The Township Center Project - 2020

Daily Diary 07-17-2020 Page 1

SUBJECT: DAILY DIARY July 17, 2020

WEATHER: 80’s degrees, sunny.

WORK DAY = 30.

E. P. DOYLE: On-Site Tony all day.

ENGINEERING SOLUTIONS TEAM: Ed on-site on and off.

PREMIUM CONCRETE: Dustin + 2. on-site today.

WALKER: Jose +1 on-site today.

WATER PROOFING: 1 on-site today.

Activities Today:

• Premium worked on punch-list items today.

• Walker on-site to establish the final sub-base finish grade for the basement.

• Water proofer on-site to work on the elevator and the northeast corner.

Activities Monday:

• Concrete for the remaining basement walls is scheduled for Monday.

Critical Path:

• Status of Com Ed Truck and potential bracing?

• Construction and delivery of the pre-cast floor planks.

Pending Items:

• How to backfill the NE corner of the building?

Please advise if there are questions or if I missed anything.

Thank you. Notes by Ed Kalina. / Please advise if there are any further thoughts or questions.

The Township Center Project - 2020

Daily Diary 07-17-2020 Page 2

Premium starting the day.

Premium starting the Day.

The Township Center Project - 2020

Daily Diary 07-17-2020 Page 3

The Outside Basement Walls.

Installing the Insulation.

top related