March 2003 1

Development CostDevelopment CostDevelopment CostDevelopment CostMANGT 497AMANGT 497A

Small Product RealizationSmall Product Realization

March 2003Development Cost

MANGT 497AR. Weissbach

2

Overview• Engineering Cost Estimation

– Labor and Material Analysis– Preliminary and Detail Design

Estimation– Classification of Estimates

• The Effect of Time on Development– Effect of Time to Market – How to Reduce Time to Market

March 2003Development Cost

MANGT 497AR. Weissbach

3

Labor Cost• Hourly Costs

– Regular Hours (x wage rate)– Overtime Hours (x 1.5 x wage rate?)

– Holidays, Vacation, Paid Sick Leave

• Non-Hourly Costs– FICA (Social Security Tax)– Workmen’s Compensation– Unemployment Insurance– Other Supplemental Insurance– Uniforms, Tools, etc.– Profit Sharing, Bonuses, Gifts

March 2003Development Cost

MANGT 497AR. Weissbach

4

Material Costs• Cost of Material can be estimated from

historical or measured data• Bill of Material (BOM)/Parts List

– Itemized list of materials for a design• Part Number or Symbol• Descriptive Title• Quantity• Material• Stock Size, Weight, Volume, etc.

March 2003Development Cost

MANGT 497AR. Weissbach

5

Material Costs (Cont)• Cost of Direct Material Equals…

– [(Cost/Unit Shape) x Shape] – Salvage• Shape

– Actual shape of the material in units of area, volume, mass, etc.

• Sa = St(1+L1+L2+L3)– Sa = Shape– St =Theoretical Shape Required– L1 = Loss Due to Scrap (human error)– L2 = Loss Due to Waste (chips)– L3 = Loss Due to Shrinkage (deterioration, theft,

shelf life)

March 2003Development Cost

MANGT 497AR. Weissbach

6

Preliminary and Detail Design Estimation Methods

• Opinion• Conference• Comparison• Unit• Cost Estimating Relationship• Probability Approach• Range

March 2003Development Cost

MANGT 497AR. Weissbach

7

Preliminary and Detail Design Estimation

Methods

• Opinion – shortage of data or time• Conference – each dept contributes

– Hidden Card Technique– Estimate-Talk-Estimate (Persuasion)– Lack of Analysis/Facts– Needs a Moderator to Direct Discussion

March 2003Development Cost

MANGT 497AR. Weissbach

8

Exercise• How much will it cost to hire

someone to successfully design, build and test a system which will enable an uncooked egg to be tossed from the roof of the Hammermill Building and land without breaking?

March 2003Development Cost

MANGT 497AR. Weissbach

9

Preliminary and Detail Design Estimation

Methods

• Comparison– Attaches a formal logic to the conference

method– Take difficult design problem (a) and

construct a simpler design problem (b)• Clever manipulation of the original design• Relaxation of technical constraints• Branch to (b) to obtain facts pertinent about (a)• Be conservative: Ca(Da) ≤ Cb(Db)

March 2003Development Cost

MANGT 497AR. Weissbach

10

Preliminary and Detail Design Estimation

Methods• Unit Cost

– Cost per… (pound/mile/year/ft2, etc.)– Based on a mean cost (y=mx + b)– Errors Introduced

• Cost may be non-linear (based on various parameters such as volume, etc.)

• Slope (m) may not be correct

March 2003Development Cost

MANGT 497AR. Weissbach

11

ExampleCast Iron Weight (lb) Cost ($)

2 23 34 6

The average cost per pound is $1.22, based on the total weight of 9 pounds and the total cost of $11.

March 2003Development Cost

MANGT 497AR. Weissbach

12

Concerns• Can we estimate the future cost

with a linear estimate?• Would it be better to estimate

linearly using a “best fit”?• Can either method be used if the

cost is non-linear?

March 2003Development Cost

MANGT 497AR. Weissbach

13

Different Analyses YieldDifferent Estimates

Comparison of Regression Analyses

-202468

10121416

1 2 3 4 5 6 7 8

Weight of Cast Iron (lb)

Co

st

($)

Regression A Regression B

March 2003Development Cost

MANGT 497AR. Weissbach

14

Preliminary and Detail Design Estimation Methods

(cont)

• Cost and Time Estimating Relationships– Statistical regression models, based on

past designs– Formulated to present estimates for end

items– Design or performance parameters

(weight, speed, etc.) are used to predict cost (“cost drivers”), since these parameters are available early

March 2003Development Cost

MANGT 497AR. Weissbach

15

Cost Estimating Relationship (CER)

• Suggested Approach– Obtain actual costs from past designs– Interview experts who have knowledge of

cost and design– Find cost drivers– Plot data roughly and understand anomalies– Re-plot and perform regression analysis– Review for accuracy, publish, distribute

March 2003Development Cost

MANGT 497AR. Weissbach

16

Preliminary and Detail Design Estimation Methods

(cont)• Probability Approach

– Looks at average and “expected value”– Requires knowledge of statistics

• Analysis of historical data• Convenient approximations (e.g., normal,

etc)• Introspection (opinion probability)

– Cumulative probability of each event

March 2003Development Cost

MANGT 497AR. Weissbach

17

Example• Market research indicates a product

will sell wholesale for $650 in year 1• Questions:

– What will be the sales volume in year 1?– What will be the cost per unit in year 1?– What will be the profit in year 1?

March 2003Development Cost

MANGT 497AR. Weissbach

18

Example Marketing Forecast

Annual Sales Volume Probability of Event Occurring15,000 0.220,000 0.225,000 0.6

Engineering ForecastCost Per Unit ($) Probability of Event Occurring

450 0.7500 0.2550 0.1

March 2003Development Cost

MANGT 497AR. Weissbach

19

Profit Analysis Options• Look at most likely scenario

– Most likely to sell 25,000 units at $450/unit ($200 profit)– Total Profit = $5M

• Look at the expected value – Expected Value of Sales

• (15,000)(0.2)+(20,000)(0.2)+(25,000)(0.6) = 22,000– Expected Value of Unit Cost

• ($450)(0.7)+($500)(0.2)+($550)(0.1) = $470/unit– Expected Profit per unit = $180– Total Profit = ($180)(22,000) = $3.96M

• A difficulty is being able to guess the opinion probabilities

March 2003Development Cost

MANGT 497AR. Weissbach

20

Preliminary and Detail Design Estimation Methods

(cont)• Range Estimation

– Use the Beta probability density function

– Estimated Cost = (L + 4M + H)/6 where• L = lowest estimated cost• M = most likely cost• H = highest estimated cost

March 2003Development Cost

MANGT 497AR. Weissbach

21

Marginal Cost• The added cost of adopting a

change in operations or making an engineering change order for a product.

• Requires a detailed cost estimate to perform marginal analysis.

March 2003Development Cost

MANGT 497AR. Weissbach

22

Marginal Cost (cont)• Cm = d(CT)/d(n), where

Cm = marginal cost ($/unit)

CT = total cost function

= nCv + Cf

n = number of production units per periodCv = variable cost per unit

Cf = fixed cost per period

• Requires polynomial regression analysis• Measures the rate of increase of total cost and

approximates the cost of a small additional unit of output from the given level.

March 2003Development Cost

MANGT 497AR. Weissbach

23

Marginal Return• Parallel to Marginal Cost• Rm = d(RT)/d(n), where

Rm = marginal return ($/unit)

RT = total revenue function

= nRv + Rf

n = number of production units per periodRv = variable return per unit

Rf = fixed return per period (often = 0)

March 2003Development Cost

MANGT 497AR. Weissbach

24

Breakeven Analysis• The point of production or

operation where there is neither loss, nor profit.

• n = (Cf-Rf)/(Rv-Cv)

March 2003Development Cost

MANGT 497AR. Weissbach

25

Classification of Estimates

Design Fundamental Characteristic

Symbolic Measure of

Economic Want

Example

Operation Worker and Tool Cost Crew Worker Assembler and Hand Tools

Product Quantity Price Toys, Vehicles Project Single End Item Bid Bridge

Plant Addition Refinery

System Configuration Effectiveness Weapon System Hospital

Rapid Transit System

March 2003Development Cost

MANGT 497AR. Weissbach

26

Systems• Made up of operations, products and

projects• Contains intangibles such as:

– Function– Beauty– Safety– Quality of Life– Ease of Use

• No specific profit entry, instead looking at the value of “effectiveness”

March 2003Development Cost

MANGT 497AR. Weissbach

27

System Effectiveness?• The ability to do the correct thing

efficiently (e.g., hospital)Cost Item Investment Opportunity Recurring Nonrecurring

Cost Cost Cost Cost

ContingenciesMarginal Cost Analysis xOperation Estimates xProduct Estimates x xProject Estimates x x

Engineering Estimates x

March 2003Development Cost

MANGT 497AR. Weissbach

28

The Effect of Time on Development

• Time to market is a crucial element in being successful in the global marketplace

• A six month delay can be worth 33% of life cycle profits (Reinertsen)

• There is a perceived trade-off between development speed and product quality

March 2003Development Cost

MANGT 497AR. Weissbach

29

ExampleWriting a book takes 12-18 months.

Putting out a Sunday newspaper takes approximately one day.

Both have approximate the same number of words.

March 2003Development Cost

MANGT 497AR. Weissbach

30

Why Develop Products Faster?

• Increased Sales– Customer loyalty– Higher peak sales– Higher profit margins

• Beat the Competition to Market• Be Responsive to Changing

Markets, Styles, Technologies

March 2003Development Cost

MANGT 497AR. Weissbach

31

Why Develop Products Faster? (cont)

• Maintain a Market Leadership Position

• “More New Products” is the wrong focus

March 2003Development Cost

MANGT 497AR. Weissbach

32

What Developing Products Doesn’t Imply• Developing products in half the

time doesn’t mean that productivity will double.

• It means providing more up-front resources to complete the project, with heavier staffing and people dedicated full time to the project.

March 2003Development Cost

MANGT 497AR. Weissbach

33

The Basic Economic Modeling Process

Develop Baseline Model

Develop Variatons

Calculate Total Profit

Impact

Convert to Decision

Rules

Development Expense Overruns

Initial Product Cost Overruns

Unit Sales Reduced due to Product Problems

Product Introduction is Delayed

March 2003Development Cost

MANGT 497AR. Weissbach

34

Potential Effects of Delayed Product

Introduction

• Case 1 - Inelastic products with limited competition– Total unit sales do not decrease– Customers are locked into a product– Cost of delay is due to price erosion

• Units are shipped during a relatively low-margin period in the product’s life

March 2003Development Cost

MANGT 497AR. Weissbach

35

Potential Effects of Delayed Product

Introduction (cont)

• Case 2 - Timing of the peak in market demand is determined by the marketplace, rather than the date of the product.– Lower market share throughout the

life of the product

March 2003Development Cost

MANGT 497AR. Weissbach

36

Potential Effects of Delayed Product

Introduction (cont)

• Case 3 – Delay results in loss of “design-in” victories (OEM markets)– Severe and continuous reduction in sales– Inability to dislodge the competitor

March 2003Development Cost

MANGT 497AR. Weissbach

37

Example: Product with a Long Product Life

March 2003Development Cost

MANGT 497AR. Weissbach

38

Half of the time spent on many development

projects occurs before the design team is assembled

and starts work

Need

Team

Starts Ship

Inefficient Development Time

March 2003Development Cost

MANGT 497AR. Weissbach

39

Advantages of Reducing the “Fuzzy

Front End”• It lasts a long time• It is a cheap place to reduce cycle

time– Much cheaper than the cost of cycle

time at the end of the development process

• It allows for competitive advantage

March 2003Development Cost

MANGT 497AR. Weissbach

40

How to Improve Front-End Processes

• Make Front-End Cycle Time a Measured Parameter– Parameters not measured do not

improve– Start the clock when the need is

addressed to management

March 2003Development Cost

MANGT 497AR. Weissbach

41

How to Improve Front-End Processes (cont)

• Calculate the Cost of Delay (Sensitivity Analysis due to reduced market share)

• Assign Responsibilities• Assign Resources and Deadlines• Capture Opportunities Early & Often

– Ensure it’s easy to submit an idea to management

March 2003Development Cost

MANGT 497AR. Weissbach

42

How to Improve Front-End Processes (cont)

• Overlap Planning and Design– Try to remove planning from the

critical path as much as possible

• Create a Quick-Reaction Plan

March 2003Development Cost

MANGT 497AR. Weissbach

43

Other Tips on Speeding the Development

Process• Develop Your Own Process• Move Beyond the “Phases” Mentality

– Focus more on the critical path– Overlap activity timeframes

• Requires more communication between teams.

• Find Examples where Processes were Sped Up Successfully

March 2003Development Cost

MANGT 497AR. Weissbach

44

Deliverables• Ensure the Final Business Plan

includes at least one method of estimating development cost

• Quiz on Monday (4/7/03) on Development Cost