319 Fleming Creek FINISHED Project

2018

District 5 and Fleming Creek Road

Project Location

Breaking Ground November 26, 2018 Culvert #1 BEFORE

Spring 2018 Breaking Ground!

Culvert #1 District 5 Road

Before (Inlet)

Culvert #1 Finished Inlet

Culvert #1

Before (Outlet)

After

Culvert #1 Outlet Finished

Culvert # 2 Fleming Creek Road- Before

Spring 2018- Inlet Spring 2018- Outlet

Culvert # 2 Work Begins!!!

Breaking Ground Inlet Diversion

Making Progress!!!

Working Hard!!!

Finished Culvert #2

Finished Inlet

Outlet Culvert #2 Fleming Creek Road

Spring 2018 Finished Outlet

Cross Drain Installed

CULVERTS: $15,930.77* WILLOWS: $100.00* R&B EQUIPMENT COSTS: $16,075.50* R&B LABOR: $15,536.56 MATERIALS: $6,223.40 SWCC: MATCH $3,287.16 BSCD: MATCH $1680.00 ADMIN: $3530.00

TOTAL PROJECT COST: $62,363.39 60% $37,418.03 40% $24,945.36

$5311.76 TOWARDS LABOR AND MATERIALS

Biggest Highlight

• Thank you to Boundary County Road and Bridge and all of your hard

work!