impact of critical path method (cpm) of scheduling on on
Post on 16-Oct-2021
7 Views
Preview:
TRANSCRIPT
University of South CarolinaScholar Commons
Theses and Dissertations
2018
Impact Of Critical Path Method (CPM) OfScheduling On On-Time Completion OfTransportation ProjectsFahim AhmedUniversity of South Carolina
Follow this and additional works at: https://scholarcommons.sc.edu/etd
Part of the Civil Engineering Commons
This Open Access Thesis is brought to you by Scholar Commons. It has been accepted for inclusion in Theses and Dissertations by an authorizedadministrator of Scholar Commons. For more information, please contact dillarda@mailbox.sc.edu.
Recommended CitationAhmed, F.(2018). Impact Of Critical Path Method (CPM) Of Scheduling On On-Time Completion Of Transportation Projects. (Master'sthesis). Retrieved from https://scholarcommons.sc.edu/etd/4568
IMPACT OF CRITICAL PATH METHOD (CPM) OF SCHEDULING ON ON-TIME
COMPLETION OF TRANSPORTATION PROJECTS
by
Fahim Ahmed
Bachelor of Science
Bangladesh University of Engineering and Technology, 2014
Submitted in Partial Fulfillment of the Requirements
For the Degree of Master of Science in
Civil Engineering
College of Engineering and Computing
University of South Carolina
2018
Accepted by:
Nathan N. Huynh, Director of Thesis
Robert L. Mullen, Reader
Charles E. Pierce, Reader
Cheryl L. Addy, Vice Provost and Dean of the Graduate School
ii
© Copyright by Fahim Ahmed, 2018
All Rights Reserved.
iii
DEDICATION
I dedicate this work to my parents, Sk Shafi Ahmed and Shirin Akter, and to my
beloved wife, Mishma. I thank them for believing in me, supporting through difficult times
and continuous care.
iv
ACKNOWLEDGEMENTS
I would like to express my sincere gratitude to my advisor, Dr. Nathan Huynh, for
his thoughtful guidance, patient, and support in completion of the thesis.
I am very thankful for the support, encouragement, and critiques of my thesis
committee members, Dr. Robert Mullen and Dr. Charles Pierce. I would also like to express
my appreciation to my lab mates and colleagues in my graduate school for all the help and
to make my journey more colorful and
Finally, I would like to thank the South Carolina Department of Transportation
(SCDOT) for supporting my graduate study at the University of South Carolina .
v
ABSTRACT
This study addresses the effectiveness of Critical Path Method (CPM) scheduling
on project delivery. Specifically, the on-time completion of projects with and without a
CPM schedule is explored. The paper uses data from 2,097 South Carolina transportation
projects let after February 2008 and substantially completed by August 2015. The delay
analysis uses the original contract completion date as well as the completion date adjusted
by change orders. Chi-Squared tests are used to examine the relationship between CPM
scheduled projects and delayed projects, and t-tests are used to compare the mean delay (in
days) between CPM scheduled and unscheduled projects. The results of these tests indicate
that both the fraction of delayed projects and the mean delay (in days) are larger in projects
with CPM schedules. Several conjectures that explain these unexpected results are given.
A nationwide survey was conducted to find out the viewpoint on CPM schedules of state
Departments of Transportation(DOTs), resident construction engineers and contractors.
The survey revealed that most state DOTs use CPM along with Gantt chart for scheduling
and perceived complexity and risk are used to select projects for CPM schedules. Resident
construction engineers indicated that delay before the start of work on the field do not
impact the overall duration of the project. The contractors acknowledge the importance of
CPM schedules but they sometimes fail to make most out of CPM schedules. The issues
regarding selection criteria, enforcing and skilled person for CPM schedules are addressed
in the study and recommendations are provided.
vi
TABLE OF CONTENTS
DEDICATION ....................................................................................................................... iii
ACKNOWLEDGEMENTS ........................................................................................................ iv
ABSTRACT ............................................................................................................................v
LIST OF TABLES ................................................................................................................. viii
LIST OF FIGURES ...................................................................................................................x
CHAPTER 1: INTRODUCTION ..................................................................................................1
1.1 Background and problem statement .......................................................................1
1.2 Scope of the Study ..................................................................................................3
1.3 Overview of the Study Approach ...........................................................................3
1.4 Organization of Thesis ...........................................................................................4
CHAPTER 2: LITERATURE REVIEW .........................................................................................6
2.1 Introduction ............................................................................................................6
2.2 Scheduling Techniques ...........................................................................................7
2.3 Overview of Project Management Software ........................................................11
2.4 Current Practices of the State DOTs ....................................................................13
2.5 Chapter Summary .................................................................................................15
CHAPTER 3: METHODOLOGY ...............................................................................................16
3.1 Introduction ..........................................................................................................16
3.2 Selection of Variables ..........................................................................................16
vii
3.3 Descriptive Statistics and Statistical Analysis ......................................................17
3.4 Survey of Use of CPM .........................................................................................23
3.5 Data Description ...................................................................................................26
3.6 Chapter Summary .................................................................................................33
CHAPTER 4: FINDINGS .........................................................................................................35
4.1 Introduction ..........................................................................................................35
4.2 Descriptive Statistics ............................................................................................35
4.3 Impact of CPM Schedule on Project Delay ..........................................................38
4.4 Identification of Factors Associated with Delay .................................................42
4.5 Survey Results of the Use of CPM ......................................................................47
4.6 Chapter Summary .................................................................................................69
CHAPTER 5: DISCUSSION .....................................................................................................70
5.1 Introduction ..........................................................................................................70
5.2 Observations from the Statistical Analysis ..........................................................70
5.3 Observations from the Survey Results .................................................................73
5.4 Chapter Summary .................................................................................................78
CHAPTER 6: CONCLUSIONS ..................................................................................................79
REFERENCES .......................................................................................................................82
APPENDIX A: EVALUATION OF CONSTRUCTION STANDARD SPECIFICATIONS OF DOTS ..........87
APPENDIX B: RESULTS OF STATISTICAL ANALYSIS OF PROJECT TYPES .................................93
APPENDIX C: ONLINE QUESTIONNAIRE SURVEY RESULTS ..................................................101
viii
LIST OF TABLES
Table 2.1 Focus groups for standard specifications for construction of DOTs ................ 14
Table 3.1 Topic focused on the survey for DOT headquarter personnel, Resident
Construction Engineer and Contractors ................................................................ 24
Table 3.2: Lists of DOTs for phone interviews ................................................................ 26
Table 3.3 Raw project data description in SiteManager provided by SCDOT ................. 27
Table 3.4 Description of different types of projects in the SiteManager database ........... 29
Table 3.5 Database development and variables calculated ............................................... 31
Table 4.1: Distribution of SiteManager Projects, SST Projects and SSPRIM Projects by
Project Types ........................................................................................................ 36
Table 4.2 Distribution of Projects by Project SCDOT districts ........................................ 37
Table 4.3 Distribution of Projects by Project Size Groups ............................................... 37
Table 4.4 Distribution of Projects by Project Duration Groups ........................................ 37
Table 4.5 Impact of Using a Critical Path Method (CPM) Schedule on Project Delays by
Project Type .......................................................................................................... 38
Table 4.6 Impact of Using a Critical Path Method (CPM) Schedule on Project Delays by
Project Size ........................................................................................................... 40
Table 4.7 Impact of Using a Critical Path Method (CPM) Schedule on Project Delays by
Project Duration groups ........................................................................................ 41
Table 4.8 Chi-Squared Test Results for Project Types, SCDOT Districts and Project Size
Groups ................................................................................................................... 43
Table 4.9 t-test Results for Project Types (Considering Original and Adjusted Completion
Date for Delay) ..................................................................................................... 44
ix
Table 4.10 t-test Results for SCDOT Districts (Considering Original and Adjusted
Completion Date for Delay) .................................................................................. 45
Table 4.11 t-test Results for Project Size Groups (Considering Original and Adjusted
Completion Date for Delay) .................................................................................. 45
Table 4.12 t-test Results for Project Duration Groups (Considering Original and Adjusted
Completion Date for Delay) .................................................................................. 46
Table 5.1 Summary of the statistical tests ........................................................................ 72
Table 5.2 Summary of the online questionnaire surveys .................................................. 75
x
LIST OF FIGURES
Figure 3.1 Statistical Analysis framework for the study ................................................... 17
Figure 3.2 SCDOT engineering districts .......................................................................... 28
Figure 3.3 Enterprise Project Structure of Primavera database ........................................ 30
Figure 4.1 Comparison of delayed (TT_Delay) SSPRIM projects and delayed SSNULL
projects (by project type). ..................................................................................... 39
Figure 4.2 Comparison of delayed (CO_Delay) SSPRIM projects and delayed SSNULL
projects (by project type). ..................................................................................... 40
Figure 4.3 State DOTs answer to question 10 .................................................................. 48
Figure 4.4 State DOTs response to question 3 .................................................................. 49
Figure 4.5 State DOTs responses to question 4 ................................................................ 50
Figure 4.6 State DOTs responses to question 5 ................................................................ 50
Figure 4.7 State DOTs responses to question 6 ................................................................ 51
Figure 4.8 State DOTs responses to question 7 ................................................................ 52
Figure 4.9 State DOTs response to question 9 .................................................................. 53
Figure 4.10 State DOTs responses to question 14 ............................................................ 53
Figure 4.11 State DOTs responses to question 15 ............................................................ 54
Figure 4.12 RCEs responses to question 2........................................................................ 56
Figure 4.13 RCEs responses to question 3........................................................................ 56
Figure 4.14 RCEs response to question 4 ......................................................................... 57
Figure 4.15 RCEs responses to question 5........................................................................ 58
xi
Figure 4.16 RCEs responses to question 6........................................................................ 58
Figure 4.17 RCEs responses to question 7........................................................................ 59
Figure 4.18 RCEs responses to questions 8 ...................................................................... 60
Figure 4.19 RCEs response to question 10 ....................................................................... 61
Figure 4.20 Contractors responses to question 2 .............................................................. 62
Figure 4.21 Contractors responses to question 3 .............................................................. 63
Figure 4.22 Contractors responses to question 7 .............................................................. 63
Figure 4.23 Contractors responses to question 4 .............................................................. 64
Figure 4.24 Contractors response to question 5 ................................................................ 64
Figure 4.25 Contractors responses to question 6 .............................................................. 65
Figure 4.26 Contractors responses to question 8 .............................................................. 66
Figure 4.27 Contractors responses to question 9 .............................................................. 67
Figure 4.28 Contractors responses to questions 10 ........................................................... 68
Figure 4.29 Contractors responses to question 11 ............................................................ 68
Figure 4.30 Contractors responses to question 12 ............................................................ 69
1
CHAPTER 1: INTRODUCTION
1.1 Background and Problem Statement
Construction delays of transportation projects are one of the most recurring and
critical problems facing state agencies. Several studies have assessed the efficiency of
projects managed by State Departments of Transportation (DOTs) and the results show that
only about half of the projects met their projected budgets and schedule. According to the
study by Crossett and Hines (Crossett & Hines, 2007), the average on-budget project
delivery is 46% over a five-year period (2001 – 2005), and in a follow-up study by Crossett
and Schneweis (Crossett & Schneweis, 2011), the average is 47% over a ten-year period
(2001 – 2010). The on-time performance is only slightly better at 53% (Crossett & Hines,
2007) over the five-year period and 55% over the ten-year period (Crossett & Schneweis,
2011). The delay in a construction project may affect the overall productivity of the project
due to its adverse effects, such as cost escalation, poor quality of products, reduced
productivity, late completion of work, disruption of work, and termination of contracts
(Kaliba, Muya, & Mumba, 2009, Aibinu & Jagboro, 2002). In addition, delay affects all
parties involved in the construction project, such as owners, contractors, consultants, etc.
(Boland, 2007). Lastly, project delay on transportation projects affect nearby communities
and the traveling public (Hugh, 2003).
The Critical Path Method (CPM) is the most popular tool for scheduling and
planning in construction industry. Surveys conducted in 1974, 1990 and 2003 on CPM
2
usage reveal an increasing trend (1974: 90%; 1990: 92.6%; 2003: 98.5%) of CPM
utilization in the construction industry (Kelleher, 2004; Tovakoli & Riachi, 1990). CPM
has grown in popularity over the years since its inception by DuPont in 1950 due to ease
of use (Kelleher, 2004) and analytical simplicity compared to other scheduling methods
(i.e. PERT) (Galloway, 2006). CPM is also a popular project management tool used in
transportation projects managed by the DOTs. According to an on-line survey conducted
as part of this study and information reported from the Alabama DOT’s website, it was
found that 65% to 75% of state DOTs specifies CPM as a requirement in their specification.
Indeed, the popularity of CPM scheduling has grown so much since the fifties (‘50s) that
scheduling in the construction industry and use of CPM scheduling have become
synonymous (Yates, 1993). In addition to detail planning and controlling of projects, CPM
has also been used for estimation and bidding, claim analysis (Kelleher, 2004) and as well
as risk management (Galloway, 2006). The reported benefits of using CPM in project
management include improved planning, scheduling, controlling, minimizing disputes,
time and cost saving and more control over risks and uncertainties.
Given that most transportation projects today are required to use CPM, this thesis
seeks to address the following research question: Is CPM scheduling effective in reducing
delay for transportation projects? To our knowledge, this is the first attempt to quantify
the effectiveness of the use of CPM in managing project delay. On-time completion of
projects is selected as measure of effectiveness for the study. This thesis also identifies the
factors that are associated with project delay. The findings from this paper will help other
state DOTs recognize the factors of delay in transportation construction projects. If the
3
factors are known a priori, then special attention can be given to these causes to minimize
their impact.
1.2 Scope of the Study
The scope of study is included in the following:
Transportation Project: All the project information was acquired from South
Carolina Department of Transportation (SCDOT). All SCDOT construction contract types
were considered for the study except design-build projects. Projects include:
• Paving (hot mix asphalt, concrete)
• Structures (bridges, drainage structures, sidewalks, gutters, guardrails)
• Paint and marking (epoxy pavement markings, raised pavement markers, thermal
pavement marking)
• Sign and signal (highway signs, traffic signals)
• General (landscaping, other or mixed projects)
Analysis period: The projects that let after February 2007 and that were
substantially completed on June 2015 were considered for the present study.
Geographical Extent: The present study considered all the projects in the analysis
period from the seven (7) SCDOT districts.
1.3 Overview of the Study Approach
This study examines the impact of CPM schedules in reducing the time delay of
transportation projects. To accomplish this, the study is conducted in two parts. The first
part is to conduct the statistical analysis of the transportation project data acquired from
SCDOT. The statistical analysis is performed in two steps. The first step is to examine the
4
relationship between transportation projects with a CPM schedule and delay. Chi-square
test of independence is used to examine the relationship. The second step is to compare the
delay statistic (i.e. mean delay) for projects with a CPM schedule and unscheduled projects.
In both, the statistical analysis delay is considered after original completion date and
adjusted completion date. In the second part, survey on scheduling practices and on the use
of CPM is performed. This part is also a conducted in two steps. In the first step, survey of
the standard specifications for construction of the DOTs is performed to acquire
information of current scheduling practices. In the second step, an online questionnaire
survey of state DOTs, resident construction engineers and contractors is conducted to
gather information on their experience and viewpoint of the impact and use of CPM
schedules for transportation projects.
1.4 Organization of Thesis
This thesis is divided into six (6) chapters. Chapter 1 presents the research
background and problem statement. It also explains the research needs as well as research
scope and objectives. Chapter 2 presents an extensive literature review of the research. This
chapter covers the growth, use, advantages, disadvantages, and success factors for CPM
scheduling method. In addition to that, the chapter provides overview of project
management software. The current practices in the state DOTs in construction is also
discussed in this chapter. Chapter 3 describes the data collection and analysis method of
the data. The data collection process includes acquiring information of transportation
projects from South Carolina Department of Transportation (SCDOT). This chapter also
describes the design of online questionnaire survey of DOT personnel, resident
construction engineers and contractors. The results of the statistical analysis of the SCDOT
5
transportation project data and questionnaire surveys are presented in Chapter 4. Chapter
5 illustrates the insights obtained from the research study. Chapter 6 presents an overall
summary and conclusion for the statistical analysis results and surveys. This chapter also
provided recommendations and limitations for the study. Survey results on standard
specification of DOTs are presented in Appendix A. Detailed statistical analysis results are
presented in Appendix B. Online questionnaire survey questions and results are illustrated
in Appendix C.
6
CHAPTER 2: LITERATURE REVIEW
2.1 Introduction
Numerous research efforts have been published addressing the factors contributing
to delay. Identification of delay factors in construction projects has been studied focusing
on general construction projects (Chan & Kumaraswamy, 1996; Sambasivan & Soon,
2007), building projects (Assaf, Al-Khalil, & Al-Hazmi, 1995; Ogunlana, Promkuntong,
& Jearkjirm, 1996), road construction projects (Kaliba, Muya, & Mumba, 2009; Mahamid,
Bruland, & Dmaidi, 2012), and large projects (Assaf & Al-Hejji, 2005). Delay factors are
also analyzed in various economic conditions in different countries (Al‐Kharashi &
Skitmore, 2009; Arditi & Gunaydin, 1998; Assaf & Al-Hejji, 2005; Doloi, Sawhney, Iyer,
& Rentala, 2012; Kaliba, Muya, & Mumba, 2009; Mansfield, Ugwu, & Doran, 1994;
Sambasivan & Soon, 2007). Some of the common causes for delay of transportation
projects identified in the literature include financial difficulties in client organization, poor
contract management, shortages of material or equipment, change orders from owner, poor
site management and awarding contracts to lower bidder (Kaliba, Muya, & Mumba, 2009;
Mahamid et al., 2012; Mansfield et al., 1994; Park & Papadopoulou, 2012). A study by
Bordat et al. (Bordat, Mccullouch, & Labi, 2004) on the Indiana DOT transportation
projects reported that the contributing factors for time, cost overruns and change orders are
contract bid amount, difference between the winning bid and second bid, difference
between the winning bid and the engineer’s estimate, project type and location by districts.
7
Aibinu and Jagboro (Aibinu & Jagboro, 2002) categorized the effects of construction delay
into six factors which include time overrun, cost overrun, dispute, arbitration and litigation
and total abandonment. Santoso and Soeng (Santoso & Soeng, 2016) conducted a
questionnaire survey on effect of delay and found that respondents have given larger weight
on on-time performance relative to cost and quality. Different project management
techniques are used to successfully execute projects.
2.2 Scheduling Techniques
Modern project management technique dates to the work of Harry Gantt who
developed a graphical method for tracking projects with multiple tasks (Gantt, 1910). The
shortcomings of a Gantt chart are that it does not show the interrelationships between the
activities within a work sequence. In the 1950s, DuPont developed the Critical Path Method
(CPM) to tackle the interrelationships of separate activities within a project schedule. Thus,
Critical Path Method is a project management tool aim to make a project efficient. CPM
breaks down the complex activities of a project into sequence of small activities or tasks
associated with costs and resources. (Galway, 2004) defined CPM as network
representation of activities with non-stochastic (deterministic) estimation of task duration.
It facilitates the computation of critical path (set of tasks determine the project length).
CPM encourages efficiency by optimizing the sequence of scheduled activities, or tasks,
in a project. It is the essential part of the project for developing logic of the network and
also for managing day to day project activities. It provides the direction required for success
to the project. Another technique of project management was developed in mid of 1950s.
The lack of project management tool in 1950s lead the US navy’s Polaris programme
officers to develop a new management tool named Programme evaluation and Review
8
Technique (PERT). The main difference from CPM in the method was embedded in
calculation of the duration for each task. The novelty comes from introducing statistical
calculation as oppose to deterministic time calculation. A probability distribution for each
tasks were calculated with the help of expert engineers and three time estimates were
reported: pessimistic time, optimistic time and most likely time (Galway, 2004;
Klementowski, 1978).
2.2.1 Critical Path Method
Critical path method (CPM) scheduling is the application of logic relationship and
precedence between activities. This procedure determines the activities that are critical
works in a schedule. Critical works are required to perform on time to manage the project
successfully. On the other hand, the noncritical activities have float. The sequence of
connected critical activities establishes the anticipated project duration.
The popularity of CPM method of scheduling gained through two means,
enhancement of computation through computers over time and loss of interest of user in
PERT scheduling method. One of the reasons CPM preferred over PERT was due to its
analytical simplicity (Galway, 2004). The use of CPM method of scheduling has grown
over the years since its inception as commercial software since 1950s. Three surveys were
conducted to answer the question on how Engineering News Record’s (ENR) top 400
companies use CPM. The first survey was conducted in 1974 by Edward Davis , second
one in 1990 by Tovakoli & Riachi, and a third survey focusing the same objective took
place in 2003.The first survey revealed that 90% of the companies use CPM while in the
second it was 92.6% and it increased to 98.5% in 2003. The survey data show an increasing
9
trend in use of CPM for project management by the companies. The increase in usage of
CPM schedule for project management is due to the development of certain technologies
in mid of 1980s that facilitated the growth (Kelleher, 2004; Liberatore, Pollack-Johnson,
& Smith, 2001). The popularity of CPM scheduling grew so much that the scheduling in
construction industry and use of CPM scheduling became synonymous (Yates, 1993).
CPM schedules are used for many reasons in different types of companies. The
effective use of CPM schedules as Galloway (Galloway, 2006) and Hildreth and Munoz
(Hildreth & Munoz, 2005) pointed out are as follows:
• Project time related works: predicts project completion date and time
window for activities, evaluate time impact changes to assess time-base
claims.
• Cost management: helps managing money by predicting cash flows, avoid
liquidate damages, compute progress payments.
• Coordination and communication: coordination of subcontractors, client-
supplied information.
• Conflict resolution: helps addressing conflicts among trades, mitigate
supply-demand conflicts.
• Effective project control tool
In addition to these usages, the survey conducted by Galloway (Galloway, 2006)
adds to the use of CPM scheduling for estimation and bidding, planning of work prior to
construction and operation and maintenance of the projects. (Kelleher, 2004) indicated that
the use of CPM also varies with the size of the company. Larger companies are more likely
10
to manage complex projects than smaller companies. Kelleher (Kelleher, 2004) showed
that large companies are more successful user of CPM method than medium or small sized
companies.
The advantages of CPM scheduling method over bar charts are that it can show
detailed breakdown of activities and also relationships among activities. A CPM schedule
can also be loaded with resources. The resources can be of various forms, such as
manpower, costs. Another key advantage of CPM is that it can utilize multiples calendars
in the schedules which helps in managing projects. The use of CPM in scheduling improves
planning, scheduling, controlling, estimating and bidding, communicating, and
understanding of projects. It also minimizes disputes between contractor and owner,
reduces delay and saves time and cost of the project. Using CPM also trains people in the
company who have the potential to become a project manager in the future. (Kelleher,
2004) indicated that all large companies perceive an economic benefit in using CPM
schedules.
Though CPM generally viewed as an effective tool for project management, the
surveys of 2003 (Kelleher, 2003) and 2006 (Galloway, 2006) data revealed some of the
disadvantages faced by the project stakeholders and companies. Most of the contract
require a CPM schedule from the contractor. It found that contractors sometimes take
advantage of this privilege and perform negative analysis. One of the reasons to abuse the
scheduling is due to retaliation (Mccullough, 1999). In the survey in the 1990 of ENR’ top
400 companies, input and output abuses by the contractor were regarded as the biggest
disadvantages of CPM. Galloway’s (Galloway, 2006) on-line survey found this to be a
unsolved issue as owners complained about the manipulation of schedule in the program
11
by the contractor’s. The common disadvantages found in both surveys of 1990 and 2006
were excessive work and time requirement for input, constant updating for reliability and
CPM acts as ineffective communication tool to connect field personal. In addition to those
2006 survey points out that requirement of skilled personal for operation as the software
became more sophisticated as another disadvantage of CPM. In the survey of 1990 lack of
support from the field people and lack of support from project manager were attributed as
the reason for unsuccessful use of CPM.
Success of CPM as a project management tool depends upon efficient utilization of
the method in projects. Co-ordination on each level of organization is necessary for a
successful project. In the survey of Engineering News Record’s (ENR) top 400 companies
in 1990 (Tavakoli and Riachi, 1990), the successful users of CPM scheduling pointed out
that support from project manager, from top managers and good computer programs as the
key reasons for the success. Other success factors indicated by (Kelleher, 2004) that the
correct use of the technology (i.e. software) for well-maintained, updated and reliable
schedules. (Galloway, 2006) pointed out another important success factor for CPM, the
experience (or lack of) of the scheduler and recommends training programs for scheduling
personnel.
2.3 Overview of Project Management Software
There are many available tools for the implementation of scheduling technique for
project management. The choices include customized forms, checklists and the use of
commercial software. Some of these choices are more complex and requires skilled persons
to perform. The advancement of computing enhanced the capabilities of these tools but it
12
also made it complicated to implement. The commercial software such as Primavera
products is used for complex project while simpler tools include Microsoft Excel,
Microsoft Project. The state DOTs also use AASHTOWare project SiteManager to manage
its projects. The choice of which software to use depend upon perceived project
complexity, risks, and project size and duration. A brief description of some of the
common software used in project management.
AASHTOWare® Project SiteManager
The AASHTOWare project management software is used by the DOTs of 50 states
and also Canadian transportation agencies. The key features of this software are easy to
comply with Federal Highway Administration regulations, AASHTO standards and
industry best practices (AASHTOWare, 2017). The software is also flexible to
accommodate differences of state-to-state in construction standards. The SCDOT uses the
SiteManager software to manage construction contracts and use as a repository of contract
records. It also keeps the record the detailed work information, resource used, and change
orders.
Microsoft Products
Bar charts are a common technique for scheduling and is well used in small and
short duration projects. Microsoft excel can be used to show the activities and bar charts.
These bar charts show the dates and duration of each activity. However, bar charts fail to
show the breakdown of activities and relationship between activities. Hence, Microsoft
project is used where more details to be presented than only the bar charts. The advantage
of using this software is that it can show the relationship between the activities. Another
13
feature for Microsoft project is that it can also determine the critical path of the project.
The cost of scheduling in Microsoft project is lower than Primavera. The disadvantage is
that it is not well suited for complex projects and for implementing extensive analytical
techniques (Liberatore,2001).
Primavera Products
Primavera software is more appropriate for scheduling complex projects and to
apply more analytical technique in scheduling. The survey of Galloway (Galloway, 2006)
revealed that, 65% contractor s indicated that they prefer Primavera software. There are
various types of packages available from Primavera. One can choose any one of these
depending upon the usage level.
2.4 Current Practice of the State DOTs
To find out the current practices, the online standard specifications for construction
of each DOTs was surveyed. This survey provides information on the methods and
preferred software used by the DOTs to manage their projects. The focus of the survey
grouped into five categories: techniques for analyzing and displaying schedules, type of
projects schedules, preferred software for scheduling, type of payment method for
scheduling and requirement of appointed scheduler. The categories and unique values to
measure current practices from the survey of standard specifications are presented in Table
2.1.
Rowings (Rowings, Harmelink, & Rahbar, 1993) conducted a statewide survey of
the state DOTs to gather information of the scheduling practices. Thirty-six (36) DOTs
responded to the survey and some of the key highlights of the survey are presented here.
14
Calculation of project duration was conducted by experience, type, size of the project
(44%), past history of the projects (22%) and only 4% used CPM for the calculation. Forty-
seven (47%) responded that DOTs do not require a schedule specification. The two most
popular method of scheduling at that time were CPM and bar charts. In regard to
information loading with schedules, most of the DOTs did not request any cost or resource
loaded schedules.
Table 2.1 Focus groups for standard specifications for construction of DOT
Scheduling
techniques
CPM
requirement
Preferred software Payment
method
Appointed
scheduler
1. Only CPM Yes 1. Primavera
Product
Incidental
to work
item
Yes
2. Only Bar chart No 2. MS Project Payment for
the item
No
3. CPM and Bar
chart
3. SureTrak
4. CPM and other
techniques (Other includes activity
chart; Written narration
etc.)
4. Asta
Powerproject
5. Form(s)
prescribed by
department
6. Any computer
developed
schedule
The survey results of the standard specifications of each DOT is presented in
Appendix-A. This reveals that most of the DOTs require scheduling in most of their
projects. The level of scheduling may differ from state to state. For example, California
DOT requires three levels of scheduling depending upon the workings day and bid amount
of the projects. In all cases it requires a CPM schedule but the specifications are different
for each level.
15
Depending upon the level of effort for scheduling DOTs use different scheduling
techniques. Most common techniques employed are bar charts and CPM. Other techniques
include written narrative, activity chart, any network diagram etc. Some DOTs also use
customized charts. For example, Texas DOT uses TxDOT standard spec item 8.5 for
monitoring projects.
In case of scheduling tools for CPM schedules, bar charts and CPM are most
common among the state DOTs. Some DOTs also require written narrative along with
these schedules, for example Kentucky DOT.
Payment for schedules are important parameter for measuring whether the CPM
schedules extensively used in the project or it is just a specification requirement. The state
DOTs most often include the payment for schedule as incidental to any work item. But
some DOTs explicitly pay for CPM scheduling. Some DOTs request a dedicated scheduler
for a project. This indicates the emphasize of the that DOT on CPM scheduling.
2.5 Chapter Summary
Project management literature have examined numerous causes and effects of
project delay. The use, advantages, disadvantages, and adaptation of CPM scheduling in
project management have also been studied. Most of these results are from the surveys of
owners, contractors, and state DOTs. But to the authors knowledge, no study has
investigated the use of Critical Path Method (CPM) schedules as a factor in on-time project
completion. This study aims to investigate in this unexplored gap.
16
`CHAPTER 3: METHODOLOGY
3.1 Introduction
This chapter discusses the framework and methods used for analyzing the impact
of time overrun on the transportation projects. The methodology includes selection of
independent and dependent variable, preliminary descriptive statistics, chi-square test of
independence and two sample t-tests. It also discusses the method of conducting online
questionnaire survey to find out the impact of using CPM in projects.
3.2 Selection of Variables
To find the general trend in the data, a graphical trend analysis of the datasets for
the study is conducted. Project type, project size, project duration, and project location are
the independent variables and the time delay is considered as dependent variable. The
variable project type and project location were already categorized in the provided datasets.
The independent variable project size was categorized into three levels: small, medium,
and high. The other independent variable project duration was also categorized into three
groups: short, medium, and long. The details of categorizing the data by project size and
project duration are presented in section 3.5.
17
3.3 Descriptive Statistics and Statistical Analysis
The study aims to find out the impact of the CPM method of scheduling on time
delay of transportation projects. The descriptive analysis of the datasets reveals insights on
this objective. Simple descriptive graphs are used to characterize the data by independent
variables. Single and grouped bar plots of independent variables and frequency table
provide information to understand the data. In order to measure the relative significance of
independent variables descriptive figures such as grouped bar plots are used.
The statistical analysis is focused on determining two aspects of the data. The first
one is to examine the relationship of the variables. The second one is to determine the
difference in statistics (i.e. mean) from two populations. The Chi-square test of
independence is used to examine the relationships between variables and t-test is used to
measure the difference in statistics from two samples. The overall framework of the
statistical analysis is shown in Figure 3.1
Figure 3.1 Statistical Analysis framework for the study
Statistical Analysis Framework for the study
Graphical trend
Analysis
Examine a relationship
Variable type: Categorical
Chi-square Test of
Independence
Test a Hypothesis
Variable type: Quantitative
Two samples
(two sample t-test)
Independent sample
Equal Variance
Pooled two-sample
t-test
Not equal Variance
Welch's t-test
18
3.3.1 Chi-square test of independence
Chi-square test of independence is used to examine the relationship between
categorical variables. Chi-square test (also known as Pearson Chi-square test) is one of the
most commonly used non-parametric test. The advantage of using a non-parametric test
lies in its assumptions. The assumptions for the Chi-square test are:
• Distribution of the sample data does not follow any specific distribution
(distribution free test).
• Sample data is collected from two categorical variables (i.e. sample data can
be distributed into distinct categories).
• The data in distinct categories should be in frequencies or counts.
• The categories of variables are mutually exclusive.
• The frequency of expected value in any cell of the contingency table of
categories should be 5 or more in at least eighty percent of the cells. In
addition to that, expected value in any cell should not be less that one.
A Chi-square test of independence is conducted by determining the distinct
category of variables for the test. The count or the frequency from the sample data are
divided into distinct categories of variables. Thus, a contingency table of observed values
is constructed from the sample data. The frequency or count on each cell of the contingency
table should follow the assumption of the Chi-square test state above. Then Chi-square test
is performed to determine if the categorical variables are related (i.e. associated) to each
other. The hypothesis tested in the Chi-square test of independence is as follows:
𝐻0: 𝐼𝑛 𝑡ℎ𝑒 𝑝𝑜𝑝𝑢𝑙𝑎𝑡𝑖𝑜𝑛, 𝑡ℎ𝑒𝑟𝑒 𝑖𝑠 𝑛𝑜 𝑟𝑒𝑙𝑎𝑡𝑖𝑜𝑛𝑠ℎ𝑖𝑝 𝑏𝑒𝑡𝑤𝑒𝑒𝑛 𝑡ℎ𝑒 𝑐𝑎𝑡𝑒𝑔𝑜𝑟𝑖𝑐𝑎𝑙 𝑣𝑎𝑟𝑖𝑎𝑏𝑙𝑒𝑠.
19
𝐻𝑎: 𝐼𝑛 𝑡ℎ𝑒 𝑝𝑜𝑝𝑢𝑙𝑎𝑡𝑖𝑜𝑛, 𝑡ℎ𝑒𝑟𝑒 𝑖𝑠 𝑟𝑒𝑙𝑎𝑡𝑖𝑜𝑛𝑠ℎ𝑖𝑝 𝑏𝑒𝑡𝑤𝑒𝑒𝑛 𝑡ℎ𝑒 𝑐𝑎𝑡𝑒𝑔𝑜𝑟𝑖𝑐𝑎𝑙 𝑣𝑎𝑟𝑖𝑎𝑏𝑙𝑒𝑠.
To perform this test, first the two categorical variables are summarized in the form
of a contingency table as illustrated below
Second categorical variable
First categorical
variable
1 . j Total
1 C11 . . R1
I . . . Ri
Total C1 . Cn n
The Chi-square test statistics is used to test the hypothesis. The formula to calculate
the chi-square test statistics is:
The 2 test statistic is calculated as follows (25).
r
i
c
j ij
ijij
E
)EO(
1 1
2
2 (1)
where,
2 the test statistic
ijO the observed count in cell (i, j)
ijE the expected count in cell (i, j)
r = number of rows
c = number of columns
The expected count in each cell is calculated as follows.
n
CRE
ji
ij (2)
where,
Rj and Ci are the row and column totals, respectively.
The degree of freedom is calculated using the following formula:
df = (r-1)(c-1) ; where df = degree of freedom (3)
20
The chi-square test statistics finds the answer to the question whether the expected
value differs significantly from our observed value. For the decision making on the null
hypothesis a level of significance (α) is set and p-value is calculated from the chi-square
statistics by the formula P(𝜒2> 𝜒2∗) with degrees of freedom = (number of rows -
1)*(number of columns - 1). If the p-value is less than ‘α’ the null hypothesis is rejected.
The chi-square test is conducted to find if there is any association between the
depended variable (i.e. delay, cost overrun) and the use of CPM for schedules. Both the
variable is treated as binary variables. For example, the binary variable ‘delay’ is classified
as whether there is a delay (defined as ‘1’) or not (defined as ’0’). Again, for use of CPM
for schedules, whether CPM schedules used for the project or not. Two-way contingency
table is created using the two categorical variables. The null hypothesis tested is that there
is no relationship between dependent variable and the use of CPM for schedules. The test
is conducted for each independent variable (project type, project size, project location).
The results of Chi-square test of independence are presented in Appendix-B, Table 4.8.
3.3.2 t-test
The t-test is conducted to compare two means of independent variable to find out
whether these means are significantly different from each other. This test is also known as
two sample t-test. The assumptions of two sample t-test are:
• The data is continuous.
• The data follows normal probability distribution.
• The two samples are independent.
• The variances of the two populations are equal.
21
The assumption of variance in the two-sample t-test determines which t-test to use
for the comparison of the means of the samples. If the variance of the two populations are
equal (Homogeneous variances) pooled two-sample t-test is used. If the variances are not
equal (Heterogeneous variances) Welch’s two sample t-test is used.
The two independent samples are taken for each independent variable. To test the
homogeneity of variance the F-test for variance is used to test the homogeneity of variance
of the samples. The hypothesis for the F-test is:
𝐻0: 𝑇ℎ𝑒 𝑣𝑎𝑟𝑖𝑎𝑛𝑐𝑒𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑡𝑤𝑜 𝑝𝑜𝑝𝑢𝑙𝑎𝑡𝑖𝑜𝑛𝑠 𝑎𝑟𝑒 𝑒𝑞𝑢𝑎𝑙. ( 𝜎12 = 𝜎2
2)
𝐻𝑎: 𝑇ℎ𝑒 𝑣𝑎𝑟𝑖𝑎𝑛𝑐𝑒𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑡𝑤𝑜 𝑝𝑜𝑝𝑢𝑙𝑎𝑡𝑖𝑜𝑛𝑠 𝑎𝑟𝑒 𝑛𝑜𝑡 𝑒𝑞𝑢𝑎𝑙. ( 𝜎12 ≠ 𝜎2
2)
The result from the F-test for homogeneity indicates whether to conduct the pooled two
sample t-test or Welch’s t-test. The null hypothesis tested in both the cases is as follows:
𝐻0: 𝑇ℎ𝑒𝑟𝑒 𝑖𝑠 𝑛𝑜 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 𝑖𝑛 𝑚𝑒𝑎𝑛𝑠 𝑜𝑓𝑡ℎ𝑒 𝑡𝑤𝑜 𝑠𝑎𝑚𝑝𝑙𝑒𝑠 ( µ1 = µ2)
𝐻𝑎: 𝑇ℎ𝑒𝑟𝑒 𝑖𝑠 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 𝑖𝑛 𝑚𝑒𝑎𝑛𝑠 𝑜𝑓𝑡ℎ𝑒 𝑡𝑤𝑜 𝑠𝑎𝑚𝑝𝑙𝑒𝑠 ( µ1 ≠ µ2)
The equation of test statistics depends upon which t-test is conducted. The equation for test
statistic of the pooled sample t-test is:
𝑡∗ = �̅�1 − �̅�2
𝑠𝑝√1
𝑛1+
1𝑛2
Where, �̅�1 = mean of sample 1
�̅�1 = mean of sample 2
𝑛1 = sample size of sample 1
𝑛1 = sample size of sample 2
𝑠𝑝 = Common standard deviation = √(𝑛1−1)𝑠1
2 +(𝑛2−1)𝑠22
𝑑𝑓
22
𝑠12= variance of sample 1
𝑠22= variance of sample 2
𝑑𝑓 = degrees of freedom = 𝑛1 + 𝑛2 − 2
The equation for test statistics of Welch’s t-test and the degrees of freedom is
slightly different form the above method and is as follows:
𝑡∗ = �̅�1 − �̅�2
√1
𝑛1+
1𝑛2
With 𝑑𝑓 = degrees of freedom = (𝑛1−1).(𝑛2−1)
(𝑛2−1).𝐶2 +(1−𝐶)2(𝑛1−1) and 𝐶 =
𝑠12/𝑛1
𝑛12
𝑛1+
𝑛22
𝑛2
The test statistics finds the answer to the question whether the means of sample 1
significantly differs from the mean of sample 2. For the decision making on the null
hypothesis a level of significance (α) is set and p-value is calculated from the test statistics
by the formula P (𝑡 >𝑡∗). The degrees of freedom to calculate the p-value is associated the
type of two sample t-test is conducted on the samples. If the p-value is less than ‘α’ the
null hypothesis is rejected. Generally, in engineering application the ‘α’ value is set to 0.05
for comparison of means of samples using two sample t-test.
The t-test is used to find out whether the depended variable (i.e. time delay, cost
overrun) significantly differed by the use of CPM schedules. The two samples were taken
from the unscheduled projects and projects scheduled by CPM method. Then the samples
were categorized by independent variable (i.e. project type, project size and project
location). The dependent variables were quantitative variables acquired from the
SiteManager database. The null hypothesis tested is that there is no significant different in
23
dependent variable when using CPM method for scheduling the projects. The results of t-
test presented in Appendix-A, Table 4.9, Table 4.11.
3.4 Survey of Use of CPM
The aim of the survey is to understand the methods used by the state agencies to
manage time delay of their projects. The survey was conducted in two steps. The first step
was to conduct online survey on the standard specifications for construction of each agency
to find out the current practices of their project management. The second step was a
questionnaire survey to acquire information on the effectiveness of Critical Path Method
(CPM) for scheduling. In addition to these steps, phone interviews of selected DOT
personnel managing projects were conducted to better understand the ins and outs of the
CPM use in practice.
3.4.1 Survey methodology
The online questionnaire survey was conducted to find the effectiveness of CPM
schedules for managing time delay of the projects. The purpose of the survey was to gather
information about selection criteria for CPM schedule for projects, contractual
requirements of CPM, preferred software, evaluation of contractor on CPM use, impact of
CPM schedules on project time extension, and different practices and approaches of project
management in transportation projects. The targeted participants of the survey were the
DOT personals, the Resident Engineers and contractors working on DOT projects. Online
questionnaire was created to conduct the survey for each category of participants.
Three separate online surveys were created for DOT personnel, Resident
Construction Engineers and contractors. All the questions were crafted to gather
24
information from the participants to meet the study and were distributed to other DOT
personnel, RCEs and contractors by SCDOT.
Table 3.1 Topic focused on the survey for DOT headquarter personnel, Resident
Construction Engineer and Contractors
Topic focused on the survey DOT
headquarter
personnel
Resident
Construction
Engineer
Contractors
Scheduling technique
employed/preferred
Q2, Q9 Q6
Selection of projects for CPM schedule Q3 Q2
Contract requirements / specifications of
CPM scheduling
Q4, Q5 Q2
Scheduling software used/preferred Q6, Q11,
Q12, Q13,
Decision making based on CPM
schedules
Q3 Q4
Storage and Access of schedule database Q8, Q14,
Q17
Effort made to follow CPM schedule Q4
Use of CPM schedule (planning, claim
analysis, revisions of CPM etc.)
Q15, Q16 Q5, Q10 Q3, Q7, Q8
Project extension / Delay associated with
CPM schedule
Q6, Q7, Q8,
Q9
Schedulers requirements and tasks Q9, Q10,
Q11
Cost of CPM application Q5
Value of CPM for success of the
company
Q12
The breakdown of the questions in the survey for DOT personnel, resident
engineers and contractors are shown in Table 3.1. There were seventeen questions for each
DOT personnel which is divided into six areas: (1) Selection for projects for CPM, (2)
25
Contract specifications for CPM, (3) Scheduling techniques use, (4) Scheduling software
preference, (5) Scheduling database storage and access, and (6) Different usages of CPM
schedule.
For resident engineers, there were ten questions which focused on five areas: (1)
Selection of projects for CPM schedule, (2) Decision making using CPM schedule, (3)
Different usages of CPM schedule, (4). Delay associated with CPM schedule, and (5)
Assessment of contractors’ effort. The survey questionnaire for contractors includes
eleven questions to focus on (1) Contract specification for CPM, (2) Scheduling software
preference, (3) Decision making using CPM schedule, (4) Different usages of CPM
schedule, (5) Scheduler appointment and tasks, and (6) Cost and success of CPM use areas.
The first question of each survey is excluded in the survey matrix of Table 3.2 because it
contains information about respondent’s identity.
The participants of the survey responded to the online survey through web-based
survey tool, Google Forms. The survey is shown in Appendix-C And the results of analysis
are discussed in chapter 4 and 5.
3.4.2 Phone Interviews
Phone interviews were planned for other DOTs to verify information and
understand the schedule practices in other States. The results from the survey of DOTs of
their standard specifications and respond from the online questionnaire survey were
analyzed in order to select five state DOTs for phone interview. These selected DOTs for
phone interview had well planned and organized standard specifications that provided the
26
indication of good and effective practices of CPM schedule for their projects. Table 3.3
shows the criteria used for selection from standard specifications.
Table 3.2: Lists of DOTs for phone interviews
State DOT Scheduling
method
Required
Preferred software Payment method Designated
scheduler
California
(CALTRANS)
CPM Primavera P6 Paid for CPM
Maryland
(MDOT)
CPM
Paid for CPM Yes
Texas
(TxDOT)
CPM,
Bar Chart
Incidental to work
Item
Yes
Utah
(UDOT)
CPM Primavera P6 No payment
(Contractor’s
Obligation)
New York
State
(NYSDOT)
CPM,
Bar Chart
Approved by
Department
(currently Primavera
P6)
No payment
(Contractor’s
Obligation)
Among the five state DOTs, three of them responded to our online survey. These
DOTs provided interesting response regarding selection of CPM schedule to use in their
projects and use of CPM schedule for different complexity and duration levels.
3.5 Data Description
All the data regarding projects for analysis of schedule impact on delay were
collected from the information provided by the SCDOT. The timeframe of the projects is
approximately eight years: projects let after February 2007 to June 2015. All the projects
reached substantial completion data within this timeframe. There were 2,097 projects in
the period of analysis.
27
SCDOT uses two types of software for the purpose of project management. The
AASHTOWARE Project SiteManager® computer application is used to manage
information regarding contracts. The dataset contains general information of SCDOT
projects, change order information, Daily Work Report (DWR) and item used in projects.
The data for time overrun analysis is recorded in the general information table of the
provided dataset. The SiteManager dataset provided by SCDOT is in Microsoft Access®
format. The codes used in the dataset are indicated in Table 3.3.
Table 3.3 Raw project data description in SiteManager provided by SCDOT
Variable Name Description
Information
type
CONT_ID Unique code identifying each project Project
FED_ST_PRJ_NBR
Unique code for funding management
purposes
Project
LEV3_OFFICE_NBR Engineering district that manages the project Project
LEV4_OFFICE_NBR
Resident Construction Engineer (RCE)
office
Project
VEND_ID ID for prime contractor Project
TOT_BID_AMT Original bidding amount for the project Cost
NET_C_O_AMT Total change order amount Cost
Total_Paid Total amount paid Cost
TTBID TOT_BID_AMT plus NET_C_O_AMT Cost
NTP_Date Notice to proceed date Time/Dates
Adj_Comp_Date
Adjusted completion date
(original completion date plus time change
order)
Time/Dates
CompDate Substantial completion date Time/Dates
Letting_Date Date the project was let Time/Dates
WRK_T
Type of project (i.e. Bridge, surfacing,
painting etc.)
Project
ORGC_Date
Original completion date when the project
was let
Time/Dates
DESC1 Brief description of the project Project
LOC_DESC1 Brief description of the project location Location
28
From Table 3.3 four types of information (e.g. project related, time related, cost
related, and project location related) for a project were separated from the database. The
information type and their related fields is also shown in Table 3.3.
Time related information includes letting date, notice to proceed date, original and
adjusted completion date and substantial completion date for each project. The total bid
amount and net change order amount data were retrieved from the dataset for cost related
analysis. For geographical information of the projects, SCDOT districts were extracted
from the database. There are seven SCDOT districts which are marked with the numbers
from 1 to 7 in Figure 3.2. These district numbers are provided in the location information
field (LEV3_OFFICE_NBR) to retrieve the geographical information of the projects.
Figure 3.2 SCDOT engineering districts (Source:http://www.scdot.org/inside/engineering_directory.aspx accessed on 25 March, 2017)
There is a total of 2,097 projects in the SiteManager database, which are divided
into 16 different project types defined in Table 3.4. The type of project information is
recorded in the WRK_T field in the SiteManager database table.
29
Table 3.4 Description of different types of projects in the SiteManager database
Type Description
ASPT Surface treatment
BRDG Bridge
BRPT Bridge paint
CGSW Curb, gutter, side walk
DRST Drainage structure
GDRL Guardrail
GNRL
Projects are spread between several different categories, such as widening
projects but without any dominating project type like HMAS or ASPT in
terms of percentage of project cost. The project team refers to this type of
projects by general construction projects.
HMAS Hot-mixed Asphalt paving
LDSC Landscaping
PCCP Concrete pavement
PMEP Epoxy pavement marking
PMPT Pavement marking
PMRP Raised pavement Markers
PMTH Thermal pavement marking
SGNL Traffic signal
SIGN Roadway signs
The primavera software is used by the SCDOT for planning, managing and
executing its projects. The primavera database contains information regarding Critical Path
Method (CPM) schedules of the project. The “OBSPROJ” table contains information
regarding the EPS structure and the schematic diagram of different levels of EPS is shown
in Figure 3.3. The Enterprise Project Structure (EPS) shows that all the projects in
Primavera are contained under Resident Construction Engineer (RCE) level.
The Primavera database was provided in a SQL format. The “PROJECT” table of
the primavera database contains records of all projects scheduled using this software. The
30
“PROJWBS” table contains each of the projects in “PROJECT” table with additional
information of update.
Figure 3.3 Enterprise Project Structure of Primavera database
3.5.1 Database Development
The extracted information from the SiteManager and Primavera database are
merged together to produce a completely new database for analysis. The SiteManager and
Primavera datasets were joined using the unique project identifier “CONT_ID” in
SiteManager and the “proj_short_name” field in the Primavera table “dbo_PROJECT”.
The data items in the database are listed in Table 3.5.
For the analysis of project delay following variables are used:
• CO_Delay - Time delay (in days) measured in terms of number days
beyond adjusted completion date, only for projects with a CO_delay > 0
• TT_Delay - Time delay (in days) measured in terms of number of days
beyond original completion date, only for projects with a TT_delay > 0
SCDOT Schedules
SCDOT Districts
Resident Construction Engineer (RCE)
Projects
31
Table 3.5 Database development and variables calculated
Data
item
Database Variable code Meaning P
roje
ct r
elat
ed
Sit
eMan
ager
CONT_ID Unique identifier of the project
TYPE Category of the type of the project
Code used in Table 5.3
Pri
mav
era
PROJ_SHORT_NAME Unique identifier of the project
PROJ_ID Unique identifier of the project
WBS_SHORT_NAME Title of the project
Tim
e re
late
d
Sit
eMan
ager
LET_DT Letting date of the project
NTP_DT Notice to proceed date
ORGC_DT Planned completion date of the project at
award
ADJ_COMP_DT Adjusted completion date of the project
after change order
COMP_DT Substantial completion date of the project
TT_DELAY Delay after planned completion date;
(COMPDATE – NTP_DATE)
Cal
cula
ted
CO_DELAY Delay after adjusted completion date;
(ADJ_COMP_DATE – NTP_DATE)
TT_CODE 1, if there is TT_DELAY > 0;
0, otherwise
CO_CODE 1, if there is TT_DELAY > 0;
0, otherwise
TOT_BID_AMT Total bid amount (USD) at the time of
contract award
NET_CO_AMT Net change order amount (USD) for the
project
Cost
rel
ated
Sit
eMan
ager
TTBID Total bid amount after incorporation
change order
LEV3_OFFICE_NBR SCDOT districts as in Figure 5.1
TASKS Number of tasks associated with each
project
32
Loca
tion
rela
ted
Sit
eMan
ager
SSP_CODE 1, if there is payment item for schedule;
0, otherwise
Sch
edule
rel
ated
Cal
cula
ted SSPRIM_CODE 1, if the project has a real schedule in
Primavera;
0, otherwise
Sit
eMan
ager
SST_CODE 1, if there the has an entry in Primavera for
schedule;
0, otherwise
The Primavera database contains projects that do not have a CPM schedule.
Observations from the “OBS” table in the Primavera database show that under each
Resident Engineer (RE), there are some projects that are marked as “No CPM”. Also, some
of the project titles (WBS_SHORT_NAME) indicate that these projects do not have a CPM
schedule. These projects are identified by using the following criteria: -
i. The projects contained in the “No CPM” or “No CPM Reqd” level in the
Primavera database.
ii. Indication of a non-real CPM schedule activities: Projects that have only
“payout” or “cash flow only” or “estimate only” activities.
iii. Indication of a non CPM schedule: The title of the project (WBS_NAME
in “PROJWBS” table) contains phrases: “Non CPM” or “non cpm
schedule” or “NO CPM Required”.
The above criteria are used to refine SST projects. Projects that fall into the above
criteria are excluded from the SST projects and then further categorized all the projects as
follows: -
• SSPRIM – all the projects in Primavera with real schedule. These projects are
defined as SST projects that do not fall into criteria (i), (ii) or (iii).
33
• SSNULL - all the projects in SiteManager that are not SSPRIM.
To measure the effectiveness of the use of CPM on the delay of SCDOT projects
in terms of project size, the projects are categorized into three groups by total contract bid
amount (in USD in the corresponding year of the project in the analysis period):
• Small projects: Total contract bid amount between $0 to $ 360,000.
• Medium projects: Total contract bid amount between $360,000 to $1,000,000.
• Large projects: Total contract bid amount greater than $1,000,000.
Again, to measure the effectiveness of the use of CPM on the delay of SCDOT
projects in terms of project duration, the projects are categorized into three groups by
original duration of the projects (in months):
• Short projects: original duration of the project less than 6 months
• Medium projects: original duration of the project between 6 to 12 months
• Long projects: original duration of the project more than 12 months (1 year)
3.6 Chapter Summary
This chapter discussed the framework, methods and underlying assumptions of
statistical analysis to understand the impact of use of CPM technique in projects for project
delay. The methodology used in statistical analysis included examining relationship of
categorical variables by Chi-square test of independence and hypothesis test by students’
t-test. In addition to that, the process of two-step surveys and phone interviews are also
discussed. First step of survey was conducted to gather information from standard
specifications for construction of state DOTs for the current practices of CPM used in
34
managing their projects. Second step was to conduct an online survey of DOT personnel,
Resident Construction Engineers and contractors about the use of CPM in their projects.
Phone interviews were also conducted for five state DOT personnel to gather information
about their practices and improve SCDOT scheduling techniques.
35
CHAPTER 4: FINDINGS
4.1 Introduction
This chapter describes the findings obtained from online questionnaire surveys and
the statistical analysis on transportation projects from SCDOT. It provides the basic
information describing general characteristics of the project data obtained from
SiteManager and Primavera database. A detailed description of time delay classified by
various categories used in the statistical analysis gives an explicit overview of the variable.
The dependent variable, time delay, is expressed both in terms of original completion date
and adjusted completion date. The chapter also presents the survey results from the online
questionnaire surveys. Survey information reveals the viewpoint of the survey participants
on CPM method of scheduling in the transportation projects.
4.2 Descriptive Statistics
Table 4.1 shows the distribution of projects by project types. It shows that the
majority of the projects in the SiteManager database are either HMAS (48%) or GNRL
(14.5%). Table 4.1 also shows that in the Primavera database slightly more than half of
the projects have a CPM schedules (SSPRIM: 55.22%). The paint and marking projects
(BRPT, PMEP, PMPT, PMRP, and PMTH) and sign and signal projects (SGNL, SIGN)
do not generally use CPM. This is also true for other project types such as guardrail
(GDRL), drainage structure (DRST) and landscape (LDSC). Based on the results from
36
Table 4.1, it can be concluded that certain types of projects are more likely to have a CPM
schedule.
Table 4.1: Distribution of SiteManager Projects, SST Projects and SSPRIM Projects
by Project Types
Type SiteManager Entry in Primavera
(SST)
Valid CPM schedule
projects (SSPRIM)
HMAS 1,007 833 764
GNRL 304 242 195
CGSW 153 107 42
PMTH 108 62 4
ASPT 102 63 52
BRDG 98 83 77
PMRP 89 41 1
GDRL 85 13 2
SGNL 47 22 8
PMEP 21 10 0
PMPT 21 10 0
PCCP 14 12 8
DRST 13 7 2
LDSC 13 7 1
SIGN 12 6 2
BRPT 10 4 0
Total 2,097 1,522 1,158
Table 4.2 presents the distribution of projects by SCDOT districts (3 projects in the
data were not assigned a district). The average number of projects in each district is 299.
The district with most number of projects is district 5 with 352 projects. The number of
projects for each district range from 250 to 352. It can be concluded that the number of
projects is reasonably uniform across districts. All the districts use CPM schedules for more
than half of its projects except for District 7. The district that uses CPM schedules for
majority of their projects than other districts is District 2 (174 out of 287: 60.6%) followed
by District 5 (209 out of 352: 59.4%).
37
Table 4.2 Distribution of Projects by Project SCDOT districts
Districts Total number of Projects Total number of SSPRIM
Projects
1 333 193
2 287 174
3 283 149
4 289 168
5 352 209
6 300 157
7 250 108
Total 2,094 1,158
Table 4.3 shows the distribution of the projects by project size (large, medium and
small). Each group contains about the same number of projects. The last column in Table
4.3 shows the number of scheduled projects in each category.
Table 4.3 Distribution of Projects by Project Size Groups
Project size Groups Total number of Projects Total number of SSPRIM
Projects
Small Projects 702 206
Medium Projects 670 382
Large Projects 725 570
Total 2,097 1,158
Table 4.4 shows the distribution of projects by project duration. Long projects have
larger fraction (286 out of 439: 65.2%) of projects than other two types of projects (short:
43.41% and medium: 55.2%).
Table 4.4 Distribution of Projects by Project Duration Groups
Project duration Groups Total number of
Projects
Total number of
SSPRIM Projects
Short Projects 364 158
Medium Projects 1,294 714
Long Projects 439 286
Total 2,097 1,158
38
4.3 Impact of CPM Schedule on Project Delay
Using the transportation project data described above, the relationship between
project delay and use of CPM schedules are evaluated. In addition to using the TT_Delay
and CO_Delay variables for delay analysis, the following variables are also used to
measure project delay:
• nCO_Delay – Number of projects with a CO_Delay delay greater than zero.
• nTT_Delay – Number of projects with a TT_Delay delay greater than zero.
Table 4.5 Impact of Using a Critical Path Method (CPM) Schedule on Project
Delays by Project Type
Project
Type
Total
number of
projects
Number of projects delayed
after original completion date
(nTT_Delay)
Number of projects delayed
after adjusted completion date
(nCO_Delay)
Delayed
SSPRIM
Delayed
projects
Delayed
SSPRIM
Delayed
projects
ASPT 102 18 38 10 20
BRDG 98 48 58 11 13
BRPT 10 0 5 0 1
CGSW 153 19 64 6 23
DRST 13 1 6 0 3
GDRL 85 2 63 0 3
GNRL 304 108 161 27 39
HMAS 1,007 423 506 113 153
LDSC 13 1 10 0 0
PCCP 14 2 6 0 0
PMEP 21 0 11 0 9
PMPT 21 0 6 0 2
PMRP 89 0 35 0 14
PMTH 108 1 69 0 32
SGNL 47 5 29 1 5
SIGN 12 1 8 0 2
Total 2,097 629 1,075 168 319
•
39
Table 4.5 shows the total number of SSPRIM projects that were delayed versus the
total number of projects that were delayed in terms of nTT_Delay and nCO_delay,
respectively. The results indicate that more than half (nTT_Delay: 629 out of 1,075,
58.51% and nCO_Delay: 168 out of 319, 52.66%) of the delayed projects have a CPM
schedule. The results also indicate that fewer scheduled projects have delay after
considering the impact of change orders.
Figure 4.1 and Figure 4.2 show the impact of having a schedule on the risk of
project delay. Figure 4.1 shows that in the dataset, having a schedule was not effective in
reducing the fraction of delayed projects for most project types. In fact, the project types
that have a significant number of projects (i.e. HMAS, GNRL) show a marked increase in
the fraction of delayed projects when scheduled.
Figure 4.1 Comparison of delayed (TT_Delay) SSPRIM projects and delayed
SSNULL projects (by project type).
40
Figure 4.2 Comparison of delayed (CO_Delay) SSPRIM projects and
In comparing the results shown in Figure 4.1 and Figure 4.2, it can be seen that
there is a reduction in the number of delayed projects when delay is measured using the
adjusted completion date. Moreover, across all project types, the percent of change order
adjusted delayed in scheduled projects is 14.51% compared to 16.08% in the unscheduled
group. This is one of only a few scenarios where scheduling resulted in a reduction in the
number of delayed projects.
Table 4.6 Impact of Using a Critical Path Method (CPM) Schedule on Project
Delays by Project Size
Project size
Groups
Total
number of
Projects
Total
number of
SSPRIM
Projects
Number of Delayed Projects
Number of
projects delayed
after original
completion date
(nTT_Delay)
Number of
projects delayed
after adjusted
completion date
(nCO_Delay)
Small Projects 702 206 275 85
Medium Projects 670 382 338 104
Large Projects 725 570 462 130
Total 2,097 1,158 1,075 319
41
Table 4.6 shows the effectiveness of using CPM schedules on the delay of SCDOT
projects in terms of project size. It also shows the number of SSPRIM projects in each
group that were delayed in terms of original completion date (TT_Delay) and adjusted
completion date (CO_Delay), respectively.
From Table 4.6, the large-sized projects have an increased fraction of projects with
a schedule than the other two groups. Most of the projects in the large group are scheduled
(78.62%). In each group, the number of projects that were delayed, measured by adjusted
completion date (nCO_Delay) is lower than those measured by original completion date
(nTT_Delay).
Table 4.7 Impact of Using a Critical Path Method (CPM) Schedule on Project
Delays by Project Duration groups
Project duration
Groups
Total
number of
Projects
Total
number of
SSPRIM
Projects
Number of Delayed Projects
Number of
projects delayed
after original
completion date
(nTT_Delay)
Number of
projects delayed
after adjusted
completion date
(nCO_Delay)
Short Projects 364 158 175 66
Medium Projects 1,294 714 642 200
Long Projects 439 286 258 53
Total 2,097 1,158 1,075 319
From Table 4.7, In case of delay after original completion date (nTT_Delay), long
project group has fewer fraction of projects (48.1%) that were delayed than the other two
groups (short: 58.8% and medium: 49.6%). This same scenario of delay is also found in
case of delay after adjusted completion date (nCO_Delay).
42
4.4 Identification of Factors Associated with Delay
The statistical significance between the number of projects that were scheduled and
projects that were delayed is tested by Chi-Squared test for independence across all project
types, SCDOT districts and project size. The original completion date (TT_Delay) and
adjusted completion date (CO_Delay) are used to measure delay. The results of the Chi-
Square test for numerous projects are presented in Table 4.8.
Only two combinations are found to be statistically significant at 0.05 level of
significance and they are shown in bold face in Table 4.8. The results indicate that there
is statistically significant evidence that the number of scheduled projects is not independent
of the number of delayed projects when considering all projects and TT_Delay for
determining delay.
The same association is found for scheduled HMAS projects for nTT_Delay.
However, the two statistically significant values considering the TT_Delay mentioned
above show a larger fraction of delayed projects in SSPRIM vs. SSNULL (all projects:
54.32% vs. 47.50% and for HMAS project: 55.35% vs. 34.02%).
Chi-Squared test results for SCDOT districts are also shown in Table 4.8. There
are only two districts (i.e., District 1 and District 7) that show statistically significant
difference in delay (TT_Delay) between SSPRIM and SSNULL projects. In these two
districts, the SSPRIM projects show an increase in the fraction of delayed projects using
nTT_Delay. However, District 5 shows statistically significant evidence that there is a
difference in nCO_Delay between SSPRIM and SSNULL projects and a reduction of
7.58% in the fraction of delayed projects for SSPRIM (4.31% vs 11.89) projects.
43
Table 4.8 Chi-Squared Test Results for Project Types, SCDOT Districts and Project
Size Groups
Number of projects delayed after
original completion date (nTT_Delay)
Number of projects delayed after
adjusted completion date (nCO_Delay)
Delayed
scheduled
Projects
(%)
Delayed
unschedule
d
Projects
(%)
p-value
Delayed
scheduled
Projects
(%)
Delayed
unschedule
d
Projects
(%)
p-value
Chi-square test results for project types
ALL 54.32 47.50 0.002 14.51 16.08 0.339
ASPT 34.62 40 0.7208 19.23 20 >0.999
BRDG 62.33 47.62 0.334 14.29 9.52 0.8357
CGSW 45.24 40.54 0.7323 14.28 15.32 >0.999
GNRL 55.38 48.62 0.3112 13.84 11 0.5957
HMAS 55.35 34.02 0.000 14.75 16.60 0.553
Chi-square test results for SCDOT districts
1 73.57 62.14 0.035 20.21 15.71 0.367
2 57.47 49.55 0.233 14.37 15.04 >0.999
3 46.31 41.79 0.519 13.42 17.91 0.381
4 55.36 54.55 0.986 20.83 23.14 0.746
5 36.36 34.26 0.771 4.31 11.89 0.014
6 53.50 47.55 0.361 15.29 14.69 >0.999
7 60.19 43.66 0.014 14.81 14.79 >0.999
Chi-square test results for project size groups
Small 35.92 40.52 0.293 8.74 13.51 0.102
Medium 48.43 53.13 0.260 15.18 15.97 0.864
Large 64.91 59.35 0.237 16.14 24.52 0.022
Chi-square test results for project duration groups
Short 48.1 48.06 >0.999 13.29 21.84 0.049
Medium 52.66 45.86 0.017 14.85 16.21 0.551
Long 61.89 52.94 0.087 14.33 7.84 0.066
Chi-squared test results for different project size are also shown in Table 4.8. The
test results show that for large projects, there is statistically significant evidence that the
number of scheduled projects (SSPRIM) is not independent of the number of delayed
projects when considering CO_delay. For large projects, there is a reduction of 8.38% in
the fraction of delayed projects in SSPRIM vs. SSNULL (16.14% vs. 24.52%).
44
Table 4.9 t-test Results for Project Types (Considering Original and Adjusted
Completion Date for Delay)
Project
Type
Scheduled
projects
(SSPRIM)
Unscheduled
projects
(SSNULL) Improvement
for having a
schedule (%)
t-value Variance p-
value Mean
delay
(days)
S.D.
(days)
Mean
delay
(days)
S.D.
(days)
t-test results for project type considering Delay (in days) after original completion date
(TT_Delay)
All 121.47 143.59 95.61 106.93 -27.05 3.384 Not Equal 0.0007
ASPT 81.5 105.88 94.4 89.03 13.66 -0.408 Equal 0.686
BRDG 156.44 221.58 50.7 54.98 -208.56 2.905 Not Equal 0.005
CGSW 66.16 69.08 75.98 79.17 12.92 -0.469 Equal 0.64
GNRL 153.76 187.15 86.57 89.96 -77.62 3.076 Not Equal 0.002
HMAS 114.11 121.52 70.88 105.48 -60.99 3.025 Equal 0.003
t-test results for project type considering delay (in days) after adjusted completion date
(CO_Delay)
All 32.20 50.13 38.85 52.31 17.11 -1.158 Equal 0.248
ASPT 46.5 56.12 44.5 52.13 -4.50 0.083 Equal 0.935
BRDG 27.55 23.72 7.5 3.54 -267.27 1.152 Equal 0.274
CGSW 18.5 29.51 32.41 48.13 42.92 -0.659 Equal 0.517
GNRL 47.15 91.13 29.92 30.81 -57.60 0.876 Not Equal 0.387
HMAS 28.81 37.05 34.23 42.01 15.81 -0.766 Equal 0.445
In the above, the number of delayed projects is discussed. In the following, the
mean delay (in days) is analyzed. The null hypothesis (H0) is that there is no statistical
difference between the mean number of delay (in days) between SSPRIM and SSNULL
projects. These tests are conducted for all projects by type, SCDOT district and project
size.
The results of the t-test for different project types are shown in Table 4.9
considering both TT_Delay and CO_Delay, respectively. The results from Table 4.9 show
that, for the TT_Delay, all, bridge, general, and hot-mixed asphalt paving have statistically
significant increase in the mean delay for projects with a CPM schedule.
45
Table 4.10 t-test Results for SCDOT Districts (Considering Original and Adjusted
Completion Date for Delay)
SCDOT
District
Scheduled projects Unscheduled
projects Improve
ment for
having a
schedule
t-value Variance p-value Mean
Delay*
SD(days
)
Mean
Delay
*
SD(day
s)
t-test results for SCDOT districts considering delay (in days) after original completion date
(TT_Delay)
1 163.73 152.93 133.60 138.73 -22.55 1.50 Equal 0.135
2 96.14 156.54 77.86 82.31 -23.48 0.813 Not Equal 0.418
3 69.96 77.22 68.91 74.64 -1.52 0.076 Equal 0.939
4 101.68 113.68 87.21 94.68 -16.59 0.846 Equal 0.398
5 131.64 146.27 110.71 145.60 -18.91 0.782 Equal 0.435
6 125.88 153.34 87.38 69.98 -44.06 1.914 Not Equal 0.057
7 133.52 154.04 89.92 100.44 -48.49 1.87 Not Equal 0.062
t-test results for SCDOT districts considering delay (in days) after adjusted completion date
(CO_Delay)
1 43.90 60.73 29.25 27.91 -50.08 0.811 Not Equal 0.421
2 26.35 30.39 29.09 29.78 9.41 -0.258 Equal 0.798
3 24.28 38.55 28.38 25.07 14.44 -0.286 Equal 0.776
4 26.17 35.25 45.68 57.12 42.71 -1.664 Not Equal 0.101
5 44.18 65.98 51 53.68 13.38 -0.266 Equal 0.792
6 45.52 72.03 44.08 38.27 -3.24 0.065 Not Equal 0.948
7 15.35 15.88 43.35 82.88 64.59 -1.482 Not Equal 0.147
Table 4.11 t-test Results for Project Size Groups (Considering Original and
Adjusted Completion Date for Delay)
Project Size
Groups
Scheduled
projects
Unscheduled
projects Improve
ments
for
having a
schedule
t-
value Variance
p-
value Mean
Delay
(days)
SD
(days)
Mean
Delay
(days)
SD
(days)
t-test results for project size groups considering delay (in days) after original completion date
(TT_Delay)
Small 67.01 65.89 82.52 98.64 18.79 -1.50 Not Equal 0.136
Medium 88.57 106.63 99.12 89.58 10.64 -0.85 Equal 0.396
Large 150.28 163.88 119.18 128.77 -26.09 1.956 Not Equal 0.052
t-test results for project size groups considering delay (in days) after adjusted completion date
(CO_Delay)
Small 16.61 11.75 36.12 54.73 54.01
-2.70 Not
Equal 0.009
Medium 28.31 35.64 40.26 54.84 29.68 -1.28 Not Equal 0.205
Large 37.71 60.84 41.95 45.42 10.11
-
0.436 Not Equal 0.664
46
The results of t-test for all the SCDOT districts are also presented in for TT_Delay
and CO_Delay respectively. The mean delay based on original completion date is less in
unscheduled projects in all districts albeit the p-values are greater than 0.05. The delay
including change orders by district is not statistically significant.
Table 4.11 shows the t-test results for the projects categorized by project size.
There is an almost significant decrease in the mean delay from 150 to 119 days for
unscheduled large projects (p-value = 0.052). Small-sized projects show an increase in the
change order adjusted delay for unscheduled projects. This one category indicates CPM
schedules mitigate project delays. Table 4.12 shows similar results for project duration
groups.
Table 4.12 t-test Results for Project Duration Groups (Considering Original and
Adjusted Completion Date for Delay)
Project
Duration
Groups
Scheduled
projects
Unscheduled
projects Improve
ments
for
having a
schedule
t-
value Variance
p-
value Mean
Delay
(days)
SD
(days)
Mean
Delay
(days)
SD
(days)
t-test results for project duration groups considering delay (in days) after original completion
date (TT_Delay)
Short 100.05 103.31 56.58 77.85
2.621 Not
Equal 0.009
Medium 104.77 129.59 85.7 96.92 1.585 Not Equal 0.115
Long 166.15 174.43 72.5 46.46
4.805 Not
Equal 0.0
t-test results for project size groups considering delay (in days) after adjusted completion date
(CO_Delay)
Short 27.33 20.68 43.77 67.18
-
1.093 Not Equal 0.278
Medium 31.67 50.07 36.94 46.86
-
0.765 Equal 0.445
Long 36.07 35.33 60.58 23.29 0.063 Not Equal 0.949
47
4.5 Survey Results of the Use Of CPM
The online questionnaire survey was distributed nationwide to all the DOTs,
Resident construction Engineers and contractors working with DOTs. The survey was open
for a period of little over 1 month, from June 14, 2017 to July 23, 2017. A total of 22 states
with 23 people from the DOTs, 51 resident engineers form 16 different states and 45
contractors working in 16 different states responded to the survey. The survey centered on
selection criteria for CPM projects, preferred scheduling techniques and software use,
contract requirements of CPM projects, decision making on CPM schedules, delay factors
associated with CPM, RCE evaluation of CPM use by the contractors, appointment and
tasks of schedulers and value of CPM in the company. Section 5.6.1 to 5.6.3 presents the
viewpoint of DOTs, RCEs and contractors on CPM.
4.5.1 State DOTs viewpoint on CPM scheduling
Question 2 in the DOT survey asked about the use of CPM method in DOT projects.
It is found from the survey that; CPM schedule method is undoubtedly most widely used
scheduling technique used by the state DOTs.
CPM schedule method is undoubtedly most widely used scheduling technique used
by the state DOTs. From the survey of state DOTs, nearly 95% of the responding state
DOTs (22 out of 23) use CPM for project management. The state DOTs not only use CPM
but also use other scheduling techniques. shows that the eight (8) state DOTs (36.4%) only
use CPM schedules for project management. Figure 4.3 Other techniques used by state
DOTs for scheduling that includes Gantt charts (50%), milestone charts (13.6%) and other.
The responding state DOTs mentioned in the comment section of the other techniques for
48
scheduling which includes bar charts, customized scheduling forms, and monitoring charts.
Among these other techniques, 50% of state DOTs (11 out of 22) that use CPM scheduling
also use Gantt charts and it also stands out as a popular technique of scheduling.
Figure 4.3 State DOTs answer to question 10
Question 3 explores the criteria for selecting a project for CPM scheduling. Figure
4.3 shows that the top three reasons for selecting a project for CPM schedules indicated by
the state DOTs are: complexity of the project (16 out of 23, 69.6%), risk associated with
the project (12 out of 23, 52.2%), total bid amount of the project (6 out of 23, 26.1%).
Other reasons for the selection of CPM schedules include: following rules and regulation
of the agency (21.7%), contract special provisions, incentives/disincentives, preference of
contractors, and use CPM schedules for all projects.
49
Figure 4.4 State DOTs answer to question 3
Questions 4 and 5 examined the contractual specifications of CPM for projects.
Figure 4.5 reveals that the state DOTs (22) that use CPM schedules, only 13.6% state DOTs
(3 out of 22) indicated that they do not require CPM specification for each of their projects.
Among the state DOTs that require a CPM specification for each of their projects, the state
DOTs were equally split (8 out of 22, 36.4%) as to whether all or some of the projects
require CPM specifications. The remaining state DOTs (3 out of 22, 13.6%) require CPM
specification for most of their projects. Figure 4.6 shows that half of the state DOTs (11
out of 22) reported that they use a standard CPM specifications for all the projects while
nearly 18% (4 out of 22) of them use a customized CPM specifications for project
management.
50
Figure 4.5 State DOTs responses to question 4
Figure 4.6 State DOTs responses to question 5
51
Questions 6, 11, 12, and 13 dealt with software preferences for scheduling for
transportation projects. Different versions of Primavera P6 are the first choice for CPM
scheduling. Figure 4.7 shows that all the responding state DOTs reported that they use
different versions of Primavera P6 and half of the state DOTs (11 out of 22) use Primavera
P6, version 8 for project management. Also, the use of other software for scheduling
indicated by the state DOT includes: Primavera P3 (9.1%), different versions of MS Project
(MS project 2010: 13%, MS project 2013: 4.3%, MS project 2016: 13%), and Asta
PowerProject. In response to questions 11, 12, and 13 the respondents’ software preference
includes MS Excel, contractors’ choice, pen/paper and customized DOT form (i.e. MDOT
form 1130).
Figure 4.7 State DOTs responses to question 6
52
In response to question 7, as shown in Figure 4.8, reveals the type of information
loaded with CPM schedules. Most DOTs incorporate either resource (5 out of 22, 22.7%)
or cost (2 out of 22, 9%) or both (6 out of 22, 27.3%) in their CPM schedule. Other
information in CPM schedules includes different specifications for cost and resource
loading (i.e. cost and/or resource for if contract amount exceeds certain dollar values), and
project specific calendars.
Figure 4.8 State DOTs responses to question 7
Question 8, 9, and 14 explores the option of cloud storage of schedule database and
access to the database. Only three (3 out of 22) state DOTs are currently hosting their
database on the cloud. Figure 4.9 shows that the state DOTs are indecisive about hosting
its scheduling database on the cloud in the future. While nearly 10% (2 out of 22) have a
certain plan to move its database to the cloud, 45% (10 of 22) of state DOTs indicated that
53
they “may” move its scheduling database on to the cloud in the next five years. The
remaining state DOTs (7 out of 22, 31.8%) have no plan to move its database on the cloud.
Figure 4.9 State DOTs response to question 9
Figure 4.10 State DOTs responses to question 14
54
Figure 4.10 reveals that the state DOTs are very restrictive in terms of allowing
contractors to access its schedules. More than two-thirds (17 out of 22, 77.3%) of the state
DOTs do not allow contractors to access their schedules. Only few (2 out of 22, 9.1%)
provide access to its scheduling provided it is recorded in the contract and the remaining
respondent DOTs (3 out of 22, 13.6%) provide access to the schedules database.
Figure 4.11 State DOTs responses to question 15
Questions 15 aims to find the reasons for a revised CPM schedule. Figure 4.11
shows that almost all of the state DOTs (21 out of 22, 95.5%) agreed that a revised CPM
schedules is required if changes occur in the critical path of the project. Nearly 65% (14
out of 22) of the responding state DOTs indicated that change orders in a project was
another reason for a revised CPM schedules. Other situations for a revised CPM schedules
include: resource un-availability, changes of activity original duration, monthly updates,
55
contract time changes, contractors’ deviation from current progress schedules, project
behind schedules exceeds certain days, and time extension for revised schedules.
It is unanimously agreed by all the state DOTs from responses on question 16 that
they use CPM schedules as a forensic tool. All the state DOTs (22 out of 22) reported that,
they rely on the CPM schedules for assessing claims. Among these state DOTs, little over
40% (9 out of 22) use CPM for all the claims for the project and the remaining state DOTs
(13 out of 22) use it for assessing selected claims.
4.5.2 Resident construction engineers’ viewpoint on CPM scheduling
A total of 51 resident construction engineers from sixteen (16) different states
responded to the online questionnaire survey. Most of the participants of the survey (33 out
of 51, 64.7%) are working for South Carolina Department of Transportation (SCDOT).
Resident construction engineers were asked in the question 2 of the survey for the
criteria of selecting a project for CPM schedules. Figure 4.12 shows than, the top three
reasons indicated were: complexity of the project (92.2%), risk associated with the project
(60.8%), total duration of the projects (52.9%). Other reasons for selection of CPM
schedules include: total bid amount of the project, previous experience with similar type of
work or contractor, following rules and regulations of the agency/client. In addition to these
some RCEs also mentioned anticipated conflicts, time incentives, and use CPM schedules
for all projects as criteria for selecting projects.
There were couple of survey questions for the resident engineers regarding
contractors’ use of CPM schedules for projects. Nearly 30% of the resident construction
56
Figure 4.12 RCEs responses to question 2
Question 3 examined the decision-making aspect of CPM schedules by the RCEs.
More than 80% (44 out of 51) of the responding resident engineers indicated that they rely
on CPM for making decision on projects. Figure 4.13 presents that among them (34 out of
51, 66.7%) occasionally refer to CPM schedules for decision making. Close to 20% of
responding RCEs (10 out of 51) refers CPM frequently while remaining 13.7% (7 out of
51) never use CPM schedules for decision making on the project.
Figure 4.13 RCEs responses to question 3
57
Figure 4.14 RCEs response to question 4
Questions 4 and 5 aimed at evaluating contractors’ effort to use regarding CPM
schedule by RCEs. Figure 4.14 shows that almost 70% of the responding RCEs (36 out of
51) replied that contractors strive to follow CPM schedules. Among the respondents who
believe contractors make considerable effort to follow the CPM schedules indicated that
nearly 69% (25 out of 36) do it for most of the projects. There were no resident engineers
who mentioned that contractors strive to follow CPM schedules for all the projects.
Responses of question 5 is shown in Figure 4.15. It reveals that over half of the responding
resident engineers (28 out of 51, 54.9%) indicated that contractors prepare a CPM
schedules whether it is required by the contract or not.
58
Figure 4.15 RCEs responses to question 5
Questions 6 through 9 are aimed to find the factors perceived by the resident
engineers that results in extension of project planned duration. Figure 4.16 shows that a
little over 55% of the resident engineers (29 out of 51) experience that the duration between
the NTP and start of work of the construction projects consume a significant fraction of the
total duration of the project. Among them, two-thirds (22 out of 29) of the resident
engineers indicated that it occurs for some of the projects but not for all projects.
Figure 4.16 RCEs responses to question 6
59
In response to question 7, as shown in Figure 4.17, nearly 68% (35 out of 51) of the
resident engineer observed that significant number of change orders from contractors
occurs in the last third of the project. Among these resident engineers, 71% (25 out of 35)
indicated that it occurs for some of projects but not for all projects.
Question 8 tries to find out the common reasons for project time extension. Figure
4.18 indicates the top reasons for requesting project extension indicated by the resident
engineers are: contract modifications (70.6%), weather (66.7%), and change orders by
owner (56.9%). Other reasons for project extension includes: inadequate planning and
Figure 4.17 RCEs responses to question 7
60
Figure 4.18 RCEs responses to questions 8
scheduling, resource constraints, delay in approving drawing and materials by owner. The
main comment for this question from the resident engineers was that utility issues (i.e.
conflicts, relocations, permissions, delays) play significant part for project time extension.
Answer from resident engineer for Question 9 indicates that nearly 60% (31 out of 51) of
the resident engineers indicated the CPM schedules do not reduce the number of change
orders.
Answer to the Question 10 of the survey reveals that it is a widespread practice to
use CPM for claim analysis and decision making for projects. Figure 4.19 shows that more
than 80% (41 out of 51) of the resident engineers use CPM for assessing claims to some
extent. Among them, 39% (16 out of 41) use CPM for all the claims related to projects.
61
Figure 4.19 RCEs response to question 10
4.5.3 Contractors viewpoint on CPM scheduling
A total of 45 contractors working in sixteen (16) different states responded to the
survey. Some of the contractors are working for multiple states and a few are working
across all states. The top two responses are from the contractors working in the state of
Michigan (17 out of 45, 37.8%) and South Carolina (12 out of 45, 26.7%).
Question 2 examined the contractual specification that requires a CPM schedule for
the project. Figure 4.20 shows that more than 90% (41 out of 45) of the responding
contractors replied that the projects require a CPM schedule. Majority of the contractors
(17 out of 45, 37.8%) indicated that CPM schedule is required for most of the projects and
62
close to 30% (13 out of 45, 28.9%) of contractors replied that it is a common requirement
when the project contract amount is greater than 5 million.
Figure 4.20 Contractors responses to question 2
Questions 3 and 7 aimed to find if the contractors maintained a separate schedule
for projects. Figure 4.21 shows that two-thirds (30 out of 45) of the responding contractors
prepare a CPM schedule whether it is required in the contract or not. In addition to that,
answer to question 7 shown in Figure 4.22 reveals that three-fourth (34 out of 45) of the
contractors maintain a separate schedule for work apart from the contract specified
schedule. One-fourth (11 out of 45) of the responding contractors maintain a separate
schedule for all their projects. It shows that having a CPM schedules for projects is
important to the contractors.
63
Figure 4.21 Contractors responses to question 3
The result of question 4, shown in Figure 4.23, revealed that more than 80% (37
out of 45) of the responding contractors use CPM for making decision on projects. In
addition to that, contractors who use CPM schedule for decision making, more than half of
them (20 out of 37) use it frequently.
Figure 4.22 Contractors responses to question 7
64
Figure 4.23 Contractors responses to question 4
Figure 4.24 Contractors response to question 5
65
Question 5 discovers the cost of CPM schedule with respect to total cost of project.
Figure 4.24 reveals that nearly 64% (29 out of 45) of the contractors indicated that the cost
of applying CPM schedules in projects is below 0.5% of the total cost.
Question 6 explores the schedule technique used by the contractors. Figure 4.25
shows that nearly 30% (13 out of 45) of the responding contractors indicate that they only
use CPM for scheduling. The use of only CPM schedules may be because of contract
requirement from the owner. Gantt (26 out of 45, 57.8%) and Milestone charts (22 out of
45, 48.9%) are probably preferred techniques used by the contractors than only using CPM
for scheduling. Apart from these three techniques for scheduling other techniques include
bar charts, line chart, and two or 3 weeks look ahead schedules.
Figure 4.25 Contractors responses to question 6
66
Figure 4.26 Contractors responses to question 8
Question 8 was about the use of CPM schedule as forensic tool. Figure 4.26 shows
that more than 80% (37 out of 45) of the contractors use CPM for assessing claims to some
extent. Among them 11.1% (11 out of 45) use CPM for all the claims related to projects.
Questions 9 to 11 aimed to find out the importance of a scheduler and tasks of
scheduler. Figure 4.27 shows that more than half of the contractors (25 out of 45) only use
their in-house personnel to perform the task of CPM scheduling. Contractors rarely (2 out
of 45, 4.4%) use only outside consultant to perform CPM scheduling, but 40% (18 out of
45) of the contractors reported that they use a combination of in-house and outside
consultant to prepare CPM schedules.
67
Figure 4.27 Contractors responses to question 9
Answer to question 10, as shown in Figure 4.28, shows that only close to 30% (13
out of 45) of the contractors indicated that they employ a dedicated person responsible for
planning and scheduling tasks.
Question 11 explores the tasks of scheduler. Contractors responses, as shown in
Figure 4.29 reveals that the in-house individuals not only prepare CPM schedules (6 out of
45) but also performs other duties such as, cost estimation (24 out of 45), project
management other than scheduling (32 out of 45), and administration (12 out of 45).
Comments made by the contractors to this question indicated some other duties the
scheduler performed that includes: supervision, engineering, surveying, IT, labor, and
organizing training program.
68
Figure 4.28 Contractors responses to questions 10
Figure 4.29 Contractors responses to question 11
69
Figure 4.30 Contractors responses to question 12
Question 12 evaluates the importance of CPM schedule for the success of their
company. On a scale of 4 (1 being very important and 4 being unsure) as shown in Figure
4.30, contractors ranked the importance of CPM. Less than one-fifth (8 out of 45)
contractors have doubts regarding the contribution of using CPM schedules on their
projects for future success. This is contrary to the belief that using CPM schedules for
projects enhances the chance of a project to be successful.
4.6 Chapter summary
This chapter discusses findings into two parts. First part explores the statistical
analysis of the transportation data and the later part shows the information acquired from
the survey of DOTs, RCEs and contractors. Chi-square test of independence showed that
scheduled project has association for certain project types, size and duration groups.
Similar type of results is also found when comparing the mean delay for scheduled and
unscheduled projects using t-tests. The survey reveals the viewpoint on CPM from DOTs,
RCEs and contractors’ perspective.
70
CHAPTER 5: DISCUSSION
5.1 Introduction
This chapter provided insights of the results from statistical analysis of the project
data presented in chapter 4. The chapter discusses the results in two parts. First part focuses
on the results obtained from the statistical analysis of the project data. The second part
concentrates on the result from the online questionnaire survey.
5.2 Observations from the Statistical Analysis
Descriptive statistical analyses are shown in Table 4.1 to Table 4.4. Descriptive
statistical analysis aims to find out the distribution of total number of projects in
SiteManager and total number of project with a valid CPM schedules in Primavera
database. The distribution of projects is explored in terms of independent variables, such
as project types, project locations, project size groups, and project duration groups.
The SiteManager database contains a total of 2,097 projects for the analysis period
(2007 - 2015). Most of the project are Hot-mixed Asphalt paving (HMAS: 48%). More
than half of the total projects have a valid CPM schedules. Table 4.1 shows that certain
types of projects are likely to have a CPM projects (i.e. ASPT, BRDG, GNRL, HMAS)
than other types of project (i.e. paint and marking; sign and signal). The distribution of
projects across the SCDOT districts is reasonably uniform. The total number of projects
range from 250 to 352 with an average of 299 projects. All the SCDOT districts used CPM
71
schedules for more than half of its projects except for District 7 (43.2%). District 2 used
CPM schedules for majority of the projects (60.6%) comparing with other SCDOT
districts. Distribution of projects by project size in Table 4.3 reveals that CPM schedules
are more frequent in projects with larger bid amount than other groups. The same
distribution is also found in case of project duration groups. Projects with longer duration
tend to have a CPM schedule than others. CPM schedules helps in planning and managing
projects. Since, larger and longer projects have more risks involved, they are inclined to
CPM schedules. It can be concluded that, larger bid amount and longer projects of certain
types of transportation projects are more likely to have a CPM schedules.
Table 4.5 to Table 4.7 and Figure 4.1 to Figure 4.2 explores the relationship
between project delay and the use of CPM schedules in transportation projects. Project
delay is measure in terms of original completion date and adjusted completion date. More
than half of the projects that were delayed have a CPM schedules. Having a schedule was
found to be not effective when considering the original completion date for delay. Besides,
numerous project types (i.e. HMAS, GNRL) have shown an increase in fraction of delayed
projects when scheduled. On the other hand, considering the adjusted completion date for
delay shows that a CPM schedule was effective in reducing the fraction of delayed projects.
This results also reciprocate for particular types of projects (i.e. ASPT, CGSW, HMAS)
but not for all types. Across all project size groups, more projects were delayed considering
original completion date than adjusted completion date. Similar results are also found when
projects are categorized by project duration. These results show that for certain types of
projects with any project size and duration, fewer scheduled projects have delay after
considering the impact of change order.
72
A summary of the results from both chi-square test of independence and t-tests are
shown in Table 5.1.
Table 5.1 Summary of the statistical tests
Independent
variable
Chi-square test of Independence t-tests
TT_Delay CO_Delay TT_Delay CO_Delay
Project type
ALL Significant (-) - Significant (-) -
ASPT - - - -
BRDG - - Significant (-) -
CGSW - - - -
GNRL - - Significant (-) -
HMAS Significant (-) - Significant (-) -
Districts
1 Significant (-) - - -
2 - - - -
3 - - - -
4 - - - -
5 - Significant (+) - -
6 - - - -
7 Significant (-) - - -
Project size
Small - - - Significant (+)
Medium - - - -
Large - Significant (+) - -
Project Duration
Short - Significant (+) Significant (-) -
Medium Significant (-) - - -
Long - - Significant (-) -
“-“is used if the result is not statistically significant for significance level of 0.05
(+) indicates that, improvement (reduced delay) for having a schedule.
The chi-square test of independence is used to answer the following question: is
there a statistically significant association between the number scheduled projects and
number of delayed projects? Considering original completion date for delay, the chi-square
test of independence shows that number of scheduled projects of certain project types (i.e.
ALL, HMAS), particular SCDOT districts (i.e. District 1 & 7) and medium duration
projects are not independent of the number of delayed projects. However, all these
73
statistically significant values show a larger fraction of delayed projects are scheduled
projects. On the other hand, when considering adjusted completion date for delay, the
number of scheduled projects for projects in particular districts (District 5), large-sized,
and short duration are not independent of the number of delayed projects. The results
indicate that fewer fraction of scheduled projects are delayed after taking into account of
the impact of change order.
The t-tests tries to find the answer to the following question: is there a statistically
significant difference in mean delay days between scheduled projects and unscheduled
projects? Considering original completion date for delay, the t-test shows statistically
significant results for certain project types (i.e. ALL, HMAS), short, and long duration
projects. However, the mean delay of scheduled projects for these categories are larger than
the unscheduled projects. When delay is measured using adjusted completion date, only
small-sized projects are found to be significant. The mean delay for scheduled small-sized
projects are smaller than the unscheduled projects.
5.3 Observations from the Survey Result
The purpose of the survey was to explore the viewpoint of DOT personnel, resident
construction engineers and contractors on the impact and use of CPM schedules for
transportation projects. The survey also tried to identify issues regarding specifications of
CPM schedules for projects. The survey focused on the topics indicated in
Table 3.1. Twenty-three (23) DOT personnel, fifty-one (51) RECs and forty-five
(45) contractors responded to three separate the surveys. The survey questions are attached
74
in Appendix-C and the summary of the surveys is presented in the Table 5.2. Some of the
issues faced by DOTs, RCEs and contractors are:
• Gantt and Milestone charts method of scheduling are more popular than
CPM among contractors. It is due to fact that these methods are easier to
implement and do not require skilled personnel.
• Selection of CPM for projects depend mainly upon perceived risks and
complexity of projects. The risks and complexities are measured in terms of
size and duration of the project. More sophisticated risk analysis is required.
• Specifications of scheduling is common in transportation contracts. But
most of the state agencies do not request resource/cost loading to enforce
the use of CPM schedules.
• Contractors sometimes maintain separate schedule for work. As a result, the
state agencies do not get a chance to review the actually implemented
schedules on work. This reveals the enforcing issue faced by the state
DOTs.
• Popular scheduling tool includes Primavera products and Microsoft
products.
• Delay before starting work in the field generally do not impact the original
duration of the project.
• Contractors do not feel the need for a dedicated person as a scheduler. But
CPM scheduling required skilled person which may impede the benefits of
CPM schedules.
75
Table 5.2 Summary of the online questionnaire surveys
Topic focused
on the survey DOTs RCEs Contractors Summary
Scheduling
technique
preferred
Q2,
Q9 - Q6
• Almost all the state DOTs use CPM method of scheduling. One of the popular
method of scheduling among DOTs along with CPM is Gantt charts.
• Among the contractors Gantt chart and Milestone charts scheduling method are
more popular than CPM.
Selection of
projects for
CPM
schedule
Q3 Q2 -
• The top two reasons for selecting projects for CPM schedule from DOT and
RCEs viewpoint are: complexity and risks associated with projects.
• There is difference on opinion between DOTs and RCEs in the third reason for
the selection criteria. DOTs selected total bid amount though RCEs selected
total duration of the projects.
Contract
requirements /
specifications
of CPM
scheduling
Q4,
Q5,
Q7
- Q2
• Most of the DOTs require CPM specification for each project. In most cases,
these specifications are a standard one but there are few exceptions.
• The contractors also acknowledged that they find specification for CPM
schedules in the contracts.
• Most of the contractors (two-thirds of responding contractors) prepare CPM
schedules even though the requirement is waived in the specification.
• DOTs do not necessary request for cost-loaded or resource-loaded or both
information loaded schedules from the contractors.
Scheduling
software
used/preferred
Q6,
Q11,
Q12,
Q13
- -
• The preferred software among DOTs are the different versions of Primavera
P6 products for CPM scheduling.
• Besides other software like MS Project, Asta Powerproject are also used.
• Some DOTs also have customized forms for scheduling. These forms provide
more control over the projects.
Decision
making Q3 Q4
• Both the RCEs and contractors use CPM schedules for decision making.
76
Topic focused
on the survey DOTs RCEs Contractors Summary
• RCEs consult schedule occasionally while contracts consult it more frequently.
Storage and
Access of
schedule
database
Q8,
Q14,
Q17
- -
• Only a few DOTs store its schedule database on the cloud.
• Most of the DOTs are unsure about the cloud storage of its database in next
five years.
• DOTs have a restrictive mindset in allowing access to its schedule database.
Effort made
to follow
CPM
schedule
- Q4 -
• In evaluating contractors’ efforts to use CPM use, more than one-fourth of
RCEs perceive that contracts do not make enough attempts to follow CPM
schedules.
Use of CPM
schedule
(planning,
claim
analysis,
revisions of
CPM etc.)
Q16 Q5,
Q10 Q3, Q7, Q8
• The most unanimously agreed reason to use CPM schedule other than
scheduling is assessing claims.
• Most of the contractors maintain a separate CPM schedules for work along
with contract specified schedule.
• Though the importance of CPM schedules among contractors are
acknowledged, a significant fraction of RCEs perceive that the contractors do
not make sufficient effort to follow the CPM schedule for project management.
Project
extension /
Delay
associated
with CPM
schedule
-
Q6,
Q7,
Q8,
Q9
-
• Most of the RCEs indicate that the time between NTP and first start of work
do not impact the project delay.
• Most of the RCEs agree that the majority of the change orders of the project
occurs in the last third of the projects. But they also think that a CPM schedule
do no help in reducing the number of change orders.
• Contract modification is identified as the major cause of project extension by
the RCEs, followed by weather and change orders from owners. Also, ‘utility
conflicts’ is another reason identified for project extension.
77
Topic focused
on the survey DOTs RCEs Contractors Summary
Schedulers
requirements
and tasks
- - Q9, Q10,
Q11
• Most contractors do not have a dedicated person for scheduling. Scheduling is
performed by either in-house only or combination of in-house and outside
consultant.
• The schedulers not only perform the task of scheduling but also executes other
tasks such as administration, cost estimation, supervision etc.
Cost of CPM
application - - Q5
• From contractors’ perspective, the cost of CPM schedule rarely exceeds 2.5%
of the total cost of the project.
Value of
CPM for
success of the
company
- - Q12
• The average rating for the value of CPM is 2.1 (scale 1 to 4, 1 being very
important) from the contractors’ perspective. It shows that contractors
recognize CPM schedule as important but not evident yet.
78
5.4 Chapter Summary
This chapter provide insights on the findings from the statistical analysis and online
questionnaire survey. The statistical analysis reveal that CPM schedules have association
for particular project types, districts, size, and duration groups but not for all. The surveys
reveal some of the issues like enforcing the use of CPM schedules, sophisticated risks
analysis as selection criteria, and need of a skilled scheduler.
79
CHAPTER 6: CONCLUSIONS
The analysis and results provided in Chapter 4 and 5 gives insight on the general
characteristics of project data in South Carolina, associations between fraction of delayed
projects and use of CPM schedules, and the impact of a CPM schedule on the risk of delay.
The type of project has an influence on whether the requirement for a CPM
schedule is waived. Paint and marking, sign and signal, guardrail, drainage structure and
landscape projects are not generally associated with a CPM schedule in the South Carolina
data. In regard to delay after original contract completion date, the project types with a
significant fraction of the total number of project (i.e. HMAS, GNRL) show a marked
increase in the fraction of delayed projects when a CPM schedule is provided to the DOT.
Statistically significant relationships between mean delay and CPM scheduled projects
exists for some project types (i.e., HMAS) but not for all.
After considering adjustments due to change orders (CO_Delay), fewer scheduled
projects have delays compared to when the delay is measured using original contract
completion date (TT_Delay). However, Chi-Squared testing revealed that the number of
scheduled projects and CO_Delay are independent for all project types. Statistically
significant associations between the number of scheduled projects and CO_Delay were
found for District 5 (SSPRIM: 4.35% vs SSNULL: 11.72%) and large-sized projects
(SSPRIM: 16.14% vs. SSNULL: 24.52%).
80
Three project types: BRDG, GNRL and HMAS have statistically significant
difference in mean delay after original completion date for scheduled and unscheduled
projects. In addition, small sized projects show the statistically significant difference but
for mean delay after adjusted completion date. Finally, change order schedule adjustments
are more effective in reducing CO_Delay with projects using CPM.
Considering the widespread use of CPM, the finding of an increased fraction and
length of project delay with the use of CPM scheduling was unexpected by the authors.
We conjecture that one or more of the following are occurring:
• Construction personnel are not using CPM scheduling properly.
• The use of CPM provides an unwarranted belief that the project will be delivered
on time until late in the project.
• Having a CPM schedule does not automatically allow one to manage all the risks
associated with construction projects and mitigate delays.
• There was an unidentified selection bias of waving CPM schedules for project with
less risk of delay.
Additional research is needed to verify if one of the reasons contributed to the
ineffectiveness of CPM scheduling. The survey of state DOTs, RCEs and contractors
reveals some of the key issues regarding the use of CPM:
• Selection Criteria: The CPM schedules are selected based on the perceived
complexity and risks, generally measure in terms of project size and duration. More
sophisticated risk analysis should be incorporated in the selection criteria.
81
• Enforcing: Specifications for schedule do not necessarily request cost/resource
loaded schedules. A resource loaded schedule will help the DOT personnel to
review the schedule that represent practical situations. Hence, regular updates and
review should be enforced.
• Scheduler: CPM schedules requires skilled person to implement correctly. Most of
the contractors do not employ a dedicated scheduler in their workforce. As a result,
the full potential of CPM schedules is not put into practice.
82
REFERENCES
Aibinu, A. A., & Jagboro, G. O. (2002). The effects of construction delays on project
delivery in Nigerian construction industry. International Journal of Project
Management, 20(8), 593–599. http://doi.org/10.1016/S0263-7863(02)00028-5
Al‐Kharashi, A., & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector
construction projects. Construction Management and Economics, 27(1), 3–23.
http://doi.org/10.1080/01446190802541457
AASHTOWare. (n.d.). About AASHTOWare. Retrieved October 31, 2017, from
http://www.aashtoware.org/Pages/About-AASHTOWare.aspx
Arditi, D., & Gunaydin, H. M. (1998). Factors That Affect Process Quality in the Life
Cycle of Building Projects. Journal of Construction Engineering and Management,
124(3), 194–203. http://doi.org/10.1061/(ASCE)0733-9364(1998)124:3(194)
Assaf, S. a., & Al-Hejji, S. (2005). Causes of delay in large construction projects.
International Journal of Project Management, 24(4), 349–357.
http://doi.org/10.1016/j.ijproman.2005.11.010
Assaf, S. a., Al-Khalil, M., & Al-Hazmi, M. (1995). Causes of Delay in Large Building
Construction Projects. Journal of Management in Engineering, 11(2), 45–50.
http://doi.org/10.1061/(ASCE)0742-597X(1995)11:2(45)
Boland, P. J. (2007). Statistical and probabilistic methods in actuarial science. Chapman
& Hall/CRC Press.
83
Bordat, C., Mccullough, B. G., Labi, S., & Sinha, K. C. (2004). An Analysis of Cost
Overruns and Time Delays of INDOT Projects (Rep. No. FHWA/IN/JTRP-2004/7).
West Lafayette, IN: Purdue University.
doi:https://docs.lib.purdue.edu/cgi/viewcontent.cgi?article=1482&context=jtrp
Chan, D. W. M., & Kumaraswamy, M. M. (1996). An evaluation of construction time
performance in the building industry. Building and Environment, 31(6), 569–578.
http://doi.org/10.1016/0360-1323(96)00031-5
Crossett, J., & Hines, L. (2007). Comparing State DOTs’ Construction Project Cost and
Schedule Performance: 28 Best Practices from Nine States. (Rep. No. NCHRP
Project 20-24). doi:http://onlinepubs.trb.org/onlinepubs/archive/notesdocs/20-
24(37)a_fr.pdf
Crossett, J., & Schneweis, K. Measuring Performance among State DOTs: Sharing Best
Practices-Construction and Budget Performance Update. (Rep. No. NCHRP Report
20-24 (37) A (01)), Transportation Research Board, Washington, D.C., 2011.
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting
delays in Indian construction projects. International Journal of Project
Management, 30(4), 479–489. http://doi.org/10.1016/j.ijproman.2011.10.004
Galloway, P. D. (2006). Survey of the Construction Industry Relative to the Use of CPM
Scheduling for Construction Projects. Journal of Construction Engineering and
Management, 132(7), 697–711. http://doi.org/10.1061/(ASCE)0733-
9364(2006)132:7(697)
Gantt, H. L. (1910). Work, Wages and Profit, The Engineering Magazine, New York, 1910.
84
Galway, L. (2004). Quantitative Risk Analysis for Project Management (Working paper
No. WR-112-RC).
doi:http://citeseerx.ist.psu.edu/viewdoc/summary?doi=10.1.1.320.1739
Hildreth, J., & Munoz, B. (2005). An introduction to the management principles of
scheduling. (Report No. TR-05-04). Blacksburg, VA: Virginia Department of
Transportation.
Kaliba, C., Muya, M., & Mumba, K. (2009). Cost escalation and schedule delays in road
construction projects in Zambia. International Journal of Project Management,
27(5), 522–531. http://doi.org/10.1016/j.ijproman.2008.07.003
Kelleher, A. H. (2004). An investigation of the expanding role of the critical path method
by ENRS top 400 contractors. (Master's thesis). Virginia Tech., Blacksburg,
Virginia. doi:http://hdl.handle.net/10919/9889
Klemenstowksi, L.J., (1978). PERT/CPM and Supplementary Analytical Techniques: AN
Analysis of Aerospace Usage. (Master’s Thesis). Air Force Institute of Technology,
Wright-Patterson/AFB, Dayton OH.
Liberatore, M. J., Pollack-Johnson, B., & Smith, C. A. (2001). Project management in
construction: software use and research directions. Journal of Construction
Engineering and Management, 37(4), 101–107.
Mahamid, I., Bruland, A., & Dmaidi, N. (2012). Causes of Delay in Road Construction
Projects. Journal of Management in Engineering, 28(3), 300–310.
http://doi.org/10.1061/(ASCE)ME.1943-5479.0000096
85
Mansfield, N. R., Ugwu, O. O., & Doran, T. (1994). Causes of delay and cost overruns in
Nigerian construction projects. International Journal of Project Management.
12(4), 254-260. http://doi.org/10.1016/0263-7863(94)90050-7
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996). Construction delays in a fast-
growing economy: Comparing Thailand with other economies. International
Journal of Project Management, 14(1), 37–45. http://doi.org/10.1016/0263-
7863(95)00052-6
Park, Y.-I., & Papadopoulou, T. C. (2012). Causes of cost overruns in transport
infrastructure projects in Asia: Their significance and relationship with project size.
Built Environment Project and Asset Management, 2(2), 195–216.
http://doi.org/10.1108/20441241211280873
Rowings, J. E., Harmerlink, D. J., & Rahbar, F. (1993). A multi-project scheduling
procedure for transportation projects. (Project No. HR-339). Ames, IA: Iowa
Department of Transportation. Retrieved from:
https://www.iowadot.gov/research/reports/Year/2003andolder/fullreports/hr339.p
df
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian
construction industry. International Journal of Project Management, 25(5), 517–
526. http://doi.org/10.1016/j.ijproman.2006.11.007
Santoso, D. S., & Soeng, S. (2016). Analyzing Delays of Road Construction Projects in
Cambodia: Causes and Effects. Journal of Management in Engineering, 32(6),
5016020. http://doi.org/10.1061/(ASCE)ME.1943-5479.0000467
86
Tavakoli, A., & Riachi, R. (1990). CPM use in ENR top 400 contractors. Journal of
Management in Engineering, 53(3), 160.
http://doi.org/10.1017/CBO9781107415324.004
Yates, J. K. (1993). Construction Decision Support System for Delay Analysis. Journal of
Construction Engineering and Management, 119(2), 226–244.
87
APPENDIX – A: EVALUATION OF CONSTRUCTION
STANDARD SPECIFICATIONS OF DOT
Symbols, abbreviations and its meaning:
Not required
Required for some projects
Required for all projects
Required fulfilling one of the formats of scheduling
CPM Critical Path Method
PSC Progress Schedule Chart
TSLD Time-Scaled logic diagram
AC/ASC Activity Chart/ Activity Schedule chart
WN Written narration
ND Network diagram
88
DOT
Scheduling technique required/ preferred/ used by
state DOT
Required
software to use
Payment
method
Designated
Scheduler
Required
Bar
Char
t
CP
M
PS
C
TS
LD
AC
or
AS
C
WN
ND
ALABAMA
ARIZONA
ALASKA
ARKANSAS
CALIFORNIA Primavera P6 Paid for
CPM
COLORADO
Primavera
product;
MS Project
Incidental to
work item
DELAWARE Incidental to
work item
for PSC;
Paid item for
CPM
DISTRICT OF
COLUMBIA
Primavera
Product;
Other, approved
by engineer
FLORIDA
GEORGIA Form, prescribed
by engineer
HAWAII Primavera
SureTrak;
89
Other, specified
in the contract
ILLINOIS Primavera
SureTrak;
MS Project
IDAHO Incidental to
work item
INDIANA Paid for the
Item
IOWA Computer
developed
schedule;
Other, approved
by engineer
Incidental to
work item
KANSAS Incidental to
work item
KENTUCKY
LOUISIANA
MAINE Incidental to
work item
MARYLAND Incidental to
work item
for AC;
Paid item for
CPM
YES
MASSACHUSETTES
MICHIGAN Form (1130)
prescribed by the
Department
Incidental to
work item
MINNESOTA Primavera P6
90
MISSISSIPI Form prescribed
by the
Department
MISSOURI
MONTANA Primavera P6;
Any Primavera
Product
Paid for the
Item
NEBRASKA
NEVADA Any Primavera
product
NEW HAMPSHIRE Primavera
Product;
MS Project
Incidental to
work item
NEW JERSY Paid for the
Item
NEW MEXICO Computer
developed
schedule;
Other, directed
by the
Department
NEW YORK No payment
(contractor’s
obligation)
NORTH CAROLINA Form prescribed
by the
Department
NORTH DAKOTA MS Project Paid for the
Item
OKLAHOMA
91
OREGON PRIMAVERA
P3/ SureTrak /
other approved ;
MS Project
OHIO Incidental to
work item
PENNSYLVANIA Asta
Powerproject or
compatible
Paid for the
CPM
RHODE ISLAND
SOUTH DAKOTA
TEXAS Incidental to
work item
YES
TENNESSEE Computerized
Schedule
software for
some projects
UTAH Primavera P6 No payment
(contractor’s
obligation)
VEMONT
VIRGINIA Primavera
Product
Incidental to
work item
WEST VIRGINIA
WISCONSIN Computer
developed
schedule;
Other, directed
by the
Department
92
WASHINGTON
WYOMING Primavera P6 Incidental to
work item
for bar chart;
Paid for
CPM
93
APPENDIX – B: RESULTS OF STATISTICAL ANALYSIS OF PROJECT TYPES T
YP
E
TO
TA
L
Unscheduled Projects
(SSNULL)
Scheduled (SSPRIM)
projects Chi-square test Student’s t-test
CO
_D
EL
AY
TT
_D
EL
AY
CO
_D
EL
AY
TT
_D
EL
AY
CO
_D
EL
AY
TT
_D
EL
AY
CO
_D
EL
AY
TT
_D
EL
AY
Del
ay
No d
ela
y
Del
ay
No d
ela
y
Del
ay
No d
ela
y
Del
ay
No d
ela
y
stati
stic
p-v
alu
e
stati
stic
p-v
alu
e
stati
stic
p-v
alu
e
stati
stic
p-v
alu
e
AL
L
20
97
939
115
8
Number of
projects 151 788 446
49
3 168 990 629 529
Percentage of
project (%)
16.
08
%
83.
92
%
47.
50
%
52.
50
%
14.5
1%
85.
49
%
54.
32
%
45.68
%
0.87
671
0.349
1
9.383
7
0.002
18
Mean delay
(days)
38.
847
68
95.
605
3
32.2
023
8
121
.46
9
-
1.158
0
0.247
69 3.3839
0.0
00
74
SD
52.
302
55
106
.92
8
50.1
312
7
143
.59
2
Improvement
for having a
schedule
17.1
060
4
-
27.
052
5
94
AS
PT
10
2
50 52
Number of
projects 10 40 20 30 10 42 18 34
Percentage of
project (%)
20.
00
%
80.
00
%
40.
00
%
60.
00
%
19.2
3%
80.
77
%
34.
62
%
65.38
% 0
>0.99
9
0.127
77
0.720
8
Mean delay
(days)
44.
5
94.
4 46.5
81.
5
0.082
5683
0.935
10 -0.4078
0.6
85
80
SD
52.
132
84
89.
038
9
56.1
194
2
105
.87
6
Improvement
for having a
schedule
-
4.49
438
13.
665
2
BR
DG
98
21 77
Number of
projects 2 19 10 11 11 66 48 29
Percentage of
project (%)
9.5
2%
90.
48
%
47.
62
%
52.
38
%
14.2
9%
85.
71
%
62.
34
%
37.66
%
0.04
3
0.835
7
0.933
15 0.334
Mean delay
(days) 7.5
50.
7
27.5
454
5
156
.43
7
1.151
707
0.273
85 2.90475
0.0
05
31
SD
3.5
355
34
54.
976
23.7
307
2
221
.57
5
Improvement
for having a
schedule
-
267.
272
7
-
208
.55
5
B RP T
10
10 0
95
Number of
projects 1 9 5 5 0 0 0 0
Percentage of
project (%)
10.
00
%
90.
00
%
50.
00
%
50.
00
%
0.00
%
0.0
0%
0.0
0%
0.00
% 6.4
0.011
41 0
>0.9
99
Mean delay
(days) 45
87.
2 0 0
SD
Improvement
for having a
schedule
CG
SW
15
3
111 42
Number of
projects 17 94 45 66 6 36 19 23
Percentage of
project (%)
15.
32
%
84.
68
%
40.
54
%
59.
46
%
14.2
9%
85.
71
%
45.
24
%
54.76
%
1.25
E-
31
>0.99
9 0.117
0.732
3
Mean delay
(days)
32.
411
76
75.
977
7 18.5
66.
157
8
-
0.659
63
0.516
65 -0.0469
0.6
40
04
SD
48.
134
79.
167
1
29.5
076
3
69.
076
6
Improvement
for having a
schedule
42.9
219
6
12.
924
6
DR
ST
13
11 2
Number of
projects 3 8 5 6 0 2 1 1
Percentage of
project (%)
27.
27
%
72.
73
%
45.
45
%
54.
55
%
0.00
%
100
.00
%
50.
00
%
50.00
%
5.20
E-
32
>0.99
9
9.92
E-32
>0.9
99
96
Mean delay
(days)
SD
Improvement
for having a
schedule
GD
RL
8
5
83 2
Number of
projects 3 80 61 22 0 2 0 2
Percentage of
project (%)
3.6
1%
96.
39
%
73.
49
%
26.
51
%
0.00
%
100
.00
%
0.0
0%
100.0
0%
6.19
E-
31
>0.99
9
0.000
831 0.977
Mean delay
(days)
121
.45
9 166 0.68925
0.4
93
27
SD
88.
778
3
142
.83
5
Improvement
for having a
schedule
-
36.
671
6
GN
RL
30
4
109 195
Number of
projects 12 97 53 56 27 168 108 87
Percentage of
project (%)
11.
01
%
88.
99
%
48.
62
%
51.
38
%
13.8
5%
86.
15
%
55.
38
%
44.62
%
0.28
148
0.595
7
1.025
8
0.311
2
Mean delay
(days)
29.
916
67
86.
566
04
47.1
481
5
153
.75
93
2.771
327 0.009
3.07647
6
0.0
02
45
7
97
SD
30.
808
67
89.
963
78
91.1
337
6
187
.15
41
Improvement
for having a
schedule
-
57.5
982
7
-
77.
620
8
HM
AS
1
00
7
243 764
Number of
projects 40 203 83
16
0 113 651 423 341
Percentage of
project (%)
16.
46
%
83.
54
%
34.
16
%
65.
84
%
14.7
9%
85.
21
%
55.
37
%
44.63
%
0.28
009
0.596
6
32.33
3
1.30
E-08
Mean delay
(days)
34.
225
70.
879
52
28.8
141
6
114
3.1
11
-
0.765
9466
0.444
904
3.02478
2
0.0
02
SD
42.
011
9
105
.47
61
37.0
546
3
121
.51
55
Improvement
for having a
schedule
15.8
196
1
-
60.
993
1
LD
SC
13
12 1
Number of
projects 0 12 9 3 0 1 1 0
Percentage of
project (%)
0.0
0%
100
.00
%
75.
00
%
25.
00
%
0.00
%
100
.00
%
100
.00
%
0.00
%
9.30
77
0.002
282
4.074
53-
30
>0.9
99
Mean delay
(days)
SD
98
Improvement
for having a
schedule
PC
CP
14
6 8
Number of
projects 0 6 4 2 0 8 2 6
Percentage of
project (%)
0.0
0%
100
.00
%
66.
67
%
33.
33
%
0.00
%
100
.00
%
25.
00
%
75.00
%
0.28
571 0.593
1.026
9
0.310
9
Mean delay
(days)
95.
75 147 1.33664
0.2
52
30
1
SD
45.
309
12
41.
012
19
Improvement
for having a
schedule
-
53.
524
8
PM
EP
21
21 0
Number of
projects 9 12 11 10 0 0 0 0
Percentage of
project (%)
42.
86
%
57.
14
%
52.
38
%
47.
62
% 0 0 0 0
0.42
857
0.512
7
0.014
762
0.827
3
Mean delay
(days)
SD
Improvement
for having a
schedule
99
PM
PT
21
21 0
Number of
projects 2 19 6 15 0 0 0 0
Percentage of
project (%)
9.5
2%
90.
48
%
28.
57
%
71.
43
% 0 0! 0 0
13.7
62
0.000
2075
3.857
1
0.049
53
Mean delay
(days)
SD
Improvement
for having a
schedule
PM
RP
89
88 1
Number of
projects 14 74 35 53 0 1 0 1
Percentage of
project (%)
15.
91
%
84.
09
%
39.
77
%
60.
23
%
0.00
%
100
.00
%
0.0
0%
100.0
0%
4.17
E-
31
>0.99
9
4.47
E-30
>0.9
99
Mean delay
(days)
SD
Improvement
for having a
schedule
PM
TH
104 4
Number of
projects
10
8
32 72 68 36 0 4 1 3
Percentage of
project (%)
30.
77
%
69.
23
%
65.
38
%
34.
62
%
0.00
%
100
.00
%
25.
00
%
75.00
%
0.58
456
0.444
5
1.253
8
0.262
8
Mean delay
(days)
100
SD
Improvement
for having a
schedule
SG
NL
47
39 8
Number of
projects 4 35 24 15 1 7 5 3
Percentage of
project (%)
10.
26
%
89.
74
%
61.
54
%
38.
46
%
12.5
0%
87.
50
%
62.
50
%
37.50
%
6.4E
-30
>0.99
9
6.3E-
31
>0.9
99
Mean delay
(days)
195
.79
17 60 -1.8998
0.0
68
18
SD
154
.94
04
68.
209
24
Improvement
for having a
schedule
69.
355
18
SIG
N
12
12
10 2
Number of
projects 2 8 7 3 0 2 1 1
Percentage of
project (%)
20.
00
%
80.
00
%
70.
00
%
30.
00
%
0.00
%
100
.00
%
50.
00
%
50.00
%
6.25
E-
32
>0.99
9
2.63
E-31
>0.9
99
Mean delay
(days)
SD
Improvement
for having a
schedule
101
APPENDIX – C: ONLINE QUESTIONNAIRE SURVEY RESULTS
SURVEY OF STATE DOTs ON CPM SCHEDULE
1. Which agency do you represent (e.g., South Carolina DOT)?
A total of 23 responses (out of 50, 46%) were received from the state dot headquarter
personnel. 2. Do you use Critical Path Method (CPM) for project management?
Count Percentage
Yes 22 95.65%
No 1 4.35%
23 3. How do you select projects for CPM scheduling? (select all that apply)
Count Percentage
Based on complexity of the project 16 72.3%
Based on risk associated with the project 12 54.5%
Based on total bid amount of the project 6 27.3%
Following the rules and regulations of the agency 5 22.7%
Other… 6
• Based on contract special provision
• Incentive/ disincentive
• CPM for all projects
• Contractor option
Total 22
4. Do you require CPM specifications for each project? (i.e. ensures least interference with
traffic, employ sufficient labor and equipment at all times, use of certain methods or
equipment, etc.)
Count Percentage
Yes, for all projects 8 36.4%
Yes, for most of the projects 3 13.6%
Yes, for some of the projects 8 36.4%
No 3 13.6%
22
102
5. Are specifications for scheduling the same for all projects or customized for each project?
Count Percentage
Standard, for all projects 11 50.00%
Standard, for most of the projects
(customized for some projects) 7 31.82%
Customized, for all projects 4 18.18%
22
6. What software does your agency currently use for scheduling? (select all that apply)
Count Percentage
Primavera P6 , version 15 or newer 6 27.3%
Primavera P6 , version 8 (8.1, 8.2, 8.3, 8.4) 11 50%
Primavera P6 , version 7 or older 4 18.2%
Primavera P3 2 9.1%
SureTrak 0 -
Microsoft Project 2010 3 13.6%
Microsoft Project 2013 1 4.6%
Microsoft Project 2016 3 13.6%
Other
• Asta Powerproject
• Paper
• Contractor preference
22
7. What types of information are loaded with schedules?
Count Percentage
Resource 5 22.7%
Cost 2 9.1%
Both (resource and cost) 6 27.3%
None 5 22.7%
Other… 4 18.2%
• Activities
• Project specific calendar
• Conditional resource loading
• (i.e. project > 7.5 mill)
22
103
8. Do you currently host your schedule database on the cloud?
Count Percentage
Yes 3 13.6%
No 19 86.4%
22
9. Do you have plans to move your database to the cloud in the next five years?
Count Percentage
Yes 2 9.1%
No 7 31.8%
Maybe 10 45.5%
No response 3 13.6%
Total 22
10. What scheduling technique do you use other than CPM? (select all that apply)
Count Percentage
CPM only 8 36.4%
Gantt charts 11 50.0%
Milestone charts 3 13.6%
Other…
• Bar Charts (Excel)
• TxDOT standard specs item 8.5
• Monitoring charts
22
11. What software is used for Gantt charts scheduling technique? (i.e. Excel, pen/paper)
12. What software is used for Milestone charts scheduling technique? (i.e. Excel, pen/paper)
13. What software is used for "other" scheduling technique? (i.e. Excel, pen/paper)
• MS Excel
• Asta powerproject
• MS Word
• Pen-paper
• DOT provide contractor the option to choose their desired software.
• DOT specific form is used for milestone charts
14. Do you allow contractors to access your schedule database?
Count Percentage
Yes 3 13.6%
No 17 77.3%
Depends on the contract 2 9.1%
22
104
15. In what situations do you require a revised CPM schedule? (select all that apply)
Count Percentage
Critical path changes 21 95.5%
Change orders 14 63.6%
Resource unviability 4 18.2%
Other… • Activity original duration changes
• Monthly updates
• Mandatory monthly updates
• Contract time changes
• Contractor deviates from current progress
schedule
• Project behind schedule greater than
certain days (i.e. 10 days)
• Time extension require for revised CPM
16. Do you use CPM for assessing claims?
Count Percentage
Yes, for all claims 9 40.9%
Yes, for selected claims 13 59.2%
No 0 0.00%
22
17. If your agency has any documents related to construction project management and
practice that can be shared, please provide a link below or email a copy to the PI of the
project (Dr. Robert L Mullen) at rlm@sc.edu
18. If you would like to receive a copy of the survey results, please provide an email address
19. Thank you for taking time out to participate in our survey. During our research, we may
find it helpful to follow up with you for additional information, please provide an email
or phone number for us to contact you for follow-up questions
105
SURVEY OF RESIDENT CONSTRUCTION ENGINEERS ON CPM SCHEDULE
1. Which agency do you represent (e.g., South Carolina DOT)?
2. If you have the authority, how would you select projects for CPM scheduling? (select all
that apply)
Count Percentage
Based on complexity of the project 47 92.2%
Based on risk associated with the project 31 60.8%
Based on total duration of the project 27 52.9%
Based on total bid amount of the project 20 39.2%
Based on the previous experience with
similar type of work/contractor 21 41.2%
Following the rules and regulations of the agency/client 7 13.7%
Other…
All projects require CPM
anticipated conflicts
Time incentives
Total 51
3. How often do you refer to CPM (Critical Path Method) schedule for decision making on
projects?
Count Percentage
Frequently 10 19.6%
Occasionally 34 66.7%
Never 7 13.7%
Total 51
4. Do you find contractors strive to follow CPM schedule?
Count Percentage
Yes, for all projects 0 -
Yes, for most of the projects 11 21.6%
Yes, for some of the projects 25 49.02%
No 15 29.4%
Total 51
5. If not required by the contract, do contractors still use a CPM schedule?
Count Percentage
Yes, all 0 -
Yes, most of the contractors 2 3.9%
Yes, some of the contractors 26 50.9%
No 23 45.1%
Total 51
6. Do you find the duration between the Notice to proceed (NTP) and start of work in
construction projects consume a significant fraction of the total duration of the project?
106
Count Percentage
Yes, for all projects 1 1.96%
Yes, for most of the projects 6 11.76%
Yes, for some of the projects 22 43.14%
No 22 43.14%
Total 51
7. Do you observe a significant fraction of the change orders from contractors in the last
third of the project?
Count Percentage
Yes, for all the projects 1 1.96%
Yes, for most of the projects 9 17.7%
Yes, for some of the projects 25 49.02%
No 16 31.4%
Total 51
8. What are the most common reasons for requesting project extension? (select all that
apply)
Count Percentage
Weather 34 66.7%
Contract modifications 36 70.6%
Resource constraints 5 9.8%
Inadequate planning and scheduling 16 31.4%
Change orders by owner 29 56.9%
Delay in approving drawing and materials by owner 1 1.96%
Slowness in decision making process 9 17.7%
Other…
• Inadequate planning and scheduling
• by contractor but blames scope of work
• Inadequate plans
• Utilities
• Utility conflicts
• Utility Delays
• Utility Relocations
• Utilities/ Permitting
Total 51
9. From your observations, does the use of a CPM schedule reduce the number of change
orders in projects?
Count Percentage
Yes, for all projects 0 -
Yes, for most of the projects 6 11.8%
Yes, for some of the projects 14 27.5%
No 31 60.8%
51
107
10. Do you use CPM for assessing claims?
Count Percentage
Yes, for all claims 16 31.4%
Yes, for selected claims 25 49%
No 9 17.6%
No response 1
51
11. If you would like to receive a copy of the survey results, please provide an email address
12. Thank you for taking time out to participate in our survey. During our research, we may
find it helpful to follow up with you for additional information, please provide an email
or phone number for us to contact you for follow-up questions
108
SURVEY OF CONTRACTORS ON CPM SCHEDULE
1. Which state is your company/organization registered in? (e.g., South Carolina)
2. Do you find contracts now contain specifications requiring CPM (Critical Path Method)
schedule?
Count Percentage
Yes, always 3 6.7%
Yes, most of the time 17 37.8%
Projects greater than $5 million 13 28.9%
Projects greater than $10 million 5 11.1%
Projects greater than $20 million 1 2.2%
Projects greater than $50 million 2 4.4%
Projects greater than $100
million
0 -
Rarely 3 6.7
No 1 2.2%
Total 45
3. If not required (or, if waived in the contract), do you still prepare a CPM schedule?
Count Percentage
Yes 30 66.7%
No 15 33.3%
45
4. How often do you make decisions based on CPM schedule?
Count Percentage
Frequently 20 44.4%
Occasionally 17 37.8%
Never 8 17.8%
45
5. On average, what is the cost of CPM application as a percentage of the total project cost?
Count Percentage
Below 0.5% 29 64.4%
0.5% - 2.5% 12 26.7%
Above 2.5% 4 8.9%
45
6. Do you use scheduling techniques other than CPM for project management? (select all
that apply)
Count Percentage
CPM only 13 29.9%
Milestone charts 22 48.9%
Gantt charts 26 57.8%
Other…
109
• Excel
• Short term schedule
• 3 week look ahead
• 2 week look ahead
• Line chart
• Bar chart
45
7. Do you maintain a separate schedule for work in addition to the contract specified
schedule?
Count Percentage
Yes, for all projects 11 24.4%
Yes, for most of the projects 8 17.8%
Yes, for some of the projects 15 33.3%
No 11 24.4%
45
8. Do you use CPM for assessing claims?
Count Percentage
Yes, for all claims 5 11.1%
Yes, for selected claims 32 71.1%
No 6 13.3%
No response 2 4.4%
45
9. Is your CPM scheduling performed by:
Count percentage
In-house personnel 25 55.6%
Outside consultant 2 4.4%
Combination of in-house and
outside consultants
18 40%
45
10. Do you have a dedicated person responsible for planning and scheduling?
Count percentage
Yes 13 28.9%
No 32 71.1%
45
11. What other duties does your scheduler perform?
Count percentage
Schedule only 6 13.3%
Cost estimation 24 53.3%
Project management other than
scheduling
32 71.1%
110
Administration 12 26.7%
Other…
• Engineering
• Supervision
• Surveying
• Project Manager/ someone from
project team does CPM
training organizer
• Do mostly scheduling and
updates
Total 45
12. How important is CPM scheduling for the future success of your company?
Count percentage
1 (Very Important) 16 35.6%
2 7 15.6%
3 12 26.7%
4 (unsure) 8 17.8%
No response 2 4.4%
45
13. If you would like to receive a copy of the survey results, please provide an email address
14. Thank you for taking time out to participate in our survey. During our research,
we may find it helpful to follow up with you for additional information, please
provide an email or phone number for us to contact you for follow-up questions
top related