alkimos beach battery storage trial...
TRANSCRIPT
Strictly private and confidential
Presentation by Andy Wearmouth
Chief Engineer, Commercial
Synergy
24 February 2016
Alkimos Beach Battery Storage Trial
(ABEST)
API 2016 SUMMER SCHOOLSurfAir Beach Hotel and Conference Centre,
Marcoola BeachSunshine Coast, Queensland
DM# 9839576
1STRICTLY PRIVATE & CONFIDENTIAL |
Today’s Discussion:
Participants in Project
Why Alkimos ?
The Concept
The Technology
Where are we at ?
Questions
2STRICTLY PRIVATE & CONFIDENTIAL |
The Participants:
Synergy – project lead and implementer
Landcorp – northern suburbs development planning
Lend Lease – subdivision developer
Australian Renewable Energy Agency ( ARENA) – principal funder
3STRICTLY CONFIDENTIAL |
A time of uncertainty and rapid change
Falling grid demand (self generation) , increasing renewables penetration including rooftop solar and energy
efficiency is being forecast to a potential 50% reduction in electricity volume sold by traditional European utilities
within the next couple of decades….why will we be different ?
A result, utilities are changing their business models away from centralised distribution and focussing on
downstream opportunities
4STRICTLY PRIVATE & CONFIDENTIAL |
Why Invest in Battery Storage Technology ?Batteries are highly likely to become the storage device of choice as they move down their cost curve. ABEST
allows Synergy to be informed and provide learnings to industry through the ARENA arrangements.
• Conventional centralised, dispatchable, fossil-fuel based generation is
gradually ceding ground to renewable energy sources and distributed
generation
• Until recently, solar PV technology was largely unaffordable, and only
economically viable with the support of significant government
subsidies
• Rapid advances in innovation and technology has seen this scenario
change significantly:
– solar is exhibiting alarming learning rates of around 30% - that is
for every doubling of installed capacity, the price of an average
panel reduces by 30%
– the price of an average panel has fallen by 75% in just four years
– commercial PV in the SWIS now has a 3 – 5 year payback period,
without any government subsidies
• Combined solar PV and battery systems are already starting to
appear.
• Battery storage is the most significant technological change after solar
PV. While the price of batteries needs to fall to make this technology
commercially viable, this will only happen by deployment – the learn
by doing concept.
Decreasing costs of battery technology
5STRICTLY CONFIDENTIAL |
The Concept of a Storage Device
A simple concept that has ben around for decades - storage technology allows the time shifting of energy –
historically pumped hydro but similar rules apply to a battery.
Import from Grid Export to Grid
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47
Consumption
PV Generation
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
(1.00)
(0.80)
(0.60)
(0.40)
(0.20)
-
0.20
0.40
0.60
Export to BatteryExport to
GridImport from BatteryImport from Grid Import from Grid
Without Battery With Battery
kWh
30-min
interval
• Solar PV does not
generate
• Source energy from Grid
• Solar PV generates energy
more than what is consumed
by the house
• Excess energy exported/sold
to the Grid
• Solar PV does not
generate
• Source energy from
Grid
30-min
interval
Export
to G
rid
(kW
h)
Import
(kW
h)
Batt
ery
Charg
e
(kW
h)
• Solar PV does not
generate
• Source energy
from Grid
• Excess energy from Solar
PV exported and stored in
Battery
• Once Battery is full, excess
energy is exported/sold to
the Grid
• Solar PV does
not generate
• Source energy
from Battery
Battery full
6STRICTLY CONFIDENTIAL |
Rationale for Synergy
Threat of
customers
bypassing
network
• The rapid adoption of rooftop Solar PV has demonstrated that energy consumers will invest en masse in new technologies if they offer a positive
business case
• Adoption by residential customers, facilitated by on-site battery storage, could be economic within 3-7 years. Early adoption for non-economic reasons
is likely to occur much sooner
• The household business case for energy storage will improve as battery and PV capital costs fall and retail electricity tariffs continue to rise
Ensuring
efficient use of
existing assets
• The Project offers customers the benefits of on-site energy storage using the existing electricity network.
• Potentially delays the need for network reinforcements
Alternative
business model
for retail
services
• Batteries represent a new way of interacting with the customer: providing a defined energy service for a fixed fee. The service would not be tied to the
customer’s electricity consumption
• The project would also demonstrate the (favourable) impact of district energy storage on distribution infrastructure requirements, raising the possibility
that new communities might be more economically served by a “micro utility” than by traditional infrastructure providers.
• Synergy would, in partnership with others, be a plausible provider of micro-utility services.
Opportunities
for wholesale
services
• The Project would provide the opportunity to investigate the optimal use of storage for services to customers, network operators and the wholesale
market
• An appropriate treatment of storage in the wholesale electricity market would need to be negotiated through the Rules Change process
Insight into
customer
preferences and
behaviour
• The project will need to analyse customer consumption data, both for customers using Synergy’s services and for a control group, at half-hourly
resolution to understand fully the impact of ABEST
7STRICTLY CONFIDENTIAL |
Why Alkimos Beach?
• Lend Lease, together with LandCorp are developing a new land
sub-division, 40km north of Perth at Alkimos Beach
• The vision for Alkimos Beach is to create a new benchmark for
community development in WA, via innovative planning, in areas
including:
– water and energy efficiency
– waste management
– reduction of carbon emissions
– use of green space
– other sustainable development opportunities
• At completion in 2032, Alkimos Beach will be home to 15,000
residents across 710 hectares (it will be the same size as the area
from Kings Park to the Coast)
The Alkimos Beach Energy Storage Project will demonstrate the feasibility of a new energy servicing model using
both demand side and supply side products and services within the new residential land development of Alkimos
Beach
8STRICTLY CONFIDENTIAL |
Why Alkimos Beach?
• The marketing of the subdivision by Lend Lease is likely to attract
residents predisposed to take part in a trial using new technologies.
• Public engagement with residents has indicated great support for
the initiative.
• Land is available to locate the required infrastructure without undue
disturbance of amenity.
• Western Power’s electricity distribution network is relatively
unconstrained at this location assisting in simpler network access.
• As part of the energy efficiency initiative, Lend Lease and LandCorp
approached Synergy to lead a trial of an energy storage project,
harnessing energy created from solar PV of 100-150 households.
9STRICTLY CONFIDENTIAL |
Alkimos Beach Battery Overview
• The Project will see a 1.1 MWh, fully
contained Lithium Ion energy storage
system connected to the distribution
network
• The storage facility will be housed in a
shipping container and situated on site,
in an inconspicuous location
• The aim of the Project is to:
– unlock maximum value from solar
PV,
– reduce dependence and supply
from grid electricity
– increase value to residents
• The Project is initially set down for four
years, with an option to extend to 10
years (Battery has a life of 15+ years)
• Synergy will own the battery storage
facility
Alkimos Beach is currently the largest residential battery storage project in Australia, and will enable Synergy to be
on the leading edge of this technology
10STRICTLY CONFIDENTIAL |
How will it work?
Trial Participants
Excess PVEnergy“Credits”
Peak LoadTime(s)
Discharge
Excess PV REBS
Payment
Non Participating Resident
LowDemandCharging
Alkimos BeachBattery (1.1MWh)
Alkimos Beach Energy Storage TrialConcept Diagram
SWIS Grid
Metering Devices
Typical Profile
• Trial participants who “spill” surplus energy to the network during
the day (rooftop PV) will receive energy credits representing stored
energy.
• When participants draw from the grid on the day (most likely the
evening peak) they will use their credits first.
• Overall, less energy imported from the Grid (pay less tariff to
Synergy) and reduction in export REBS payment from Synergy.
• Discharge controlled by Synergy.
• Operations and Maintenance of the facility will be provided by the
contractor with training to Synergy personnel.
11STRICTLY CONFIDENTIAL |
How does it work?
• Round trip battery efficiency ~ 90%
• Connection voltage will be 22 kV
• Summer peak load reduction aimed at 2.5 kW per household for 4 hours
1.1 MWh / 300 kW battery storage system located next to distribution transformer within subdivision
Customers in the Project Area:
• Solar PV
• Advanced metering
• Time-of-use
• Remote meter reading
• Direct Load Control
(DLC)
Energy Storage Facility:
• Network connected, integrated system
of storage, inverter and protection /
control systems
• O&M by vendor via Service
Agreement
• Change / discharge timing controlled
by Synergy
Sub-transmission
system
Distribution
systemExcess solar
energy
Energy draw
from battery
Technical Configuration
SynergyHousehold M
Battery
Storage Grid
12STRICTLY PRIVATE & CONFIDENTIAL |
Alkimos Beach TechnologyThe Procurement Process
• The battery in particular comprised long lead time items which impacted the critical path. In
order to procure the storage device in a timely manner, Synergy has run a two stage process:
– an Expression of Interest (EOI) process conducted in November 2014 resulted in 22
interested companies submitting details of their potential offerings
– A Request for Tender (RFT) was issued to three parties that were short-listed in February
2015
• Synergy has executed a contract with Energy Made Clean (EMC) to supply, deliver and erect
an energy storage system at Alkimos Beach to support the Alkimos Beach Energy Storage
Trial (ABEST).
• The agreement with EMC for the storage system meets:
– ARENA’s Funding Agreement requirements
– Lend Lease and LandCorp requirements as partners in the ABEST
– The Western Power Technical Rules
– The Landowner (Water Corporation) requirements
• Synergy engaged with Western Power to commence the Electricity Network Access process.
13STRICTLY PRIVATE & CONFIDENTIAL |
Alkimos Beach TechnologySynergy has engaged Energy Made Clean Pty Ltd (EMC) to supply Alkimos 1.1 MWh energy storage device. EMC
will deploy Samsung technology for the lithium-ion technology, with EMC to provide EPC services
Who is Energy Made Clean?
• EMC is a Western Australian based business, that specialises in
commercial solar and off-grid power solutions
• EMC was established in 2004 and employs ~20 personal based in
Perth
• EMC’s head in Perth also houses its 2,500m2 manufacturing facility
where we manufacture our lithium ion battery storage containers
• EMC has significant experience across a range of commercial-
scale solar projects, including EMC’s Build, Own, Operate and
Maintain (BOOM) solar PV power station in Carnarvon
14STRICTLY PRIVATE & CONFIDENTIAL |
Alkimos Beach TechnologyThe Samsung Battery - the heart…….
• The individual cell cathode is a blend of Lithium Manganese Oxide LiMn2O4 and Nickle Cobalt
Manganese Oxide LiNiMnCoO2.
• The anode is natural graphite.
• 3V - 4.1V per cell
• 16 Cells per Tray (in series)
• 12 Trays in series per rack with a switchgear unit - 576 - 787.2V output (rated 42.6
kWh)
• 29 racks in parallel each with same length cable back to the DC marshalling board
15STRICTLY PRIVATE & CONFIDENTIAL |
Alkimos Beach TechnologyThe Samsung Battery - the heart…….
• The 29 rack battery has been built into a modified, 30 foot long sea container
which will weigh around 26 tonnes when complete.
16STRICTLY PRIVATE & CONFIDENTIAL |
Alkimos Beach TechnologySafety and Protection
• All li-ion technologies are vulnerable to over charging and discharging too fast – can result
in catastrophic cell failures and the risk of fire – ask Mr Boeing and others !
• Managing multiple cells in series is difficult and needs careful engineering design.
• Each cell is engineered around safety relief – safety in design.
• Each rack is individually fused to limit runaway type faults.
• Each tier is protected where it marshals to other tiers.
17STRICTLY PRIVATE & CONFIDENTIAL |
Alkimos Beach TechnologyLife
• Typical of Li-ion, maximum life is achieved by limiting cell temperatures when charging and
discharging. This will be one of the big issues for residential batteries in Australian
conditions !
• Battery container is air conditioned and carefully designed to achieve uniform cooling of
the battery racks.
18STRICTLY PRIVATE & CONFIDENTIAL |
Alkimos Beach TechnologyMaking it useful…….
• The output DC of the battery is fed to a SMA 500kVA inverter (de-rated for this application) to produce a 270 V AC , 3 phase output.
• The inverter is controlled to manage the discharge rate of the battery.
• This output feeds a 270V / 415 V 3 phase DYn11 transformer to provide further harmonic suppression.
• The inverter, transformer and control and monitoring equipment are housed in a modified and segregated second 30 foot sea
container.
• A 415V / 22kV distribution transformer connects to the facility to the Western Power 22kV network within the subdivision.
• Facility is able to be remotely monitored by both EMC and Synergy.
19STRICTLY PRIVATE & CONFIDENTIAL |
Project StatusThe time line
• To date, the Alkimos Beach Energy Storage Trial (ABEST) has:
– secured the funding arrangement with ARENA and the project partners
– completed the process for the procurement and maintenance of the Battery and issued a contract to EMC
– secured the site for the battery on Water Corporation land
– secured an off of network access to the South West Interconnected System (SWIS) from Western Power
– commenced development of new retail products
• The project is now in the ‘construction phase’ with the core deliverables being:
– fabrication and commissioning of the battery
– complete site works
– setup of the data analysis control groups
Q2 2014 – Q1 2015
Project DevelopmentBattery Construction &
CommissioningGo Live Operational reporting
Project conclusion and decommissioning
• Commercial agreements with
project partners and service
providers
• ARENA Approval
• Complete business case and
Project Plan
• Commence Data Baseline
study
• Report to ARENA the
operational performance of the
Battery
• Report client behavioural
changes
• Report other key findings
Current Status
• Issue EPC Contract
• Develop Retail products
• Commence marketing
campaign
• Connection Application into
SWIS
• Development Application to
LGA & PAWA
• Implement & Commission
Battery
• Test operation of Battery &
Retail products
• Go Live
• Initial ARENA operational
report
• Conclude study
• Decommission battery or extend
site lease with Water Corp
• Present Final report to ARENA
Q2 – Q3 2015 Q4 2015 - Q1 2016 2016 - 2020 Q4 2020