amendment in the environmental … baihar panahan jukehi karaundla noreri barhati goindi barua...

29
NOTE ON ENVIRONMENTAL IMPACTS FOR AMENDMENT IN THE ENVIRONMENTAL CLEARANCE (EC) FOR THE PROPOSED AMETHA PROJECT AT AMETHA, TEHSIL VIJAYARAGHAVAGARH, KATNI DISTRICT, MADHYA PRADESH STATE UNDER 7 (II) CATEGORY Submitted by Cement House 121, Maharshi Karve Road Mumbai – 400 020, India April, 2018

Upload: phungdung

Post on 22-Mar-2019

213 views

Category:

Documents


0 download

TRANSCRIPT

NOTE ON ENVIRONMENTAL IMPACTS

FOR

AMENDMENT IN THE ENVIRONMENTAL CLEARANCE (EC)

FOR THE PROPOSED AMETHA PROJECT AT AMETHA, TEHSIL VIJAYARAGHAVAGARH, KATNI DISTRICT,

MADHYA PRADESH STATE

UNDER 7 (II) CATEGORY

Submitted by

Cement House 121, Maharshi Karve Road Mumbai – 400 020, India

April, 2018

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

1.0 INTRODUCTION

Kymore Cement Works (KCW) of ACC limited had proposed to install new clinkerisation plant-2.7 MTPA at Ametha, expansion of existing Limestone mine (from 5.445 MTPA to 9.495 MTPA) & Captive Power Plant (from 50 MW to 85 MW), Waste heat recovery boiler (10 MW) with coal washery (0.405 MTPA) at Kymore Cement Works, Tehsil Vijayaraghavgarh, district Katni, Madhya Pradesh. Ministry of Environment and Forest & Climate Change (MoEF&CC) had granted Environmental Clearance (EC) for the above project vide letter no. J-11011/175/2008-IA.II(I) dated 24th November, 2011. The copy of the EC letter enclosed as Annexure-I. The approved units capacities and mine expansion details as per 2011 EC are presented in Table-1. Further, the existing EC is valid till November 23, 2018.

TABLE-1 APPROVALS OF VARIOUS UNITS & MINES EXPANSION DETAILS UNDER

2011 EC Sr. No.

Description Unit Existing Proposed Capacity

Expansion

After Expansion

Total Capacity 1 Clinkering plant at

village Ametha MTPA - 2.7 2.7

2 Captive Limestone Mines

MTPA 5.445 4.05 9.495

3 Additional Limestone Crusher

TPH 1200 1200 2400

4 Captive power plant at KCW, Kymore

MW 50 35 85

5 Waste Heat Recovery System at Ametha

MW - 10 10

6 Centralized Coal Processing Plant at Kymore i) Coal Crusher TPH 250 1500 1750 ii) Coal Washery Throughput

TPH - 90 90

1.1 Current Project Proposal

ACC has proposed to set up new grinding unit of 2.0 MTPA in the existing land 101.17 ha area earmarked for new green field clinkerisation plant. The clinkerisation plant will be located within the existing mining lease area. Existing EC is valid till 23rd November, 2018 hence ACC also has applied for extension of validity of EC till 23 Nov 2021.

VIMTA Labs Limited, Hyderabad 2

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

Table-2 presents the amendment request sought along with existing EC approved scope.

TABLE-2 DETAILS OF VARIOUS UNITS APPROVED UNDER EARLIER EC & AFTER

AMENDMENT REQUEST Sr. No.

Description Unit Existing EC Granted

EC Amendment Requested

1 Clinkering plant at village Ametha

MTPA - 2.7 No change

2 Grinding unit at Village Ametha

MTPA - - 2.0

3 Captive Limestone Mines

MTPA 5.445 9.495 No change

4 Additional Limestone Crusher

TPH 1200 2400 No change

5 Captive power plant at KCW, Kymore

MW 50 85 No change

6 Waste Heat Recovery System at Ametha

MW - 10 No change

7 Centralized Coal Processing Plant at Kymore i) Coal Crusher TPH 250 1750 No change ii) Coal Washery Throughput

TPH - 90 No change

1.2 Present Status of Project Implementation

ACC had to commit resources for setting up new Clinkerisation unit at Jamul as it was mandated by Government to shut down old kiln and setup state of Art integrated plant for the betterment of the environment. Therefore, deployment of resources in Ametha project had to be differed. Now the state of art Jamul plant is commissioned and ACC has now decided to go ahead with setting up Ametha integrated plant covering clinker unit and also 2.0 MTPA grinding unit.

Market demand in the eastern sector was more robust than in central sector. Central sector market had not picked up as expected by us at the time of submitting proposal for setting up plant at Ametha proposal.

VIMTA Labs Limited, Hyderabad 3

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

Market demand in central sector is huge and due to improvement in market situation in UP we are proposing to set up standalone grinding station at Tikaria-II for which Environmental Clearance is already in place. Ametha clinker unit is the source of Clinker for the proposed standalone grinding unit at Ametha and Tikaria-II project as well. At present project design is in advanced stage of completion. ACC has proposed to complete the construction of Ametha integrated project covering both clinker and grinding unit within 29 months from the receipt of amendment in the Environmental clearance for 2.0 MTPA grinding unit with extension of validity of existing Environmental Clearance and other approval. Project implementation schedule is presented in Annexure-II.

1.3 Location of the Project and Environmental Settings

Ametha project is located near Ametha village, Tehsil Vijayaraghavagarh, Katni district, Madhya Pradesh state. The project site is located 30 km away from the district head quarter Katni. The nearest rail station is Jukehi railway located at 9.5-km from plant boundary in WSW direction. The site is 120 km away from Jabalpur city, which is also the nearest airport. The plant site is located on a flat terrain and no topographical changes are anticipated due to the proposed of 2.0 MTPA grinding unit. No-ecological sensitive habitats like national parks, biosphere reserves, wildlife sanctuary, health resorts and defense installation are present within 10 km radius of the Ametha project.

Detailed environmental settings for the proposed grinding unit is given Table-3. Index map, and location map showing proposed project site and surrounding features within 10 km area are presented in Figure-1 and Figure-2 respectively.

VIMTA Labs Limited, Hyderabad 4

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

TABLE-3

DETAILS OF ENVIRONMENTAL SETTING

Sr. No. Particulars Grinding unit 1 Longitude 80°31’42” E 2 Latitude 24°00’24” N 3 Climatic Conditions

(As per IMD Umaria) Annual Max. Temperature: 44°C; Annual Min. Temp: 3.9°C; Annual Average Rainfall:1365.9 mm; Pre-dominant wind directions: W

4 Land use at the proposed project site Part of Existing Mining Lease Area (Land under possession of ACC)

5 Nearest Highway NH-7 connecting Jabalpur-Allahabad (6.5-km, NW)

6 Nearest Railway line/ Railway Station Jukehi railway station (9.5-km, WSW) 7 Nearest Village/ Township Ametha (0.5 –km, E)

Kymore (10.2 –km, ENE) 8 Nearest Airport Jabalpur (120 km, SW) 9 Nearest major City 1] Katni (30-km, SW); 2] Satna (65-km, NE);

3] Jabalpur (120-km, SW) 10 Nearest river/ water body - Tons River (4.2-km, NNW)

- Koilari Nadi- (6.2-km, SSE) - Katni Nadi (7.2-km, SSE) - Mahanadi River (11.5-km, SE)

11 Ecologically Sensitive Zones (National parks, Wildlife Sanctuaries)

None within 15-km radius

12 Reserved/ Protected Forest within 10-km radius:

Surma R 2.5 –km, NNE PF near Pala Village 7.2–km, N Goindra PF 8.0–km, SE PF near Bhainswahi 8.4–km, S Jiwara PF 8.5–km, SE Banjari RF 8.7–km, E

13 Defense Installations/ Ports None within 15-km radius 14 Major Industries within 15-km radius 1] Existing Kymore Cement Works (9.5 km,

NE) 2] Asbestos Plant of Everest Industries Ltd, Kymore ( 11km; NNE)

15 Seismic Zone Zone-II as per IS-1893 (Part-1)-2002

VIMTA Labs Limited, Hyderabad 5

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

FIGURE-1 INDEX MAP OF THE PROJECT SITE

VIMTA Labs Limited, Hyderabad 6

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

FIGURE-2 10 KM RADIUS STUDY AREA MAP

Surma RF

K Y M

O R

E

H I L L

S

GOINDRAPF

PROTECTED FOREST

PROTECTED FOREST

PF

JIWAKAPF

PF

Katni Nadi

Katni

Nad

i

Koilari Nadi

Tons River

Kevlari Nala

Tons

(Tam

asa)

R

PROTECTED FOREST

Katni Nadi

Tons River

NH 7

BANJARI R F

Mahanadi River

Tons River

Jhapawan N

ala

NH 7

PF

K Y M

O R

E

H I L L

S

PROTECTED FOREST

RamnaRamnachaighara

GauranaMajhgawan

Banjari

Bijeraghogarh

Salaiya

Jhiriya

Nanhwara Kalan

Kalhara

Ametha

Barari Duari Majhgawan

BamhangawanKhaiwara

Hospital

Tighara Khurd

Dhanwahi Khurd

Gumeti

BoriGumeti

Rahania Khurd

Surma

Dhaneri Khurd

GudugarhauhaKaihara

Dogargawan

Kottaria

PakariaGugar

GugriHardua

Patharhata

Sabhaganj

Palauha

Pragganj

Khamharia

Jamunia

Amuwa

Garhwa

Binaika

Dhaner KhurdUrdani

Jukehi RS

Punchhi

Jobi Kalan

Bistara

Majhgawan

Jobi Khurd

DitawaraMawaitola

Sahaspura

Salaiyamerhal

BhainswahiTikariya

Singhwara Deosarindar

Jiwara

Goindra

RakhipurainiJijnaurichaighara

Jijnauri

Jatwara

Baktha

Deora Kalan

Singhwarakharkhari

Sakri

Hardua Khurd

Hardua Kalan

Paraswara

Padkhuri

Kachagawan RajarwaraKharkhari

Amuwari

Banigawan

Deosari

Mehgaon

Kharkhari

BaraAmaraiya

Salaiya

Naugawan Dhanwahi

Dhanwahi

HaraiyaDurjanpur

ParaswaraGanja

Kherhai

Lukampur

Khajura

ParariyaBhimpar

Hinota

PatparhaRohaniya

ACC Colony

Dhawai

Semra

Yaduvirnagar

KharwaMahanta

Amdara Naugawan

Kuthilgawan

Tishkili Kalan

Tishkili KhurdNayagaon

Baijal

Bhopar

Mahgama

Duhri

Khurwa

Khirwa Simaria

Tikar

Baihar

Panahan

Jukehi

Karaundla

Noreri

BarhatiGoindi

Barua

Hantala

Chhiri

Karitalal

Baratitola

BhateuraGhorwai

Parrehi

Manaura

Burhagar

Matwara

RajgawanGhuhwara

Matwara

Jamuwani Khurd

Kusma

Basaundha

Gureha

GhunsurPibariya

Ponriparariya

Mohari

Chengra

KanhwaraJatwaraPatwara

Kallwara

Karhalya Kalan

Pothra

Karhalya KhurdTikarwara

Kamtalai

Kusmi

Pala

PROTECTED FOREST

KATNIPF

HARDUARF

BarhataKhirba

Pipariyakanp

Singhanpura

SinghanpuraTikuri

Majhauli

Karanpura

Bairagal

Bandhi

Khiewa

BhamrahaMahari

SCALE

80° 30'

RoadRailway Line

Nadi-NalaSettlements

Mehgaon Block

LEGEND

Forest BoundaryDistrict Boundary

Bamangaon Block

Clinker Plant & Proposed Grinding Unit

Coal Washery & CPP Expansion

80° 30'

23° 55'

24° 5'

1 0 1 2 Km

Topo Sheet No. 63 A/5, A/9, D/8, D/12.

24° 0'

80° 35'

23° 55'

80° 40'80° 35'

80° 40'

N

10 KM

24° 0'

24° 5'

80° 25'

80° 25'

ACC Kymore Lease Area

VIMTA Labs Limited, Hyderabad 7

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

2.0 REQUIREMENTS OF THE PROPOSED GRINDING UNIT

Additional raw materials, water, power, land, machinery, man power requirement for proposed project of 2.0 MTPA grinding unit are presented in the following sections.

2.1 Raw Material

Details of raw material requirement along with estimated quantity (maximum) for grinding unit, likely source of raw materials and mode of material transportation for setting up 2.0 MTPA grinding unit are given in Table-4.

TABLE-4 SUMMARY OF RAW MATERIAL FOR GRINDING UNIT

Raw

material Raw material requirement

(MT)

Source of Raw Materials

Mode of Transport

Clinker 1,240,000

Proposed grinding unit is part of integrated Ametha Clinkering unit which is source of Clinker

By belt conveyer.

Gypsum 100,000

Imported By rail / road

Fly Ash 700,000

Madhya Pradesh Power generating company Limited, Moserbaer power plant, Bajaj Power plant

Road (bulker)

2.2 Water Requirement

Since this is dry process, water requirement during the manufacturing of cement is minimal. The only source of water consumption is cooling of plant machinery during grinding. Closed loop system is in place along with cooling tower. The additional water requirement in closed cooling system is about ~35 m3/day. Only the make-up water will be added to compensate the evaporation losses. The water requirement for the proposed cement grinding unit, will be met from the existing sump of operating mines since 1949 and water reservoir created at worked out pit of existing mine by rain harvested water.

VIMTA Labs Limited, Hyderabad 8

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

2.3 Power Requirement

The additional power requirement for the 2.0 MTPA grinding unit will be 10 MW, and it will be meet from the Kymore Captive power Plant (CPP)/grid.

2.4 Land Requirement

The area required for the grinding unit will be 5.3 ha, and it will be set-up in the existing land of 101.17 ha area earmarked for new green field Clinkerisation plant which will be located within the existing mining lease area, which is in operation since 1949. Hence no additional land is required. The mine lease is owned / leased to ACC. Mine is already in operations since 1949.

2.5 Manpower Requirement During operation phase of 2.0 MTPA grinding unit about 60 people will be employed.

2.6 Plant and Machinery Requirement Details of equipment requirement for setting-up 2.0 MTPA grinding unit along with capacity and proposed Pollution Control Devices (PCD) are given in Table-5.

TABLE-5

DETAILS OF PCD AND MACHINERY REQUIREMENT FOR 2.0 MTPA GRINDING UNIT

Sr No

Name of Equipment

Capacity Proposed Pollution Control system

1 Cement Mill 1 x 325 TPH Bag Filter

2 Packer & loading facility

2 x 240 TPH Bag filter

3 Cement Silos 2 x 6000 MT Bag Filter

4 Belt Conveyors As per standard design and requirement.

Bag Filter / dust extraction system

5 Fly ash silo 2000 MT Bag Filter

Proposed grinding unit is state or art dry process grinding unit. Project will be provided along with facilities for unloading, storage, handling and covered storage for raw materials. All pollution equipment will be designated for meeting outlet particulate emission level below 30 mg/Nm3. The cement dust collected in the pollution control devices is recycled back to the cement manufacturing process. In addition to the above, additional bag filter system along with ventilation systems

VIMTA Labs Limited, Hyderabad 9

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

will be installed to control the fugitive dust generated from material handling areas, transfer points and other operational areas.

2.7 Project Cost The estimated capital cost for setting up 2.0 MTPA grinding unit will be Rs. 200 Cr. Key changes in environmental parameters w.r.t. project requirement due to EC amendment and EC granted are given in Table-6.

TABLE-6

SUMMARY OF CHANGES IN ENVIRONMENTAL PARAMETERS

Sr. No

Parameter Units EC Granted

Amendment Requested

Remark

1 Land for clinker & grinding unit, Ha

Ha 101.71 No change No change

2 Capacity Clinker

production MTPA 2.7 No change No change

Cement production

MTPA ----- 2.0 Addition of 2.0 MTPA Grinding Unit.

Captive Limestone Mines

MTPA 9.495 No change No change

Additional Limestone Crusher

TPH 2400 No change No change

CPP at KCW, Kymore

MW 85 No change No change

Waste Heat Recovery System at Ametha

MW 10 No change No change

3 Raw materials

A Clinker MTPA ----- 1.24 Positive impact. Proposed grinding unit is part of integrated Ametha Clinkering unit which is source of Clinker to proposed grinding unit. Utilization of clinker in same unit will result in reduction of 1.24 MTPA clinker transportation.

B Gypsum MTPA ----- 0.10 C Fly ash MTPA ----- 0.70 Positive Impact

Increase in waste consumption i.e fly-ash consumption increase by 0.70 MTPA

VIMTA Labs Limited, Hyderabad 10

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

Sr. No

Parameter Units EC Granted

Amendment Requested

Remark

E Limestone MTPA 4.05 No change No change F Bauxite MTPA 0.09 No change No change G Iron ore MTPA 0.09 No change No change H Laterite MTPA 0.09 No change No change I Sandstone MTPA 0.04 No change No change 4 Fuel Coal for Kiln MTPA 0.52 No change No change Coal for CPP MTPA 0.372

No change No change

5 Water consumption

m3/day 3025 35 0.9 % Increase.

Waste water generation

m3/day 580 No change No additional waste water will be generated

6 Manpower 60 7 Power 10 8 Cost Project cost Cr. 1520 200 13 % Increase

EMP cost Cr. 71.7 8 Additional Cost earmarked for

Grinding unit EMP

2.8 Cement Manufacturing Process

Cement manufacturing process: Cement manufacturing / grinding involves principally of grinding and blending of clinker with a definite proportion of Gypsum along with fly ash to produce finished product PPC. Few additives may be added during the grinding process to improve the performance of cement. The unit broadly comprises of the following sections. 1. Cement Mill section 2. Packing section 3. Dispatch section

A cement grinding plant for grinding 2 MTPA will be provided along with facilities for unloading, storage, handling for raw materials. The project provides for installation of cement silos and Packing plant for packing of cement in bags. Mechanised loading of facilities shall be provided to for loading operation. Electronic packer machines will ensure better weight compliance also.

Process selection: The process selected for the grinding system is the state of the art modern Mill Technology. This technology is suitable for the production of cement using flyash etc.

Plant operation and maintenance. The entire plant will be operated from a central control room (CCR) by operators, who will be assisted by specialists in plant maintenance. The plant will be highly automated and use state-of-the-art

VIMTA Labs Limited, Hyderabad 11

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

systems to achieve world class economies in terms of fuel and power consumption and manpower productivity. On-line condition monitoring systems such as vibration sensors, bearing temperatures etc. shall be provided to keep track on the health condition of the major equipment and auxiliaries. Continuous particulate matter monitoring system are installed in the stacks and the readings are monitored by the CCR operators. Manufacturing process flow diagram is given below.

3.0 IMPACT ON AIR ENVIRONMENT

Air quality modelling exercise was carried out to determine the pollution loads considering the emissions from the various sources such as clinker unit, CPP, coal crusher and mining activities which were approved in earlier EC and also considering 2.0 MTPA grinding unit which is proposed under EC amendment. Environmental clearance granted for clinkerisation unit for emission limit of 50 mg/Nm3. As per new emission norms for cement industry, ACC have now decided to design all our ESP and bag filter of clinkering unit to the emission Standard of

VIMTA Labs Limited, Hyderabad 12

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

30 mg/Nm3. Also ACC will comply with the New Emission Standard for cement industry for SO2 & NOx of 1000mg/Nm3 and 600 mg/Nm3 respectively.

3.1 Air Dispersion Modelling Study 3.1.1 Details of Mathematical Modelling

For prediction of maximum Ground Level Concentrations (GLC’s), air dispersion modelling software (AERMOD version 9.4.0) point and area sources options were used. AERMOD is steady state advanced Gaussian plume model that simulates air quality and deposition fields upto 50 km radius. AERMOD is approved by USEPA and is widely used software. It is an advanced version of Industrial Source Complex (ISCST3) model, utilizes similar input and output structure to ISCST3 sharing many of the same features, as well as offering additional features. The model is applicable to rural and urban areas, flat and complex terrain, surface and elevated releases and multiple sources including point, area, flare, line and volume sources.

Dispersion modelling using AERMOD requires hourly meteorological data. Site specific data is used for executing modelling studies. The site specific meteorological data is processed using AERMET processor.

3.1.2 Model set-up

The model set-up details are presented in Table-7. The predictions of point/stacks (clinker unit, CPP, coal crusher, and proposed grinding unit) and area sources (mining activities) incremental concentrations of particulate matter (PM) pollutant due to emission loads of existing and proposed project installations are estimated based on site specific meteorological conditions. The details of emissions expected from various stacks (point sources) in various units and from mines area sources considered for modeling are given in Annexure-III.

TABLE-7

MODEL SET-UP

Sr. No. Parameter Details 1 Model AERMOD (Version 9.4) 2 Model Type Steady state Gaussian Plume Air Dispersion

model 3 Topography Rural, Flat 4 Averaging Time 24 hours 5 Source Type Point Source 6 Boundary Limits 10 km radius from project site 7 Co-ordinate System Uniform Cartesian Grid 8 Receptor Height Ground level 9 Anemometer 10 m 10 Surface meteorological data Site Specific data processed by AERMET 11 Upper air Data Upper air Estimator using AERMET processor

3.1.3 Meteorological Data

VIMTA Labs Limited, Hyderabad 13

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

Hourly meteorological data have been recorded at site for post-monsoon season of 2016. The site specific meteorological data was converted to the mean hourly meteorological data as specified by CPCB and the same has been used in the current AERMOD modelling.

3.1.4 Scenarios Considered for Model Predictions

Model predictions were carried out for the following scenarios (Table-8) for determination of Particulate Matter (PM) ground level concentrations:

TABLE-8 SCENARIOS CONSIDERED

Sr. No. Units Considered for modeling PM Emission Limits

Scenario -1 (Based on EC Granted

Cumulative (CPP 85 MW + Coal crusher + Mine + Clinker Plant 2.7 MTPA)

With 50 mg/Nm3

Scenario -2 (Considering new Emission Limits)

Cumulative (CPP 85 MW + Coal crusher + Mine + Clinker Plant 2.7 MTPA)

With 30 mg/Nm3

Scenario -3 Considering new Emission Limits & Emissions from Grinding Unit)

Cumulative (CPP 85 MW + Coal crusher + Mine + Clinker Plant 2.7 MTPA) and considering 2.0 MTPA grinding unit for modeling

With 30 mg/Nm3

3.2 Emission Sources Input Data Considered For Modeling

Emission sources input data for modeling have been calculated for the comparison based stack emission limit values of 2007 (i.e. 50 mg/Nm3) and 2018 years (i.e. 30 mg/Nm3). Following Tables 9(A)-9(E) present details of emission source data considered for various modeling scenarios.

VIMTA Labs Limited, Hyderabad 14

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

TABLE-9(A)

MODEL INPUT EMISSION SOURCE DETAILS BASED ON 2007 STACK EMISSION LIMITS OF 50 mg/Nm3

(EC GRANTED FOR CPP OF 85MW, COAL WASHERY, CRUSHING UNIT, CLINKER PLANT OF 2.7 MTPA)

Plant Stack

attached to

Height, m

Diameter, m

Velocity, m/s

Temperature (°C)

Volumetric Flow

(Nm³/s)

PM Emission

Limits (mg/Nm3)

PM Emission

Rate (g/s)

CPP 85 MW

Stack attached to CPP Control System

105 2 20 140 45.3 50 2.27

Coal processing (crushing)

unit with coal washery

Plant

Crushing Unit 20 1.5 10 40 16.8 50 0.84

Clinker Plant of 2.7 MTPA

Kiln/Raw Mill 110 6.2 15 150 318.87 50 15.94

Coal mill 70 3 15 75 87 50 4.35

Clinker cooler 50 4 15 240 109.44 50 5.47

TABLE-(B) MODEL INPUT EMISSION SOURCE DETAILS

(EC GRANTED FOR LIMESTONE MINE OF 9.495 MTPA CAPACITY)

ML Area, Ha

Proposed Capacity,

MTPA

Proposed Capacity,

TPD

Emission Factor for Mine (include

of all mine activities)

kg/ton

Emissions, kg/Day

Emissions, g/s

Emissions, g/s-m2

1520.22 4.05 11095.89 1 11095.89 128.4247 0.00000845

TABLE-(C) MODEL INPUT EMISSION SOURCE DETAILS (EC AMENDMENT REQUESTED)

BASED ON CURRENT STACK EMISSION LIMITS OF 30 mg/Nm3 FOR CEMENT PLANT

Plant Stack

attached to

Height, m

Diameter, m

Velocity, m/s

Temperature (°C)

Volumetric Flow

(Nm³/s)

PM Emission

Limits (mg/Nm3)

PM Emission

Rate (g/s)

CPP 85 MW

Stack attached to CPP Control System

105.00 2.00 20.00 140.00 45.30 30.00 1.36

Coal processing

Crushing Unit 20.00 1.50 10.00 40.00 16.80 30.00 0.50

VIMTA Labs Limited, Hyderabad 15

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

Plant Stack

attached to

Height, m

Diameter, m

Velocity, m/s

Temperature (°C)

Volumetric Flow

(Nm³/s)

PM Emission

Limits (mg/Nm3)

PM Emission

Rate (g/s)

(crushing) unit with

coal washery

plant Clinker Plant of

2.7 MTPA

Kiln/Raw Mill 110.00 6.20 15.00 150.00 318.87 30.00 9.57

Coal mill 70.00 3.00 15.00 75.00 87.00 30.00 2.61

Clinker cooler 50.00 4.00 15.00 240.00 109.44 30.00 3.28

TABLE-(D)

EMISSION SOURCE DETAILS OF GRINDING UNIT FOR MODELING (EC AMENDMENT REQUESTED FOR ADDITION OF GRINDING UNIT )

Plant Stack attached

to Height,

m Dia

meter, m

Velocity, m/s

Tempe rature (°C)

Volumetric Flow

(Nm³/s)

PM Emission

Limits (mg/Nm3)

PM Emission

Rate (g/s)

Grinding unit of

2.0 MTPA

Stack attached to Cement Mill Bag House

54.00 1.70 24.00 100.00 48.60 30.00 1.46

Stack-1 attached to Paking house

37.00 1.00 10.00 60.00 8.30 30.00 0.25

Stack-2 attached to Paking house

37.00 1.00 10.00 60.00 8.30 30.00 0.25

Stack-3 attached to Paking house

37.00 1.00 10.00 60.00 8.30 30.00 0.25

Stack-4 attached to Paking house

37.00 1.00 10.00 60.00 8.30 30.00 0.25

TABLE-(E)

COMPARISON BETWEEN SOURCES AND EMISSIONS DETAILS

Plant and Capacity

Considered

Activity Earlier modelling input of PM emission rates (based on 50

mg/Nm3), g/s

Proposed modelling input of PM emission rates (based on 30

mg/Nm3), g/s

Cumulative (CPP + Coal crusher)

Activities (CPP Stack + Crusher)

3.1 1.9

Cumulative (Mine + Clinker Plant 2.7 MTPA)

Activities (Mining + Clinker Unit)

154.2 143.9

Cumulative (CPP 85 MW + Coal crusher + Mine + Clinker Plant 2.7 MTPA+ "Grinding Unit 2.0 MTPA")

Activities (CPP Stack + Crusher + mining + Clinker Unit + Grinding Unit Stacks)

157.3#

148.5

# Proposed grinding Unit emissions are not included

VIMTA Labs Limited, Hyderabad 16

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

Comparison of results for various scenarios are presented in Table-10, and model output isopleths of the same are shown in Figure–3 to Figure-5.

TABLE-10 COMPARISON BETWEEN CUMULATIVE MODELLING INCREMENTAL AND

RESULTANT CONCENTRATIONS

Scenario-1 : As Per Approved EC with Old Emission Norm for PM i.e. 50 mg/Nm3

Pollutants Distance/Direction

Baseline Concentratio

n (µg/m3) (A)

Incremental Ground Level Concentrations (µg/m3)

Resultant Concentration, (A+D),

(µg/m3)

NAAQ Limits,

(µg/m3)

Due to CPP and Coal

Crusher (B)

Due to Clinker

Plant and Mine (C)

Total (D=B+C)

PM 2.3 35.4 2.2 1.9 4.1 39.5 100

Scenario-2: As Per New Emission Norm for PM i.e. 30 mg/Nm3

Pollutants Distance/Dir

ection Baseline

Concentration (µg/m3) (A)

Incremental Ground Level Concentrations (µg/m3)

Resultant Concentration, (A+D), (µg/m3)

NAAQ Limits,

(µg/m3) Due to CPP and Coal

Crusher (B)

Due to Clinker

Plant and Mine (C)

Total (D=B+C)

PM 2.3 35.4 0.34 1.29 1.63 37.03 100

Scenario-3: As Per New Emission Norm for PM i.e. 30 mg/Nm3 and Including Proposed Grinding Unit of 2.0 MTPA

Pollutants Distance/ Direction

Baseline Concentratio

n (µg/m3) (A)

Incremental Ground Level Concentrations (µg/m3)

Resultant Concentration,

(A+D), (µg/m3)

NAAQ Limits,

(µg/m3) Due to

CPP and Coal

Crusher (B)

Due to Clinker

Plant and Mine (C)

Due to Proposed Grinding

Unit of 2.0 MTPA (GU)

Total (D=B+C+GU)

PM 2.3 35.4 2.7 2.7 37.9 100

Note: ACC will comply with the New Emission Standard for cement industry for SO2 & NOx of 1000mg/nm3 and 600 mg/nm3 respectively

From the above results, it can be observed that incremental and resultant concentrations of PM reveals a significant decrease in the ambient PM10 levels due to implementation of emission limit of 30 mg/Nm3.

It is to be noted that even after inclusion of proposed grinding unit of 2.0 MTPA, the maximum Ground Level concentration (GLC) were found to be 2.7 µg/m3 and the resultant GLC was found to be 37.9 µg/m3, which is well below the CPCB ambient air quality limit of 100 µg/m3 for PM10.

VIMTA Labs Limited, Hyderabad 17

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

FIGURE-3

PARTICULATE MATTER MAXIMUM GLC’S SCEANRIO -1 WITH 30 mg/NM3 – CLINKER PLANT & LIMESTONE MINE

VIMTA Labs Limited, Hyderabad 18

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

FIGURE-4

PARTICULATE MATTER MAXIMUM GLC’S SCEANRIO -2 WITH 30 mg/NM3 – CPP & COAL CRUSHER

VIMTA Labs Limited, Hyderabad 19

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

FIGURE-5 PARTICULATE MATTER MAXIMUM GLC’S

SCEANRIO -3 WITH 30 mg/NM3 – CLINKERISATION PLANT, LIMESTONE MINE CPP,COAL CRUSHER & PROPOSED GRINDING UNIT

VIMTA Labs Limited, Hyderabad 20

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

3.5 Conclusions

• No additional land is required for the setting up of 2.0 MTPA grinding unit. • Utilization of clinker in same unit will result in reduction of 1.24 MTPA clinker

transportation. • Additional power requirement of 10 MW will be met from Kymore Captive

Power Plant. • The additional water requirement of 35 m3/day will be met from the existing

sump of operating mine and water reservoir created at worked out pit of Bamangon mine. No waste water will be generated.

• Significant decrease in the ambient PM10 levels due to implementation of emission limit of 30 mg/Nm3.

• Marginal increase in ambient PM10 levels were expected by additional of 2.0 MTPA grinding unit.

It is to be noted that Environmental Clearance (EC) was granted for clinkerisation unit based on emission limit of 50 mg/Nm3. It is evident that with implementation new emission standard of 30 mg/Nm3, there is a reduction in ambient air quality levels. From the modeling results, after inclusion of proposed 2.0 MTPA grinding unit, the predicted particulate matter GLC’s were found to be slightly higher when compared with the earlier pollution loads of considered for issue Environmental Clearance. Hence, there is no significant impact on the AAQ levels due to the proposed 2.0 MTPA grinding unit.

VIMTA Labs Limited, Hyderabad 21

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

ANNEXURE-I COPY OF THE EC LETTER

VIMTA Labs Limited, Hyderabad 22

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

VIMTA Labs Limited, Hyderabad 23

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

VIMTA Labs Limited, Hyderabad 24

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

VIMTA Labs Limited, Hyderabad 25

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

VIMTA Labs Limited, Hyderabad 26

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

VIMTA Labs Limited, Hyderabad 27

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

VIMTA Labs Limited, Hyderabad 28

ACC Note on Environmental Impacts for Amendment in the Environmental Clearance for the Proposed Ametha Project at Ametha, Tehsil Vijayaraghavagarh, Katni District, Madhya Pradesh

ANNEXURE-II

PROJECT IMPLEMENTATION SCHEDULE .

VIMTA Labs Limited, Hyderabad 29