ELENA PROJECTPlanning H- source

Evolution

N. GILBERT

End LS1

Bldg 393

Kicker pltf

H- ??

March 2012

Evolution of the situation• LS1 prolonged by 2 months• Annexed building start was delayed• Consequently kicker platform postponed• Planning magnet too short (prototype phase necessary)

• H- : 2014 period (1/3 – 30/11) moved to 2015

End LS1

Bldg 393

Kicker pltf

H-