BIM strategy in practice

Sylvain Kubicki, Arch. Dr. May 21st, 2014

Overview

1. Building Information Modelling

2. BIM strategy and implementation

3. Conclusion

Tudor’s team and partnership

Construction Program@CRP Henri Tudor: our competencies

•  Business “experts” (Architects, Civil Engineer / Dr., PhD students)

•  IT scientists •  Appropriation, networking, IPR

Our team is historically involved in CRTI-B

innovation projects

•  Standardization of electronic collaboration

Today Tudor is co-animator of the NeoBuild

innovation pole

•  Series of BIM workshops

CRTI-B

Public owners -  Ministère du Développement Durable et des infrastructures -  Administration des Bâtiments Publics -  Administration des Ponts et Chaussées

Designers - Ordre des Architectes et Ingénieurs-Conseils Contractors -  Fedil -  Fédération des artisans -  Chambre des Métiers

Building Information Modelling

… Not a technology or software system … Not a single-discipline model BIM is reliable data about a facility

What is BIM?

Program, geometry (3D), technical (structure, MEP), project management (planning, RFIs, change requests), financial…

What is BIM?

Program, geometry (3D), technical (structure, MEP), project management (planning, RFIs, change requests), financial…

Multi-dimensions and enrichment of information

Building Information Modelling

Succar, 2009

Modelling Facility-related Production and

usage processes

Collective process

Building Information Modelling Industry-driven research challenge

•  Huge cost of lack of interoperability between software systems in design/construction

•  Cost of uninformed decision making in Facility Management

•  “Facility-related Data” as an economical and innovation driver

BIM & BIM •  Building Information Model

•  Knowing its building & assets to optimize property management (asbestos cement areas, lift maintenance, security, taxes,

•  R&D challenge of describing building-related concepts •  Building Information Modeling

•  A collaborative design/construction/use process

BIM is a reality in several regions

•  USA, Finland, UK, Singapore, Canada… •  January 2014: EC decision to recommend BIM for

public construction procurement across Europe

NBS International BIM Report 2013

Livre blanc, Caisse des dépôts FR, 2014

BIM Maturity

Maturity of organizations regarding BIM •  Company level: object-based modeling •  Project level: information exchange

processes based on models •  Sectorial level: a global view, linked to

public (procurement) policies

BIM Task Group, UK, 2014

Succar, 2009

BIM implementation

Identify BIM goals and uses

According to an organization’s own goals •  With level of importance

Within a list of BIM uses •  Identified through case studies •  Approved by practitioners

Design BIM project execution process

Reference process(es) for BIM execution planning •  Activities perfomed •  Information exchanged

Template from BIM Project Execution Planning Guide Version 2.1 Pennstate University - CIC

Developing information exchanges (IE)

It requires to identify: •  The model receiver: project team members that will receive the IE •  The model file type: define the software used to manipule the IE •  The level of detail (LoD) of the IE •  The responsible actor authoring the information

Then it is necessary to verify the matching between authored

information and requested information

Developing information exchanges (IE)

It requires to identify: •  The model receiver: project team members that will receive the IE •  The model file type: define the software used to manipule the IE •  The level of detail (LoD) of the IE •  The responsible actor authoring the information

Then it is necessary to verify the matching between authored

information and requested information

BIM Project Execution Planning Guide Version 2.1 Pennstate University - CIC

Technological implementation

Exchange formats to be used

•  Test of exchanges between software systems

•  Customization of export/import

Technological infrastructure needs

•  In terms of software and hardware

•  Authoring/review/collaboration

Quality Controls •  Checking methods

Model checking / Solibri

Conclusion

Some remarks

BIM strategy •  Owner requirements

•  Required data for asset management •  Requirement regarding project management

and decision-making through BIM •  BIM project organization

BIM Implementation •  Design/construction/consultancy teams

should be deeply involved •  Taking into account the maturity of

organizations involved •  Structured, time-consuming process

Contractual issues •  Legal value of BIM data vs. usual

documentation •  Liability for BIM data

Crédit : CRP Henri Tudor / Sylvain

Kubicki

Thank you for your attention