Earthwork and Ground Technology
Site Improvement
Slides adapted and upgraded from original presentation slide by College of Engineering, University of Washington.
Methods of site improvement
• Removal and replacement• Preloading• Vertical drains• In-situ densification• Grouting• Stabilization using admixtures• Reinforcement
Removal and replacement
• One of oldest and simplest methods is simply to remove and replace the soil
• Soils that will have to be replaced include contaminated soils or organic soils
• Method is usually practical only above the groundwater table
Preloading
• Simply place a surcharge fill on top of the soil that requires consolidation
• Once sufficient consolidation has taken place, the fill can be removed and construction takes place
• Surcharge fills are typically 10-25 feet thick and generally produces settlement of 1 to 3 feet.
• Most effective in clay soil
Advantages of preloading
• Requires only conventional earthmoving equipment
• Any grading contractor can perform the work
• Long track record of success
Disadvantages of preloading
• Surcharge fill must extend horizontally at least 10 m beyond the perimeter of the planned construction, which may not be possible at confined sites
• Transport of large quantities of soil required
• Surcharge must remain in place for months or years, thus delaying construction
Vertical Drains
• Vertical drains are installed under a surcharge load to accelerate the drainage of impervious soils and thus speed up consolidation
• These drains provide a shorter path for the water to flow through to get away from the soil
• Time to drain clay layers can be reduced from years to a couple of months
Vertical Drains
PVD (Prefabricated Vertical Drain)
• Geosynthetics used as a substitute to sand columns
• Installed by being pushed or vibrated into the ground
• Most are about 100 mm wide and 5 mm thick
Vertical Drain Installation
Photo from: http://www.joostdevree.nl/bouwkunde/vertical_drain_2_www_imtek_com_tr.jpg
Photo adapted from vertical drain supplier
Typical installation of PVD
• Typically spaced 3 m on centers
Prefabricated Drains Available in Malaysia
•Nylex
•Emaskiara
• etc
Principle of Effective Overburden Pressure
When load is applied to soil, the deformation which occurs will depend on the grain to grain contacts (inter-granular forces) and the amount of water in the voids (pore water).
For saturated soil, the more permeable a soil is, the faster the deformation under load will occur. (remember PranginMall)
Only the inter-granular forces is effective in resisting shear and limiting compression. Therefore it is called effective stress. It is the controlling factor.
Overburden pressureThe effective overburden pressure (Po) at any depth is
determined by accumulating the weights of all layers above that depth as follows:
1) Soil above water table – multiply the total unit wt by the thickness of each respective soil layer above the level.
2) Soils below the water table – reduce the total unit wt by the wt of water (1000 kg/m3) … i.e. use the effective unit wt.
ExampleFind Po at 6 meter below ground level in a sandy deposit with total unit wt of 1762 kg/m3 (17.62 kN/m3). Water table is 3 m below ground.
Step 1: 3 m x 17.62 = 52.86 kPa (Po above water table)
Step 2: 3 m x (17.62 – 10) = 22.86 kPa (Po below water table)
Po = 52.86 + 22.86 = 75.72 kPa
75.72
3
6
0
52.86
0
Exercise
Elv: 60m
Elv: 45 m
Elv: 51 m
Water table 6 m below ground
Ground level 60 m
Clay γ = 20kN/m3
Sand γ = 17 kN/m3
Draw Po diagram and determine the overburden pressure at 9, 12 and 15 m below ground.
Pressure Diagram
40
45
50
55
60
65
0 102 123 183
Pressure (KPa)
Elev
atio
n (m
)
Road Settlement Problem
Existing Ground level 60 m
Clay γ = 20kN/m3
Sand γ = 17 kN/m3
Elv: 45 m
Elv: 51 m
Elv: 60m
Water table 6 m below ground
FRL 66m
Granular Fill γ = 18 kN/m3
0
108
210231
291
0 0
102123
183
0
50
100
150
200
250
300
350
66 60 54 51 45
Elevation (m)
Pres
sure
(KPa
)
PfPo
Primary Settlement
o
f
o PP
eCcH log
)1( +×=Δ
H = thickness of Clay layer
Cc =coefficient of consolidation
Eo = initial void ratio
Pf = pressure after fill
Po = existing overburden pressure