Environmental Impacts @ MRPartidário 1
Prof. Doutora Maria do Rosário Partidário
!EIA post evaluation !
Environmental Impacts"
Environmental Impacts @ MRPartidário
Environmental assessment and planning cycle
(Storey, 1995: 310)
Environmental Impacts @ MRPartidário
EIA POST-EVALUATION
It is the stage in EIA that more closely follows the logic of Environmental Management Systems
Decree-Law no. 151-B/2013, of October 31, as amended by Decree-Law no. 47/2014, of March 24
«Post-evaluation» – process conducted after DIA is issued, includes monitoring programmes and auditing
(…)” DIA - Declaração Impacte Ambiental (Environmental
Impacts Declaration)
Environmental Impacts @ MRPartidário
SCREENING
SCOPING
EIS PREPARATION
REVIEW
DECISION
POST-EVALUATION I
POST-EVALUATION II
EIA post-evaluation objectives
• Assess the response of the environmental system to project effects;"
• Assure projects environmental surveillance and check the effectiveness of environmental managements measures adopted, and decide on the need for further and more effective measures; "
• Verify and analyse the effectiveness of the mitigation measures and the environmental management as laid out in the EIS and DIA to avoid, reduce, or compensate the negative impacts and stimulate the positive impacts; "
• Verify impacts when there was uncertainty;"
• Verify unexpected impacts; and "
• Improve knowledge - learn about impacts for certain categories of projects in certain locations."
Environmental Impacts @ MRPartidário
What Is EIA Follow-Up?
EIA follow-up can be simply defined as the monitoring and evaluation of the impacts of a project or plan (that has been subject to EIA) for management of, and communication about, the environmental performance of that project or plan (Morrison-Saunders and Arts 2004). Follow-up is essential for determining the outcomes of EIA. By incorporating feedback into the EIA process, follow-up enables learning from experience to occur. It can and should occur in any EIA system to prevent EIA being just a pro forma exercise.
Environmental Impacts @ MRPartidário
What Is EIA Follow-Up? EIA follow-up comprises four elements (Arts et al., 2001): 1. Monitoring – the collection of activity and environmental data both before (baseline monitoring) and after activity implementation (compliance and impact monitoring). 2. Evaluation – the appraisal of the conformance with standards, predictions or expectations as well as the environmental performance of the activity. 3. Management – making decisions and taking appropriate action in response to issues arising from monitoring and evaluation activities. 4. Communication – informing the stakeholders about the results of EIA follow-up in order to provide feedback on project/plan implementation as well as feedback on EIA processes.
Environmental Impacts @ MRPartidário
EIA Post-evaluation activities
• monitoring - programme of systematic observation,
measurement and registry actions, which is the proponent responsibility; should be conducted as established in the DIA, or in the EIS.
• auditing, is the objective and independent verification of conformity of the oberved practice in relation to expected predictions, or quality patterns and procedures, which is the responsibility of the EIA Authority.
Environmental Impacts @ MRPartidário
Monitoring objectives
• Monitor (measure) the response of the environmental system to the effects of the project;
• Verify the nature and magnitude of the expected impacts
• Verify the effectiveness of adopted mitigation and environmental management measures and the fulfilment of conditions laid out in the DIA;
• Use results of monitoring to quantify mitigation measures.
Environmental Impacts @ MRPartidário
Monitoring Planning
• monitoring places, including sampling and controlling
points,
• monitoring frequency, • monitoring indicators, and parameters, • data collection and storage methods per disciplines,
data analysis and presentation; and • necessary resources and costs.
Environmental Impacts @ MRPartidário
Is not the same but is related to State of the
Environment monitoring
e.g. INAG Water Quality National network (Rede Nacional de Qualidade
da Água)
EIA POST-EVALUATION
Environmental Impacts @ MRPartidário
Auditing
"• Engages verification of a system of registries
that result from a monitoring programme. "
• Performed by designated auditors (In portugal designated by the EIA Authority)."
• As far as possible is value judgement free.
Environmental Impacts @ MRPartidário
1. Post-evaluation for verification of conformity of the Execution Project with DIA, when DIA was issued, and the EIS was prepared for the Previous Studies or pre-project phase
2. General post-evaluation, that includes monitoring and auditing everywhere in the world
EIA POST-EVALUATION The specific case of Portugal
Environmental Impacts @ MRPartidário
1. Post-evaluation for verification of conformity of the Execution Project with DIA
RECAPE - Relatório de Conformidade Ambiental
do Projecto de Execução com a DIA Report on the Environmental Conformity of the
Execution Project with DIA
EIA POST-EVALUATION The specific case of Portugal
Environmental Impacts @ MRPartidário
The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again.
EIA POST-EVALUATION The specific case of Portugal
The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again.
Screening
Scoping
EIS preparation
Review
Decision - DIA
Post-evaluation
The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again.
Review
Decision - DIA
EIS in Execution Project phase
Construction
The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again.Post-evaluation
The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again.
RE C AP E
EIS in Previous Studies or pre-project phase The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again.
Review
Decision - DIA
Review of RECAPE
Decision
Construction
The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again.Post-evaluation
Environmental Impacts @ MRPartidário
Monitoring Report
Objective: document and present the results of monitoring Timing of the report is established in DIA It should follow the Monitoring Plan esyablished in DIA or RECAPE
Environmental Impacts @ MRPartidário
I – Introduction a. Identification and monitoring objectives; b. Scope (environmental factors, spatial and time limits for monitoring); c. Legal framework; d. Struture of monitoring report; e. Technical authorship. II – Background a) Reference to EIS, DIA, and Monitoring Plan in RECAPE, previous MR
and previous decisions of the EIA authority; b) References to the adoption of measures to prevent or reduce impacts
that are being monitored. Timing for the adoption of such measures in relation to monitoring;
c) References to possible claims or conflicts concerning the environmental factors that are being monitored.
Monitoring Report structure
Environmental Impacts @ MRPartidário
III – Description of Monitoring Programmes (for each environmental factor)
a) Measurements and registry parameters. Sampling places, measurement and registry;
b) Data collection methods and equipment; c) Data treatment methods, d) Data relationship with the characteristics of the project and
with the environmental context; e) Data evaluation criteria.
Monitoring Report structure (cont.)
Environmental Impacts @ MRPartidário
Monitoring Report structure (cont.)
IV – Results of Monitoring Programmes (for each environmental factor)
a) Results obtained; b) Discussion, interpretation and evaluation of results in face of the criteria
defined; c) Effectiveness assessment of the adopted measures to prevent or reduce the
impacts that are the object of monitoring; d) Comparison of EIA predictions, including, when aplicable, the validation and
calibration of prediction models. V – Conclusions VI – Annexes