Resolution 2019-15-PT

Item No.: 4CDate of Meeting: 12/19/19

Approval of Resolution 2019-15-PT committing the Port of Tacoma to providing a contribution to the State Route 167 project of up to $27 million in the form of cash and/or other in-kind contribution.

Action requested

Background

Background

Background (continued)

Background (continued)

Background (continued)

Engrossed Senate Bill 5096 § 306(20)(b))

The secretary of transportation must develop a memorandum of understanding with local project stakeholders that identifies a schedule for stakeholders to provide local matching funds for the Puget Sound Gateway project. Criteria for eligibility of local match includes matching funds and equivalent in-kind contributions including, but not limited to, land donations. The memorandum of understanding must be finalized by July 1, 2018. The department must submit a copy of the memorandum of understanding to the transportation committees of the legislature and report regularly on the status.

Scope

• Commit to an additional $27 million investment into SR 167;

• Specific details to be included in subsequent ILAs; and

• ILAs subject to commission approval.

Project schedule

Project DevelopmentNEPA re-evaluation 2017-2018Interchange Justification Report 2017-2018Traffic and revenue analysis for tolling 2017-2018Legislative authorization for tolling 2019Stage 1A (70th Avenue bridge replacement)Design 2017-2019Right-of-way 2017-2019Construction 2019-2021Stage 1B (I-5 to SR-509)Design 2017-2021Right-of-way 2017-2021Construction 2021-2025Stage 2 (I-5 to SR-167)Design 2021-2023Right-of-way 2017-2023Construction 2023-2028

Financial summary

Item Port Total Contribution

Expenditure to Date

AdditionalFuture CashExpenditures

Additional FutureIn-Kind

Contribution

Total Future Expenditures

SR 167 Project

$30 million $3 million $22 million $5 million $27 million

TOTAL $30 million $3 million $22 million $5 million $27 million

Alternatives considered

• No financial contribution.

• ILAs only without resolution.

• Preferred alternative: resolution + ILAs

Economic investment/job creation

• 44% truck trips bound to Kent/Puyallup valleys

• 15% travel time improvement• 14,000 hours • $940 million

• $10.1 billion in long-term payroll

• 2,437 construction jobs

Environmental impacts

• 26% reduction in air emissions

• 1,000 acres of contiguous habitat–70% increase in ecological services

• 50% reduction in flooding along Hylebos Creek

Next steps

Approval of Resolution 2019-15-PT committing the Port of Tacoma to providing a contribution to the State Route 167 project of up to $27 million in the form of cash and/or other in-kind contribution.