Community Program Community Program Advisory CommitteeAdvisory Committee

Tuesday, May 17, 2005Tuesday, May 17, 2005

Today’s MeetingToday’s Meeting

• Program Update

• $161 million in contracts awarded

• Bay View Wastewater Treatment Plant

• Point Place

• River Road

• LTCP/EPA Update

• Next Meeting

BVWWTP – EQ BasinBVWWTP – EQ Basin

• Construction begins in June

• Completed by December 2006

• Low bid was $28 million

• Contract with Rudolph Libbe being finalized

BVWWTP – Grit FacilityBVWWTP – Grit Facility

• Construction began in April

• Completed by Fall 2006

• $13.9 million

• Contractor is Rudolph Libbe

BVWWTP – Grit FacilityBVWWTP – Grit Facility

BVWWTP – Grit FacilityBVWWTP – Grit Facility

BVWWTP – Grit FacilityBVWWTP – Grit Facility

BVWWTP – BVWWTP – Wet Weather/Wet Weather/Ballasted FlocculationBallasted Flocculation• Construction begins in May

• Completed by Fall 2006

• $40 million

• Contractor is Mosser Construction

290290thth Street Pump Station Street Pump Station

• Substantially complete

• Landscaping underway

• Contractor was Gardner Mechanical

290290thth Street Pump Station Street Pump Station

290290thth Street Pump Station Street Pump Station

290290thth Street Pump Station Street Pump Station

290290thth Street Pump Station Street Pump Station

Edgewater Pump StationEdgewater Pump Station

• Working on startup, plan to start testing in a few weeks

• Completed by early Summer

• $4 million

• Contractor is Walbridge Aldinger

Edgewater Pump StationEdgewater Pump Station

Edgewater Pump StationEdgewater Pump Station

Edgewater ConstructionEdgewater Construction

• Currently testing 24-inch force main, then will test 8-inch force main

• Completed this Summer; resumes Winter 2005

• $2.5 million

• Contractor is Crestline Paving

Edgewater ConstructionEdgewater Construction

Edgewater ConstructionEdgewater Construction

River Road ParkRiver Road Park

• Construction underway

• Completed by Fall 2007

• $3.6 million (pump station and basin)

• Contractor is E.S. Wagner

River Road ParkRiver Road Park

River Road ParkRiver Road Park

River RoadRiver Road

• Water line nearly complete

• Sewer line will be completed by Fall 2005

• $1.8 million

• Contractor is Anderzack Pitzen

River RoadRiver Road

River RoadRiver Road

LTCP/EPA updateLTCP/EPA update

• LTCP

• EPA

Next meetingNext meeting

• Other issues

• Next meeting date, time