aim through safety case idec – mumbai - may 2013

35
AIM Through Safety Case IDEC – MUMBAI - MAY 2013

Upload: cleopatra-lang

Post on 13-Jan-2016

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

AIM Through Safety Case

IDEC – MUMBAI - MAY 2013IDEC – MUMBAI - MAY 2013

Page 2: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

Introduction to Bureau Veritas

Page 3: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

3IDEC - MUMBAI – MAY 2013

Bureau Veritas 2012 revenue: € 3,9bn

8 Global Businesses

Broad Geographical Presence

Asia Pacific

Europe, Middle East & Africa

Americas

Marine & Offshore

IVSCertification

Industry

Consumer Products

Construction

Well Balanced Portfolio

Commodities

20%

12%12%

9%

18%

11%

7% 12%

28% 23%

49%

GSIT

Page 4: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

4IDEC - MUMBAI – MAY 2013

Offshore Units & Equipment Certification

► Design review, survey of construction, inspection of equipment, supervision of installation to assess compliance with specified standards and international regulations.

► BV recognized by 130 Flag States for the implementation of international conventions (statutory)

► Certification can be combined with classification

Consulting & Outsourcing

► Project management► FEED review► Technical assistance services: risk analysis,

hydrodynamics, mooring, structural strength and fatigue, vibrations and noise

► Services to operators: Asset Integrity Management, Expertise

Offshore Floating Units & Equipment Classification

► Design review, survey of construction, inspection of equipment, supervision of installation to assess compliance with classification rules.

► Maintenance of class in service through periodical inspections

► Cover hull, mooring and topsides (PROC).

BV Offshore services

Offshore Units Independent Verification

► Risk based safety assessment scheme required by a national authority.

► IVB can be combined with classification and certification

Page 5: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

5IDEC - MUMBAI – MAY 2013

BV Involvement

Concept

Concept Design

FEED

Detailed Design

ConstructionInstallation

In-Service

Concept Approval

- Basic approval- Concept Design

approval- Final concept approval- Qualification of

unproven technology

ClassificationCertification

In service survey

Concept / FEED Approval

Certificate(s)

Class Certificate

Maintenance of Certificates

Project phases Approval type BV Certificates

Page 6: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

6IDEC - MUMBAI – MAY 2013

Marine & Offshore Division : the global network

2000 marine technical staff: naval architects, marine engineers and surveyors180 survey stations in more than 90 countries

16 Local Technical Centres & Plan Approval

Offices

12 regional Marine Centres and Customer

Support Centres

4 Regional Training Centres

Local plan approval offices Marine operations centre Regional training centreSurvey stations

4 MARINE ZONES

•North Asia Zone

•South Asia Zone

•Europe, Africa and North Zone

•Hellenic, Black Sea & Middle East Zone

Page 7: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

7IDEC - MUMBAI – MAY 2013

FSO & FPSO: Class & Technical Assistance studies

SKARV FPSOfor BP / STATOIL in Norway

More than 120 FSOs & FPSOs studied by BV

Present in all MODU types

Page 8: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

AIM Through Safety Case

Page 9: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

9IDEC - MUMBAI – MAY 2013

Asset Integrity Management

► I.M. is responsible of safety and availability of the asset.

Needs Risk Ranking and Decision Making (Priorities)

► It includes the follow-up and fullfilment of Class and Verification

► Must keep track of all inspection/maintenance schedules

Integrity Management

(Duty Holder)

Class & FlagRequirements

Verification Requirements

(SCEs) InspectionServices

e.g. NDT, VisualCompany

Requirements(BCEs)

Page 10: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

10IDEC - MUMBAI – MAY 2013

Asset Integrity Management means…

►Accountability, roles and responsabilities

►Consistency

►Competence

►Management of Change

►Data Management

Document Center: Categories (ex: hull, mooring, stability, topsides, SURF, stability, integrity management)

What should be considered as « Must Have »?Expert reports, processed inspection reports as opposed to raw data (nice-to-have)

Page 11: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

11IDEC - MUMBAI – MAY 2013

Asset Integrity Management means…

► Risk Management

Extract from the IADC HSE Case Guidelines and based on ISO IEC Guide 73:2002

Page 12: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

12IDEC - MUMBAI – MAY 2013

AIM & SAFETY CASE

NOPSEMA Safety Case Content and Level of Detail - N-04300-GN0106 - Revison 4, December 2011NOPSEMA Safety Case Content and Level of Detail - N-04300-GN0106 - Revison 4, December 2011

FACILITY DESCRIPTIONFACILITY DESCRIPTION

FORMAL SAFETY ASSESSMENTFORMAL SAFETY ASSESSMENT

SAFETY MANAGEMENT SYSTEMSAFETY MANAGEMENT SYSTEM

SAFETY MEASURESSAFETY MEASURES

EMERGENCIESEMERGENCIES

RECORDSRECORDS

5 YR REVISION5 YR REVISION

Page 13: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

14IDEC - MUMBAI – MAY 2013

3P’s: Plant, People and Processes

Any operation requires equipment to execute an activity, people to operate and maintain the equipment and a business process to guide the operations and maintenance.

CONTENT OF HSE CASE:

Part Content

1 Introduction, Summary of all parts

2 Operations HSE Management System

3 Catalogue of Critical Activities

4 Description of Facility, Process, Safety Systems, Manning Philosophy

5 HER, MAH, SCE, Summary of PS, MOPO, Summary of FSA (QRA, EERA, ESSA, TRIA)

6 Proposed Remedial Actions

7 Conclusion, Statement of Fitness

Page 14: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

15IDEC - MUMBAI – MAY 2013

DOCUMENT HIERARCHY

Level 1: Overall Guidance

Level 2: Specific Guidance

Level 3: Generic Examples

Level 4: Asset Specific

Guidance Document for MAHGuidance Document for MAH

Guidance Document for SCE 1Guidance Document for SCE 1

Guidance Document for PS and Assurance Tasks

Guidance Document for PS and Assurance Tasks

•Guidance Document for Verification

•Guidance Document for Verification

Asset Specific Performance StandardsAsset Specific Performance Standards

Level 1

Level 3

Level 2

Level 4

Generic Document for MAH

Generic Document for MAH

Generic Document for PS and Assurance

Tasks

Generic Document for PS and Assurance

Tasks

Generic Document for

SCE 1

Generic Document for

SCE 1

Specific Equipment Reliability Plan (SERPs)Specific Equipment Reliability Plan (SERPs)

Asset Specific HSE Case

Asset Specific HSE Case

•Engineering Data

•Engineering Data

• Technical Data

• Design Data

• Assessment Data

• Historical Data

Asset Specific Safety Critical Elements

Asset Specific Safety Critical Elements

Guidance Document for MAHGuidance Document for MAH

Guidance Document for SCE 1Guidance Document for SCE 1

Guidance Document for PS and Assurance Tasks

Guidance Document for PS and Assurance Tasks

•Guidance Document for Verification

•Guidance Document for Verification

Asset Specific Performance StandardsAsset Specific Performance Standards

Level 1

Level 3

Level 2

Level 4

Generic Document for MAH

Generic Document for MAH

Generic Document for PS and Assurance

Tasks

Generic Document for PS and Assurance

Tasks

Generic Document for

SCE 1

Generic Document for

SCE 1

Specific Equipment Reliability Plan (SERPs)Specific Equipment Reliability Plan (SERPs)

Asset Specific HSE Case

Asset Specific HSE Case

•Engineering Data

•Engineering Data

• Technical Data

• Design Data

• Assessment Data

• Historical Data

Asset Specific Safety Critical Elements

Asset Specific Safety Critical Elements

Page 15: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

16IDEC - MUMBAI – MAY 2013

3P’s: Plant, People and Processes

Plant;

►Know the equipment – Asset Register in Hierarchical fashion.

►Classify equipment according to criticality to HSE, Production etc.

►Select appropriate tools to determine task requirements (task, frequency, man-power, spares and specialist tools etc.).

►Have a management system in place to generate the work orders, record work history, provide management reports etc.

►Keep the correct critical spares in the correct location(s).

►Establish performance indicators, aligned with the equipment functionality to measure performance. Establish target values and have a Continuous Improvement process in place.

Page 16: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

17IDEC - MUMBAI – MAY 2013

PhysicalChemical

Biological

Ergonomic

Psychological

Types of HazardsHealth Hazards

Individual Safety Hazards

A hazard is defined as a situation with the potential for causing harm to human health or safety (NOPSEMA Control Measures and Performance Standards N-04300-GN0271 Dec.2011)

A hazard is a situation that poses a level of threat to life, health, property, or environment. (Wikipedia)

A source or a situation with a potential for harm in terms of human or ill-health, damage to property, damage to the environment, or a combination of these (AS / NZS 4804:1997).

Page 17: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

18IDEC - MUMBAI – MAY 2013

MAJOR ACCIDENT HAZARDS & MAJOR ACCIDENTS

Page 18: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

19IDEC - MUMBAI – MAY 2013

MAJOR ACCIDENT EVENTS

NOPSEMA Hazard Identification - N-04300-GN0107 - Revision 4, December 2011NOPSEMA Hazard Identification - N-04300-GN0107 - Revision 4, December 2011

As per the definition given in OPGGS(S) regulation 1.5, a major accident event is an event connected with a facility, including a natural event, having the potential to cause multiple fatalities of persons at or near the facility. Thus MAEs by definition are consequence based.

As per the definition given in OPGGS(S) regulation 1.5, a major accident event is an event connected with a facility, including a natural event, having the potential to cause multiple fatalities of persons at or near the facility. Thus MAEs by definition are consequence based.

Major accident events usually occur as a result of a combination of factors. Care needs to be taken during the formal safety assessment that combinations of events that could lead to high consequence incidents are not dismissed as ‘double contingency’ or ‘double jeopardy’ events.

Major accident events usually occur as a result of a combination of factors. Care needs to be taken during the formal safety assessment that combinations of events that could lead to high consequence incidents are not dismissed as ‘double contingency’ or ‘double jeopardy’ events.

Page 19: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

20IDEC - MUMBAI – MAY 2013

Major Accident Hazards (MAH)

THE FIVE STAGES OF THE MAJOR ACCIDENT HAZARD AND SAFETY CRITICAL ELEMENT MANAGEMENT PROCESS

1.Identify Major Accident Hazards (MAH)

2.Identify Safety Critical Elements (SCEs) from these MAHs,

3.Identify Performance Standards (PS) for each SCE

4.Identify assurance processes that maintain or ensure continued suitability of the SCEs (i.e. that they meet PS requirements)

5.Verify all steps have been undertaken, and thus that MAHs are being controlled.

Page 20: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

21IDEC - MUMBAI – MAY 2013

SCE Identification

SCE IDENTIFICATION PROCESS FLOW

YES

NO

Is equipment designed to protect process equipment in order to avoid

catastrophic failure / injury?

Is the element design to provide control, shutdown, alarm or

mitigation during an emergency?

NO

Does the element contain flammable hydrocarbons or other hazardous

chemicals?

Could the release from the element cause serious injury to multiple

people or an environmental event?

Could failure cause an event resulting in catastrophic release from upstream or

downstream process?

Could failure of the element cause Major Accident or does the element prevent, control or mitigate a Major Accident?

Does the element prevent harm to people in the event of a Major Accident?

Safety Critical

•Not

Safety Critical

Not Safety Critical

Not Safety Critical

YES

YES

YES

YES

YES

YES

YES

NO

NO

NO

NO

NO

NO

YES

NO

Is equipment designed to protect process equipment in order to avoid

catastrophic failure / injury?

Is the element design to provide control, shutdown, alarm or

mitigation during an emergency?

NO

Does the element contain flammable hydrocarbons or other hazardous

chemicals?

Could the release from the element cause serious injury to multiple

people or an environmental event?

Could failure cause an event resulting in catastrophic release from upstream or

downstream process?

Could failure of the element cause Major Accident or does the element prevent, control or mitigate a Major Accident?

Does the element prevent harm to people in the event of a Major Accident?

Safety Critical

•Not

Safety Critical

Not Safety Critical

Not Safety Critical

YES

YES

YES

YES

YES

YES

YES

NO

NO

NO

NO

NO

NO

YES

NO

Is equipment designed to protect process equipment in order to avoid

catastrophic failure / injury?

Is the element design to provide control, shutdown, alarm or

mitigation during an emergency?

NO

Does the element contain flammable hydrocarbons or other hazardous

chemicals?

Could the release from the element cause serious injury to multiple

people or an environmental event?

Could failure cause an event resulting in catastrophic release from upstream or

downstream process?

Could failure of the element cause Major Accident or does the element prevent, control or mitigate a Major Accident?

Does the element prevent harm to people in the event of a Major Accident?

Safety Critical

•Not

Safety Critical

Not Safety Critical

Not Safety Critical

YES

YES

YES

YES

YES

YES

YES

NO

NO

NO

NO

NO

NO

YES

NO

Is equipment designed to protect process equipment in order to avoid

catastrophic failure / injury?

Is the element design to provide control, shutdown, alarm or

mitigation during an emergency?

NO

Does the element contain flammable hydrocarbons or other hazardous

chemicals?

Could the release from the element cause serious injury to multiple

people or an environmental event?

Could failure cause an event resulting in catastrophic release from upstream or

downstream process?

Could failure of the element cause Major Accident or does the element prevent, control or mitigate a Major Accident?

Does the element prevent harm to people in the event of a Major Accident?

Safety Critical

•Not

Safety Critical

Not Safety Critical

Not Safety Critical

YES

YES

YES

YES

YES

YES

YES

NO

NO

NO

NO

NO

NO

NO

Is equipment designed to protect process equipment in order to avoid

catastrophic failure / injury?

Is the element design to provide control, shutdown, alarm or

mitigation during an emergency?

NO

Does the element contain flammable hydrocarbons or other hazardous

chemicals?

Could the release from the element cause serious injury to multiple

people or an environmental event?

Could failure cause an event resulting in catastrophic release from upstream or

downstream process?

Could failure of the element cause Major Accident or does the element prevent, control or mitigate a Major Accident?

Does the element prevent harm to people in the event of a Major Accident?

Safety Critical

•Not

Safety Critical

Not Safety Critical

Not Safety Critical

YES

YES

YES

YES

YES

YES

YES

NO

NO

NO

NO

NO

NO

NO

Is equipment designed to protect process equipment in order to avoid

catastrophic failure / injury?

Is the element design to provide control, shutdown, alarm or

mitigation during an emergency?

NO

Does the element contain flammable hydrocarbons or other hazardous

chemicals?

Could the release from the element cause serious injury to multiple

people or an environmental event?

Could failure cause an event resulting in catastrophic release from upstream or

downstream process?

Could failure of the element cause Major Accident or does the element prevent, control or mitigate a Major Accident?

Does the element prevent harm to people in the event of a Major Accident?

Safety Critical

•Not

Safety Critical

Not Safety Critical

Not Safety Critical

YES

YES

YES

YES

YES

YES

YES

NO

NO

NO

NO

NO

NO

Page 21: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

22IDEC - MUMBAI – MAY 2013

Safety Cases

BOW TIE DIAGRAMA Bow Tie diagram displays the relationships between the major accident events, the associated causes and consequences, Safety Critical Elements and Activities and factors affecting SCE integrity

Page 22: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

23IDEC - MUMBAI – MAY 2013

Scope Of Work: Validation

What Is Validation ? Scope Of Validation

Hazard Identification & Risk AssessmentHazard Identification & Risk Assessment

Identification Of Major Accident Events (MAES)Identification Of Major Accident Events (MAES)

Identification Of Barriers To Those MAESIdentification Of Barriers To Those MAES

Safety Critical ElementsSafety Critical Elements

FORMAL SAFETY ASSESSMENT (FSA)FORMAL SAFETY

ASSESSMENT (FSA)

Forms the basis of

=EQUALS

Page 23: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

24IDEC - MUMBAI – MAY 2013

Page 24: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

25IDEC - MUMBAI – MAY 2013

Control Measures & Performance Standards

►Control measures include the physical features of a facility, and elements of the operator’s management system employed at the facility, that eliminate, prevent, reduce or mitigate the risk of major accident events and other hazardous events. They can take many forms including physical equipment, process control systems, management processes, operating or maintenance procedures, the emergency plan, key personnel and their actions

► Preferential order should be considered when selecting controls. The hierarchy of control measures typically includes, in order of priority, elimination, prevention, reduction and mitigation.

► The operator’s safety management system for a facility must specify the performance standards that apply. The performance standards are the parameters against which control measures for MAEs are assessed to ensure they reduce the risks to ALARP on an ongoing basis

NOPSEMA Control Measures and Performance Standards Rev 3, December 2011- N-04300-GN0271NOPSEMA Control Measures and Performance Standards Rev 3, December 2011- N-04300-GN0271

Page 25: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

26IDEC - MUMBAI – MAY 2013

Examples of Control Barriers

Page 26: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

28IDEC - MUMBAI – MAY 2013

SAFETY MANAGEMENT SYSTEM

the SMS itself must meet the requirements of items (a) to (i), not necessarily the detailed description.

the SMS itself must meet the requirements of items (a) to (i), not necessarily the detailed description.

NOPSEMA Safety Case Content and Level of Detail - N-04300-GN0106 - Revison 4, December 2011NOPSEMA Safety Case Content and Level of Detail - N-04300-GN0106 - Revison 4, December 2011

Page 27: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

29IDEC - MUMBAI – MAY 2013

Safety Case Cycle

STAGE 1IDENTIFY MAJOR ACCIDENT HAZARDS

TestInspectMaintain

FORMAL SAFETY ASSESSMENT

QRA, EERA , ESSA, NFHA, Dropped Object, Ship Collision, TRISIA, F&G

Mapping, HAC, etc.

STAGE 2IDENTIFY SAFETY CRITICAL ELEMENTS

DEMONSTRATION OF MAH & SCE MANAGEMENT

LikelihoodConsequenceRisk

AvoidPreventControl / MitigateEmergency Response

STAGE 3DEFINE PERFORMANCE STANDARDS

FACILITY HSE CASE

FunctionalityAvailabilityReliabilitySurvivabilityInteractions / Dependencies

STAGE 4DEVELOP / REVIEW AND IMPLEMENT

ASSURANCE PROCESSES

STAGE 5MANAGE NON-CONFORMING SCEs

HER AND HEMP

SAFETY CASE IMPLEMENTATION

STAGE 5INDEPENDENT VERIFICATION ACTIVITIES

MAH SUITABILTY ASSESSMENT

SCE SUITABILTY ASSESSMENT

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

IdentifyManage Interim Risk Until ResolutionRepair / Replace / Redesign / Rectify

Page 28: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

30IDEC - MUMBAI – MAY 2013

TestInspectMaintain

FORMAL SAFETY ASSESSMENT

QRA, EERA , ESSA, NFHA, Dropped Object, Ship Collision, TRISIA, F&G

Mapping, HAC, etc.

STAGE 2IDENTIFY SAFETY CRITICAL ELEMENTS

DEMONSTRATION OF MAH & SCE MANAGEMENT

AvoidPreventControl / MitigateEmergency Response

STAGE 3DEFINE PERFORMANCE STANDARDS

FACILITY HSE CASE

FunctionalityAvailabilityReliabilitySurvivabilityInteractions / Dependencies

STAGE 4DEVELOP / REVIEW AND IMPLEMENT

ASSURANCE PROCESSES

STAGE 5MANAGE NON-CONFORMING SCEs

HER AND HEMP

SAFETY CASE IMPLEMENTATION

STAGE 5INDEPENDENT VERIFICATION ACTIVITIES

MAH SUITABILTY ASSESSMENT

SCE SUITABILTY ASSESSMENT

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

IdentifyManage Interim Risk Until ResolutionRepair / Replace / Redesign / Rectify

STAGE 1IDENTIFY MAJOR ACCIDENT HAZARDS

LikelihoodConsequenceRisk

Safety Case Cycle

Page 29: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

31IDEC - MUMBAI – MAY 2013

STAGE 1IDENTIFY MAJOR ACCIDENT HAZARDS

TestInspectMaintain

FORMAL SAFETY ASSESSMENT

QRA, EERA , ESSA, NFHA, Dropped Object, Ship Collision, TRISIA, F&G

Mapping, HAC, etc.

DEMONSTRATION OF MAH & SCE MANAGEMENT

LikelihoodConsequenceRisk

STAGE 3DEFINE PERFORMANCE STANDARDS

FACILITY HSE CASE

FunctionalityAvailabilityReliabilitySurvivabilityInteractions / Dependencies

STAGE 4DEVELOP / REVIEW AND IMPLEMENT

ASSURANCE PROCESSES

STAGE 5MANAGE NON-CONFORMING SCEs

HER AND HEMP

SAFETY CASE IMPLEMENTATION

STAGE 5INDEPENDENT VERIFICATION ACTIVITIES

MAH SUITABILTY ASSESSMENT

SCE SUITABILTY ASSESSMENT

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

IdentifyManage Interim Risk Until ResolutionRepair / Replace / Redesign / Rectify

STAGE 2IDENTIFY SAFETY CRITICAL ELEMENTS

AvoidPreventControl / MitigateEmergency Response

Safety Case Cycle

Page 30: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

32IDEC - MUMBAI – MAY 2013

STAGE 1IDENTIFY MAJOR ACCIDENT HAZARDS

TestInspectMaintain

FORMAL SAFETY ASSESSMENT

QRA, EERA , ESSA, NFHA, Dropped Object, Ship Collision, TRISIA, F&G

Mapping, HAC, etc.

STAGE 2IDENTIFY SAFETY CRITICAL ELEMENTS

DEMONSTRATION OF MAH & SCE MANAGEMENT

LikelihoodConsequenceRisk

AvoidPreventControl / MitigateEmergency Response

FACILITY HSE CASE

STAGE 4DEVELOP / REVIEW AND IMPLEMENT

ASSURANCE PROCESSES

STAGE 5MANAGE NON-CONFORMING SCEs

HER AND HEMP

SAFETY CASE IMPLEMENTATION

STAGE 5INDEPENDENT VERIFICATION ACTIVITIES

MAH SUITABILTY ASSESSMENT

SCE SUITABILTY ASSESSMENT

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

IdentifyManage Interim Risk Until ResolutionRepair / Replace / Redesign / Rectify

STAGE 3DEFINE PERFORMANCE STANDARDS

FunctionalityAvailabilityReliabilitySurvivabilityInteractions / Dependencies

Safety Case Cycle

Page 31: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

33IDEC - MUMBAI – MAY 2013

STAGE 1IDENTIFY MAJOR ACCIDENT HAZARDS

FORMAL SAFETY ASSESSMENT

QRA, EERA , ESSA, NFHA, Dropped Object, Ship Collision, TRISIA, F&G

Mapping, HAC, etc.

STAGE 2IDENTIFY SAFETY CRITICAL ELEMENTS

DEMONSTRATION OF MAH & SCE MANAGEMENT

LikelihoodConsequenceRisk

AvoidPreventControl / MitigateEmergency Response

STAGE 3DEFINE PERFORMANCE STANDARDS

FACILITY HSE CASE

FunctionalityAvailabilityReliabilitySurvivabilityInteractions / Dependencies

STAGE 5MANAGE NON-CONFORMING SCEs

HER AND HEMP

SAFETY CASE IMPLEMENTATION

STAGE 5INDEPENDENT VERIFICATION ACTIVITIES

MAH SUITABILTY ASSESSMENT

SCE SUITABILTY ASSESSMENT

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

IdentifyManage Interim Risk Until ResolutionRepair / Replace / Redesign / Rectify

TestInspectMaintain

STAGE 4DEVELOP / REVIEW AND IMPLEMENT

ASSURANCE PROCESSES

Safety Case Cycle

Page 32: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

34IDEC - MUMBAI – MAY 2013

STAGE 1IDENTIFY MAJOR ACCIDENT HAZARDS

TestInspectMaintain

FORMAL SAFETY ASSESSMENT

QRA, EERA , ESSA, NFHA, Dropped Object, Ship Collision, TRISIA, F&G

Mapping, HAC, etc.

STAGE 2IDENTIFY SAFETY CRITICAL ELEMENTS

DEMONSTRATION OF MAH & SCE MANAGEMENT

LikelihoodConsequenceRisk

AvoidPreventControl / MitigateEmergency Response

STAGE 3DEFINE PERFORMANCE STANDARDS

FACILITY HSE CASE

FunctionalityAvailabilityReliabilitySurvivabilityInteractions / Dependencies

STAGE 4DEVELOP / REVIEW AND IMPLEMENT

ASSURANCE PROCESSES

HER AND HEMP

SAFETY CASE IMPLEMENTATION

STAGE 5INDEPENDENT VERIFICATION ACTIVITIES

MAH SUITABILTY ASSESSMENT

SCE SUITABILTY ASSESSMENT

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

STAGE 5MANAGE NON-CONFORMING SCEs

IdentifyManage Interim Risk Until ResolutionRepair / Replace / Redesign / Rectify

Safety Case Cycle

Page 33: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

35IDEC - MUMBAI – MAY 2013

TestInspectMaintain

FORMAL SAFETY ASSESSMENT

QRA, EERA , ESSA, NFHA, Dropped Object, Ship Collision, TRISIA, F&G

Mapping, HAC, etc.

STAGE 2IDENTIFY SAFETY CRITICAL ELEMENTS

DEMONSTRATION OF MAH & SCE MANAGEMENT

AvoidPreventControl / MitigateEmergency Response

STAGE 3DEFINE PERFORMANCE STANDARDS

FACILITY HSE CASE

FunctionalityAvailabilityReliabilitySurvivabilityInteractions / Dependencies

STAGE 4DEVELOP / REVIEW AND IMPLEMENT

ASSURANCE PROCESSES

STAGE 5MANAGE NON-CONFORMING SCEs

HER AND HEMP

SAFETY CASE IMPLEMENTATION

STAGE 5INDEPENDENT VERIFICATION ACTIVITIES

MAH SUITABILTY ASSESSMENT

SCE SUITABILTY ASSESSMENT

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

INDEPENDENT VERIFICATION OF SUITABILTIY AND EXECUTION

IdentifyManage Interim Risk Until ResolutionRepair / Replace / Redesign / Rectify

STAGE 1IDENTIFY MAJOR ACCIDENT HAZARDS

LikelihoodConsequenceRisk

Safety Case Cycle

Page 34: AIM Through Safety Case IDEC – MUMBAI - MAY 2013

36IDEC - MUMBAI – MAY 2013

Asset Integrity Management & Safety Case

► Objective

Life-Cycle oriented

Operating facilities safely

Minimizing down-time. Avoidance of non-expected shutdowns

Implementation of a Learning process

Avoidance of swiss-cheese effects. Avoidance of orphan items/systems

Event Consequence

Page 35: AIM Through Safety Case IDEC – MUMBAI - MAY 2013