alafaya presentation 3 3-11

16
Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard Jennifer Thompson, District 4 Commissioner Stone Lakes Elementary School March 3, 2011 Mark Twain Boulevard Avalon Park Boulevard & Innovation Way Alafaya Trail 3.8 Miles

Upload: jennthomp

Post on 05-Jul-2015

1.234 views

Category:

Education


0 download

TRANSCRIPT

Page 1: Alafaya presentation 3 3-11

Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Jennifer Thompson, District 4 CommissionerStone Lakes Elementary School

March 3, 2011

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Page 2: Alafaya presentation 3 3-11

Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Project History

Procurement and Construction

What to Expect

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Page 3: Alafaya presentation 3 3-11

Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Project History

Procurement and Construction

What to Expect

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Page 4: Alafaya presentation 3 3-11

Planning, Design & Right-of-Way

Identified in Comprehensive Plan

Public/Private Partnership Agreement Approved by BCC

– Avalon & Associates: Design

– Morgran: Up-Fronted Cash & Ponds

Construction Plans Finalized 2009

Right-of-Way Acquisition Completed August 2010

Project History

Page 5: Alafaya presentation 3 3-11

Design Elements

10 Stormwater Ponds

4 Travel Lanes

Raised Grass Median

12,000 Feet of Retaining Wall

Project History

Utility Work

– Wastewater, Reuse, Water Mains

(Pipe Size Varies from 24” to 36”)

Page 6: Alafaya presentation 3 3-11

Design Elements

3 Signalized Intersections (One New)

No Landscaping or Lighting Due to Budgetary Constraints

Project History

Existing

Signal

Upgrade

Golfway Bv.

Existing

Signal

Upgrade

Innovation Way

New

Signal

Stoneybrook Bv.

Page 7: Alafaya presentation 3 3-11

Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Project History

Procurement and Construction

What to Expect

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Page 8: Alafaya presentation 3 3-11

Construction

Bid Recommendation Approved – January 25, 2011

Contract Executed – February 11, 2011

Pre-Construction Conference – February 23, 2011

Notice to Begin – Effective March 21, 2011

Procurement and Construction

Page 9: Alafaya presentation 3 3-11

Construction

Construction Duration 2-1/2 Years

(September 2013)

County’s $19.6 Million Roadway Estimate: $11.1 Million Utilities

$30.7 Million Total

Procurement and Construction

Page 10: Alafaya presentation 3 3-11

Construction Bids:

Company Estimated Bid Amount

Jr. Davis $30,203,373

Halifax $31,042,574

Prince $33,359,946

Ranger $34,610,030

County’s $30,700,000

Estimate

Procurement and Construction

Page 11: Alafaya presentation 3 3-11

Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Project History

Procurement and Construction

What to Expect

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Page 12: Alafaya presentation 3 3-11

Construction Phases

During the First 7-8 Months:

– Installation of Water Main, Force Main & Reuse Main

– Clearing and Stormwater Pond Excavation

– Temporary Lanes Constructed on the North Side for Utility Work & Stormwater Piping

• During the Next 6-7 Months

– Southbound Travel Lanes Begin Construction

– Two-way Traffic Moves from Temporary Lanes to Southbound Lanes When Complete

What to Expect

Page 13: Alafaya presentation 3 3-11

Construction Phases

During the Next 5-6 Months:

– Remaining Stormwater Piping Installed

– Northbound Travel Lanes Begin Construction

• During the Final Phase

– Structural Asphalt, Friction Course & Temporary/Final Pavement Markings Installed

What to Expect

Page 16: Alafaya presentation 3 3-11

Orange County Highway Construction

William Totten

Senior Engineering Inspector

407-836-7911

321-354-7330

Steven Stokes

Engineering Inspector

321-354-7395

Contacts