14-nov-11 pac - prague global design effort 1 barry barish pac - prague 14-nov-11 global design...

Post on 04-Jan-2016

219 Views

Category:

Documents

4 Downloads

Preview:

Click to see full reader

TRANSCRIPT

14-Nov-11 PAC - Prague

Global Design Effort 1

Barry BarishPAC - Prague

14-Nov-11

Global Design EffortDirector’s Report

Grooved Insert forCesrTA Wiggler

Fermilab NML: RF Unit Test FacilitySystems Tests

14-Nov-11 PAC - Prague

Global Design Effort 2

GDE Status & Plans

• Update on ILC accelerator R&D

• The Technical Design Report– Top level changes– Baseline Technical Reviews ; PM level changes– TDR Scope and Plans – Cost Estimate– Project Implementation Planning

• ILC Systems Tests

• Post-TDR planning

• Japan CFS News and Plans

• SCRF• ATF-2• Electron Cloud

Update on ILC accelerator R&D

14-Nov-11 PAC - Prague

Global Design Effort 3

14-Nov-11 PAC - Prague

Global Design Effort 4Global Design Effort

Major R&D Goals for Technical Design

SCRF• High Gradient R&D - globally coordinated program to

demonstrate gradient by 2010 with 50%yield; improve yield to 90% by TDR (end 2012)

• Manufacturing: plug compatible design; industrialization, etc.• Systems tests: FLASH; plus NML (FNAL), STF2 (KEK) post-TDR

Test Facilities• ATF2 - Fast Kicker tests and Final Focus design/performance

EARTHQUAKE RECOVERY• CesrTA - Electron Cloud tests to establish damping ring

parameters/design and electron cloud mitigation strategy• FLASH – Study performance using ILC-like beam and

cryomodule (systems test)

14-Nov-11 PAC - Prague

Global Design Effort 5

The ILC SCRF Cavity

- Achieve high gradient (35MV/m); develop multiple vendors; make cost effective, etc

- Focus is on high gradient; production yields; cryogenic losses; radiation; system performance

Global Plan for ILC Gradient R&D

14-Nov-11 PAC - Prague

Global Design Effort 6

New baseline gradient:Vertical acceptance: 35 MV/m average, allowing ±20% spread (28-42 MV/m)Operational: 31.5 MV/m average, allowing ±20% spread (25-38 MV/m)

14-Nov-11 PAC - Prague

Global Design Effort 7

Cavity Gradient Milestone Achieved

2010Milestone

TDRGoal

• Toward TDR goal• Field emission;

mechanical polishing• Other progress

14-Nov-11 PAC - Prague

Global Design Effort 8

ATF2 – Beam size/stability and kicker tests

IP Shintake Monitor

Final Doublet

14-Nov-11 PAC - Prague

Global Design Effort 9

14-Nov-11 PAC - Prague

Global Design Effort 10

• Mitigating Electron Cloud

• Simulations – electrodes; coating and/or grooving vacuum pipe• Demonstration at CESR critical tests

eCloud R&D

14-Nov-11 PAC - Prague

Global Design Effort 11

CesrTA - Wiggler Observations

IWLC2010 - CERN, Geneva, Switzerland

0.002”radiusElectrode best performance

14-Nov-11 PAC - Prague

Global Design Effort 12

Field Region

Baseline Mitigation RecommendationAlternatives for

Further Investigation

Drift* TiN Coating Solenoid Windings NEG Coating

Dipole Grooves with TiN Coating

Antechambers for power loads and photoelectron control

R&D into the use of clearing electrodes.

Quadrupole*

TiN Coating   R&D into the use of clearing electrodes or grooves with TiN coating

Wiggler Clearing Electrodes

Antechambers for power loads and photoelectron control

Grooves with TiN Coating

Proposed ILC Mitigation Scheme

– Top level changes– Baseline Technical Reviews

(lower level changes)– TDR Scope and Plans (Walker)– Cost Estimate (Dugan)– Project Implementation Planning (Paterson)

The Technical Design Report

14-Nov-11 PAC - Prague

Global Design Effort13

14-Nov-11 PAC - Prague

Global Design Effort 14

Establishing Baseline for the TDR

14-Nov-11 PAC - Prague

Global Design Effort 15

Proposed Design changes for TDR

RDR SB2009• Single Tunnel for main linac

•Move positron source to end of linac ***

• Reduce number of bunches factor of two (lower power) **

• Reduce size of damping rings (3.2km)

• Integrate central region

14-Nov-11 PAC - Prague

Global Design Effort 16

Technical Design Phase and Beyond

AD&I studies

2009 2010

RDR ACD concepts

R&D Demonstrations

TDP Baseline Technical Design

2011 2012 2013

RDR Baseline

Be

ijing

Wo

rks

ho

p

TDR

TDP-1 TDP-2ChangeRequest

SB2009 evolve

change control processAAPPACPhysics

CE

RN

Wo

rks

ho

p

Technical Volumes

15.11.2011

Reference Design Report

ILC Technical Progress Report (“interim report”)

TDR Part I:R&D

TDR Part II:BaselineReferenceReport

Technical Design Report

~250 pagesDeliverable 2

~300 pagesDeliverables 1,3 and 4

* end of 2012 – formal publication early 2013

AD&I

Nick Walker - PAC, Prague

ILC Project Implementation Planning

• Contents• Executive Summary• Governance• Funding Models• Project Management• Host Responsibilities• Siting Issues• In-Kind Contribution Models• Industrialisation and Mass Production of the

SCRF Linac Components• Project Schedule• Future Technical Activities

14-Nov-11 PAC - Prague

Global Design Effort 18

14-Nov-11 PAC - Prague

Global Design Effort 19

Project Implementation Planning

14-Nov-11 PAC - Prague

Global Design Effort 20

(Global) Mass Production (SCRF)

• Critically important TDP2 activity

• Learn from XFEL experience• 5% ILC

• Learn from LHC experience

• Develop realistic models on which to base cost estimate

• With industry

TLCC-1

Global S1TDP-2

PIPGovernance

SCRF

14-Nov-11 PAC - Prague

Global Design Effort 21

14-Nov-11 PAC - Prague

Global Design Effort 22

19m x 14m ISO class-5 clean room

Chemical Polish room

KEK Industrial R&D Pilot Plant

Press machine

Triming machine

Electron Beam Welder

work together with industry to develop cost-effective cavity production techniques

– TDR – Post - TDR

Systems Tests

14-Nov-11 PAC - Prague

Global Design Effort 23

14-Nov-11 PAC - Prague

Global Design Effort 24

FLASH: Stability

• 15 consecutive studies shifts (120hrs), and with no downtime

• Time to restore 400us bunch-trains after beam-off studies: ~10mins

• Energy stability with beam loading over periods of hours: ~0.02%

• Individual cavity “tilts” equally stable

Energy stability over 3hrs with 4.5mA

~0.02% pk-pk

9 Feb 2011

14-Nov-11 PAC - Prague

Global Design Effort 25

Fermilab – NML SRF Schedule

14-Nov-11 PAC - Prague

Global Design Effort 26

KEK – STF Plans for Cryomodule Tests

14-Nov-11 PAC - Prague

Global Design Effort 27

– “Value Costs” - Plans and Scope– Comparisons with RDR costs

TDR Cost Estimate

14-Nov-11 PAC - Prague

Global Design Effort 28

TDR Cost estimate: Scope

• The cost estimate covers only the costs for the 500 GeV design as detailed in the TDR, to be expended during the 8 year construction period.

• Costs for project engineering and design, R&D prior to construction authorization, commissioning, pre-operation, operation, and de-commissioning are not included.

• Costs for upgrading the machine to 1 TeV are not included in the baseline estimate, except the cost of those systems which would be very difficult to provide after construction of the 500 GeV machine.

• An approximate cost for the 1 TeV upgrade will be provided separately.

04/20/23 ILC PAC 29

OECD PPP (Yen/USD)-annual average by year

EX-exchange rateGDP: PPP based on all goods/services in GDP of each regionM&E: PPP based on machinery and equipmentConst: PPP based on civil construction

Full PPP determinations were done for 2005 and 2008; other year points based on GDP inflation rates

14-Nov-11 PAC - Prague

Global Design Effort 30

PPP = Purchasing Power Parity

– Extending the energy of the ILC– Continued R&D – especially SCRF– Organization? (ILCSC)

Post TDR

14-Nov-11 PAC - Prague

Global Design Effort 31

14-Nov-11 PAC - Prague

Global Design Effort 32

CY

Technical Design Report completeBaseline established

2011 2012 2013 2014 20162010

ILC

2015

Technical design & R&D program

2017 2018

ILC possible timeline

SRF system tests

TDR reviews

Site EOI’s

Cost Estimating

Decision to proceed

Site/host established

Project Implementation Plan complete XFEL operation

LHC

Physics Run 1 Physics Run 2Interconnect repair

Existence of low-lying SUSY known

Higgs energy scale known

timegap

14-Nov-11 PAC - Prague

Global Design Effort 33

CY

Technical Design Report completeBaseline established

2011 2012 2013 2014 20162010

ILC

2015

Technical design & R&D program

2017 2018

ILC possible timeline

SRF system tests

TDR reviews

Site EOI’s

Cost Estimating

Decision to proceed

Site/host established

Project Implementation Plan complete XFEL operation

LHC

Physics Run 1 Physics Run 2Interconnect repair

Existence of low-lying SUSY known

Higgs energy scale known

timegap

14-Nov-11 PAC - Prague

Global Design Effort 34

Post – TDR (ILCSC)

• ICFA LC Parameters subcommittee (2003 and 2006)

14-Nov-11 PAC - Prague

Global Design Effort 35

Extending the reach of the ILC

Extending the reach of the ILC

• Upgrade option for study:

- Power < 300MW AC - New linac grad = 45 MV/m- Q0 = 2 1010

• Strawman TeV parameters

• Post-TDR program:•Improve cavity gradient•Cost effective production

• Flexibilty: Initial ILC energy: higher or lower energy, as informed by LHC results14-Nov-11 PAC - Prague

Global Design Effort 36

14-Nov-11 PAC - Prague

Global Design Effort 37

Post-TDR ILC Interim Goals & Organization• GDE will have successfully completed its mandate after TDR

& PIP delivered + reviewed (mid-2013 at latest + transition)

• What should follow GDE (mandate and organization) for an interim 3-5 year period? (ILCSC – Bagger)

• GDE position paper submitted to ILCSC Aug 2011. The paper addresses:– Technical Goals proposed for 2012+ program?

• Value engineering; Continued system demonstrations; Increasing energy reach; +

– Organizational Issues for 2012+ post GDE? • What are primary GDE assets that should be preserved?• What are the primary GDE weaknesses that should be improved?

• We must define what systems tests must demonstrate for each LC option before construction of a LC? ICFA??

Two Candidate Sites in Asia/Japan

- GDE-CFS group visited two sites,

Oct., 2011

Common Features

ILC-GDE PMs, 11-11-11 ILC Cavity Industrialization 39

Courtesy: M. Miyahara

Studies for 8 Cases of Tunnel Design

‘Bread Shape’ under Study

Cost-and time-effective in Japan

CFS Study: Progress in Japan

JFY Progress

2009 AAA volunteered to study ‘ILC tunnel design’ for SB2009,

2010 Local communities (LCs) organized geological survey by themselves.KEK studied 8 cases of the tunnel design, and reached a ‘Bread-shape (Kamaboko) shape tunnel’ to be an economical candidate, specifically, in Japanese mountainous regions.

2011 AAA re-volunteered to evaluate the tunnel design and environmental conditions, to assist KEK.LCs reported the geological survey to KEK.KEK going to progress the engineering work of tunneling, electrical, and mechanical issues, based on the information given by AAA and LCs, Japanese Civil Engineer Association is active to professionally assess the geological surveys and civil engineering.S&T Policy Council of the Cabinet received a brief report from MEXT on Sept. 1, on science objectives of the ILC project and global status.A Supplemental Budget being discussed at the Diet to encourage/boost recovery of national and regional activities. It may include some support for further site-dependent geological studies at the candidate sites in cooperation of KEK with the local communities (universities, and local Gov.)

14-Nov-11 PAC - Prague

Global Design Effort 43

Conclusions

• The major R&D milestones for TDR are essentially in-hand

• The Technical Design Report will be a self-contained comprehensive R&D report; with a design based on new baseline; a new value costing; and a section on project implementation planning

• We seek your advice / concurrence on our system tests goals and program

• Post–TDR program is being planned: extend energy reach; complete systems tests; evolve design based on technology development and LHC results

top related