AIRM Review Forum #2
Monday 12th September 2011Eurocontrol, Brussels
Welcome
by Joe Gorman,NATMIG/SINTEF, Norway
CCB Chairman
1
Review Forum Meetings
Review Forum #1 Review Forum #2
Date 11th April 2011 12th September 2011
Number of participants
18 (attended) 54 (registered)
Focus: AIRM
• What it is, purpose • Overview of changes• Details of key parts
Focus: Governance
• Overview• Role of AIRM Review
Forum
• Brief overview• Role of AIRM Review
Forum
2
Agenda
3
What is AIRM Governance?
4
AIRM
Governance: Procedures todecide changes to
* Information Model* Consolidated Logical Data Model
* Supporting documents
Scope of Governance
Procedures to change models Procedures to change governance Notations to express models Practical tools, storage etc. issues Technical judgments about what domain
information needs to be modelled Procedures used within domain-specific modelling
projects
5
In Scope
CRs (Change Requests):core of Governance
6
Change Request (CR)A proposal to add a new model,
modify the AIRM to fulfill some perceived need ormodify governance
Change ProposalA CR that contains specific
details for exactly howto meet the need expressed
in the CR
FastTrack:true/false
Status:CR approved,
Reject,CR implemented,
…….
Working in CCB Meetings
Synchronous:Face-to-face
Asynchronous:Online discussion forum
Duration < 1 day Several weeks
# Participants Probably a subset of CCB members, partially depending on which CRs to be discussed
Probably most members (since offline format does not require constant participation – easier to attend)
Scope Any CRs, but especially the controversial ones
Only CRs, with status “FastTrack” (urgent or uncontroversial)
7
AIRM Review Forum: Role in Governance
8
AIRMCCBMeetings
CCBS
CCBMembers
AIRM Review Forum
CCB = Change Control BoardCCBS = Change Control Board Secretariat (from 8.1.3)
8.1.* Projects
Disseminateinformation on
Periodicreviews of
AIRM
Submit CRs on behalf of parties outside CCB
Submit CRs
Check that changes made as planned
Implement Changes
Organise and prepare inputs to
FormalDecisions
Issues for “Open Floor Discussion”
9
“Open” It’s up to
you!
Questions: seek better
understanding of AIRM status and plans
Questions & Suggestions:
AIRM development approach / governance
process
Possible CRs (Change Requests):
Indicate areas where CRs may be needed
Frequency of AIRM Review Forum
meetings + date of next meeting
Step 1 and Step 2 model should be separate? Level of detailing Relationship with FIXM/AIXM/WXXM and ICAO Link to services Link to SWIM Action Plan A meta-rulebook? Parallel sessions in future meetings Validation against operational requirements e.g.
by operational experts
ReserveSlides
11
AIRM Change Control Board (CCB):Direct Involvement in Governance
12
Before submitting a CR
Check existing CRs – may already be (partially) covered by an existing CR• Possible to modify an existing CR (e.g. to add some
details)
Is the CR large/complex? Consider split into several smaller
Is it likely that the CR will have major impact on other projects? Contact them and cooperate efforts to submit a combined CR
13
Decision Process
14