ADBADBFIDIC Training FIDIC Training
8-10 June 20048-10 June 2004ManilaManila
FIDIC FIDIC Contracts for Construction WorksContracts for Construction Works
and and Dispute Resolution Mechanisms Dispute Resolution Mechanisms
in Project Administrationin Project Administration
Gwyn OwenGwyn OwenBSc MSc CEng FICE FConsE FCIArbBSc MSc CEng FICE FConsE FCIArb
Chartered Arbitrator, Adjudicator, MediatorChartered Arbitrator, Adjudicator, Mediatorwww.gwynowen.comwww.gwynowen.com
ContentsContents
IntroductionIntroduction FIDIC DocumentsFIDIC Documents RiskRisk ProcurementProcurement StrategyStrategy First 100 daysFirst 100 days ResponsibilitiesResponsibilities Nominated s/cNominated s/c Staff & labourStaff & labour
Plant & MaterialsPlant & Materials CommencementCommencement DelaysDelays Taking OverTaking Over MeasurementMeasurement GuaranteesGuarantees ClaimsClaims Short FormShort Form DisputesDisputes
FIDIC FIDIC AN INTRODUCTIONAN INTRODUCTION
Founded in 1913Founded in 1913 Expanded in 1945 to include 40 national Expanded in 1945 to include 40 national
associationsassociations Published first Conditions of Contract in Published first Conditions of Contract in
19571957 In 2004 has 64 member associationsIn 2004 has 64 member associations Headquarters in SwitzerlandHeadquarters in Switzerland Web Site : www.fidic.orgWeb Site : www.fidic.org
FIDIC FIDIC AN INTRODUCTIONAN INTRODUCTION
Pre 1957 – no internationally Pre 1957 – no internationally recognised contract conditionsrecognised contract conditions
First “red book” based on UK ICE First “red book” based on UK ICE conditions conditions
FIDIC has international committees FIDIC has international committees to improve contracts to improve contracts
FIDIC DocumentsFIDIC Documents
Old “rainbow books” needed revisionOld “rainbow books” needed revision Changes within International Projects & Changes within International Projects &
ContractingContracting StandardisationStandardisation Clauses to meet current practiceClauses to meet current practice Update “Engineer” Update “Engineer” Introduce “Disputes Adjudication Board” Introduce “Disputes Adjudication Board”
Contract Documents 1999Contract Documents 1999
Conditions of Contract for Conditions of Contract for Construction (Red Book)Construction (Red Book)
Conditions of Contract for Plant & Conditions of Contract for Plant & Design Build (Yellow Book)Design Build (Yellow Book)
Conditions of Contract for EPC Conditions of Contract for EPC Turnkey Projects (Silver Book)Turnkey Projects (Silver Book)
Short Form of Contracts (Green Short Form of Contracts (Green Book)Book)
FIDIC Contracts FIDIC Contracts What’s Changed?What’s Changed?
Simple LanguageSimple Language• 20 Clauses & 163 Sub Clauses20 Clauses & 163 Sub Clauses
Engineer instead of Employer’s Engineer instead of Employer’s Representative Cl.1.1.2.4Representative Cl.1.1.2.4
Employer's Claims Cl.2.5Employer's Claims Cl.2.5 Contractor’s Claims Cl.20.1Contractor’s Claims Cl.20.1 Value Engineering Cl.13.2Value Engineering Cl.13.2 QUALITY & PROCEDURES: QUALITY & PROCEDURES:
• Cl.4.9, 4.18, 6.7, 8.3, 13.2 & 13.3Cl.4.9, 4.18, 6.7, 8.3, 13.2 & 13.3
FIDIC Document FormatFIDIC Document Format
AcknowledgementsAcknowledgements Foreword & ChartsForeword & Charts General ConditionsGeneral Conditions DAB ConditionsDAB Conditions Guidance NotesGuidance Notes Forms of AgreementForms of Agreement Appendix to TenderAppendix to Tender
FIDIC Document UsageFIDIC Document UsageConditions of Contract for Conditions of Contract for
ConstructionConstruction
Works designed by Employer or Works designed by Employer or EngineerEngineer
Contractor Constructs in accordance Contractor Constructs in accordance with designs providedwith designs provided
May include some design elementsMay include some design elements
FIDIC Document UsageFIDIC Document UsageConditions of Contract for Conditions of Contract for
Plant & Design BuildPlant & Design Build
Electrical & Mechanical PlantElectrical & Mechanical Plant May include building and engineeringMay include building and engineering Design & Execution of worksDesign & Execution of works Contractor designs and constructs in Contractor designs and constructs in
accordance with Employer’s Requirementsaccordance with Employer’s Requirements Engineer AdministersEngineer Administers
Plant & Design BuildPlant & Design Build
General Comments:General Comments:• Contractor will economiseContractor will economise• Employer will superviseEmployer will supervise• No good for Employer VariationsNo good for Employer Variations• Good for Lump SumGood for Lump Sum• Design SavingsDesign Savings• Employer responsible for ER errorsEmployer responsible for ER errors• Risk SharedRisk Shared
FIDIC Document UsageFIDIC Document UsageConditions of Contract for Conditions of Contract for
EPC/Turnkey ProjectsEPC/Turnkey Projects
Process or Power PlantProcess or Power Plant Infrastructure ProjectsInfrastructure Projects High Degree of CertaintyHigh Degree of Certainty Contractor has total responsibility for Contractor has total responsibility for
Design & ExecutionDesign & Execution Administered by EmployerAdministered by Employer
EPC/TurnkeyEPC/Turnkey
General CommentsGeneral Comments• Not suitable when:Not suitable when:
No time to tenderNo time to tender Much underground worksMuch underground works If Employer wishes to superviseIf Employer wishes to supervise If payments need to be administeredIf payments need to be administered
FIDIC Document UsageFIDIC Document UsageShort Form of ContractShort Form of Contract
Small capital value projectsSmall capital value projects Simple contentSimple content Contractor constructs to Employer’s Contractor constructs to Employer’s
designsdesigns No “Particular Conditions”No “Particular Conditions” No “Impartial” EngineerNo “Impartial” Engineer
FIDIC Document UsageFIDIC Document UsageCOMMUNICATIONSCOMMUNICATIONS
Cl.1.3: Cl.1.3: • Approvals, Certificates, Consents, Approvals, Certificates, Consents,
Determinations, Notices, Requests Determinations, Notices, Requests In WritingIn Writing DeliveredDelivered Not be unreasonably withheld or Not be unreasonably withheld or
delayeddelayed CopiesCopies
RISKRISK
ALLOCATION OF RISKALLOCATION OF RISK
Scope / Cost of ChangeScope / Cost of Change
CONTRACTUAL RISKSCONTRACTUAL RISKS
All contracts contain risksAll contracts contain risks FIDIC allocates responsibilitiesFIDIC allocates responsibilities Key Requirement:Key Requirement:
o Understand General ConditionsUnderstand General Conditionso Understand Particular ConditionsUnderstand Particular Conditionso Set out responsibilitiesSet out responsibilities
RISK OVERVIEWRISK OVERVIEW Contractual Risk Overview: Contractual Risk Overview:
o StrategyStrategyo IdentifyIdentifyo EvaluateEvaluateo MitigateMitigateo Plan ResponsePlan Responseo ReportReporto ManagementManagemento Close out reviewClose out review
CLAIMS RISKS LOCAL LAWSCLAIMS RISKS LOCAL LAWS
Incorporate provisions of local laws Incorporate provisions of local laws into Particular Conditionsinto Particular Conditions
FIDIC Guidance Notes give general FIDIC Guidance Notes give general adviceadvice
Complex task Complex task
CONTRACTUAL RISKSCONTRACTUAL RISKS
Cl.1.5 Priority of DocumentsCl.1.5 Priority of Documents Employer’s Documents have priorityEmployer’s Documents have priority Care in Prequalification PDB & EPCT – note that Care in Prequalification PDB & EPCT – note that
Financial Risk for design with Contractor but Financial Risk for design with Contractor but resolution will be in favour of Employerresolution will be in favour of Employer
““Contract Agreement” is high priority – Contract Agreement” is high priority – Commencement Date binding under Cl.1.1.3.2 & Commencement Date binding under Cl.1.1.3.2 & 8.18.1
Cl.3.3 PDB & Cons empower Engineer to make Cl.3.3 PDB & Cons empower Engineer to make Decisions – EPC no such authorityDecisions – EPC no such authority
FIDIC RELATIONSHIPS FIDIC RELATIONSHIPS
CONTRACTUAL RISKSCONTRACTUAL RISKS
Cl.1.9 DrawingsCl.1.9 Drawings Cl.2.1 SiteCl.2.1 Site Cl.4.7 Setting OutCl.4.7 Setting Out Cl.4.12 Cl.4.12
UnforeseeableUnforeseeable Cl.4.24 FossilsCl.4.24 Fossils Cl.7.4 TestingCl.7.4 Testing Cl.8.4 EoTCl.8.4 EoT
Cl.8.4 Adverse Cl.8.4 Adverse Climatic ConditionsClimatic Conditions
Cl.13.7 LegislationCl.13.7 Legislation Cl.13.8 Changes in Cl.13.8 Changes in
CostCost Cl.14.8 Delayed Cl.14.8 Delayed
paymentspayments Cl.19.4 Force Cl.19.4 Force
MajeureMajeure
Contract SelectionContract SelectionBasic Principles – Red BookBasic Principles – Red Book
Design by EmployerDesign by Employer Works to be Re-MeasuredWorks to be Re-Measured Employer appoints EngineerEmployer appoints Engineer Engineer can vary the works – but Engineer can vary the works – but
not change the Contractnot change the Contract Engineer’s “Determinations” Cl.3.5Engineer’s “Determinations” Cl.3.5 DAB appointed within 28 daysDAB appointed within 28 days
Contract SelectionContract SelectionBasic Principles – Red BookBasic Principles – Red Book
Additional Documents – Cl.1.5 Additional Documents – Cl.1.5 PriorityPriority
Importance of Particular ConditionsImportance of Particular Conditions• PCC priority over GCPCC priority over GC• PCC provides all relevant conditions and PCC provides all relevant conditions and
LawLaw• Contradictions between documentsContradictions between documents
BoQ – re-measured worksBoQ – re-measured works
Contract SelectionContract SelectionBasic Principles – Yellow BookBasic Principles – Yellow Book
Employers RequirementsEmployers Requirements Contractor Designs & BuildsContractor Designs & Builds ER errors – Employer’s riskER errors – Employer’s risk Fixed sum contractFixed sum contract Administered by EngineerAdministered by Engineer Variations by EngineerVariations by Engineer Cl.5 & 12 differ from Red BookCl.5 & 12 differ from Red Book
PROCUREMENTPROCUREMENT
PROCUREMENT PROCEDUREPROCUREMENT PROCEDURE
Establish StrategyEstablish Strategy Procurement methodProcurement method Form of TenderForm of Tender Time SchedulesTime Schedules
PrequalifyPrequalify InvitationInvitation DocumentsDocuments AnalysisAnalysis SelectionSelection
NotifyNotify
PROCUREMENT PROCEDUREPROCUREMENT PROCEDURE
Prepare tender DocumentsPrepare tender Documents IssueIssue Site VisitSite Visit QuestionsQuestions Submission & OpeningSubmission & Opening AdjudicationAdjudication
PROCUREMENT PROCEDUREPROCUREMENT PROCEDURE
Award ContractAward Contract Issue Letter of AcceptanceIssue Letter of Acceptance Performance SecurityPerformance Security Contract AgreementContract Agreement Notify unsuccessful tenderersNotify unsuccessful tenderers
PROJECT STRATEGYPROJECT STRATEGYDefinitionsDefinitions
General Provisions Cl.1General Provisions Cl.1• Definitions of wordsDefinitions of words• Persons include corporations & other Persons include corporations & other
legal entitieslegal entities• Letter of AcceptanceLetter of Acceptance• Employer’s Requirements (YB)Employer’s Requirements (YB)• Goods – ContractorGoods – Contractor
Cl.1.3 Cl.1.3
PROJECT STRATEGYPROJECT STRATEGYDefinitionsDefinitions
Cl.1.4 Law & LanguageCl.1.4 Law & Language• CompatibilityCompatibility
Cl.1.9 Cl.1.9 • Delays to drawings (RB) Delays to drawings (RB) • Errors to ER (YB) Errors to ER (YB) • Confidentiality (SB)Confidentiality (SB)
PROJECT STRATEGYPROJECT STRATEGYProject Control IssuesProject Control Issues
Cl.1.9 Delay to detailsCl.1.9 Delay to details Cl.2.4 Finance DetailsCl.2.4 Finance Details Cl.2.5 Employers ClaimsCl.2.5 Employers Claims Cl.3.3 Instructions by EngineerCl.3.3 Instructions by Engineer Cl.4.1 Method StatementCl.4.1 Method Statement Cl.4.21 ReportingCl.4.21 Reporting Cl.8.3 ProgrammeCl.8.3 Programme
PROJECT STRATEGYPROJECT STRATEGYProject Control IssuesProject Control Issues
Cl.12.1 MeasurementCl.12.1 Measurement Cl.13 Variations & Value EngineeringCl.13 Variations & Value Engineering Cl.14 PaymentsCl.14 Payments
• Planning Planning • Funding & BudgetFunding & Budget• Disbursement approvalDisbursement approval
Cl.18 InsurancesCl.18 Insurances Cl.20 Contractor’s Claims / RecordsCl.20 Contractor’s Claims / Records
FIDIC -FIDIC -THE FIRST 100 DAYSTHE FIRST 100 DAYS
AN INTRODUCTIONAN INTRODUCTION
The First Hundred Days of a New The First Hundred Days of a New FIDIC contractFIDIC contract
Pre Award PhasePre Award Phase Award to Commencement DateAward to Commencement Date Commencement Date to CD + 28 Commencement Date to CD + 28
DaysDays
THE FIRST 100 DAYSTHE FIRST 100 DAYS
Pre Award Check List Pre Award Check List GeneralGeneral
Document negotiated changesDocument negotiated changes Prioritise and sign changes – Cl 1.5Prioritise and sign changes – Cl 1.5 Agree terms of insurances – Cl 18.2Agree terms of insurances – Cl 18.2 Agree DAB membershipAgree DAB membership Confirm communication and Confirm communication and
addresses – Cl 1.3addresses – Cl 1.3
Pre Award Checklist Pre Award Checklist Engineer’s Duties & AuthorityEngineer’s Duties & Authority
Employer names EngineerEmployer names Engineer Employer’s constraints on Engineer’s Employer’s constraints on Engineer’s
Authority – Cl 3.1Authority – Cl 3.1 Delegation of Engineer’s Authority to Delegation of Engineer’s Authority to
Resident Engineer – Cl 3.2Resident Engineer – Cl 3.2 Engineer’s Determination – Cl 3.5Engineer’s Determination – Cl 3.5
Pre Award ChecklistPre Award ChecklistEmployer’s RisksEmployer’s Risks
Right of Access - Cl 2.1Right of Access - Cl 2.1 Provision of Specifications – Cl 1.8Provision of Specifications – Cl 1.8 Supply of Drawings – Cl 1.9Supply of Drawings – Cl 1.9
Award to Commencement DateAward to Commencement Date
Formal Letter of Acceptance signed – Formal Letter of Acceptance signed – Cl 1.1.1.3Cl 1.1.1.3
Contract Agreement - Cl 1.1.1.2, 1.6 Contract Agreement - Cl 1.1.1.2, 1.6 Date on which the Contract becomes Date on which the Contract becomes
legally bindinglegally binding Instruction of Commencement Date – Instruction of Commencement Date –
Engineer Cl 8.1 – 7 days noticeEngineer Cl 8.1 – 7 days notice Time for Completion – Cl 1.1.3.3Time for Completion – Cl 1.1.3.3
Award to Commencement Date Award to Commencement Date Check ListCheck List
Contractor’s obligationsContractor’s obligations
Performance Security – Cl 4.2Performance Security – Cl 4.2 Consent for sub-contractorsConsent for sub-contractors Commencement of sub-contract wksCommencement of sub-contract wks Compliance with applicable laws, etc Compliance with applicable laws, etc
prior to Commencementprior to Commencement
Award to Commencement Date Award to Commencement Date Check ListCheck List
Employer’s obligationsEmployer’s obligations
Obtaining planning, zoning etc Obtaining planning, zoning etc permits for the Permanent Works – Cl permits for the Permanent Works – Cl 1.131.13
Ensuring that the Contractor will Ensuring that the Contractor will have right of access to and have right of access to and possession of all parts of the Sitepossession of all parts of the Site
Commencement Date to + 28 Commencement Date to + 28 Employer’s ActionsEmployer’s Actions
Right of access & possession – Cl 2.1Right of access & possession – Cl 2.1 Ensuring Employer’s personnel are Ensuring Employer’s personnel are
aware of responsibilities – Cl 2.3aware of responsibilities – Cl 2.3 Preparing evidence of Employer’s Preparing evidence of Employer’s
financial arrangements – Cl 2.4financial arrangements – Cl 2.4 Provision of copies of the Contract Provision of copies of the Contract
and Drawings Cl 1.8 & 1.9and Drawings Cl 1.8 & 1.9
Commencement Date to + 28 Commencement Date to + 28 Engineer’s ResponsibilitiesEngineer’s Responsibilities
Advising Contractor of Engineer’s Advising Contractor of Engineer’s Authority and Delegations – Cl 3.2Authority and Delegations – Cl 3.2
Ensuring assistants are suitably Ensuring assistants are suitably qualifiedqualified
Providing reference survey points, Providing reference survey points, lines and necessary data – Cl 4.7lines and necessary data – Cl 4.7
Commencement Date to + 28 Commencement Date to + 28 Contractor’s ResponsibilitiesContractor’s Responsibilities
General obligations – adequacy, General obligations – adequacy, stability & safety – Cl 4.1 stability & safety – Cl 4.1
Provide Performance Security prior to Provide Performance Security prior to access to Site – Cl 4.2access to Site – Cl 4.2
Submit name of Contractor’s Submit name of Contractor’s Representative for consent – Cl 4.3Representative for consent – Cl 4.3
Commencement Date to + 28 Commencement Date to + 28 Contractor’s ResponsibilitiesContractor’s Responsibilities
Give notice of any delegation of CR’s Give notice of any delegation of CR’s responsibilitiesresponsibilities
Obtain consent for sub-contractors Obtain consent for sub-contractors not named in Contract – Cl 4.4not named in Contract – Cl 4.4
Give notice of commencement of Give notice of commencement of sub-contract worksub-contract work
Commencement Date to + 28 Commencement Date to + 28 Contractor’s ResponsibilitiesContractor’s Responsibilities
Provide details of suppliers not Provide details of suppliers not named in Contract (see Cl 4.16) named in Contract (see Cl 4.16)
Make objections to any Nominated Make objections to any Nominated Sub-contractors who the Contractor Sub-contractors who the Contractor does not wish to employdoes not wish to employ
Submit detailed time programme Submit detailed time programme within 28 days of receipt of the within 28 days of receipt of the notice to commence – Cl 8.3notice to commence – Cl 8.3
Commencement Date to + 28 Commencement Date to + 28 Contractor’s ResponsibilitiesContractor’s Responsibilities
Give notice of probable future events Give notice of probable future events or circumstances which may increase or circumstances which may increase price or delay completionprice or delay completion
Confirm working hours – Cl 6.5 Confirm working hours – Cl 6.5 Site health & safety facilities – Cl 6.7Site health & safety facilities – Cl 6.7 Appoint Accident Prevention OfficerAppoint Accident Prevention Officer
RESPONSIBILITIESRESPONSIBILITIES
Responsibilities Responsibilities EmployerEmployer
Cl.2Cl.2• Provides Access to the Site Provides Access to the Site
(not access & other areas – Cl.14.15 & 14.23)(not access & other areas – Cl.14.15 & 14.23)
• Assists Contractor with PermitsAssists Contractor with Permits• Financial ArrangementsFinancial Arrangements
See Variations & Cl.16.1 Suspension (strike out??)See Variations & Cl.16.1 Suspension (strike out??)
• Notice of ClaimsNotice of Claims Appoints the Engineer Cl.3.1Appoints the Engineer Cl.3.1
Responsibilities Responsibilities EmployerEmployer
Cl.14.7 make Payments !!Cl.14.7 make Payments !! Cl.20.2 appointment of DAB Cl.20.2 appointment of DAB
membersmembers
Responsibilities Responsibilities EngineerEngineer
Exercises stated authorityExercises stated authority Employer’s Approval – PCEmployer’s Approval – PC When he exercises specific authority When he exercises specific authority
deemed to have Employer’s approvaldeemed to have Employer’s approval Acts for EmployerActs for Employer
• Cl.3.5 – “Fair Determination” Cl.3.5 – “Fair Determination”
Responsibilities Responsibilities EngineerEngineer
Cl.3Cl.3• Employer undertakes not to impose Employer undertakes not to impose
further constraints (Breach of Contract)further constraints (Breach of Contract)• No authority to amend contractNo authority to amend contract• Acts for EmployerActs for Employer• No authority to relieve the parties of No authority to relieve the parties of
duties or obligations etc.duties or obligations etc.
Responsibilities Responsibilities EngineerEngineer
Cl.3Cl.3• Delegation – except Cl.3.5Delegation – except Cl.3.5• Instructions in writingInstructions in writing
Oral – confirmation by contractor – writtenOral – confirmation by contractor – written
• Employer instructions to EngineerEmployer instructions to Engineer• Determination Determination
Consult – agreement – fair determinationConsult – agreement – fair determination Give notice Give notice Give effect unless Cl.20Give effect unless Cl.20
Responsibilities Responsibilities EngineerEngineer
Cl.4.1 Method StatementsCl.4.1 Method Statements Cl.8.1 Give Commencement NoticeCl.8.1 Give Commencement Notice Cl.8.6 Rate of ProgressCl.8.6 Rate of Progress Cl.12.1 MeasurementCl.12.1 Measurement Cl.13.1 VariationsCl.13.1 Variations Cl.14.6 Interim Payment CertificatesCl.14.6 Interim Payment Certificates Cl.20.1 Records / DeterminationCl.20.1 Records / Determination
Responsibilities Responsibilities ContractorContractor
Cl.4Cl.4• Execute & Complete the Works Execute & Complete the Works
Cl.8.1 due expedition & without delayCl.8.1 due expedition & without delay Adequacy & safetyAdequacy & safety Method StatementMethod Statement Fit for purposeFit for purpose
• Performance BondPerformance Bond• Engineer’s Approval of RepresentativeEngineer’s Approval of Representative• May delegateMay delegate• Fluent in languageFluent in language• Sub Contractor approval Sub Contractor approval
Responsibilities Responsibilities ContractorContractor
Setting Out to lines & levels of Setting Out to lines & levels of EngineerEngineer
Quality Assurance Quality Assurance • Details in SpecificationDetails in Specification• ProceduresProcedures• Compliance documentsCompliance documents
Responsibilities Responsibilities ContractorContractor
Site dataSite data• Costs includedCosts included• RiskRisk• InspectionsInspections• All relevant data – obligationAll relevant data – obligation• Care in Tender – failure to provideCare in Tender – failure to provide
Sufficiency of Contract AmountSufficiency of Contract Amount
Responsibilities Responsibilities ContractorContractor
Unforeseeable Physical ConditionsUnforeseeable Physical Conditions• Excludes climatic conditionsExcludes climatic conditions
Cl.8.4 & 17.3hCl.8.4 & 17.3h
• Extension of timeExtension of time• Payment of cost Payment of cost
(see Cl.1.1.4.3 includes off site)(see Cl.1.1.4.3 includes off site)
• No profit No profit (as a general rule not included where risk is (as a general rule not included where risk is
not the fault of either party)not the fault of either party)
Responsibilities Responsibilities ContractorContractor
Transport to siteTransport to site Protection of the EnvironmentProtection of the Environment
• EmissionsEmissions• Surface dischargesSurface discharges• EffluentEffluent• Local LawLocal Law
Responsibilities Responsibilities ContractorContractor
Progress ReportProgress Report Monthly – 6 copiesMonthly – 6 copies
• See also (Cl.4.9 procedures) and:See also (Cl.4.9 procedures) and:• Cl. 6.7 Accident RecordsCl. 6.7 Accident Records• Cl. 6.10 PersonnelCl. 6.10 Personnel• Cl.14.3 Application for paymentCl.14.3 Application for payment• Cl.20.1 Contemporary records Cl.20.1 Contemporary records
Responsibilities Responsibilities ContractorContractor
Progress Report:Progress Report:• ChartsCharts• PhotographsPhotographs• Manufacturing reportManufacturing report• PersonnelPersonnel• QA documentsQA documents• Claims Cl.2.5 & 20.1Claims Cl.2.5 & 20.1• Safety statisticsSafety statistics• ProgressProgress
Responsibilities Responsibilities ContractorContractor
SecuritySecurity Staff & LabourStaff & Labour
• Facilities / Health & SafetyFacilities / Health & Safety Tests on Completion Cl.9.1Tests on Completion Cl.9.1 Value Engineering Cl.13.3Value Engineering Cl.13.3 Application for Payment Cl.14.3Application for Payment Cl.14.3 Contemporary records Cl.20.1Contemporary records Cl.20.1
Nominated Nominated SubcontractorsSubcontractors
Clause 5 Clause 5 Applies to Subcontractors and Applies to Subcontractors and
suppliers nominated by Employer or suppliers nominated by Employer or as instructed by the Engineer under as instructed by the Engineer under Cl.13Cl.13
Payment Cl.5.3Payment Cl.5.3
Nominated Nominated SubcontractorsSubcontractors
Grounds to object Cl.5.2Grounds to object Cl.5.2• Reasonable ObjectionReasonable Objection• Supporting detailsSupporting details• Lack of competence, recourses, financial Lack of competence, recourses, financial
strengthstrength• Lack of indemnityLack of indemnity• Lack of obligations and liabilityLack of obligations and liability
Staff & LabourStaff & Labour
Clause 6Clause 6 Engagement of Staff & LabourEngagement of Staff & Labour
• Payment, housing feeding & transportPayment, housing feeding & transport• Cl.8.4d & 13.7Cl.8.4d & 13.7
Rates of pay & conditionsRates of pay & conditions NO Poaching !! (Cl.6.3)NO Poaching !! (Cl.6.3)
Staff & LabourStaff & Labour
Labour Laws (including immigration)Labour Laws (including immigration) Working Hours (days of rest)Working Hours (days of rest) Facilities (including Employer’s Facilities (including Employer’s
Personnel)Personnel) Health & SafetyHealth & Safety
• Medical staff & facilitiesMedical staff & facilities• Accident prevention officerAccident prevention officer• RecordsRecords
Staff & LabourStaff & Labour
Cl.4.3 – Contractor’s RepresentativeCl.4.3 – Contractor’s Representative Cl.6.8 – Superintendence (Language)Cl.6.8 – Superintendence (Language) Personnel – qualified, skilled, Personnel – qualified, skilled,
experiencedexperienced Records monthly (cl.4.9 procedures) Records monthly (cl.4.9 procedures)
PLANT PLANT & MATERIALS& MATERIALS
Plant MaterialsPlant Materials& Workmanship& Workmanship
Cl.7Cl.7 Execution of works as specifiedExecution of works as specified
• Recognised good practiceRecognised good practice• Proper facilitiesProper facilities• Non hazardous materialsNon hazardous materials
SamplesSamples• For consentFor consent• Labelled origin / intended useLabelled origin / intended use
Plant MaterialsPlant Materials& Workmanship& Workmanship
Inspection:Inspection:• Access to locations of natural materialsAccess to locations of natural materials• Place of manufacturePlace of manufacture• Provide access, facilities, permissions, safety Provide access, facilities, permissions, safety
equipmentequipment• Give notice and provide opportunityGive notice and provide opportunity• Testing – may proceed after noticeTesting – may proceed after notice• Delay claimDelay claim• Test Reports & Certificates Test Reports & Certificates
Plant MaterialsPlant Materials& Workmanship& Workmanship
Rejection – Retest – costs Cl.2.5Rejection – Retest – costs Cl.2.5 Remedial worksRemedial works Ownership of Plant & MaterialsOwnership of Plant & Materials
• Local lawLocal law• When deliveredWhen delivered• When contractor entitled to payment When contractor entitled to payment
under Cl.8.10 (suspension)under Cl.8.10 (suspension) RoyaltiesRoyalties
COMMENCEMENTCOMMENCEMENT& DELAYS& DELAYS
Commencement, Delays Commencement, Delays & Suspension& Suspension
Contract becomes effective when Contract becomes effective when Letter of Acceptance has been Letter of Acceptance has been received by Contractorreceived by Contractor
Cl.8.1 Commencement DateCl.8.1 Commencement Date• Engineer Engineer SHALLSHALL• Contractor Contractor SHALLSHALL
Engineer determines the date or 42 Engineer determines the date or 42 days after the LA days after the LA
CompletionCompletion
Cl.8.2 Fundamental obligation to Cl.8.2 Fundamental obligation to complete within Time for Completioncomplete within Time for Completion• Includes all of WorksIncludes all of Works• Includes all testsIncludes all tests• See Cl.10.1See Cl.10.1
ProgrammeProgramme
Programme of Works Cl.8.3 Programme of Works Cl.8.3 • Within 28 daysWithin 28 days• Specific requirements of programmeSpecific requirements of programme• Methods of executionMethods of execution• Details of personnel & equipmentDetails of personnel & equipment
Engineer does not approve (21 days)Engineer does not approve (21 days) Employer may rely on programmeEmployer may rely on programme
ProgrammeProgramme
Specific, Probable, Future eventsSpecific, Probable, Future events Revisions to programmeRevisions to programme Monthly progress chartsMonthly progress charts Engineer may request a revised Engineer may request a revised
programmeprogramme
Extension of TimeExtension of Time
Contractor Contractor SHALLSHALL be entitled be entitled• Not dependant upon further decisionNot dependant upon further decision• If no extension then “time at large”If no extension then “time at large”• VariationVariation• Sub Clause giving delay Sub Clause giving delay • Exceptionally adverse climatic conditionsExceptionally adverse climatic conditions• Unforeseeable shortages personnel & goodsUnforeseeable shortages personnel & goods• Employer’s delayEmployer’s delay
Cl.20.1Cl.20.1 Cl.3.5 Engineer’s DeterminationCl.3.5 Engineer’s Determination
Extension of TimeExtension of Time
Cl.20.1 & 3.5 give time limits to Cl.20.1 & 3.5 give time limits to Engineer to Determine – or Cl.13 Engineer to Determine – or Cl.13 shall not be unreasonably withheld or shall not be unreasonably withheld or delayeddelayed
Delays by authoritiesDelays by authorities
Rate of ProgressRate of Progress
Engineer may instruct submission of Engineer may instruct submission of revised programmerevised programme
Contractor to proceed with due expedition Contractor to proceed with due expedition and without delay and without delay
Delay DamagesDelay Damages• Failure to complete by due dateFailure to complete by due date• Delay damagesDelay damages• Limit of damagesLimit of damages
Suspension – Engineer may instructSuspension – Engineer may instruct
TESTS, DEFECTSTESTS, DEFECTS& TAKING OVER& TAKING OVER
Tests on CompletionTests on Completion Cl.9Cl.9
• Contractor shall give 21 days noticeContractor shall give 21 days notice• Tests carried out within 14 days of noticeTests carried out within 14 days of notice• Certified report Certified report
Delayed testsDelayed tests• Employer Cl.7.4 or 10.3 applyEmployer Cl.7.4 or 10.3 apply• Contractor to complete 21 days after noticeContractor to complete 21 days after notice
FailureFailure• RetestRetest• Cl.11.4Cl.11.4
Taking Over ResponsibilitiesTaking Over Responsibilities
Responsibilities under Financing Responsibilities under Financing AgreementAgreement• Proper use of fundsProper use of funds• Proper management of constructionProper management of construction• Final paymentFinal payment
Responsibilities under the Contract:Responsibilities under the Contract:• Before Taking OverBefore Taking Over• After Taking OverAfter Taking Over
Taking Over ResponsibilitiesTaking Over Responsibilities
Before Taking Over: Before Taking Over: • Take over on CompletionTake over on Completion• Tests on CompletionTests on Completion• Contractor’s request for TO CertificateContractor’s request for TO Certificate
Cl.10.1 The Employer Cl.10.1 The Employer SHALLSHALL take over take over when:when:• Works completedWorks completed• Tests completedTests completed• TO certificate issuedTO certificate issued
Employer’s Taking OverEmployer’s Taking Over
Cl.10Cl.10• TO Certificate issued when works completed and ready TO Certificate issued when works completed and ready
for intended purposefor intended purpose• Minor outstanding work may be completed after issue of Minor outstanding work may be completed after issue of
TOCTOC Contractor may apply for TOC within 14 days of Contractor may apply for TOC within 14 days of
Works being completeWorks being complete Sectional CompletionSectional Completion Engineer mayEngineer may
• Issue TOC Reject application giving reasonsIssue TOC Reject application giving reasons Failure of Engineer to issue TOC or rejectFailure of Engineer to issue TOC or reject
• Within 28 daysWithin 28 days• TOC deemed to be issuedTOC deemed to be issued
Employer’s Taking OverEmployer’s Taking Over
Sectional Taking OverSectional Taking Over• TestsTests• Cost due to STOCost due to STO• Delay Damages reduced after STO Delay Damages reduced after STO
Certificate issuedCertificate issued• Reduction in ratio of value of STO WorksReduction in ratio of value of STO Works• No difference to maximum damagesNo difference to maximum damages
Reinstatement of ground or surfaceReinstatement of ground or surface
Employer’s Taking OverEmployer’s Taking Over
Taking Over CertificateTaking Over Certificate• Appendix listing all minor defects Appendix listing all minor defects • Listing all works yet to be carried outListing all works yet to be carried out
Contractor responsible to carry out Contractor responsible to carry out repairs before end of Defects repairs before end of Defects Notification PeriodNotification Period
Defects LiabilityDefects Liability
Cl.11Cl.11• Provides procedures and responsibilities Provides procedures and responsibilities
under the Defects Notification Periodunder the Defects Notification Period• Works are accepted by Engineer on the Works are accepted by Engineer on the
issuance of Performance Certificateissuance of Performance Certificate
Defects LiabilityDefects Liability
Works & Documents completedWorks & Documents completed• Fair wear & tear acceptedFair wear & tear accepted• Complete all o/s work in TOCComplete all o/s work in TOC• Remedy defects & damage notified by the end Remedy defects & damage notified by the end
of the DNPof the DNP Remedy works at Contractor’s costRemedy works at Contractor’s cost Extension to DNPExtension to DNP
• Max 2 years, orMax 2 years, or• Suspension Cl.8.8 or 16.1Suspension Cl.8.8 or 16.1
Defects LiabilityDefects Liability
Failure to RemedyFailure to Remedy• Reasonable noticeReasonable notice• Carry out work himself or by othersCarry out work himself or by others• Contractor has no responsibilityContractor has no responsibility• Reduction in Contract PriceReduction in Contract Price• Recover all sums paid & costsRecover all sums paid & costs
RemovalRemoval• Further TestsFurther Tests• Right of accessRight of access• Contractor to searchContractor to search
Performance CertificatePerformance Certificate
Performance CertificatePerformance Certificate• Contractor’s obligations completeContractor’s obligations complete• Engineer to issueEngineer to issue• DateDate• Issue within 28 days of DNP expiryIssue within 28 days of DNP expiry• After submission of all documentationAfter submission of all documentation• All tests completeAll tests complete• All remedying works completeAll remedying works complete
Constitutes Acceptance of WorksConstitutes Acceptance of Works• Liability for fulfilment of obligationsLiability for fulfilment of obligations• Removal of equipment, rubbish etc…Removal of equipment, rubbish etc…• Contractor may be liable for latent defectsContractor may be liable for latent defects
Measurement, Evaluation Measurement, Evaluation & Variations& Variations
This clause only applies to Red BookThis clause only applies to Red Book Yellow Book Cl.12 deals with tests Yellow Book Cl.12 deals with tests
after completionafter completion Measurement by EngineerMeasurement by Engineer Standard method of measurement as Standard method of measurement as
specified in schedulesspecified in schedules
Measurement, Evaluation Measurement, Evaluation & Variations& Variations
Cl.12.3 Basis of evaluationCl.12.3 Basis of evaluation• Rates in contract will applyRates in contract will apply• New rates may be determinedNew rates may be determined
Qty changed more than 10%Qty changed more than 10% VariationVariation Not specifiedNot specified No appropriate rateNo appropriate rate
• Reasonable Cost & ProfitReasonable Cost & Profit Cl.12.4 CompensationCl.12.4 Compensation
Measurement, Evaluation Measurement, Evaluation & Variations& Variations
Under Yellow Book no such clausesUnder Yellow Book no such clauses Cl.13.3 DeterminationsCl.13.3 Determinations Means of measurement may be Means of measurement may be
necessarynecessary Payment schedule linked to Payment schedule linked to
“milestones” Cl.14.4“milestones” Cl.14.4
VariationsVariations
Cl.13.1 Engineer has the right to varyCl.13.1 Engineer has the right to vary• Prior to issue of TO certificatePrior to issue of TO certificate• List of variation inclusionsList of variation inclusions
Value Engineering Cl.13.2Value Engineering Cl.13.2• Development risk with ContractorDevelopment risk with Contractor• Savings 50/50Savings 50/50
Variation ProcedureVariation Procedure
Engineer requests proposal from Engineer requests proposal from ContractorContractor• Contractor responds with:Contractor responds with:
DescriptionDescription ProgrammeProgramme EvaluationEvaluation
• Work proceeds without delayWork proceeds without delay
Variation due to LegislationVariation due to Legislation
Local law at Base DateLocal law at Base Date Cl.20.1 claimCl.20.1 claim
• Extension of timeExtension of time• Payment of costPayment of cost
Contract Price Contract Price & Payment& Payment
Considerations:Considerations:• Payment schedulesPayment schedules• Disbursement approvalDisbursement approval• Particular ConditionsParticular Conditions• BudgetingBudgeting
Funding availabilityFunding availability Additional Costs / VariationsAdditional Costs / Variations
Contract Price Contract Price & Payment& Payment
Advance paymentAdvance payment• DesignDesign• MobilisationMobilisation• Funding facilitationFunding facilitation
Interim paymentsInterim payments• 56 days56 days
Final PaymentFinal Payment• 84 days84 days
Contract Price Contract Price & Payment& Payment
Aid funding requires:Aid funding requires:• Authority approvalAuthority approval• TimingTiming• VariationsVariations• Routine audit checksRoutine audit checks• Time to transfer fundsTime to transfer funds• Advance notice of changeAdvance notice of change
Contract Price Contract Price & Payment& Payment
Cl.14 requires prompt action within Cl.14 requires prompt action within time constraintstime constraints
Finance costs will lead to claimsFinance costs will lead to claims Alter Cl.14 by Particular Conditions to Alter Cl.14 by Particular Conditions to
suit funding authoritysuit funding authority
Contract Price Contract Price & Payment& Payment
Financial planning:Financial planning:• Check estimates & budgetsCheck estimates & budgets• Prepare draft payment schedulesPrepare draft payment schedules• Update estimates & programmeUpdate estimates & programme• Check fundingCheck funding• Cl.14.4 estimates each 90 daysCl.14.4 estimates each 90 days
Budget ForecastBudget Forecast
Engineer prepares for EmployerEngineer prepares for Employer• Regular intervalsRegular intervals• Updated budgetUpdated budget• Report of changesReport of changes
Data for report:Data for report:• Cl.2.4, 2.5, 3.5, 4.21, 8.3, 13.1, 13.3, Cl.2.4, 2.5, 3.5, 4.21, 8.3, 13.1, 13.3,
14.3, 13.8, 14.3, 14.6, 20.1, 20.4 14.3, 13.8, 14.3, 14.6, 20.1, 20.4
Contract Price Contract Price & Payment& Payment
Cl.14 Contract PriceCl.14 Contract Price• Measured and will vary – Red BookMeasured and will vary – Red Book• Fixed Lump Sum – Yellow BookFixed Lump Sum – Yellow Book• Fixed Lump Sum – Silver BookFixed Lump Sum – Silver Book• Lump Sum or Remeasure – Green BookLump Sum or Remeasure – Green Book
Advance PaymentAdvance Payment
Cl.14.2 Advance paymentCl.14.2 Advance payment• Interest free loan for mobilisationInterest free loan for mobilisation
GuaranteeGuarantee Application Cl.14.3Application Cl.14.3 Performance Security – Performance Security – approved by approved by
EmployerEmployer
• RepaymentRepayment Commence after when certificates >10%Commence after when certificates >10% Deductions 25% of each Certificate Deductions 25% of each Certificate
Interim PaymentInterim Payment
Cl.14.3 ApplicationCl.14.3 Application• 6 copies6 copies• In a form approved (Cl.4.9)In a form approved (Cl.4.9)• Cl.4.21Cl.4.21• List of items (a) – (g)List of items (a) – (g)• Note : Cl.20 items includedNote : Cl.20 items included
Interim PaymentInterim Payment
Cl.14.4 Schedule of payments:Cl.14.4 Schedule of payments:• Payment dates not recommended Payment dates not recommended • Engineer determination Cl.3.5Engineer determination Cl.3.5• Cross guaranteesCross guarantees• Milestones preferredMilestones preferred
Interim PaymentInterim Payment
Cl.14.6 Issue of IPCCl.14.6 Issue of IPC• Engineer determines Engineer determines FAIRLYFAIRLY• IPC IPC SHALLSHALL not be withheld not be withheld
Cl.14.7 PaymentCl.14.7 Payment• IPC paid within 56 days after Engineer IPC paid within 56 days after Engineer
receives Statementreceives Statement Cl.14.8 Interest on late payments Cl.14.8 Interest on late payments
Non PaymentNon Payment
Cl.16.1 SuspensionCl.16.1 Suspension• Engineer fails to certifyEngineer fails to certify• Employer does not provide Cl.2.4 detailsEmployer does not provide Cl.2.4 details• Non paymentNon payment• 21 days notice21 days notice
Cl.16.2 TerminationCl.16.2 Termination
Guarantees & BondsGuarantees & Bonds
Cl.4.2 Performance SecurityCl.4.2 Performance Security Contractor finance Contractor finance
• Guarantee by EmployerGuarantee by Employer• No Cl.8.1 notice before Guarantee No Cl.8.1 notice before Guarantee
Cl.14.2 Advance Payment GuaranteeCl.14.2 Advance Payment Guarantee
Risk & ResponsibilityRisk & Responsibility
Cl.17.1 Basis for IndemnityCl.17.1 Basis for Indemnity Cl.17.2 Full responsibility for Works & Cl.17.2 Full responsibility for Works &
Goods until TO CertificateGoods until TO Certificate Cl.17.3 Employer’s RisksCl.17.3 Employer’s Risks Cl.17.4 Compensation & Claims Cl.17.4 Compensation & Claims
InsuranceInsurance Cl.18Cl.18
• Employer to approve insurersEmployer to approve insurers• Agreed termsAgreed terms• CurrencyCurrency• Payments to be used to rectify lossPayments to be used to rectify loss• Cl.18.3 – Appendix minimum amount Cl.18.3 – Appendix minimum amount
Force MajeureForce Majeure
Basic Principles:Basic Principles:• Exceptional eventExceptional event• Not reasonably provided against Not reasonably provided against • Not reasonable to overcome / avoidNot reasonable to overcome / avoid• Not attributable to either partyNot attributable to either party• Beyond control of affected partyBeyond control of affected party
Force MajeureForce Majeure
Cl.19.1 DefinitionsCl.19.1 Definitions• (i) – (iv) man made(i) – (iv) man made
Cl.19.4 ConsequencesCl.19.4 Consequences• EoTEoT• Man made – costMan made – cost• Man made in country – costMan made in country – cost• Cl.19.6 TerminationCl.19.6 Termination
CLAIMS & CLAIMS & CONTRACTUAL CONTRACTUAL PROCEDURESPROCEDURES
CAUSES OF CLAIMS FOR CAUSES OF CLAIMS FOR CONTRACTORSCONTRACTORS
Unforeseeable ground conditionsUnforeseeable ground conditions Delayed drawingsDelayed drawings Delayed paymentDelayed payment Lack of possession of siteLack of possession of site Consequence of riskConsequence of risk SuspensionSuspension Force MajeureForce Majeure
CONTRACTOR’S CLAIM CONTRACTOR’S CLAIM PROCEDUREPROCEDURE
Clause 20.1Clause 20.1o Sets out Contractor procedureSets out Contractor procedureo Condition PrecedentCondition Precedento Not later than 28 daysNot later than 28 dayso Sets out Engineer procedureSets out Engineer procedure
CONTRACTOR’S CLAIM CONTRACTOR’S CLAIM PROCEDUREPROCEDURE
Contractor gives noticeContractor gives noticeo Within 28 daysWithin 28 days
Contractor keeps contemporary recordsContractor keeps contemporary recordso Engineer may monitorEngineer may monitoro Engineer may instruct further recordsEngineer may instruct further records
Fully detailed claim Fully detailed claim o Supporting documentsSupporting documentso Within 42 days of eventWithin 42 days of event
CAUSES OF CLAIMS FOR CAUSES OF CLAIMS FOR EMPLOYERSEMPLOYERS
Quality below SpecificationQuality below Specification Delay in Completion DateDelay in Completion Date Slow Rate of ProgressSlow Rate of Progress Defective MaterialsDefective Materials Failures of TestsFailures of Tests
EMPLOYER’S CLAIM EMPLOYER’S CLAIM PROCEDUREPROCEDURE
Employer gives noticeEmployer gives noticeo As soon as practicableAs soon as practicable
Contractor Receives NoticeContractor Receives Noticeo No obligation to respondNo obligation to respond
Engineer proceeds with Cl.3.5Engineer proceeds with Cl.3.5 Contractor can dispute if dissatisfiedContractor can dispute if dissatisfied Engineer’s determination applied to Engineer’s determination applied to
Certificate of PaymentCertificate of Payment
CONTEMPORARY RECORDSCONTEMPORARY RECORDS
Crucial for determination of claimCrucial for determination of claim Records for any future disputeRecords for any future dispute Contractor obliged to keep recordsContractor obliged to keep records Procedure for this work Procedure for this work Employer & Engineer to agree Employer & Engineer to agree
Engineer’s actionsEngineer’s actions
CONTRACTOR’S CLAIM CONTRACTOR’S CLAIM PROCEDUREPROCEDURE
Cl.20.1 continuing procedureCl.20.1 continuing procedure After 42 days:After 42 days:
o Claim submission is considered interimClaim submission is considered interimo Further monthly claimsFurther monthly claimso Final claim with 28 days of end of effectsFinal claim with 28 days of end of effects
CONTRACTOR’S CLAIM CONTRACTOR’S CLAIM PROCEDUREPROCEDURE
Engineer’s Response:Engineer’s Response:o Within 42 days of receiving claimWithin 42 days of receiving claimo Approval / DisapprovalApproval / Disapprovalo Detailed commentsDetailed comments
May ask for further detailsMay ask for further details Proceed with Cl.3.5Proceed with Cl.3.5 May certify interim sumsMay certify interim sums
CLAUSE 3.5 DETERMINATIONSCLAUSE 3.5 DETERMINATIONS
Engineer makes a DeterminationEngineer makes a Determination Makes his own evaluationMakes his own evaluation Shall NOT delegate Cl.3.5 authorityShall NOT delegate Cl.3.5 authority
CLAUSE 3.5 DETERMINATIONCLAUSE 3.5 DETERMINATIONPROCEDUREPROCEDURE
Engineer shall consult both PartiesEngineer shall consult both Parties Try to reach agreementTry to reach agreement Give notice with supporting Give notice with supporting
particularsparticulars Where no agreement then Engineer Where no agreement then Engineer
makes a FAIR determinationmakes a FAIR determination
DISSATISFACTION WITH DISSATISFACTION WITH Cl.3.5 DETERMINATIONCl.3.5 DETERMINATION
Dispute : Refer to Dispute Dispute : Refer to Dispute Adjudication BoardAdjudication Board
No definition of “Dispute”No definition of “Dispute”o Rejection of DeterminationRejection of Determinationo No agreement with continued discussionNo agreement with continued discussiono One party declines to discussOne party declines to discusso No progress in protracted discussion No progress in protracted discussion
Subsequent procedure - Clause 20.4Subsequent procedure - Clause 20.4
FIDIC Short FormFIDIC Short Form
Recommended for projects without Recommended for projects without problems problems
Small Capital Value <$0.5MSmall Capital Value <$0.5M Simple or repetitive worksSimple or repetitive works No specialist subcontractorsNo specialist subcontractors Short durationShort duration No Impartial EngineerNo Impartial Engineer Named AdjudicatorNamed Adjudicator
FIDIC Short FormFIDIC Short Form
Increased responsibility on EmployerIncreased responsibility on Employer• Define project Define project • Undertake designUndertake design• Scope of worksScope of works• SupervisionSupervision• Avoid letters of intent / acceptanceAvoid letters of intent / acceptance• Offer & Acceptance in AppendixOffer & Acceptance in Appendix
FIDIC Short FormFIDIC Short Form
Priority of documents – undefinedPriority of documents – undefined No “ruling language”No “ruling language” Cl.2.4 to avoid argument Cl.2.4 to avoid argument
• ““approval” only used for Cl.4.4 & 14.2approval” only used for Cl.4.4 & 14.2 Cl.4.4 Performance Bond - no modelCl.4.4 Performance Bond - no model
FIDIC Short FormFIDIC Short Form
Risk & Claims Risk & Claims • Cl.6.1 lists all Employers LiabilitiesCl.6.1 lists all Employers Liabilities• No bad weather claimNo bad weather claim• EoT Cl.7.3 to avoid “time at large”EoT Cl.7.3 to avoid “time at large”• Cl.10.3 Early WarningCl.10.3 Early Warning
FIDIC Short FormFIDIC Short Form
Taking Over – no sectional handoverTaking Over – no sectional handover No defined Defects period – 12mthsNo defined Defects period – 12mths Employer may vary - Cl.10Employer may vary - Cl.10
• Lump sumLump sum• RatesRates• DayworkDaywork
FIDIC Short FormFIDIC Short Form
Contract price Cl.11Contract price Cl.11• Lump SumLump Sum• LS with schedule of ratesLS with schedule of rates• LS with BoQLS with BoQ• Remeasurement with BoQRemeasurement with BoQ• Cost reimbursableCost reimbursable
Consider valuation methodsConsider valuation methods
FIDIC Short FormFIDIC Short Form
Dispute resolutionDispute resolution• Amicable settlementAmicable settlement• AdjudicationAdjudication• Dissatisfaction – 28 daysDissatisfaction – 28 days• Arbitration Arbitration
Alternative Dispute Alternative Dispute ResolutionResolution
ADR - OverviewADR - Overview
Alternative Dispute ResolutionAlternative Dispute ResolutionADR - OverviewADR - Overview
ConfrontationalConfrontational Litigation Litigation Win – Win methodsWin – Win methods ADR Methods:ADR Methods:
• MediationMediation• ConciliationConciliation• AdjudicationAdjudication• ArbitrationArbitration
DISPUTE RESOLUTIONDISPUTE RESOLUTIONunder FIDICunder FIDIC
““Dispute” not defined by FIDICDispute” not defined by FIDICo Where 2 parties can not agreeWhere 2 parties can not agreeo Where something needs to be decidedWhere something needs to be decided
Certificates, Determinations, Certificates, Determinations, Instructions, VariationsInstructions, Variations
FIDIC encourages resolution by FIDIC encourages resolution by agreement – Cl.3.5agreement – Cl.3.5
No agreement - DisputeNo agreement - Dispute
Amicable SettlementAmicable Settlement
Cl.20.5 – no definitionCl.20.5 – no definition• 56 days56 days• Direct negotiationDirect negotiation• ConciliationConciliation• MediationMediation• Do not involve the DABDo not involve the DAB• Consensual Consensual • No obligation – costs ??No obligation – costs ??
MediationMediation
No facility in FIDIC contractsNo facility in FIDIC contracts Consensual procedureConsensual procedure ConfidentialConfidential Very successfulVery successful Short time frameShort time frame Low costLow cost Involve decision makersInvolve decision makers
ENGINEERS DECISIONENGINEERS DECISION
Red & Yellow Books provide for an Red & Yellow Books provide for an alternative to the DABalternative to the DAB
Engineer’s DecisionEngineer’s Decision Delete Cl.20.2 & 20.3 make Delete Cl.20.2 & 20.3 make
substitute wordingsubstitute wording Impartiality, Independence ??Impartiality, Independence ??
ADJUDICATIONADJUDICATION
Encourage the resolution of disputesEncourage the resolution of disputes Statutory / non statutoryStatutory / non statutory Provides a decision in a short timeProvides a decision in a short time Binding Binding
• Give effectGive effect• May be changed by amicable settlementMay be changed by amicable settlement• May be changed by arbitrationMay be changed by arbitration
Contractually enforceableContractually enforceable
ARBITRATIONARBITRATION
Clause 20.6Clause 20.6 Final settlement – ICCFinal settlement – ICC 3 arbitrators3 arbitrators LanguageLanguage Open up & reviewOpen up & review No limits to evidenceNo limits to evidence DAB Decision shall be admittedDAB Decision shall be admitted
ICC ARBITRATIONICC ARBITRATION
Place to be agreed in Particular Place to be agreed in Particular ConditionsConditions
Each party nominates 1 arbitrator Each party nominates 1 arbitrator and chairman selected or agreedand chairman selected or agreed
ICC court will formally appointICC court will formally appoint ICC fee scales & administration costsICC fee scales & administration costs ICC rules govern initial referral then ICC rules govern initial referral then
arbitrators set the procedurearbitrators set the procedure
ARBITRATOR’S AWARD ARBITRATOR’S AWARD
Final & BindingFinal & Binding 1958 New York Convention for 1958 New York Convention for
enforcement of awardsenforcement of awards
Dispute Adjudication BoardDispute Adjudication Board
Rules set out in Red and Yellow Rules set out in Red and Yellow booksbooks
Ad hoc – rules apply to the resolution Ad hoc – rules apply to the resolution of a referred dispute onlyof a referred dispute only
1 or 3 person board1 or 3 person board Independent & ImpartialIndependent & Impartial Decisions or advice & opinionDecisions or advice & opinion
ADVANTAGES OF THE DABADVANTAGES OF THE DAB
Resolves disputes in 84 daysResolves disputes in 84 days Lower costs than Arbitration or LitigationLower costs than Arbitration or Litigation ImpartialityImpartiality Real time assessmentReal time assessment Improves standardsImproves standards Provides clarityProvides clarity Diffuses problems (win – win)Diffuses problems (win – win) Encourages competitiveness in tendersEncourages competitiveness in tenders
DISPUTE ADJUDICATION DISPUTE ADJUDICATION BOARDBOARD
Functions: Functions: o Become FamiliarBecome Familiaro Visit the siteVisit the siteo Keep up to dateKeep up to dateo Encourage resolution of issuesEncourage resolution of issueso When a dispute is referred:When a dispute is referred:
o Act Fairly & ImpartiallyAct Fairly & Impartiallyo Convene a hearingConvene a hearingo DeliberateDeliberateo Prepare a DecisionPrepare a Decisiono Avoid unnecessary delay or expenseAvoid unnecessary delay or expense
FORMATION OF DABFORMATION OF DAB
FORMATION OF DABFORMATION OF DABRELEVANT DOCUMENTATIONRELEVANT DOCUMENTATION
Cl. 20.2 & 20.3Cl. 20.2 & 20.3 General Conditions of DAAGeneral Conditions of DAA
o Red Book - full termRed Book - full termo Yellow Book – ad-hocYellow Book – ad-hoco InterchangeableInterchangeable
Dispute Adjudication AgreementDispute Adjudication Agreement Tripartite AgreementTripartite Agreement
General Conditions of DAAGeneral Conditions of DAA
Employer decides (at tender stage)Employer decides (at tender stage)o What type of DABWhat type of DABo How many membersHow many memberso Period to agree selectionPeriod to agree selectiono Third party nominatorThird party nominator
List of candidates in tender ??List of candidates in tender ?? Employer to be ready to nominateEmployer to be ready to nominate
Formation of DABFormation of DAB
Cl.20.2 FormationCl.20.2 Formation• 1 or 3 members 1 or 3 members • Each party nominates one memberEach party nominates one member• Parties consult members and agree a Parties consult members and agree a
chairmanchairman• List of potential members in tenderList of potential members in tender
No AgreementNo Agreement• FIDIC President will nominateFIDIC President will nominate• Due consultation with partiesDue consultation with parties
DAB OBLIGATIONSDAB OBLIGATIONS
Act FairlyAct Fairly Act ImpartiallyAct Impartially Give parties a reasonable Give parties a reasonable
opportunity to pout their case & opportunity to pout their case & respondrespond
Adopt procedures:Adopt procedures:o Avoid unnecessary delayAvoid unnecessary delayo Avoid unnecessary expenseAvoid unnecessary expense
DAB MEMBERS’ DAB MEMBERS’
QUALITIESQUALITIESo ExperienceExperienceo Contract KnowledgeContract Knowledgeo LanguageLanguageo DR ExperienceDR Experienceo Procedural KnowledgeProcedural Knowledge
o QualificationsQualificationso AvailabilityAvailabilityo ImpartialityImpartialityo IndependenceIndependenceo LawyersLawyers
WARRANTIES & OBLIGATIONSWARRANTIES & OBLIGATIONS
General Conditions Cl.3 & 4General Conditions Cl.3 & 4 Warranties:Warranties:
o Experienced in WorkExperienced in Worko Experienced in DocumentationExperienced in Documentationo Fluent in Language of communicationsFluent in Language of communications
Obligations:Obligations:o IndependentIndependento ConfidentialConfidentialo AvailableAvailable
PAYMENT OF MEMBERSPAYMENT OF MEMBERS
General Conditions Cl.6General Conditions Cl.6 Retainer per calendar monthRetainer per calendar month Daily FeeDaily Fee Reasonable expensesReasonable expenses Taxes in country of contractTaxes in country of contract Retainer reduced by 50% after taking Retainer reduced by 50% after taking
overover Ad hoc DAB – no retainerAd hoc DAB – no retainer
PAYMENT OF MEMBERSPAYMENT OF MEMBERS
Payment method:Payment method:o Retainer & airfares - quarterly in Retainer & airfares - quarterly in
advanceadvanceo Other fees after site visits / hearingOther fees after site visits / hearing
Contractor pays in full within 56 daysContractor pays in full within 56 days Employer reimburses ContractorEmployer reimburses Contractor
ANNEX : PROCEDURAL RULESANNEX : PROCEDURAL RULES
Monitor progress reports against project Monitor progress reports against project documentsdocuments
Site visits Site visits o TimingTimingo Agenda / scheduling / travel arrangementsAgenda / scheduling / travel arrangementso Keep up to dateKeep up to dateo ProgressProgresso ProblemsProblemso ClaimsClaims
ANNEX : PROCEDURAL RULESANNEX : PROCEDURAL RULES
Site visits with Parties : co-ordinated Site visits with Parties : co-ordinated by Employerby Employer
DAB shall prepare a reportDAB shall prepare a report Contract & Project documentsContract & Project documents Monthly reportMonthly report
DISPUTE REFERRALDISPUTE REFERRAL
Clause 20.4 – read together with Clause 20.4 – read together with Procedural RulesProcedural Rules
Referred in writing stating ClauseReferred in writing stating Clause Sent to chairmanSent to chairman 84 days to Decide84 days to Decide Reasoned DecisionReasoned Decision UnanimousUnanimous
DAB DECISION PROCEDURESDAB DECISION PROCEDURES
Referral of DisputeReferral of Dispute Preliminary IssuesPreliminary Issues Claimant’s position paperClaimant’s position paper Respondent’s ResponseRespondent’s Response Claimant’s Reply to ResponseClaimant’s Reply to Response Copies to the other party Copies to the other party DAB to set time tableDAB to set time table
DAB DECISION PROCEDURESDAB DECISION PROCEDURES
Parties empower the DAB to:Parties empower the DAB to:o Establish procedureEstablish procedureo Decide jurisdictionDecide jurisdictiono Conduct a hearingConduct a hearingo Take initiative facts & other mattersTake initiative facts & other matterso Specialist knowledgeSpecialist knowledgeo Decide payment of finance chargesDecide payment of finance chargeso Decide ReliefDecide Relief
DAB OBLIGATIONS IN MAKING DAB OBLIGATIONS IN MAKING A DECISIONA DECISION
Act FairlyAct Fairly Act ImpartiallyAct Impartially Give parties a reasonable Give parties a reasonable
opportunity to pout their case & opportunity to pout their case & respondrespond
Adopt procedures:Adopt procedures:o Avoid unnecessary delayAvoid unnecessary delayo Avoid unnecessary expenseAvoid unnecessary expense
DAB HEARINGDAB HEARING
Adopt inquisitorial procedureAdopt inquisitorial procedure Refuse admission to hearingsRefuse admission to hearings Proceed in absence of any partyProceed in absence of any party Not formal (no oaths)Not formal (no oaths) EvidenceEvidence Written summariesWritten summaries
DAB HEARINGDAB HEARING Typical hearing:Typical hearing:
o Procedural issuesProcedural issueso Preliminary issuesPreliminary issueso Jurisdictional issuesJurisdictional issueso Oral presentation by ClaimantOral presentation by Claimant
o Witness submissionsWitness submissionso Respondent questionsRespondent questions
o Oral presentation by RespondentOral presentation by Respondento Witness submissionsWitness submissionso Respondent questionsRespondent questions
o Respondent’s summing upRespondent’s summing upo Claimant’s summing upClaimant’s summing up
Chairman does not end meeting until parties Chairman does not end meeting until parties have confirmed they have nothing further to add have confirmed they have nothing further to add
DAB DECISIONDAB DECISION
DAB meets in privateDAB meets in private Endeavour to reach a unanimous Endeavour to reach a unanimous
decisiondecision Failure of a member to attendFailure of a member to attend Decision issued in writing and signed Decision issued in writing and signed
with reasonswith reasons
FORMAT OF DAB DECISIONFORMAT OF DAB DECISION PreamblesPreambles State given under clause 20.4State given under clause 20.4 Confidential document – state circulationConfidential document – state circulation Short documentShort document Details of parties and contractDetails of parties and contract Summary of disputeSummary of dispute ProcedureProcedure Reasoning : contract clausesReasoning : contract clauses DecisionDecision Signed & datedSigned & dated
POST DECISIONPOST DECISION
Shall be binding … promptly give Shall be binding … promptly give effecteffect
May be reversed by amicable May be reversed by amicable settlement or arbitrationsettlement or arbitration
Dissatisfaction – 28 daysDissatisfaction – 28 days Otherwise after 28 days - binding Otherwise after 28 days - binding Failure to comply – arbitrationFailure to comply – arbitration Compliance is a contractual Compliance is a contractual
obligationobligation
ENFORCEMENTENFORCEMENT(non statutory)(non statutory)
Contractual obligationContractual obligation Cl.20.4 Notice of dissatisfactionCl.20.4 Notice of dissatisfaction Breach of contractBreach of contract
• Cl.14.3 – application for IPCCl.14.3 – application for IPC• Cl.14.6 – Issue of IPCCl.14.6 – Issue of IPC• Cl.14.7 – PaymentCl.14.7 – Payment• Cl.16.1 – SuspensionCl.16.1 – Suspension• Cl.16.2 - TerminationCl.16.2 - Termination