Alafaya Trail Project Update
Avalon Park Boulevard to Mark Twain Boulevard
Jennifer Thompson, District 4 CommissionerStone Lakes Elementary School
March 3, 2011
Mark Twain Boulevard
Avalon Park Boulevard
& Innovation Way
Alafaya Trail
3.8 Miles
Alafaya Trail Project Update
Avalon Park Boulevard to Mark Twain Boulevard
Project History
Procurement and Construction
What to Expect
Mark Twain Boulevard
Avalon Park Boulevard
& Innovation Way
Alafaya Trail
3.8 Miles
Alafaya Trail Project Update
Avalon Park Boulevard to Mark Twain Boulevard
Project History
Procurement and Construction
What to Expect
Mark Twain Boulevard
Avalon Park Boulevard
& Innovation Way
Alafaya Trail
3.8 Miles
Planning, Design & Right-of-Way
Identified in Comprehensive Plan
Public/Private Partnership Agreement Approved by BCC
– Avalon & Associates: Design
– Morgran: Up-Fronted Cash & Ponds
Construction Plans Finalized 2009
Right-of-Way Acquisition Completed August 2010
Project History
Design Elements
10 Stormwater Ponds
4 Travel Lanes
Raised Grass Median
12,000 Feet of Retaining Wall
Project History
Utility Work
– Wastewater, Reuse, Water Mains
(Pipe Size Varies from 24” to 36”)
Design Elements
3 Signalized Intersections (One New)
No Landscaping or Lighting Due to Budgetary Constraints
Project History
Existing
Signal
Upgrade
Golfway Bv.
Existing
Signal
Upgrade
Innovation Way
New
Signal
Stoneybrook Bv.
Alafaya Trail Project Update
Avalon Park Boulevard to Mark Twain Boulevard
Project History
Procurement and Construction
What to Expect
Mark Twain Boulevard
Avalon Park Boulevard
& Innovation Way
Alafaya Trail
3.8 Miles
Construction
Bid Recommendation Approved – January 25, 2011
Contract Executed – February 11, 2011
Pre-Construction Conference – February 23, 2011
Notice to Begin – Effective March 21, 2011
Procurement and Construction
Construction
Construction Duration 2-1/2 Years
(September 2013)
County’s $19.6 Million Roadway Estimate: $11.1 Million Utilities
$30.7 Million Total
Procurement and Construction
Construction Bids:
Company Estimated Bid Amount
Jr. Davis $30,203,373
Halifax $31,042,574
Prince $33,359,946
Ranger $34,610,030
County’s $30,700,000
Estimate
Procurement and Construction
Alafaya Trail Project Update
Avalon Park Boulevard to Mark Twain Boulevard
Project History
Procurement and Construction
What to Expect
Mark Twain Boulevard
Avalon Park Boulevard
& Innovation Way
Alafaya Trail
3.8 Miles
Construction Phases
During the First 7-8 Months:
– Installation of Water Main, Force Main & Reuse Main
– Clearing and Stormwater Pond Excavation
– Temporary Lanes Constructed on the North Side for Utility Work & Stormwater Piping
• During the Next 6-7 Months
– Southbound Travel Lanes Begin Construction
– Two-way Traffic Moves from Temporary Lanes to Southbound Lanes When Complete
What to Expect
Construction Phases
During the Next 5-6 Months:
– Remaining Stormwater Piping Installed
– Northbound Travel Lanes Begin Construction
• During the Final Phase
– Structural Asphalt, Friction Course & Temporary/Final Pavement Markings Installed
What to Expect
Construction Zones
Lots of Construction Barrels and Traffic Barriers
Expect Crews Working Along Entire Project Limits
Reduced Speed Limits & Other Temporary Signage
Travel Lane Shifts, Uneven Pavement, Temporary Pavement Markings & Reflectors
Construction Vehicles Entering/Leaving Zone
Side Street Visibility
New Traffic Signal and Signal Upgrades
What to Expect
Construction Zones
Orange County Highway Construction Administers Construction Contract
Orange County Will Have On-Site Roadway Inspector During Construction
Orange County Inspector Communicates Issues and Solutions Between Highway Construction Division, the Contractor & the Traveling Public
Normal Hours of Construction: 7:00am to 6:00pm
What to Expect
Orange County Highway Construction
William Totten
Senior Engineering Inspector
407-836-7911
321-354-7330
Steven Stokes
Engineering Inspector
321-354-7395
Contacts