Brandon Flood Protection Plan
• Funding Agreement
• Improvements
• Schedule
• Cost
Brandon Flood Protection Plan
• Funding Agreement
– $20M
– 90% Province 10% City
• Technical Review Committee
• Management Committee
Brandon Flood Protection Plan
• Improvements
– North Side of the Assiniboine
– South Side of the Assiniboine
– 17th St East Dike
– Land Drainage Sewer Upgrades (North Side)
– Wastewater Sewer Upgrades (North Side)
Brandon Flood Protection Plan
• Improvements North Side
– Create new dike west of 18th St N
– Raise dikes Kirkcaldy Drive
– Land Drainage Sewer Improvements
– Permanent Pumping Station
– New Wastewater Lift Station
• Discovery Center
• Kasiurak Bay
• Experimental Farm
• Brandon Youth Soccer
Brandon Flood Protection Plan
• Improvement South Side
– Raise dikes
– Permanent Pumping Stations
• Cattle Auction Mart
• Co-op Feeds
• Eleanor Kidd Park
• Brandon Softball
Brandon Flood Protection Plan
• Improvements 17th St East Dike
– Primary Dike on 17th St E
– Secondary CPR access
• Residents Primary Dike
• Green Spot
• CPR
• MB Hydro
Brandon Flood Protection Plan
• Improvement Discussion
• First Street will be allowed to be breached at 100+
year flood
– Economics
– Upstream impact
• PTH 110 (Eastern Access) will be raised
Brandon Flood Protection Plan
• Schedule
– 2013
• 18th St North Dike
• Kirkcaldy Dr Land Drainage Sewer
– 2014
• North, South and 17th St E Dikes
– 2015
• North, South and 17th St E Dikes
Brandon Flood Protection Plan
• Cost
– $32M reduced to $24M
– Further cost reduction through the detailed
design process.
• Revised pricing
• Tender strategy
– Future Funding 2014 and beyond
Brandon Flood Protection Plan
• Questions / Comments