241 Extension Project – Oso Parkway to Ortega Highway Area
RMV Riding Park at SJC
2035 >30k ADT
2035 5-6k ADT
RMV Riding Park at SJC
01_12_12 FE Board 241 Extension
SR 74 Connection/Evaluation findings
• Cost to connect to Ortega - 50% greater than other options – too expensive
• No appreciable difference in 241 ADT 2035 • Ortega Highway precludes future alternative
alignments • 2035 Ortega Hwy only has 5,000 to 6,000 ADT,
Cow Camp Road has more than 30,000 ADT
01_12_12 FE Board 241 Extension
Cow Camp Road Connection/Evaluation findings
• Intersection spacing impacts - Caltrans and County concerns
• This alternative takes considerable developable acreage
RMV Riding Park at SJC
3500 ft
01_12_12 FE Board 241 Extension
Solution
• Permanent interchange at G Street • Interim connection to Cow Camp Road
RMV Riding Park at SJC
RMV Riding Park at SJC
01_12_12 FE Board 241 Extension
12
Summary
Option 1 –Staff Recommended Option 2 Option 3
Parameter
G Street
Interim Cow Camp Road
Cow Camp Road
Ortega Highway
Length 4.2 mile 4.8 mile 4.8 mile 5.4 mile
Construction Cost $195M Approximately $200M $225-250M $325-350M
Estimated 241 Opening Date Fall 2014 (Cow Camp Road Completion) Spring 2016
241 ADT (2035) 41,000 44,000* 41,000**
Revenue (2035) $30M $32-34M $30-33M
* Reflects unrestrained traffic conditions **Combined Ortega and G Street