dunlap park-and-ride site development – public meeting
Post on 03-Feb-2022
1 Views
Preview:
TRANSCRIPT
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Light Rail Northwest Extension Dunlap Park-and-Ride Site Development
May 27, 2009
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Northwest Extension SDunlap Park-and-Ride Site
6:00 pm – 6:30 pm Open House6:30 pm – 7:00 pm Presentation7:00 pm – 8:00 pm Open Housep p p
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Agendage da
Introduction of Project TeamIntroduction of Project TeamProject Overview & ProgressP k d Rid Sit C tPark-and-Ride Site ConceptArtNext StepsQuestions
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Public Involvement Roleub c o e e t o e
Liaison between project Liaison between project and communityKnow and understand Know and understand the communityIssue resolutionIssue resolutionCreate project updatesC t ti f tConstruction safety
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Project TeamProject Team
Alvin Livingstone, P.E. Carla Kahn / Terry Gruver / C l B lMETRO – Project Manager
Marty SpongMETRO – Construction Manager
Coral BalcazarMETRO – Public Involvement Coordinators
Maria HyattgRichard BeltranAECOM – Designer
Erik Yingling
yCity of Phoenix
Albert SantanaCity of PhoenixErik Yingling
Sundt-Stacy Witbeck – CMAR Project Manager
Ho ard Steere
Eric JohnsonCity of Phoenix – Economic Development
Maurice GoyetteHoward SteereMETRO – Public Involvement Manager
M.B. Finnerty
Maurice GoyetteCity of Phoenix – Traffic
Jami SpearCity of Phoenix – Real Estate
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
METRO – Public Art AdministratorCity of Phoenix Real Estate
Project Overviewoject O e e
3 2 mile Alignment3.2-mile Alignment3 Stations
Glendale AvenueGlendale AvenueNorthern AvenueDunlap AvenueDunlap Avenue
Park-and-Ride Facility
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Northwest Extension o t est te s o
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
ScheduleSc edu e
Design Completion:Design Completion:Civil Design – MarchSystems Design – AprilSystems Design – AprilRoyal Palms Mitigation – MayPark-and-Ride – AugustPark and Ride August
Anticipated Construction Start – Summer 2009Opening Day December 2012Opening Day – December 2012
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Site Development ConsiderationsS te e e op e t Co s de at o s
Estimated parking needEstimated parking needConsideration of existing businesses / surrounding areasurrounding areaEfficient connection to light rail station platformEffi i t b tiEfficient bus connectionsSafe and efficient traffic movementsFacilitate future system expansionCost
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Initial Site Developmentt a S te e e op e t
Based on Parking Demand Study (May 2007)Based on Parking Demand Study (May 2007)1000-space parking facility3 l l f ki3 levels of parkingArt/community plazaShuttle bus turnaroundSecurity/operator facilityLandscaping
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Initial Site Concept: 1 000 G St t1,000-space Garage Structure
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Park-and-Ride Analysisa a d de a ys s
Parking Demand StudyParking Demand StudyBased upon MAG Local Travel ForecastDrive access demand is modeled/calculatedDrive access demand is modeled/calculatedEnd of line at 19th/Dunlap Avenue – 2010 E d f li 19th/D l A 2030End of line 19th/Dunlap Avenue – 2030
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Park-and-Ride Analysis R lt d R d tiResults and Recommendation
ResultsResultsParking required 2010: 292 – 366 spacesParking required 2030: 487 611 spacesParking required 2030: 487 – 611 spaces
Recommendation500 600 k d id 500 – 600 park-and-ride spaces
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
19th Avenue and Montebello9 e ue a d o tebe o
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Traffic Analysis Resultsa c a ys s esu ts
Study area: 19th Avenue/Dunlap Avenue intersectionStudy based on 550 park-and-ride spacesCurrent Level of Service (LOS) is FLOS F with park-and-ridep
Reduces delay by 15 secondsLOS F with light railg
Increases intersection delay by 40.5 secondsNet delay: 25.5-second increase
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Net delay: 25.5 second increase
SummarySu a y
Park and ride consisting of 484 spacesPark-and-ride consisting of 484 spacesArt/community plazaS it / t f ilitSecurity/operator facilityLandscapingCovered parkingShuttle bus turnaround
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Current Site Concept:484 S f L t484-space Surface Lot
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
METRO Art Program
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
METRO Art ProgramD l P k d RidDunlap Park-and-Ride
Artists: Matt and Maria SalengerArtists: Matt and Maria SalengerAre reviewing new concept/site configurationP t ti l t l tPotential art elements:
Community plazaShade structuresPedestrian areas
Presentation at next public meeting
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Next Stepse t Steps
Complete the design August Complete the design – August Conduct additional public meeting –July/AugustJuly/August
Dunlap Park-and-Ride Site Development – Public Meeting Presentation – May 27, 2009
Northwest Extensiono t est te s o
Carla Kahn Terr Gr erCarla KahnPublic Involvement Coordinator
ckahn@metrolightrail org
Terry GruverPublic Involvement Coordinator