air entrainment issues of pumped concrete entrainment... · retempering/adding water at site ......

30
Ins & Outs of Air Entrainment March 29 th , 2011 David C. Sethre, P.E. North Dakota Ready Mix & Concrete Products Association Bismarck Concrete Mini-Seminar In Concrete

Upload: phamdung

Post on 28-Mar-2018

220 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Ins & Outs of Air Entrainment

March 29th, 2011

David C. Sethre, P.E.North Dakota Ready Mix & Concrete Products Association

Bismarck Concrete Mini-Seminar

In Concrete

Page 2: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

How is air induced in the concrete mix?

Mixing Action with Agent◦ Needs proper size sand particles to scrub large bubbles into small ones

◦ Needs slump – a higher slump mix will entrain and maintain more bubbles than a low slump mix

◦ Temperature sensitive – cool temperatures are best to entrain air

Page 3: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Mixing Action 30 Revolutions at 15 Revs/minute at

plant

Slow roll in transit

30 Revolutions at 15 Revs/minute at discharge site

Check air

Adjust air as needed

Communicate issues to plant

Page 4: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Mixing Loss

First of all, Air Entrainment must be induced in a mixing process

At some point, mixing will likely diminish the quantity of air entrainment

Loss will increase when…◦ Temperature increases

◦ Mix loses workability (slump)

◦ Admixture wears out – defoaming takes over

Page 5: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Some will gain air with additional mixing

Retempering/Adding water at site

Admixture defoaming package is suspect

Almost always occurs in a highly fluid mix

Page 6: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Maintaining Your Air

If air is sensitive to mixing loss

Page 7: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Air Entrainment Counts

Exterior Concrete Needs Air Entrainment◦ Durability in Wet Freeze/Thaw Environment is Important

◦ Number of Freeze-Thaw Cycles Must be Considered

Page 8: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Allow your RM Producer to be the leader here

Give them the performance requirements you need at the job site

Allow addition of AEA at site initially

Expect the right air to come from the plant eventually

Page 9: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Other Expectations

Change of dosing of AEA as day heats up

Some level of QC assistance with air◦ Let your RM Producer know if this is important

◦ Of course, the right air content before dumping in forms

Page 10: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Do not supply inferior concreteEthics Says to the Producer:

Page 11: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Do not accept inferior concreteEthics to the Contractor:

Page 12: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Pumped concreteLet’s Explore:

Page 13: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Distress of Non-Air Entrained Exterior Concrete

Scaling of concrete surface

Deterioration of concrete, particularly at cracks and joints

Page 14: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

When do we not want air entrained concrete?

Any troweled surfaces

Distress is called “Delamination”

Definitions:

Delamination is a distress involving the loss of the

surface of concrete flatwork through either 1.) the

concentration of air bubbles at a certain distance

below the concrete surface forming a weak plane,

or 2.) the sealing and concentration of bleed water

below the densified troweled surface forming a

weak plane.

Page 15: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

What’s the Issue Here?

Pumping of concrete is becoming more and more prevalent

Pumping of concrete generally doesn’t have to affect the quality of the concrete

Pumping of concrete can reduce the quantity of air entrainment from truck end to final placement position

Page 16: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Last Issue

Sampling procedures can lead to false information on actual air entrainment content of in-place concrete

Page 17: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Pumping

Air content reduction of 0.5 to 3%

Pumping straight up and down(initial pressure & then free-fall mechanism)Vertical boom is problematic

High pressure or vacuum condition

Page 18: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Pumping of Concrete is OK if ……

Page 19: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Consider the Ideal-Gas Equation

PV = nRT

P = Pressure

V = Volume

n = Mass (moles)

R = Gas Constant

T = Temperature (Kelvin)

T1T2

T3

xP = —

V

Page 20: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Pumping

High pressure mechanism to start30- 40 times atmospheric pressure

size of bubbles reduced, dissolve in mix water

bubbles do not reform when pressure

released

Maintain a siphon affect in hose

Page 21: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at
Page 22: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Pumping - Partial Solutions

Minimize free-fall◦Reduce height of discharge

◦Use flexible hoseform loop in descending part of pump-line

keep concrete from sliding down under own

weight

Keep hose full of mix

Page 23: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Impingement

Do not let high velocity mix spatter or impinge on rebar or flat surfaces

Some air entrainment will be lost

Page 24: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Pumping - Partial Solutions

Reduce concrete pressure◦keep pumping pressure low

◦use pumpable concrete mixture

◦reduce boom angles

◦slow rate of pumping

◦use pumping aidsreduces friction on hose walls

Work with your RM Producer on this

Page 25: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Pumping - Partial Solutions

Use slide gaterestrict discharge and provide resistance

Reduce hose from 5 to 4 in. ◦ Use transition pipe to avoid blockage

Bury hose end in placed mix

Use double 90 degree fitting on end

Page 26: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Other Partial Solutions

Lay 10 or 20 ft hose horizontally◦ on deck pours

won’t work in columns or walls

requires labor to handle hose

Use double “90 degree fittings” at hose end

Bury hose end in concrete

Page 27: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at
Page 28: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

What about Sampling?

Keep hose full of mix, whatever you do◦ Do not have pump operator slow/stop pumping rate when obtaining sample

Move hose to sample bucket quickly at point of constant discharge to minimize spillage

If hose is not kept full, downward leg mix can enter vacuum state – sample can be defective

Page 29: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

Issues with Moving Hose End to Remote Testing Site

Operator will shut down pump Down leg is empty Initial pumped materials for sample will

be affected by high pressure, then vacuum

Need to refill downward leg to full flow conditions siphon conditions to restore equilibrium in pressure

Abandon first part of secured sample

Page 30: Air Entrainment Issues of Pumped Concrete Entrainment... · Retempering/Adding water at site ... surface of concrete flatwork through either 1.) the concentration of air bubbles at

QUESTIONS?