AL SIDRA PROGRESS REPORT About the Project:
Project Developer Bin Faqeeh Real Estate Investment Company S.P.C.
Title of Project Al Sidra Villa
Project Reference BFALSIDRA/07/0107-3107/2019
Design & Supervision Consultant
MSCEB
Interior Design Consultant
Horizon Interiors
Main Contractor Al Jameel Construction SPC
About Progress Report:
Title of Document Progress Report of Al Sidra
Reporting Period July 1, 2019 to July 31, 2019
Authors & project role MSCEB
Date August 8, 2019
DESCRIPTION PERCENTAGE (%) OF COMPLETION
REMARKS
Phase 1 Villas – 88 Nos
SUB STRUCTURE
1. Filling of Class-3 Material and compaction 100% Completed
2. Excavation for Grid beam and MEP services 100% Completed
3. Blinding Concrete 100% Completed
4. Formwork and reinforcement for grade slab 100% Completed
5. Grade slab concrete 100% Completed
SUPER STRUCTURE
Ground Floor 1. RCC for Column 100% Completed
2. Block work for walls 58% In Progress
3. Internal Plastering for walls 26% In Progress
First Floor
1. Formwork and reinforcement for First Floor Slab 92% In Progress 2. First Floor Slab Concrete 86% In Progress 3. RCC for Column (FF) 76% In Progress 4. Block work for walls 23% In Progress
5. Internal Plastering for walls 6% In Progress
Second Floor
1. Formwork and reinforcement for 2nd Floor Slab 60% In Progress
2. 2nd Floor Slab Concrete 54% In Progress
3. RCC for Column (2nd Floor) 44% In Progress
4. Block work for walls 12% In Progress
Roof Floor
1. Formwork and reinforcement for Roof Slab 40% In Progress
2. Roof Slab concrete 36% In Progress
On-site Photos:
Aerial View Phase 1 Villas
Street View Phase 1 Villas
Ph 1 Villas 2nd Floor Slab Reinforcement Ph 1 Villas External Plastering Preparation
Ph 1 Villas GF & 1F Block work in progress Ph 1 Villas GF Ceiling work in progress
On-site Photos:
Aerial View Phase 2 Villas
Phase 2 Villas Blinding for Grade Slab Phase 2 Formwork for Grade Slab in progress
DESCRIPTION PERCENTAGE (%) OF COMPLETION
REMARKS
Phase 2 Villas – 108 Nos
SUB STRUCTURE
1. Setting out of Plots 100% Completed
2. Grade Slab Preparation 45% In Progress
3. Blinding for Grade Slab 6% In Progress
4. Rebar & Formwork for Grade Slab 2.7% In Progress
5. Casting of Grade Slab 1.1% In Progress