Essex Corridor at the Superblockand Pioneer Hall Renovation Update
HSD Customer Advisory MeetingApril 9, 2019
Location Map
2
PioneerHall
North Essex Corridor
Pioneer Hall Renovation Update
3
• 256,500 square foot facility• 756 Beds• Community and Study Lounges• 850 Seat Dining Hall Serving Entire
Superblock• HRL Administrative and support
areas
Pioneer Hall Renovation Update
4
The former footprint
November 2018
Pioneer Hall Renovation Update
5
• On schedule for a June 7th
substantial completion of construction.
• Furniture & equipment installation June-July.
• First occupants move in early August.
• Open fall semester.
Pioneer Hall Renovation Update
6
• Interior finish work underway on residential floors: carpet, paint, ceramic tile, ceiling grid.
• Kitchen equipment installation begins in the next few weeks.
• Roofing finishing this spring.• Site work begins this spring.
Essex Corridor Project Extents
7
NorthHarvard-Essex CorridorAt Superblock
Essex Corridor Project Rationale• Provide fire truck access to interior of
superblock area• Improve student experience• Improve circulation through the superblock• Accommodate increased pedestrian traffic at
new Pioneer Hall dining facility• Revise crosswalks at Harvard Street and Oak
Street• Improve Paratransit access
8
Essex Corridor Design
9
Essex Corridor Design
10
Essex Corridor Schedule
11
Overall schedule April 22nd – August 16th
• April 22nd sports courts closed and will be incorporated into Pioneer Hall construction site fence.
• May 20th all sidewalks closed within the superblock, detours in place.
Essex Corridor Construction Impacts
12
Phase I: April 22nd
• Pioneer Hall site fence is modified to capture sports courts area
• Utility work begins• Circulation through
superblock still open
Essex Corridor Construction Impacts
13
Phase II: May 20th• All superblock
sidewalks closed• Mass excavation
begins• Main entries to
residence halls remain accessible
• Circulation to/from CSC and Health Sciences via Fulton Street or Delaware Street
Essex Corridor Construction Impacts
14
Essex Corridor Construction Impacts
15
Trees:• 39 trees to be
removed• 37 existing trees in
Essex corridor to remain
• 75 new trees
Other Projects in the area:
16
• Health Sciences Education Center – December 2019• MHealth Hospital Addition – New entrance August 2019• Oak Street closure at Delaware Street for storm sewer
repair (City project) - summer 2019
Review Communication Process
17
‐ Existing Bi‐Monthly (every 2 weeks) Project Newsletters for Pioneer Hall and HSEC.
‐ Notifications of Large Scale Impacts through University Relations and University Services.
‐ Contact the Call Center at 4‐2900 for issues.
Audience Questions