CPV DCS STATUS REPORT
Mikhail Bogolyubsky (IHEP, Protvino)Serguei Sadovsky (IHEP, Protvino)
CERN, DCS meeting, 30 January, 2007.
2006 DCS planning, CPV
DCS planning meeting 13.03.2006:
Detector CPV: D = 01.12.07 => D = 1-st Shut Down in 2008 (D - Date of the detector installation in the pit)
CPV FSM Pre-commissioning in Lab/CERN/SXL2 Who responsible Ready when?– Integrate all sub-systems in the DETECTOR FSM A.M., M.B. 01.07.07– Implement software interlocks (if required) A.M., M.B. 01.07.07 – Implement operations panels A.M., M.B. 01.07.07
• < D-4 weeks
• Commissioning at P2 – Hand-over PVSS project to ACC for verific.& integration S.S., M.B., A.M. D-4 weeks – Install PVSS project in server at P2 ACC D-2– Commission with sub-systems at P2 A.M., M.B. D-2– Commission the DETECTOR DCS with PHOS A.M., M.B. D– Commission together with other detectors A.M., M.B.,VO +All D+?
2006 DCS planning, CPV (2)
LV PS Pre-commissioning in Lab/CERN/SXL2 Who responsible Ready when?– Implement a “Lab setup”: PVSS-OPC-device M.B., A.M. 01.07.07– Implement FSM M.B., A.M. 01.07.07
– Implement the PVSS configuration, archival and alarms M.B., A.M. 01.07.07– Implement software interlocks (if required) M.B., A.M. 01.07.07 – Implement operations panels M.B., A.M. 01.07.07
• < D-4 weeks• Commissioning at P2• Hand-over PVSS project to ACC for verific.& integrat. S.S., M.B, A.M. D-4 weeks
– Install PVSS project in server at P2 ACC D-2– Install, cable & commission the LV PS devices at P2 V.V. D-2– Commission the LV PS devices with detector M.B., A.M. D
D = 1-st Shut Down in 2008 (D - Date of the detector installation in the pit)
2006 DCS planning, CPV (3)
HV PS Pre-commissioning in Lab/CERN/SXL2 Who responsible Ready when?– Implement a “Lab setup”: PVSS-OPC-device M.B., V.O. 01.07.06– Implement FSM M.B., V.O. 01.07.06
– Implement the PVSS configuration, archival and alarms M.B., V.O. 01.07.06– Implement software interlocks (if required) M.B., V.O. 01.07.06 – Implement operations panels M.B., V.O. 01.07.06
• < D-4 weeks• Commissioning at P2• Hand-over PVSS project to ACC for verific.& integrat. S.S., M.B, V.O. D-4
weeks– Install PVSS project in server at P2 ACC D-2– Install, cable & commission the HVPS devices at P2 V.V. D-2– Commission the HV PS devices with detector M.B., V.O. D
D = 1-st Shut Down in 2008 (D - Date of the detector installation in the pit)
2006 DCS planning, CPV (4)
Temperature Monitor Pre-commissioning in Lab/CERN/SXL2 Who responsible Ready when?– Implement a “Lab setup”: CRW-DAQ A.M., M.B. 01.08.07– Implement FSM A.M., M.B. 01.08.07
– Implement the PVSS configuration, archival and alarms A.M., M.B. 01.08.07– Implement software interlocks (if required) A.M., M.B. 01.08.07 – Implement operations panels A.M., M.B. 01.08.07
• < D-4 weeks• Commissioning at P2• Hand-over PVSS project to ACC for verific.& integration S.S., A.M., M.B. D-4 weeks
– Install PVSS project in server at P2 ACC D-2– Install, cable & commission the COOLING plant at P2 V.V. D-2– Commission the COOLING plant with detectorV.V., A.M., M.B. D
D = 1-st Shut Down in 2008 (D - Date of the detector installation in the pit)
GAS (Ar+CO2) Commissioning at P2 Who responsible Ready When? -- Hand-over PVSS project to ACC for verific. & integration GWG 1.08.06 -- Install PVSS project in server at P2 ACC 1.08.06 -- Install, cable & commission the GAS system at P2 GWG 1.08.06 -- Commission the GAS system with detector S.S., V.V., M.B. D < D-4 weeks
Detector
PVSS II PVSS II
Detector
Ethernet
Database(s)
OPCclient
DIMclient
3020
Detector(Ni100 sensors)
32
High Voltage Low Voltage Temp. Monitor
User interface
PVSS II
HV LV
PHOS-CPVC
on
tro
l ro
om
(A
CR
)[UI node]
ELMB
27/10/05
CR4-Y10
SY2527(2*A18833P)
Ethernet
E
CR3
CAEN OPCserver
PVSS IIOPC client
1
UX-C16
Wiener
E
CR3
Wiener OPCserver
PVSS IIOPC client
3
CR3
PCI-CAN
ELMB OPCserver
PVSS IIOPC client
C
1ACC
1
CR3
SG2
CR5
SG2
Gas system
PLC
Gas
E
Detector
PVSS IIDIP
[GWG]
Gas
GasPVSS
1
2 2 2
Wiener Crate State Diagram
Wiener Channel State Diagram
Wiener Control State Diagram
Wiener State Diagrams
What is Ready & in Progress
• CPV FSM – in a good progress (the first prototype exists)
• LV Power supplies of the Wiener type – almost ready
• HV Power supplies of the CAEN type – TBD (the same as in HMPID)
• Temperature monitoring (ELMB) – TBD (the same as in PHOS)
• Gas system – almost ready (GWG)
• Connection of top the CPV Level with the top PHOS Level – TBD