Inventory ManagementInventory Management12
12 – 1Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
For For Operations Management, 9eOperations Management, 9e by by Krajewski/Ritzman/Malhotra Krajewski/Ritzman/Malhotra © 2010 Pearson Education© 2010 Pearson Education
PowerPoint Slides PowerPoint Slides by Jeff Heylby Jeff Heyl
Inventory ManagementInventory Management
Inventories are important to all types of organizationsorganizations They have to be counted, paid for, used in
operations, used to satisfy customers, and managed
Too much inventory reduces profitability
Too little inventory damages customer confidence
12 – 2Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
confidence
Inventory trade-offs
28-Jun-10
2
ABC AnalysisABC Analysis
Stock-keeping units (SKU)
Identify the classes so management can control inventory levels
A Pareto chart
Cycle counting
12 – 3Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
e
100 —
90 —
80
Class C
Class A
Class B
ABC AnalysisABC Analysis
cen
tag
e o
f d
oll
ar v
alu
e 80 —
70 —
60 —
50 —
40 —
30 —
12 – 4Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
10 20 30 40 50 60 70 80 90 100
Percentage of SKUs
Per
c
20 —
10 —
0 —
Figure 12.1 – Typical Chart Using ABC Analysis
28-Jun-10
3
Economic Order QuantityEconomic Order Quantity
The lot size, Q, that minimizes total annual inventory holding and ordering costs
Fi ti Five assumptions1. Demand rate is constant and known with certainty
2. No constraints are placed on the size of each lot
3. The only two relevant costs are the inventory holding cost and the fixed cost per lot for ordering or setup
4. Decisions for one item can be made independently of decisions for other items
12 – 5Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
decisions for other items
5. The lead time is constant and known with certainty
Economic Order QuantityEconomic Order Quantity
Don’t use the EOQ Make-to-order strategy
Order size is constrained
Modify the EOQ Quantity discounts
Replenishment not instantaneous
Use the EOQ
12 – 6Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Use the EOQ Make-to-stock
Carrying and setup costs are known and relatively stable
28-Jun-10
4
Calculating EOQCalculating EOQ
Inventory depletion (demand rate)
Receive order
s) Qh
and
inve
nto
ry (
un
its Q
Averagecycleinventory
Q
2
12 – 7Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
1 cycle
On
-
TimeFigure 12.2 – Cycle-Inventory Levels
Calculating EOQCalculating EOQ
Annual holding cost
Annual holding cost = (Average cycle inventory) (Unit holding cost) (Unit holding cost)
Annual ordering cost
Annual ordering cost = (Number of orders/Year) (Ordering or setup costs)
Total annual cycle-inventory cost
12 – 8Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
y y
Total costs = Annual holding cost + Annual ordering or setup cost
28-Jun-10
5
Calculating EOQCalculating EOQ
An
nu
al c
ost
(d
olla
rs)
Holding cost
Total cost
12 – 9Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Lot Size (Q)
Ordering cost
Figure 12.3 – Graphs of Annual Holding, Ordering, and Total Costs
Calculating EOQCalculating EOQ
Total annual cycle-inventory cost
Q
whereC = total annual cycle-inventory costQ = lot sizeH = holding cost per unit per year
C = (H) + (S)Q
2DQ
12 – 10Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
H holding cost per unit per yearD = annual demandS = ordering or setup costs per lot
28-Jun-10
6
The Cost of a LotThe Cost of a Lot--Sizing PolicySizing Policy
EXAMPLE 12.1
A museum of natural history opened a gift shop which operates 52 weeks per year.operates 52 weeks per year.
Managing inventories has become a problem.
Top-selling SKU is a bird feeder.
Sales are 18 units per week, the supplier charges $60 per unit.
Ordering cost is $45.
Annual holding cost is 25 percent of a feeder’s value.
12 – 11Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
g p
Management chose a 390-unit lot size.
What is the annual cycle-inventory cost of the current policy of using a 390-unit lot size?
Would a lot size of 468 be better?
The Cost of a LotThe Cost of a Lot--Sizing PolicySizing Policy
SOLUTION
We begin by computing the annual demand and holding cost as
D (18 it / k)(52 k / ) 936 itD =
H =
C = (H) + (S)Q
2DQ = ($15) + ($45)
= $2,925 + $108 = $3,033
3902
936390
The total annual cycle-inventory cost for the current policy is
(18 units/week)(52 weeks/year) = 936 units
0.25($60/unit) = $15
12 – 12Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
The total annual cycle-inventory cost for the alternative lot size is
C = ($15) + ($45) = $3,510 + $90 = $3,6004682
936468
28-Jun-10
7
The Cost of a LotThe Cost of a Lot--Sizing PolicySizing Policy
3000
Currentcost
Figure 12.4 – Total Annual Cycle-Inventory Cost Function for the Bird Feeder
3000 –
2000 –
1000 –An
nu
al c
ost
(d
olla
rs) Total
cost = (H) + (S)Q
2DQ
Holding cost = (H)Q
2
12 – 13Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
1000
0 – | | | | | | | |
50 100 150 200 250 300 350 400
Lot Size (Q)
A
CurrentQ
Lowestcost
Best Q(EOQ)
Ordering cost = (S)DQ
Calculating EOQCalculating EOQ
The EOQ formula:
EOQ =2DS
H
Time between orders
12 – 14Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
TBOEOQ = (12 months/year)EOQ
D
28-Jun-10
8
Finding the EOQ, Total Cost, TBOFinding the EOQ, Total Cost, TBO
EXAMPLE 12.2
For the bird feeders in Example 12.1, calculate the EOQ and its total annual cycle-inventory cost. How frequently will orders betotal annual cycle inventory cost. How frequently will orders be placed if the EOQ is used?
SOLUTION
Using the formulas for EOQ and annual cost, we get
EOQ = =2DS
= 74 94 or 75 units2(936)(45)
12 – 15Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
EOQ = =H
= 74.94 or 75 units15
Finding the EOQ, Total Cost, TBOFinding the EOQ, Total Cost, TBO
Figure 12.5 shows that the total annual cost is much less than the $3,033 cost of the current policy of placing 390-unit orders.
12 – 16Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Figure 12.5 – Total Annual Cycle-Inventory Costs Based on EOQ Using Tutor 12.2
28-Jun-10
9
Finding the EOQ, Total Cost, TBOFinding the EOQ, Total Cost, TBO
When the EOQ is used, the TBO can be expressed in various ways for the same time period.
EOQTBOEOQ =
EOQD
TBOEOQ = (12 months/year)EOQ
D
TBO = (52 weeks/year)EOQ
= = 0.080 year75936
= (12) = 0.96 month75936
= (52) = 4 17 weeks75
12 – 17Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
TBOEOQ = (52 weeks/year)D
TBOEOQ = (365 days/year)EOQ
D
= (52) = 4.17 weeks936
= (365) = 29.25 days75936
Application 12.1Application 12.1
Suppose that you are reviewing the inventory policies on an $80 item stocked at a hardware store. The current policy is to replenish inventory by ordering in lots of 360 units. Additional i f ti iinformation is:
D = 60 units per week, or 3,120 units per year
S = $30 per order
H = 25% of selling price, or $20 per unit per year
What is the EOQ?
12 – 18Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
EOQ = =2DS
H= 97 units
2(3,120)(30)
20
SOLUTION
28-Jun-10
10
Application 12.1Application 12.1
What is the total annual cost of the current policy (Q = 360), and how does it compare with the cost with using the EOQ?
Current Policy EOQ Policy
Q = 360 units Q = 97 units
C = 3,600 + 260
C = $3,860
C = (360/2)(20) + (3,120/360)(30)
C = 970 + 965
C = $1,935
C = (97/2)(20) + (3,120/97)(30)
12 – 19Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Application 12.1Application 12.1
What is the time between orders (TBO) for the current policy and the EOQ policy, expressed in weeks?
TBO360 =
TBOEOQ =
(52 weeks per year) = 6 weeks360
3,120
(52 weeks per year) = 1.6 weeks97
3 120
SOLUTION
12 – 20Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
EOQ ( p y )3,120
28-Jun-10
11
Managerial InsightsManagerial Insights
TABLE 12.1 | SENSITIVITY ANALYSIS OF THE EOQ
Parameter EOQ Parameter Change
EOQ Change
Comments
Demand ↑ ↑ Increase in lot size is in proportion to the square root of D.
Order/Setup Costs ↓ ↓
Weeks of supply decreases and inventory turnover increases because the lot size decreases.
H ldi L l t j tifi d h h ldi
2DSH
2DSH
12 – 21Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Holding Costs ↓ ↑ Larger lots are justified when holding
costs decrease.2DS
H
Inventory Control SystemsInventory Control Systems
Two important questions: How much?
When?
Nature of demand Independent demand
Dependent demand
12 – 22Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
28-Jun-10
12
Inventory Control SystemsInventory Control Systems
Continuous review (Q) systemReorder point system (ROP) and fixed order
quantity system
For independent demand items
Tracks inventory position (IP)
Includes scheduled receipts (SR), on-hand inventory (OH), and back orders (BO)
12 – 23Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Inventory position = On-hand inventory + Scheduled receipts – Backorders
IP = OH + SR – BO
Selecting the Reorder PointSelecting the Reorder Point
IP IPIPOrderreceived
Orderreceived
Orderreceived
Orderreceived
On
-han
d i
nve
nto
ry
Orderplaced
Orderplaced
Orderplaced
R
Q QQ
OH OHOH
12 – 24Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Time
TBO TBO
L L
TBO
L
placed placedplaced
Figure 12.6 – Q System When Demand and Lead Time Are Constant and Certain
28-Jun-10
13
Application 12.2Application 12.2
The on-hand inventory is only 10 units, and the reorder point R is 100. There are no backorders and one open order for 200 units Should a new order be placed?200 units. Should a new order be placed?
IP = OH + SR – BO = 10 + 200 – 0 = 210
R = 100
SOLUTION
12 – 25Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Decision: Place no new order
Placing a New OrderPlacing a New Order
EXAMPLE 12.3
Demand for chicken soup at a supermarket is always 25 cases a day and the lead time is always 4 days. The shelves were justday and the lead time is always 4 days. The shelves were just restocked with chicken soup, leaving an on-hand inventory of only 10 cases. No backorders currently exist, but there is one open order in the pipeline for 200 cases. What is the inventory position? Should a new order be placed?
SOLUTION
R = Total demand during lead time = (25)(4) = 100 cases
12 – 26Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
R = Total demand during lead time = (25)(4) = 100 cases
= 10 + 200 – 0 = 210 cases
IP = OH + SR – BO
28-Jun-10
14
Continuous Review SystemsContinuous Review Systems
Selecting the reorder point with variable demand and constant lead time
Reorder point = Average demand during lead time + Safety stock
= dL + safety stock
whered d d k ( d th )
12 – 27Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
d = average demand per week (or day or months)L = constant lead time in weeks (or days or months)
Continuous Review SystemsContinuous Review Systems
Orderreceived
Orderreceived
IP IP
O d
Orderreceived
IP
On
-han
d i
nve
nto
ry
R
Q
Orderplaced
Orderplaced
Q
Orderplaced
Q
Orderreceived
12 – 28Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Time
TBO1 TBO2 TBO3
L1 L2 L3
0
Figure 12.7 – Q System When Demand Is Uncertain
28-Jun-10
15
Reorder PointReorder Point
1. Choose an appropriate service-level policy Select service level or cycle service level
Protection interval
2. Determine the demand during lead time probability distribution
3. Determine the safety stock and reorder
12 – 29Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
point levels
Demand During Lead TimeDemand During Lead Time
Specify mean and standard deviation
Standard deviation of demand during lead time
σdLT = σd2L = σd L
Safety stock and reorder point
Safety stock = zσdLT
where
12 – 30Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
wherez = number of standard deviations needed to achieve the
cycle-service levelσdLT = stand deviation of demand during lead time
Reorder point = R = dL + safety stock
28-Jun-10
16
σt = 15
+ +σt = 15
=σt = 15
Demand During Lead TimeDemand During Lead Time
+75
Demand for week 1
σt = 25.98
+75
Demand for week 2
=75
Demand for week 3
12 – 31Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
225Demand for 3-week lead time
Figure 12.8 – Development of Demand Distribution for the Lead Time
Demand During Lead TimeDemand During Lead Time
Cycle-service level = 85%
Average demand
during lead time
Probability of stockout(1.0 – 0.85 = 0.15)
12 – 32Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
lead time
zσdLT
R
Figure 12.9 – Finding Safety Stock with a Normal Probability Distribution for an 85 Percent Cycle-Service Level
28-Jun-10
17
Reorder Point for Variable DemandReorder Point for Variable Demand
EXAMPLE 12.4
Let us return to the bird feeder in Example 12.2. The EOQ is 75 units. Suppose that the average demand is 18 units per week with a standard deviation of 5 units. The lead time is constant at two weeks. Determine the safety stock and reorder point if management wants a 90 percent cycle-service level.
12 – 33Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Reorder Point for Variable DemandReorder Point for Variable Demand
SOLUTION
In this case, σd = 5, d = 18 units, and L = 2 weeks, so dσdLT = σd L = 5 2 = 7.07. Consult the body of the table in the Normal Distribution appendix for 0.9000, which corresponds to a 90 percent cycle-service level. The closest number is 0.8997, which corresponds to 1.2 in the row heading and 0.08 in the column heading. Adding these values gives a z value of 1.28. With this information, we calculate the safety stock and reorder point as follows:
12 – 34Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Safety stock = zσdLT = 1.28(7.07) = 9.05 or 9 units
2(18) + 9 = 45 unitsReorder point = dL + Safety stock =
28-Jun-10
18
Application 12.3Application 12.3
Suppose that the demand during lead time is normally distributed with an average of 85 and σdLT = 40. Find the safety stock, and reorder point R, for a 95 percent cycle-service level.
SOLUTION
Safety stock = zσdLT =
Find the safety stock and reorder point R for an 85 percent
R = Average demand during lead time + Safety stock
R = 85 + 66 = 151 units
1.645(40) = 65.8 or 66 units
12 – 35Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Find the safety stock, and reorder point R, for an 85 percent cycle-service level.
Safety stock = zσdLT = 1.04(40) = 41.6 or 42 units
R = Average demand during lead time + Safety stock
R = 85 + 42 = 127 units
Reorder Point for Variable Demand Reorder Point for Variable Demand and Lead Timeand Lead Time
Often the case that both are variable
The equations are more complicated
Safety stock = zσdLT
whered A kl ( d il thl ) d d
R = (Average weekly demand Average lead time) + Safety stock
= dL + Safety stock
12 – 36Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
d = Average weekly (or daily or monthly) demandL = Average lead timeσd = Standard deviation of weekly (or daily or monthly) demandσLT = Standard deviation of the lead timeσdLT = Lσd
2 + d2σLT2
28-Jun-10
19
Reorder PointReorder Point
EXAMPLE 12.5
The Office Supply Shop estimates that the average demand for e O ce Supp y S op est ates t at t e a e age de a d oa popular ball-point pen is 12,000 pens per week with a standard deviation of 3,000 pens. The current inventory policy calls for replenishment orders of 156,000 pens. The average lead time from the distributor is 5 weeks, with a standard deviation of 2 weeks. If management wants a 95 percent cycle-service level, what should the reorder point be?
12 – 37Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Reorder PointReorder Point
SOLUTION
We have d = 12,000 pens, σd = 3,000 pens, L = 5 weeks, and σLT = 2 weeks
From the Normal Distribution appendix for 0.9500, the appropriate z value = 1.65. We calculate the safety stock and reorder point as follows:
σdLT = Lσd2 + d2σLT
2 =
and σLT 2 weeks
(5)(3,000)2 + (12,000)2(2)2
= 24,919.87 pens
12 – 38Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Safety stock = zσdLT =
Reorder point = dL + Safety stock =
(1.65)(24,919.87) = 41,117.79 or 41,118 pens
(12,000)(5) + 41.118 = 101,118 pens
28-Jun-10
20
Application 12.4Application 12.4
Grey Wolf lodge is a popular 500-room hotel in the North Woods. Managers need to keep close tabs on all of the room service items including a special pint-scented bar soap Theservice items, including a special pint-scented bar soap. The daily demand for the soap is 275 bars, with a standard deviation of 30 bars. Ordering cost is $10 and the inventory holding cost is $0.30/bar/year. The lead time from the supplier is 5 days, with a standard deviation of 1 day. The lodge is open 365 days a year.
What should the reorder point be for the bar of soap if management wants to have a 99 percent cycle-service?
12 – 39Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Application 12.4Application 12.4
SOLUTION
d = 275 bars
L = 5 days
σd = 30 bars
σLT = 1 day
283.06 barsσdLT = Lσd2 + d2σLT
2 =
From the Normal Distribution appendix for 0.9900, z = 2.33.
12 – 40Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
We calculate the safety stock and reorder point as follows;
Safety stock = zσdLT =
Reorder point + safety stock = dL + safety stock
(2.33)(283.06) = 659.53 or 660 bars
= (275)(5) + 660 = 2,035 bars
28-Jun-10
21
Continuous Review SystemsContinuous Review Systems
Two-Bin system Visual system
An empty first bin signals the need to place an order
Calculating total systems costs
Total cost = Annual cycle inventory holding cost + Annual ordering cost + Annual safety stock holding cost
12 – 41Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
C = (H) + (S) + (H) (Safety stock)Q
2DQ
Application 12.5Application 12.5
The Discount Appliance Store uses a continuous review system (Q system). One of the company’s items has the following characteristics:
Demand = 10 units/wk (assume 52 weeks per year)
Ordering and setup cost (S) = $45/order
Holding cost (H) = $12/unit/year
Lead time (L) = 3 weeks (constant)
Standard deviation in weekly demand = 8 units
Cycle-service level = 70%
12 – 42Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Cycle service level 70%
28-Jun-10
22
Application 12.5Application 12.5
SOLUTION
What is the EOQ for this item?
D = 10/wk 52 wks/yr = 520 units
EOQ = =2DS
H= 62 units
2(520)(45)12
What is the desired safety stock?
12 – 43Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
σdLT = σd L = 8 3 = 14 units
Safety stock = zσdLT = 0.525(14) = 8 units
Application 12.5Application 12.5
What is the desired reorder point R?
R = Average demand during lead time + Safety stockR = Average demand during lead time + Safety stock
R =
What is the total annual cost?
3(10) + 8 = 38 units
($12) + ($45) + 8($12) $845 4262 520
C
12 – 44Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
($12) + ($45) + 8($12) = $845.422 62C =
28-Jun-10
23
Application 12.5Application 12.5
Suppose that the current policy is Q = 80 and R = 150. What will be the changes in average cycle inventory and safety stock if your EOQ and R values are implemented?
Reducing Q from 80 to 62
Cycle inventory reduction = 40 – 31 = 9 units
Safety stock reduction = 120 – 8 = 112 units
Reducing R from 150 to 38
12 – 45Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Periodic Review System (Periodic Review System (PP))
Fixed interval reorder system or periodic reorder system
Four of the original EOQ assumptions maintained No constraints are placed on lot size
Holding and ordering costs
Independent demand
Lead times are certain
Order is placed to bring the inventory position up
12 – 46Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Order is placed to bring the inventory position up to the target inventory level, T, when the predetermined time, P, has elapsed
28-Jun-10
24
Periodic Review System (Periodic Review System (PP))
T
Orderi d
Orderi d
Orderreceived
IP IPIPO
n-h
and
in
ven
tory
IP3
IP1
IP2
OrderplacedOrderplaced
Orderplaced
received received received
OH OHQ1
Q2
Q3
12 – 47Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
P PL L L
Protection interval
Time
Figure 12.10 – P System When Demand Is Uncertain
How Much to Order in a How Much to Order in a PP SystemSystem
EXAMPLE 12.6
A distribution center has a backorder for five 36-inch color TV sets. No inventory is currently on hand, and now is the time tosets. No inventory is currently on hand, and now is the time to review. How many should be reordered if T = 400 and no receipts are scheduled?
SOLUTION
IP = OH + SR – BO
= 0 + 0 – 5 = –5 sets
12 – 48Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
That is, 405 sets must be ordered to bring the inventory position up to T sets.
T – IP = 400 – (–5) = 405 sets
28-Jun-10
25
Application 12.6Application 12.6
The on-hand inventory is 10 units, and T is 400. There are no back orders, but one scheduled receipt of 200 units. Now is the time to review. How much should be reordered?
SOLUTION
IP = OH + SR – BO
= 10 + 200 – 0 = 210
T – IP = 400 – 210 = 190
12 – 49Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
The decision is to order 190 units
Periodic Review SystemPeriodic Review System
Selecting the time between reviews, choosing P and T
Selecting T when demand is variable and lead time is constant IP covers demand over a protection interval of
P + L
The average demand during the protection interval is d(P + L) or
12 – 50Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
T = d(P + L) + safety stock for protection interval
interval is d(P + L), or
Safety stock = zσP + L , where σP + L = LPd
28-Jun-10
26
Calculating Calculating PP and and TT
EXAMPLE 12.7
Again, let us return to the bird feeder example. Recall that demand for the bird feeder is normally distributed with a meandemand for the bird feeder is normally distributed with a mean of 18 units per week and a standard deviation in weekly demand of 5 units. The lead time is 2 weeks, and the business operates 52 weeks per year. The Q system developed in Example 12.4 called for an EOQ of 75 units and a safety stock of 9 units for a cycle-service level of 90 percent. What is the equivalent Psystem? Answers are to be rounded to the nearest integer.
12 – 51Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Calculating Calculating PP and and TT
SOLUTION
We first define D and then P. Here, P is the time between reviews, expressed in weeks because the data are expressed asreviews, expressed in weeks because the data are expressed as demand per week:
D = (18 units/week)(52 weeks/year) = 936 units
P = (52) =EOQ
D(52) = 4.2 or 4 weeks
75936
12 – 52Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
With d = 18 units per week, an alternative approach is to calculate P by dividing the EOQ by d to get 75/18 = 4.2 or 4 weeks. Either way, we would review the bird feeder inventory every 4 weeks.
28-Jun-10
27
Calculating Calculating PP and and TT
We now find the standard deviation of demand over the protection interval (P + L) = 6:
it12 2565
Before calculating T, we also need a z value. For a 90 percent cycle-service level z = 1.28. The safety stock becomes
Safety stock = zσP + L = 1.28(12.25) = 15.68 or 16 units
We now solve for T:
units12.2565 LPdLP
12 – 53Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
= (18 units/week)(6 weeks) + 16 units = 124 units
T = Average demand during the protection interval + Safety stock
= d(P + L) + safety stock
Periodic Review SystemPeriodic Review System
Use simulation when both demand and lead time are variable
S it bl t i l bi t Suitable to single-bin systems
Total costs for the P system are the sum of the same three cost elements as in the Q system
Order quantity and safety stock are calculated differently
12 – 54Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
C = (H) + (S) + HzσP + L
dP2
DdP
28-Jun-10
28
Application 12.7Application 12.7
Return to Discount Appliance Store (Application 12.4), but now use the P system for the item.
Previous informationPrevious information
Demand = 10 units/wk (assume 52 weeks per year) = 520
EOQ = 62 units (with reorder point system)
Lead time (L) = 3 weeks
Standard deviation in weekly demand = 8 units
z = 0.525 (for cycle-service level of 70%)
12 – 55Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Reorder interval P, if you make the average lot size using the Periodic Review System approximate the EOQ.
Application 12.7Application 12.7
SOLUTION
Reorder interval P, if you make the average lot size using the Periodic Review System approximate the EOQ.Periodic Review System approximate the EOQ.
P = (EOQ/D)(52) = (62/529)(52) = 6.2 or 6 weeks
Safety stock
Safety stock = LPd
units13 or 12.63680.525
12 – 56Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Target inventory
T = 10(6 + 3) + 13 = 103 units
T = d(P + L) + safety stock for protection interval
28-Jun-10
29
Application 12.7Application 12.7
Total cost
C = (H) + (S) + HzσP + L
dP2
DdP
= ($12) + ($45) + (13)($12) = $906.0010(6)
2520
10(6)
12 – 57Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Comparative AdvantagesComparative Advantages
Primary advantages of P systemsConvenient
Orders can be combined
Only need to know IP when review is made
Primary advantages of Q systemsReview frequency may be individualized
Fixed lot sizes can result in quantity discounts
12 – 58Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Fixed lot sizes can result in quantity discounts
Lower safety stocks
28-Jun-10
30
Optional replenishment systems Optimal review, min-max, or (s,S) system, like the P
system
Hybrid systemsHybrid systems
system
Reviews IP at fixed time intervals and places a variable-sized order to cover expected needs
Ensures that a reasonable large order is placed
Base-stock system Replenishment order is issued each time a withdrawal is
made
12 – 59Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
made
Order quantities vary to keep the inventory position at R
Minimizes cycle inventory, but increases ordering costs
Appropriate for expensive items
Solved Problem 1Solved Problem 1
Booker’s Book Bindery divides SKUs into three classes, according to their dollar usage. Calculate the usage values of the following SKUs and determine which is most likely to be
l ifi d l Aclassified as class A.
SKU Number Description Quantity Used per Year
Unit Value ($)
1 Boxes 500 3.00
2 Cardboard (square feet)
18,000 0.02
3 Cover stock 10,000 0.75
12 – 60Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
4 Glue (gallons) 75 40.00
5 Inside covers 20,000 0.05
6 Reinforcing tape (meters)
3,000 0.15
7 Signatures 150,000 0.45
28-Jun-10
31
Solved Problem 1Solved Problem 1
SOLUTION
The annual dollar usage for each item is determined by multiplying the annual usage quantity by the value per unit. Asmultiplying the annual usage quantity by the value per unit. As shown in Figure 12.11, the SKUs are then sorted by annual dollar usage, in declining order. Finally, A–B and B–C class lines are drawn roughly, according to the guidelines presented in the text. Here, class A includes only one SKU (signatures), which represents only 1/7, or 14 percent, of the SKUs but accounts for 83 percent of annual dollar usage. Class B includes the next two SKUs, which taken together represent 28 percent of the SKUs and account for 13 percent of annual dollar
12 – 61Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
usage. The final four SKUs, class C, represent over half the number of SKUs but only 4 percent of total annual dollar usage.
Solved Problem 1Solved Problem 1
SKU Number Description
Quantity Used per
Y
Unit Value ($)
Annual Dollar Usage ($)Number Year ($) Usage ($)
1 Boxes 500 3.00 = 1,500
2 Cardboard (square feet)
18,000 0.02 = 360
3 Cover stock 10,000 0.75 = 7,500
4 Glue (gallons) 75 40.00 = 3,000
5 Inside covers 20,000 0.05 = 1,000
6 Reinforcing tape ( )
3,000 0.15 = 450
12 – 62Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
(meters)
7 Signatures 150,000 0.45 = 67,500
Total 81,310
28-Jun-10
32
Solved Problem 1Solved Problem 1
llar
Va
lue
100 –
90 –
80 –
70 –
Class C
Class A
Class B
12 – 63Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Percentage of SKUs
Per
cen
tag
e o
f D
ol
60 –
50 –
40 –
30 –
20 –
10 –
0 –10 30 40 50 60 70 80 90 10020
Figure 12.11 – Annual Dollar Usage for Class A, B, and C SKUs Using Tutor 12.2
Solved Problem 2Solved Problem 2
Nelson’s Hardware Store stocks a 19.2 volt cordless drill that is a popular seller. Annual demand is 5,000 units, the ordering cost is $15, and the inventory holding cost is $4/unit/year.
a. What is the economic order quantity?
b. What is the total annual cost for this inventory item?
SOLUTION
a. The order quantity is
EOQ = =2DS
H2(5,000)($15)
$4
12 – 64Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
H $4
= 37,500 = 193.65 or 194 drills
b. The total annual cost is
C = (H) + (S) =Q
2DQ ($4) + ($15) = $774.60
1942
5,000194
28-Jun-10
33
Solved Problem 3Solved Problem 3
A regional distributor purchases discontinued appliances from various suppliers and then sells them on demand to retailers in the region. The distributor operates 5 days per week, 52 weeks
O l h it i f b i d bper year. Only when it is open for business can orders be received. Management wants to reevaluate its current inventory policy, which calls for order quantities of 440 counter-top mixers. The following data are estimated for the mixer:
Average daily demand (d) = 100 mixers
Standard deviation of daily demand (σd) = 30 mixers
Lead time (L) = 3 days
12 – 65Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Holding cost (H) = $9.40/unit/year
Ordering cost (S) = $35/order
Cycle-service level = 92 percent
The distributor uses a continuous review (Q) system
Solved Problem 3Solved Problem 3
a. What order quantity Q, and reorder point, R, should be used?
b What is the total annual cost of the system?b. What is the total annual cost of the system?
c. If on-hand inventory is 40 units, one open order for 440 mixers is pending, and no backorders exist, should a new order be placed?
12 – 66Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
28-Jun-10
34
Solved Problem 3Solved Problem 3
SOLUTION
a. Annual demand is
The order quantity is
D = (5 days/week)(52 weeks/year)(100 mixers/day)= 26,000 mixers/year
EOQ = =2DS
H2(26,000)($35)
$9.40
12 – 67Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
H $9.40
= 193,167 = 440.02 or 440 mixers
Solved Problem 3Solved Problem 3
The standard deviation of the demand during lead time distribution is
L 30 3 51 96
A 92 percent cycle-service level corresponds to z = 1.41
σdLT = σd L = 30 3 = 51.96
Safety stock = zσdLT = 1.41(51.96 mixers) = 73.26 or 73 mixers
100(3) = 300 mixersAverage demand during lead time = dL =
12 – 68Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Reorder point (R) = Average demand during lead time + Safety stock
= 300 mixers + 73 mixers = 373 mixers
With a continuous review system, Q = 440 and R = 373
28-Jun-10
35
Solved Problem 3Solved Problem 3
b. The total annual cost for the Q systems is
C = (H) + (S) + (H)(Safety stock)Q
2DQC = (H) + (S) + (H)(Safety stock)2 Q
C = ($9.40) + ($35) + ($9.40)(73) = $4,822.384402
26,000440
c. Inventory position = On-hand inventory + Scheduled receipts – Backorders
12 – 69Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
IP = OH + SR – BO = 40 + 440 – 0 = 480 mixers
Because IP (480) exceeds R (373), do not place a new order
Solved Problem 4Solved Problem 4
Suppose that a periodic review (P) system is used at the distributor in Solved Problem 3, but otherwise the data are the same.
a. Calculate the P (in workdays, rounded to the nearest day) that gives approximately the same number of orders per year as the EOQ.
b. What is the target inventory level, T? Compare the P system to the Q system in Solved Problem 3.
c. What is the total annual cost of the P system?
d. It is time to review the item. On-hand inventory is 40 mixers;
12 – 70Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
d. It is time to review the item. On hand inventory is 40 mixers; receipt of 440 mixers is scheduled, and no backorders exist. How much should be reordered?
28-Jun-10
36
Solved Problem 4Solved Problem 4
SOLUTION
a. The time between orders is
EOQ 440P = (260 days/year) =
EOQD
(260) = 4.4 or 4 days440
26,000
b. Figure 12.12 shows that T = 812 and safety stock = (1.41)(79.37) = 111.91 or about 112 mixers. The corresponding Q system for the counter-top mixer requires less safety stock.
12 – 71Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Figure 12.12 –OM Explorer Solver for Inventory Systems
Solved Problem 4Solved Problem 4
c. The total annual cost of the P system is
C = (H) + (S) + (H)(Safety stock)dP2
DdPC (H) (S) (H)(Safety stock)2 dP
C = ($9.40) + ($35) + ($9.40)(1.41)(79.37)100(4)
226,000100(4)
= $5,207.80
d. Inventory position is the amount on hand plus scheduled receipts minus backorders, or
IP OH + SR BO 40 + 440 0 480 i
12 – 72Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
IP = OH + SR – BO = 40 + 440 – 0 = 480 mixers
The order quantity is the target inventory level minus the inventory position, or
Q = T – IP =
An order for 332 mixers should be placed.
812 mixers – 480 mixers = 332 mixers
28-Jun-10
37
Solved Problem 5Solved Problem 5
Grey Wolf Lodge is a popular 500-room hotel in the North Woods. Managers need to keep close tabs on all room service items, including a special pine-scented bar soap. The daily d d f th i 275 b ith t d d d i ti f 30demand for the soap is 275 bars, with a standard deviation of 30 bars. Ordering cost is $10 and the inventory holding cost is $0.30/bar/year. The lead time from the supplier is 5 days, with a standard deviation of 1 day. The lodge is open 365 days a year.
a. What is the economic order quantity for the bar of soap?
b. What should the reorder point be for the bar of soap if management wants to have a 99 percent cycle-service level?
Wh t i th t t l l t f th b f i
12 – 73Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
c. What is the total annual cost for the bar of soap, assuming a Q system will be used?
Solved Problem 5Solved Problem 5
SOLUTION
a. We have D = (275)(365) = 100,375 bars of soap; S = $10; and H = $0.30. The EOQ for the bar of soap isH $0.30. The EOQ for the bar of soap is
EOQ = =2DS
H2(100,375)($10)
$0.30
= 6,691,666.7 = 2,586.83 or 2,587 bars
12 – 74Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
28-Jun-10
38
Solved Problem 5Solved Problem 5
b. We have d = 275 bars/day, σd = 30 bars, L = 5 days, and σLT = 1 day.
σdLT = Lσd2 + d2σLT
2 = (5)(30)2 + (275)2(1)2 = 283.06 bars
Consult the body of the Normal Distribution appendix for 0.9900. The closest value is 0.9901, which corresponds to a z value of 2.33. We calculate the safety stock and reorder point as follows:
12 – 75Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Safety stock = zσdLT = (2.33)(283.06) = 659.53 or 660 bars
Reorder point = dL + Safety stock = (275)(5) + 660 = 2,035 bars
Solved Problem 5Solved Problem 5
c. The total annual cost for the Q system is
Q DC = (H) + (S) + (H)(Safety stock)
Q
2DQ
C = ($0.30) + ($10) + ($0.30)(660) = $974.052,587
2100,375
2,587
12 – 76Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
28-Jun-10
39
Solved Problem 6Solved Problem 6
Zeke’s Hardware Store sells furnace filters. The cost to place an order to the distributor is $25 and the annual cost to hold a filter in stock is $2. The average demand per week for the filters is 32
it d th t t 50 k Th klunits, and the store operates 50 weeks per year. The weekly demand for filters has the probability distribution shown on the left below.
The delivery lead time from the distributor is uncertain and has the probability distribution shown on the right below.
Suppose Zeke wants to use a P system with P = 6 weeks and a cycle-service level of 90 percent. What is the appropriate value for T and the associated annual cost of the system?
12 – 77Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
for T and the associated annual cost of the system?
Solved Problem 6Solved Problem 6
Demand Probability
24 0.15
28 0.20
32 0.30
36 0.20
40 0.15
Lead Time (wks) Probability
1 0.05
2 0.25
3 0.40
4 0.25
5 0.05
12 – 78Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
28-Jun-10
40
Solved Problem 6Solved Problem 6
SOLUTION
Figure 12.13 contains output from the Demand During the Protection Interval Simulator from OM Explorer.Protection Interval Simulator from OM Explorer.
12 – 79Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Figure 12.13 – OM Explorer Solver for Demand during the Protection Interval
Solved Problem 6Solved Problem 6
Given the desired cycle-service level of 90 percent, the appropriate T value is 322 units. The simulation estimated the average demand during the protection interval to be 289 units,
tl th f t t k i 322 289 33 itconsequently the safety stock is 322 – 289 = 33 units.
The annual cost of this P system is
C = ($2) + ($25) + (33)($2)6(32)
250(32)6(32)
= $192.00 + $208.33 + $66.00 = $466.33
12 – 80Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
$192.00 $208.33 $66.00 $466.33
28-Jun-10
41
Solved Problem 7Solved Problem 7
Consider Zeke’s inventory in Solved Problem 6. Suppose that he wants to use a continuous review (Q) system for the filters, with an order quantity of 200 and a reorder point of 140. Initial i t i 170 it If th t k t t i $5 it d llinventory is 170 units. If the stockout cost is $5 per unit, and all of the other data in Solved Problem 6 are the same, what is the expected cost per week of using the Q system?
SOLUTION
Figure 12.14 shows output from the Q System Simulator in OM Explorer. Only weeks 1 through 13 and weeks 41 through 50 are shown in the figure The average total cost per week is
12 – 81Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
are shown in the figure. The average total cost per week is $305.62. Notice that no stockouts occurred in this simulation. These results are dependent on Zeke’s choices for the reorder point and lot size. It is possible that stockouts would occur if the simulation were run for more than 50 weeks.
Solved Problem 7Solved Problem 7
12 – 82Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.
Figure 12.14 – OM Explorer Q System Simulator
28-Jun-10
42