStakeholder Register

    Tools & TechniquesTools & Techniques

    InterviewsInterviews

    Focus groupsFocus groups

    Facilitated workshopsFacilitated workshops

    OutputsOutputs

    RequirementsRequirementsdocumentationsdocumentations

    RequirementsRequirementsmanagement planmanagement plan

    techniques:techniques:BrainstormingBrainstorming NominalNominalgroup techniquegroup technique The DelphiThe Delphitechniquetechnique Idea/mindIdea/mind

    mappingmapping Affinity diagramAffinity diagram

    Group decisionGroup decision

    making techniquesmaking techniques

    Questionnaires andQuestionnaires andsurveyssurveys

    ObservationsObservations

    PrototypesPrototypes

    RequirementsRequirementstraceability matrixtraceability matrix

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    6/24

    Project Charter

    After deciding what project to work on, it isimportant to formalize projects

    A project charter is a document that

    project and provides direction on theprojects objectives and management

    Key project stakeholders should sign aproject charter to acknowledge agreementon the need and intent of the project

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    7/24

    Sample Project Charter

    Project Title: IT Upgrade Project for the MOT

    Project Start Date: Jan.,10, 2006

    Projected Finish Date: Nov., 15, 2006

    Project Manager: Ehab Kamel, [email protected]

    Project Objectives: Upgrade hardware and software for all MOT

    ,

    corporate standards. See attached sheet describing the new standards.Upgrades may affect servers and midrange computers as well as network

    hardware and software. Budgeted SR 1,500,000 for hardware and

    software costs and SR 750,000 for labor costs.

    Approach: Update the IT inventory database to determine upgrade needs Develop detailed cost estimate for project and report to CIO Issue a request for quotes to obtain hardware and software Use internal staff as much as possible to do the planning, analysis, andinstallation

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    8/24

    Sample Project Charter Cont.

    Roles and Responsibilities:

    Name Role Responsibility

    Walter Schmidt, CEO Project Sponsor Monitor projectMike Zwack CIO Monitor project, provide staff

    Ehab Kamel Project Manager Plan and execute project

    Jeff Johnson Director of IT Operations Mentor Ehab

    Nanc Re nolds VP, Human Resources Provide staff, issue memo to all

    employees about projectSteve McCann Director of Purchasing Assist in purchasing hardware and

    software

    Sign-off: (Signatures of all above stakeholders)

    Comments: (Handwritten comments from above stakeholders, if applicable)

    This project must be done within ten months at the absolute latest. Mike Zwack,

    CIO

    We are assuming that adequate staff will be available and committed to supporting

    this project. Some work must be done after hours to avoid work disruptions, and

    overtime will be provided. Jeff Johnson and Ehab Kamel, Information

    Technology Department

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    9/24

    Define Scope

    InputsInputs

    Project CharterProject Charter

    RequirementsRequirementsDocumentationDocumentation

    Tools & TechniquesTools & Techniques

    Expert JudgmentExpert Judgment

    ProductProduct Analysis:Analysis:Product breakdown,Product breakdown,systems analysis,systems analysis,s stems en ineerins stems en ineerin

    OutputsOutputs

    Project Scope Statement:Project Scope Statement:Project objectives, productProject objectives, product

    scope description, projectscope description, projectrequirements, projectrequirements, projectboundaries, projectboundaries, projectdeliverables, productdeliverables, product

    OrganizationalOrganizational ProcessProcessAssetsAssets

    value engineering, valuevalue engineering, valueanalysis and functionalanalysis and functionalanalysisanalysis

    AlternativesAlternativesIdentification:Identification:Brainstorming and lateralBrainstorming and lateral

    thinkingthinking

    Facilitated workshopsFacilitated workshops

    ,,

    constraints, projectconstraints, projectassumptions, initial projectassumptions, initial project

    organization, initial definedorganization, initial definedrisks, schedule milestones, fundrisks, schedule milestones, fundlimitation, cost estimate, projectlimitation, cost estimate, projectconfiguration managementconfiguration managementrequirements, projectrequirements, projectspecifications and approvalspecifications and approval

    requirementsrequirements

    Requested ChangesRequested Changes

    ProjectProject document updatesdocument updates

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    10/24

    Importance of Good Scope Definition

    It helps improve the accuracy of time,

    cost, and resource estimates It defines a baseline for performance

    It aids in communicating clear workresponsibilities

    It is the basic step of further define thework by breaking it into manageable

    pieces

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    11/24

    Project Scope Statement

    A project scope statement is adocument used to develop and confirma common understanding of the project

    .Project justificationBrief description of the projects

    productsSummary of all project deliverablesStatement of what determines project

    success

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    12/24

    Create WBS

    InputsInputs

    ProjectProject ScopeScopeStatementStatement

    RequirementsRequirementsdocumentationdocumentation

    Tools & TechniquesTools & Techniques

    DecompositionDecomposition

    OutputsOutputs

    WBSWBS

    WBS DictionaryWBS Dictionary

    Scope BaselineScope Baseline

    Organizational ProcessOrganizational ProcessAssetsAssets

    updatesupdates

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    13/24

    The Work Breakdown Structure

    A work breakdown structure (WBS) is adeliverable-oriented grouping of thework involved in a project that defines

    It is a foundation document in projectmanagement because it provides the

    basis for planning and managing projectschedules, costs, and changes

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    14/24

    Sample Intranet WBS Organized by Product

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    15/24

    Sample Intranet WBS Organized

    by Phase

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    16/24

    Sample Intranet WBS Organized

    in Tabular Form

    1.0 Concept 1.1 Evaluate current systems 1.2 Define Requirements 1.2.1 Define user requirements 1.2.2 Define content requirements

    . .

    1.2.4 Define server owner requirements 1.3 Define specific functionality 1.4 Define risks and risk management approach 1.5 Develop project plan

    1.6 Brief web development team 2.0 Web Site Design 3.0 Web Site Development 4.0 Roll Out 5.0 Support

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    17/24

    Intranet WBS and Gant Chart

    in MS Project

    WBS Gantt Chart

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    18/24

    Approaches for WBS Development

    Top-Down approach: Start with the largest

    items and keep breaking them downBottom-Up approach: Start with the detailed

    The analogy approach: Review WBS insimilar projects

    Using guidelines: Some organizationsprovide guidelines for preparing WBS

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    19/24

    Verify Scope

    InputsInputs

    ProjectProject managementmanagementplanplan

    RequirementsRequirementsdocumentationdocumentation

    Tools & TechniquesTools & Techniques

    InspectionInspection

    OutputsOutputs

    Accepted deliverablesAccepted deliverables

    Change requestsChange requests

    Project documentProject documentupdatesupdates

    RequirementsRequirementstraceability matrixtraceability matrix

    Validated deliverablesValidated deliverables

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    20/24

    How to Improve Acceptance of

    Deliverables

    Insist that all projects have a sponsorfrom the user organization

    Have regular meetings

    Deliver something to project users and

    sponsor on a regular basis

    Co-locate users with the developers

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    21/24

    Control Scope

    InputsInputs

    Project managementProject managementplanplan

    Work performanceWork performanceinformationinformation

    Tools & TechniquesTools & Techniques

    Variance AnalysisVariance Analysis

    OutputsOutputs

    Work performanceWork performancemeasurementsmeasurements

    Organizational ProcessOrganizational ProcessAssets updatesAssets updates

    RequirementsRequirementsdocumentationdocumentation

    RequirementsRequirementstraceability matrixtraceability matrix

    Organizational ProcessOrganizational Process

    AssetsAssets

    Change requestsChange requests

    ProjectProject ManagementManagementPlanPlan updatesupdates

    Project documentProject documentupdatesupdates

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    22/24

    How to reduce incomplete and changing

    requirements Put requirements in writing and keep them current

    Provide adequate testing and conduct testing

    throughout the project life cycle

    Review changes from a systems perspective

    most important Allocate resources specifically for handling change

    requests/enhancements

    Develop and follow a requirements managementprocess

    Use techniques like prototyping, use case modeling,

    and Joint Application Development (JAD) to get moreuser involvement

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    23/24

    Resources Project Management Institute. (2008). A guide to the project management

    body of knowledge (4th ed.). Newtown Square, PA: Project Management

    Institute.

  • 8/14/2019 Ahmed El Antary - PMP Part 5 - Scope 4th Ed - General

    24/24

    Q U E S T I O N SQ U E S T I O N S

    A N S W E R SA N S W E R S