• Placed roof deck grid 7-1 on Wednesday 12.16.09. • Removing reshores on level 2 east and west wings. • Wrecking forms and pans on roof level grids 16-11.5 and reshoring. • Completed slab on carton forms at Visitor’s Center. • Pans complete for Visitor’s Center second floor scheduled to pour Tuesday. • Reinforcing on going at Visitor’s Center second floor. • West stair (stair #1) at 60% complete at HQ building. • Continue framing exterior and interior walls on the 1st floor @ HQ. • Second floor ductwork delivered and installation ongoing. • Cast iron tested and passed in crawlspace of HQ.

TRANSCRIPT

• Placed roof deck grid 7-1 on Wednesday 12.16.09.

• Removing reshores on level 2 east and west wings.

• Wrecking forms and pans on roof level grids 16-11.5 and reshoring.

• Completed slab on carton forms at Visitor’s Center.

• Pans complete for Visitor’s Center second floor scheduled to pour Tuesday.

• Reinforcing on going at Visitor’s Center second floor.

• West stair (stair #1) at 60% complete at HQ building.

• Continue framing exterior and interior walls on the 1st floor @ HQ.

• Second floor ductwork delivered and installation ongoing.

• Cast iron tested and passed in crawlspace of HQ.

• Energy Recovery Units delivered to the jobsite.

• Completed domestic cold water riser through third floor.

• Temporary power energized at building.

• Thermal piping installation ongoing

Texas A&M University Agriculture Headquarters

We e k l y R e p o r t : 1 2 / 1 4 / 0 9 - 1 2 / 1 8 / 0 9

ERU Delivery Visitor’s Center First Floor West Overhead