Page 1: AME OUTLINES
Page 2: AME OUTLINES

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

Page 3: AME OUTLINES

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

KEY PROFESSIONAL DATES AND EXPERIENCES

After his degree in Naval and Mechanical Engineering in the University of Genova (Italy) in 1963,

Carlo Avanzini has been active in the field of land and marine pipelines, first in the field of oil P/Ls, then transferring his interests to civil pipelines.

From the early 70s, he has designed or has intervened as engineer and supervisor in a wide range of projects in different countries, with own Companies

or as free-lance consultant teaming with engineering companies or colleaguesHe brings as references projects in steel, HDPE, GRP in diameters up to 4000 mm.

Page 4: AME OUTLINES

International engineering support is given to HAWLE /NOVA SIRIA on the application of Steel Compression Couplings

and, in GCC, to PROCO (USA) on the DuckBill Valves for diffusers and coastal discharges

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

The cooperation on international projects is in favor of engineering companies, material suppliers and contractors, and

includes design, preparation of specifications, construction method statements, planning and supervision.

Page 5: AME OUTLINES

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

One of the first documented project was the design and supervision of the outfall discharging pre-treated water from a paper factory in Silifke, Turkey Concrete Coated Steel 900mm x 900m (1985)

Numerous marine and outfall projects, easy or very engaging, successful or better forgotten are now past history, only

reminded in old faded out papers and photos

Locations, main data and photos of a few major projects in the last [25] years are shown in the next slides; others are collected in my CV.

Page 6: AME OUTLINES

ISTANBUL ÜSKÜDAR OUTFALL (1989)Steel, 1219.2mm, concrete coated,

275m long to -43m depthLaunched with short ramp in 3 sections joined

by rubber flexible joints, bottom pull from the site through a cable return deviation block anchored on the bottom at 350m distance

ISTANBUL BALTALIMANI OUTFALL(1989)Steel, 2 x 1727,2.2mm, 300m long to -73m depth Twin pipes launched with short ramp in 2 sections joined by rubber flexible joints.Bottom pull from opposite side of Bosphorusat 1200m distance with a cable deviation block midway on the bottom at -75m depth.

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

Page 7: AME OUTLINES

Substitution of a section of the shore approach of the Marmara Gas Pipeline, damaged by the underwater slippage of a clay lens.The pressure of the landslide had buckled the pipe upwards and caused a severe leak.The project included the construction of the new string, the cut and removal of the damaged length, the bottom pull of the news string to the junction point, lifting of the two ends for the off-barge dry-welding of the sections .The pipe was kept in position for welding by two rotating clamps and supended for the alignment to two cranes and two davits and finally lowered in position.

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

ISTANBUL, MARMARA GAS MAIN (1990)

Page 8: AME OUTLINES

The third Istanbul main outfall ….Steel, 2235.2mm, concrete coated, 2200m long with diffuser at -47m depthPrefabrication executed on long ramp with multiple welding and coating stations Installation performed with bottom pull from a barge anchored offshore.

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

ISTANBUL, TUZLA OUTFALLL(1992)

Page 9: AME OUTLINES

Offshore GRP pipelines for the cooling water system of the Thermal Power Plant

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

Nova Siria Compression Couplings

ND 2800 and 2400

were employed for the first time for

underwater tie-ins

4 x ND 2800 intake lines, 420m long 4 x ND 2400 outfalls, 1250m long

SÜGOZÜ - ISKENDERUN GULF, SOUTH TURKEY (2000)

The 4 concrete intake structures, with dimensions 9.8 x 7,5 x 8.35hand weight in air ≈ 600 ton, were connected to the pipelines with a slip-on 2800 reinforced rubber hose.

Page 10: AME OUTLINES

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

Outfall, GRP, ND 900, length 2150mVertical alignment control obtained with concrete saddles.Diffuser protected with concrete caps.

SAIDA, LEBANON, 2003

Page 11: AME OUTLINES

Concrete coated steel, 2235.2 mm, length 2308m Welding and coating on inclined long ramp

Installation with bottom pull from pulling station on the opposite coast

Slope changes obtained with rubber flexible couplings.

KADIKÖY OUTFALL, ISTANBUL, 2004

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

Page 12: AME OUTLINES

IGDAS TRANSMISSION GAS LINES TO PRINCESS ISLANDS (SEA OF MARMARA, ISTANBUL, 2005)

Steel X52, 219,1, concrete coated, installed with bottom pull

4 sections between land and the 4 islandsMain feeder 3580mTransmissions to other islands respectively 1450m, 1370m, 2150m

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

Page 13: AME OUTLINES

The need of the substitution of the original diffuser with a new taered one to be connected to the main ND2500 GRP line required an intervention to be performed with a time-limited interruption of the plant.The connection was studied on paper and a combination of GRP short spools and of tailor-made Compression Couplings, designed with 400 mm axial tolerance and ± 3° allowable angular deflection been realized in 8 hrs, practically without idisturbanceto the TPP operation.

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

AMBARLI, UNIMAR THERMAL P0WER PLANT (2005)

Page 14: AME OUTLINES

Waste W ater Outfall, GRP, ND 1800 with length 2000 mInstalled “pipe after pipe” in trench with a diffuser at -11m depth

Tie-ins and special connections were realized with Compression Couplimgs, while the shore approach andthe line were protected with mesh gabionse

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

MERSIN OUTFALL, SOUTHERN TURKEY (2007)

Page 15: AME OUTLINES

After thre years, the diffuser suffered extensive damages, causes [obviously!] unknown.The pipe brought was brought to land, cleaned and the components recovered as much as feasible.

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

MERSIN GRP DIFFUSER REPAIR (2010)

It has been interesting to see that there have been a minimum fouling of the internal surfaces.Only local limpets groups vere present.

It was provided a new section with one port and the missing length was compensated with a long, specially designed steel compression coupling.

Page 16: AME OUTLINES

BANDIRMA TPP / ATEC (2008)

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

Cooling water GRP pipelines – 2 x 2200 intake lines 200m long to -23 m depth and 1 x 2400 outfall 350m long with diffuser at -29m depth.

Page 17: AME OUTLINES

Onshore cooling water circuit, GRP 4 x ND 2500Supervision of the pipe production and delivery, site lamination, installationand testing.

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

AL KHALIJ TPP – LIBYA (2010)

Site observation of marine installation techniques [Geocean, FR]

Page 18: AME OUTLINES

GRP Discharge line ND 3500, 450m longwith special half buried short diffuser at -33mstabilized with mattresses and gabions

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

BIGA (TR) NEW 2X600 MW POWER PLANT (2010)

Page 19: AME OUTLINES

EAST DELTA ELECTRICITY PRODUCTION COMPANYEL AIN EL SOKHNA SUPERCRITICAL THERMAL POWER PLANT UNITS 1 & 22X650 MW GAS/OIL FIRED UNITS

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

EL AIN EL SOKHNA TPP EGYPT (2011)

GRP, 3 x ND3000 intake pipelinesSupervision of pipe production and installation obbehalf of PGESCo - Bechtel

Installation by Besix-Orascom

Page 20: AME OUTLINES

Design for the installation of the HDPE structural pipe ND 2000 3700 m longPipe and ballast blocks supplied by the Russian clientThe type of pipe and the blocks had been found not suitable for a safe sinking, but the client insisted nevertheless for the installation.

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

SOCHI OUTFALL, RUSSIA (2012) [FIRST STAGE]

The project was stopped after the pipe failureThe pipe was tested in Germany and resulted not meeting the standards

Prefabrication and towing started to raise doubts on the pipe’s real strength, but the first string broke after the start of the installation of the ballast blocks

Page 21: AME OUTLINES

Ballast blocks and saddles, as well as the compete installation calculations and procedures were completely redesigned

The installation of line and diffuser was completedwithout problems.

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

SOCHI OUTFALL (RUSSIA) – RESTARTED IN 2013 WITH NEW DESIGN

First 2000 m of the outfall have been substituted by a tunnel. The remaining 1413 m were delivered as HDPE ND 2000 (extruded)

Page 22: AME OUTLINES

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

SAMSUN OTV CCPP POWER PLANT –COOLING WATER PIPELINES (2011/2012)

Intake and discharge sealines in GRP, 3 x ND 2400 length 860m and 2 x ND 3200 length 600m including diffuser.

GRP intake structures with OD 14m

Page 23: AME OUTLINES

Structural HDPE ID 3000mm, length 3700m inclusive of diffuser wirh 250 T ports at -11m

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

LA TABOADA OUTFALL, LIMA, PERU (2010/2012)

Page 24: AME OUTLINES

MAR DEL PLATA, ARGENTINA (2012)Outfall, HDPE ND 2.000 mm, length 4110 m

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

Page 25: AME OUTLINES

HDPE pipes, ballasted.

Intake line ND 1400 with GRP intake structure;

Outfall line ND 900 with multiport diffuser

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

IZDEMIR ALIAGA COOLING WATER LINES (2013)

Page 26: AME OUTLINES

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

LA CHIRA OUTFALL , LIMA, PERU (2012, RESTARTED 2013/2014)

Structured HDPE ID 2400mm3600m long inclusive of diffuser at -60m depth

2012

20162015

Page 27: AME OUTLINES

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.PRESENTATION OF CAPABILITIES

GRP, ND 4000, length 700 m discharge line for 4 parallel diffuser branches, each with 7 ports

ATLAS THERMAL POWER PLANT, ISKENDERUN, TURKEY (2014)

Page 28: AME OUTLINES

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.PRESENTATION OF CAPABILITIES

Due to the long time cooperation with Cal Hayes, the Manager of Proco Proflex Division, and the long experience of Carlo Avanzini in the use of Duck Bill Valves in sewerage systems and in coastal and marine environment, Proco has entrusted to AME the exclusivity for the technical and commercial assistance of its products in the GCC.

Clients interested in PROCO PRODUCTS may refer to [[email protected]] for technical information and quotations.

TECHNICAL AND MARKETING SUPPORT TOPROCO [USA]

website: http://www.procoproducts.com

Page 29: AME OUTLINES

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.PRESENTATION OF CAPABILITIES

Since several years, many Nova Siria applications, particularly in the field of marine pipelines, have been designed by Avanzini.At present, the cooperation with Nova Siria continues as AME giving its consultancy and technical assistance to Hawle Mid East.Clients interested in Nova Siria products shall refer for technical information and quotations to Hawle Mid East FZE (E-Mail: [email protected] ; Web: www.hawle.comor www.novasiria.it for an outline of the products)

In case of technical questions on the applications, engineers and contractors may contact Carlo Avanzini at [email protected] with copy to Hawle ME

TECHNICAL CONSULTANCY ON COMPRESSION COUPLINGS’

SPECIAL LAND AND MARINE APPLICATIONS OF NOVA SIRIA/HAWLE MID EAST

Page 30: AME OUTLINES

Carlo Avanzini is the Organizer and Coordinator of MWWD CONFERENCES

E-Mail: [email protected]: www.mwwd.org

Professional registration @ Chambers of Engineers, Genova, Italy, No C.E. 8679A

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.

MWWD CONFERENCE ORGANIZATION

Page 31: AME OUTLINES

Managing DirectorAVANZINI MIDDLE EAST (FZE)Saif Zone - Q1-04-033/A – P.O.Box 121256 – Sharjah – U.A.E.Incorporated @ No. 14905E-Mail [email protected] Mob. 00971.50.9391572

Professional Engineer Marine Engineering And ConsultingCemil Topuzlu Cad. 26/1 Ciftehavuzlar, Istanbul, TurkeyE-Mail: [email protected] Mob. 0090.542.3580445

Organizer and Coordinator MWWD CONFERENCESE-Mail: [email protected]

Dr. Eng. Carlo AvanziniDegree Naval Architecture, Naval and Mechanical Engineering, University of Genova, Dept. of Naval Engineering, 1963Professional registration @ Chambers of Engineers, Genova, Italy, C.E. 8679A

AVANZINI MIDDLE EAST FZE – SHARJAH, U.A.E.