KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 1 of
METHOD STATEMENT FOR INSTALLATION STRUCTURED CABLING (IPTV,MC,CCTV& ACCESS CONTROL)
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 2 of
Project : KHALIFA UNIVERSITY EXTENSION PROJECT
MEP Contractor : FIBREX Construction Group
Document No. : DS/KUE/EL/0049
Document revision status : 02
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 3 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 4 of
Rev. Description Prepared By Checked By Approved By
02 Issued for review & Comments
Madhu Pitu Joseph
PE-MDS QC manager MEP-PM
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 5 of
REVISION CONTROL SHEET
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 6 of
PROJECT MANAGER
REV. NO. DATE PAGE NO. DESCRIPTION RECEPIENT
0 11-07-2015 All 1st Issue
1 18-08-2015 All 2nd Issue
2 29-08-2015 All 3nd Issue
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 7 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 8 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 9 of
CONTENTS
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 10 of
1.0 PURPOSE
2.0 DEFINITIONS
3.0 SCOPE OF WORK
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 11 of 4.0 RESPONSIBLE PERSONNEL ON SITE
5.0 STORAGE
6.0 PRE INSTALLATION
7.0 INSTALLATION
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 12 of
8.0 SAFETY
9.0 REFERENCE
10.0 INSPECTION CHECK LIST
11.0 ADDENDUM
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 13 of
1.0 PURPOSE:The purpose of this method statement to define the installation of STRUCTURED CABLING (IPTV,MC,CCTV& ACCESS CONTROL) proposed for Khalifa University Extension Project, Abu Dhabi.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 14 of
2.0 DEFINITIONS:
PROJECT – Khalifa University extension Project.
MEP CONTRACTOR – FIBREX
DETAILING ENGINEER – FIBREX
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 15 of HSE – Health, Safety and Environment;
PPE – Personal Protective Equipment.
AFC – Approved for Construction;
3.0 SCOPE:This Method Statement refers to various work procedures contained withinProject Control Documents, which explains and covers the installation of STRUCTURED CABLING (IPTV,MC,CCTV& ACCESS CONTROL).
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 16 of
4.0 RESPONSIBLE PERSON ON SITE:
4.1 Project Manager shall be responsible for the overall project. The project Manager will be
based on site and will be responsible for the management of the project, both on and off
site, through delegation of duties in accordance with the organization chart and for the
effective implementation of the project management system .He shall ensure that the
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 17 of proper tools and tackles are available for the timely completion of this job in a quality
manner.
4.2 MEP Coordinator is responsible on behalf of main contractor to coordinate, check and
follow up all MEP related sub-contractor’s progress and installation works in proper
sequence of activities with main contractor to achieve targeted completion.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 18 of 4.3 QA/QC Engineer shall ensure that the work is carried out ensuring that the requirement
for quality control is followed. He shall ensure that all WIR and Check List requirements are
met. QA/QC Engineer shall ensure that all necessary requests for inspection and
installation are processed and put forward to the company Engineer for notification. He
shall ensure all inspections conducted as per contract specifications, QCP (Quality control
procedures) & WIR’s to ensure all inspections proper, approved materials and shop
drawings and standards are available at the point of use. He shall be responsible for the
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 19 of total quality records related to work are completed as per quality requirements. Sub-
Contractor shall inspect the works prior to initiating WIR for the Main Contractor and
company approval.
4.4 HSE officer will monitor and implement all HSE related issues. He shall ensure that all
necessary requirements health, safety and environment concerns are met and adhered
to .The HSE officer shall ensure that all permits and authorization are on hand prior to
starting any site operation.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 20 of 4.5 Site Engineer Shall ensure that all works are carried out according to approved shop
drawings, approved material submittal and approved method statement. Ensure all safety
equipment’s proper tools & tackles are available at the point of use. Aware of all
procedures, work method (instruction, quality requirements for the timely completion of
the job and explains to the task force for execution of the job applicable code of practice
and approved shop drawings.
5.0 STORAGE
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 21 of 5.1 Materials shall be properly supported and stacked on a flat surface
5.2 Materials shall be protected from sunlight and moisture by covering them with tarpaulin
5.3 Materials shall be stacked properly in neat and orderly manner.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 22 of 6.0 PRE INSTALLATION
6.1 All material shall be as per Material Submittal no: MS-KUE-EL-0041 REV 05
6.2 All materials used shall be specified by the system manufacturer and used / installed with
manufacturer’s instructions.
7.0 INSTALLATION :
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 23 of 7.1 All installation shall be carried out as per approved shop drawings and specification with
approved materials as per manufacturer recommendation & industry standard EIA/TIA 568
C.2.
Cable Pulling – General guidelinesWhen cable is received at the job site, the cable length is verified to ensure the cable will reach
between the end points. Both ends of the cable will also be verified in terms of the footage markings
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 24 of on the outer jacket and the computation of the actual length of the jacket whenever available. The
cable shall be identified, labeled, and the shop drawings updated to reflect the work operation.
A good cable pulling setup means all materials are in place so the cables can be handled properly and
safely. Specialized equipment capable of holding large reels will be used as and when needed.
Smaller equipment, such as cable trees, will also be used to handle the many reels of cable
containing low pair count cable.
The pathway of a cable will checked first to be free of sharp bends and turns. The manufacturer’s
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 25 of recommended pulling tension and minimum bend radius (while under tension) shall not be
exceeded. The use of cable lubricants as and when deemed necessary will significantly reduce friction
and speed up cable installation especially within the conduits. The lubricant will be selected based on
cable manufacturer’s recommendations.
When the large, high pair count copper cables are installed in conduits, the pulling of the cable
places significant tension on the conduit. A winch can be used if required in this high pair count
placing operation.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 26 of Communication with co-workers is essential in every cable pull. Each of the co-workers will be pre -
pared to alert the person pulling the cable, to ensure the cable is traversing the route smoothly
without twisting, or getting bound up.
Pulling Horizontal cable in conduits
Horizontal cable is installed between the telecommunications room and work area outlets. Cable
shall not be bent. Should the cable be damaged during installation, do not attempt to repair,
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 27 of instead replace the entire cable.
The cables and their reels will be labeled prior to pulling cable into place. It is easier to identify
and label the cables before they are pulled through the conduit.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 28 of Pulling Horizontal cable in open ceiling
The procedure for cable installation in open ceilings is different from that in conduits. Cables shall
be supported whenever available by suitable cable trays and cable baskets.( A maximum of 60
Cables can be accommodated in a cable tray of 100x50mm).
Pulling backbone in vertical pathways from top to bottom
Cable is generally easier to install from the top down rather than from the bottom up because
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 29 of gravity helps with the pull. When pulling cable from top down, a reel brake will be used. A reel
brake is a mechanical device used to stop or slow a freewheeling reel, thus keeping it from
unreeling too fast due to gravity. In the room where the cable will enter the vertical pathway, a
bull wheel will be used to ensure that the jacket is not damaged as it enters the pathway.
Pulling – Horizontal
Horizontal Cable is used to connect telecommunications rooms to the different end users outlets.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 30 of In the room where the cable will enter the horizontal, a bull wheel may be used to ensure that
the jacket is not damaged as it enters the pathway. A pull wire will be used and the cable will be
pulled from end to end by taking all necessary precautions as per the requirements of the cable
manufacturer. Inspection Materials located near the bends will be closely monitored during cable
pulling in order to avoid cable mishandling.
Precautions
To verify receipt of undamaged cable, while the cable is still on the reel, the installer should verify
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 31 of that there is continuity with the cable still on the reel. For copper cable, continuity can be verified
by use of an ohm-meter.
For optical fiber cable, continuity can be verified by shining a light source (e.g., flashlight) into the
fiber strands or using a power meter or optical time domain reflectometer (OTDR).
Pulling backbone – Vertical
For optical fiber pulling, common sense is the best guideline to follow. Some of the primary
installation concerns that should be addressed during the installation of an optical fiber cabling
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 32 of system are:
Tensile Load / Installation Pull
Bend Radius( In general the max acceptable bend for Cat 6A copper cable is 4 times its
outer diameter & for Fiber 10 times the outer diameter.
The maximum length of a Cat6A permanent link is 90Meters. The number of bends in a link is not
defined as long as the bends maintain the bend radius criteria)
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 33 of The installer shall follow the manufacturer’s recommendations. During pulling, installer should
avoid crushing the cable by stepping on it or having it out in the open when man or machine may
trample it. Even though the crush resistance of the optical fiber cabling is usually around 700%
greater than that of CAT6 A UTP, one must remember that it is still made of glass.
Cable Termination
Cable termination involves the organizing of cables by destination, forming and dressing cables, and
labeling, as well as actually creating a connection with a copper or fiber conductor.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 34 of Cable termination preparation not only improves the quality of the job but also decreases the
amount of time required for termination.
The performance of pre-termination functions involves organizing the cable by destination. Cable to
be terminated should be placed at the point of termination and must also be identified to ensure it is
terminated in the designated position. Cable connection is not complete until all terminations are
identified and labeled.
Crosstalk is associated with copper balanced twisted-pair cabling and an issue of which the installer
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 35 of must be aware. This issue can be mitigated by allowing cables to have a more natural lay rather than
forming tight bundles and allowing cables to be run next-and-parallel to each other. While forming
and dressing the cable at the point of termination may be visually pleasing, doing so for longer dis-
tances, such as within a cable tray, may lead to alien crosstalk performance issues. Separation of
balanced F/UTP cables should follow the guidance of ANSI/TIA568-B.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 36 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 37 of
Copper Termination
Copper terminations are used for balanced twisted-pair cabling and the use of insulation
displacement contact (IDC) is recommended. When terminating balanced twisted-pair copper
cable:
• Remove only as much cable jacket as is required for termination and trimming.
• Follow the manufacturer’s instructions for mounting, termination, and cable management.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 38 of • Minimize the amount of untwisting in a pair as a result of termination to connecting
hardware. For untwisting cabling, maintain pair twists as close as possible to the termination
point.
The T568A and the optional T568B wiring schemes (see Figure 19) are recognized for use with
horizontal copper cable. Only one of the wiring schemes shall be used in a project. (TIA568B)
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 39 of Fiber Termination
In the current project, there are two specific types of optical fiber used: multimode and
single-mode. Each specific type of fiber has its own characteristics. Multimode optical fiber has an
outside diameter of 125 µm. The glass core of the fiber, which carries the optical signal, has a
diameter of 50 µm. Single-mode optical fiber has an outside diameter of 125 µm. The glass core
of the fiber, which carries the optical signal, has a diameter of 8-9 µm.
Optical fiber cores must be precisely aligned between connecting cables to ensure that the
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 40 of maximum transfer of light energy is obtained. In this project, pigtails will be used for termination.
Splicing will be done by using a fusion splicing method as directed by cable manufacturer.
EQUIPMENTS USED Hand Tools such as Crimping Tools ,Cable cutters …
Ladders & Cable Pulling stand
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 41 of
8.0 SAFETY:
8.1 Proper TOOL BOX talk will be given to the personnel involved in carrying out the
installation of STRUCTURED CABLING SYSTEM. The method statement & RA shall be
communicated to the crew during the tool box talk.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 42 of 8.2 PPE: Safety Shoes, Helmet, Hand Gloves appropriate for the task shall be used.
8.3 Site engineers shall ensure all safety equipment; proper tool and tackle area available at
the point of use.
8.4 Safety officer will ensure that all safety precautions are taken as per the project HSE plan
and in co ordination with main contractor Safety Officer.
8.5 Check the hazard warnings on the equipments
8.6 Strictly follow the safety instructions mentioned in the installation manual.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 43 of
9.0 REFERENCE:
9.1 Material submittal ( MS-KUE-EL-0041 REV 05 ).
9.2 Schematic Diagram.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 44 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 45 of
INSPECTION CHECKLIST
Project: KHALIFA UNIVERSITY EXTENSION
Area/ Location: Dwg & Spec. No.
WIR No: Contractor: Fibrex Date:
SI. No. INSTALLATION INSPECTION CHECK LIST ITEMSCOMPLIANCE
YES NO N/A
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 46 of
1 Check all materials are as per specification and approved MAR ,approved shop drawing & from approved supplier.
2 Check the trunk,pipes and fittings are installed as per approved drawings.
3Check all the connectivity on the SCS patch panel/Fiber patch panel.
4Check all have correct labels and identification Properly done (Outlet/Patch panel side)
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 47 of 5 Check all Termination as per the EIA/TIA 568 Standards.
6 Ensure cable bends are maintained as specified.
7 Check all Telephone/MDF rooms earthing is done.
8 Check All Telephone/MDF room need to maintain constant temperature in order to protect network switches.
Remarks:
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 48 of
CONTRACTORMAIN
CONTRACTOR CONSULTANT
Name
Sign
Date
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 49 of
11. ADDENDUM
Cable Data Sheet
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 50 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 51 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 52 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 53 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 54 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 55 of
Other Accessories.
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 56 of
PROJECT MANAGER
KHALIFA UNIVERSITY EXTENSION PROJECT 30-08-2015
METHOD STATEMENT FOR INSTALLATION Page No. : Page 57 of
PROJECT MANAGER