AMIT Transition to RMS
AMIT is closed, Steering has Sunset Closing documents and final records will be
filed in Project No. 41172 Development Oversight opened for remaining
functionality, including 3rd Party Ongoing work adopted by AMWG AMIT list serve to be closed
3
Project 41171 - Repository
Official Record for:1)Interim Project2)Web Portal Project3)Settlement Project4)HAN Project5)Retail Project6)DR Project7)Other Documents – Reports, comments, etc.
4
AMWG Objectives
Identify Service Level Agreements and needed reports from SMT concerning SMT performance, metrics, and statistics as necessary
Receive and review reports concerning performance, metrics, and statistics regarding the SMT core services
Report SMT performance, metrics, and statistics to RMS
Maintain SMT issues log and distribute to RMS and Staff as needed
5
AMWG Objectives
Identify, address and/or propose solutions for SMT operational and performance issues
Recommend changes to SMT and/or updates to SMT FAQs through the SMT change control process
Maintain the Texas Advanced Metering Guide Help increase market and customer awareness and
understanding of and promote usage of SMT through RMS interactions; and
Help increase customer awareness and understanding of the benefits of advanced meters through RMS interactions.
6
Outstanding Items
HAN Task ForceSupported by the Joint TDUsReports to RMS, AMWG, and SMT DOIn place to ensure:
HAN Support Model in place; Call Center scripts complete; HAN User Guide complete and available on SMT; no substantive market issues relating to HAN support
remaining; smooth operation of HAN issues for the Joint TDU Low
Income distribution of HAN devices
7
Outstanding Items
Texas Advanced Metering Guide Task Force completes the initial version of the Guide Ongoing activities are folded into the AMWG
Guide is owned by RMS* the Guide is designed to be used as reference material only, and will be managed, maintained, and updated solely by RMS with changes to the Guide not requiring ERCOT Board approval
8
SMT Development Project
Project No. 41172, Staff Monitoring of Final Releases for the Joint TDU Web Portal
Primary responsibility will be to bring the remaining SMT releases to completion. Specifically this group will: Review SMT issues as identified through RMS by
AMWG Consider SMT Change Requests created by AMWG Make future SMT design decisions Discuss design/implementation issues Discuss any HAN support issues as needed
9
Future Functionality
Rebranding of Smart Meter Texas Usability review of existing website On Demand Read (Release 4.2) Third Party Access (Release 4.3) Security Enhancements (Release 4.4) Mobile Application (Release 4.5) Content Management, FAQ, News Flash and Twitter
*See Functionality Tracker for full list and explanation10
Third Party Update
First Meeting of SMT DO held End to End Review
Steps 1-4 Completed Steps 5-7 Not required Steps 6-9B Completed Step 9 C – Finalize Content Based on Design
Decisions and Feedback – In Process
11
Next Steps
Review & Finalize Screen content, emails, etc Development, Testing, UAT Focus Groups – Functionality Demo on
Usability Review & Assess Focus Group Feedback for
Incorporation into Site & Usability Refinement Process Launch – Q4 2013
12
Contact Information
Christine WrightInfrastructure & Reliability Division512.936.7376www.puc.texas.govChristine.Wright@puc.texas.gov