alternate site and tunnel configuration status report kek (1)

7
Conventional Facilities and Siting Conventional Facilities and Siting 1 Alternate Site and Tunnel Configuration Status Report KEK (1) Nov. 2008, Chicago Global Design Effort Atsushi Enomoto, Shigeki Fukuda, Masami Tanaka

Upload: wendy-rojas

Post on 30-Dec-2015

35 views

Category:

Documents


2 download

DESCRIPTION

Alternate Site and Tunnel Configuration Status Report KEK (1). Atsushi Enomoto, Shigeki Fukuda, Masami Tanaka. Nov. 2008, Chicago. Global Design Effort. 1. Alternate Site and Tunnel Configuration Status Report KEK (part 1). Aternate Site Study. Nov. 2008, Chicago. Global Design Effort. 2. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Alternate Site and Tunnel Configuration Status Report KEK (1)

Conventional Facilities and SitingConventional Facilities and Siting

1

Alternate Site and Tunnel

ConfigurationStatus Report KEK (1)

Nov. 2008, Chicago Global Design Effort

Atsushi Enomoto, Shigeki Fukuda, Masami Tanaka

Page 2: Alternate Site and Tunnel Configuration Status Report KEK (1)

Alternate Site and Tunnel Configuration Status Report KEK (part 1)

Aternate Site Study

Nov. 2008, Chicago Global Design Effort 2

Page 3: Alternate Site and Tunnel Configuration Status Report KEK (1)

Nov. 2008, Chicago Global Design Effort 3

  Proposed Site IDTunnel depth

Tunnel configurationAccess to tunnel(s)

Access to klystron

Site Availabilityin Japan

1 RDR Americas &

European sample site

Deep Twin Shaft   Anytime Not available

2 RDR Asian

sample site

Deep TwinSloped tunnel

Anytime Available

3 Dubna site Shallow

Twin (shallow beam tunnel, near-

surface service tunnel)

Shaft Anytime Not available

4 DESY Site Shallow Single Shaft No Depend on

tunnel depth

5 Americas

Alternative (RF Cluster)

Deep Single Shaft Anytime Available

6 Asian Alternative

(DRFS)Deep Single

Sloped tunnel

No Available  

Applicability of site / tunnel configuration

Page 4: Alternate Site and Tunnel Configuration Status Report KEK (1)

4

Cost evaluation

Cost(5): Variation (II): Most cost effective method

Circulator elimination by power feeding to 2

cavities from one klystron. Output power is 732kW. Modulated Anode Klystron (MAK) is adopted.

Anode modulation pulser does not need the high power and cost efficient pulser is manufactured.

DC Power Supply is common for 26 cavities and voltage drop during the pulse is compensated with appropriate circuits at the level that LLRF can feed back.

• It is easy to suppress the collector power dissipation without rf in MAK by adjusting the modulated anode voltage.

• Are Disconnection SWs necessary?

Page 5: Alternate Site and Tunnel Configuration Status Report KEK (1)

Configuration

Rough Sketch for DRFS• Single tunnel layout. 5m diameter (like DESY)• Cryomodule is hanged down from the top of the

tunnel.• RF sources are connected thru circulator, but plan

without circulator is possible and discussed.• In this drawing, a modulator applies the voltage to

two RF source. Working space are considered as shown in the drawing.

• Modulators, LLRF units and other electrical devices are installed in the shielding tunnel.

• There is a choice that the DC power supplies or chargers are concentrated for 4 or 8 units or more.

• Layout of using a modulated anode klystron is possible.

5m

0.965m

Page 6: Alternate Site and Tunnel Configuration Status Report KEK (1)

BCD DESY Shallow Tunnel RF Cluster DRFS

Deep/Shallow Deep Middle Shallow  Middle DeepCivil Cost High Middle Shallow tunnel cost ? CheepCooling  Cost ○ ◎ ◎ ◎ ○

Dubna OK J apan J apan ?  -> longer WG

LLRF handling ○ ○ ○   △ ◎

Redundancy ○ ○ ○   △ ◎

R&D Cost ○ ○ ○   △ ◎

Total Cost

Vector Sum  26 cav. Vector Sum26 cav. Vector Sum26 cav. Vector Sum

26 Cavity StopEasy KlystronReplace

Easy KlystronReplace

Scattered failuresection26 Cavity Stop26 Cavity StopKly Failure Impact

Very SimpleConfigurationOther Issues

3 Cryomodule/26Cavity= 1 RF unit

3 Cryomodule/26Cavity= 1 RF unit

3 Cryomodule/26Cavity= 1 RF unit

Difficult to evaluateone minimum unit

Very small systemTest Facility

Long Vacuum WGSystemLong HV Cable

Heat source of RFin the tunnel

Modulator on thesurface

Heat source of RFon the surface

Heat source of RFon the surface

Heat source of RFin the tunnel

780 cav. VectorSum 1 to 1

Scheme

OK J apan Mountain Site? OK

   Heat source

Site Dependence

6

Alternative scheme proposedDUBNA

Page 7: Alternate Site and Tunnel Configuration Status Report KEK (1)

Summary

(1) An alternate site/tunnel configuration which has a single tunnel configuration and suitable for the Asian sample site has been studied.

(2) The basic feature is compact size of RF source units directly attached with a couple of cavities, of which scheme enables lower high voltages, lower powers. This seems a scheme easier to treat (transport, install, …) and operate (power feed, water-cool, control, …), then is more reliable and safe in operation.

(3) Cost impacts will be studied hereafter.

Nov. 2008, Chicago Global Design Effort 7